This document is a presolicitation notice for a multiple award task order contract to provide design-build and design-bid-build construction services throughout Italy. The U.S. Army Corps of Engineers Europe District intends to award up to five indefinite-delivery indefinite-quantity contracts with a total value not to exceed $49.99 million over five years. Task orders will be issued for projects primarily located in Vicenza, Livorno, and Aviano involving construction, repair, renovation, and environmental work. Interested firms must submit qualification documents by March 22, 2019 demonstrating compliance with Italian certification requirements to be included on a restricted planholders list and receive the formal solicitation, which will include a two-phase selection process and be issued on or after March 29, 2019 with proposals due at least 30 days thereafter. A pre-proposal conference is planned for April 8, 2019 in Vicenza, Italy.
Attachment 11 - SEED Project #1 Package
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE ARMY
US ARMY CORPS OF ENGINEERS, EUROPE DISTRICT
KONRAD ADENAUER RING 39
65187 WIESBADEN, GERMANY
7 June 2019
SUBJECT: Request for Proposal (RFP) for a new Task Order under the FY19 Italy Design Build / Design Bid Build MATOC resulting from RFP W912GB19R0031;
Buildings 6A and 6B Renovations Caserma Ederle, Vicenza, Italy (DC-19-0062) - SEED Project #1
RFP Phase Two Offerors:
You are requested to submit a proposal for the enclosed project under the provisions of the Multiple Award Task Order Contract (MATOC). The contract numbers are listed above. The Statement of Work (SOW), specifications, and drawings are attached.
1. Project Description. The purpose of this project is for the design and construction services to renovate existing buildings 6A and 6B on Caserma Ederle that function as barracks. The functional purpose of the building will not change. The renovation includes interior architectural upgrades and systems upgrades (mechanical, electrical, communications and plumbing), and new fire suppression system.
2. Proposal Deadline and Submission Method. Proposals are due no later than the Phase II Proposal deadline as stated on the W912GB19R0031 SF1442. Seed Project Proposals shall be provided with the rest of the Phase II proposal.
3. Proposal Requirements. See Phase II of the FY 19 DB / DBB Italy MATOC Solicitation, W912GB-19-R-0031, Factor 4 and 5 for Submission Requirements.
4. Separate attachments and FAR clauses incorporated by reference. Separate attachments and FAR clauses referenced below will be incorporated into the resulting contract. Clauses incorporated by reference will have the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:
(1) https://www.acquisition.gov/browse/index/far
(2) http://www.acq.osd.mil/dpap/dars/dfarspgi/current/
SUBJECT: Request for Proposal (RFP) for a new Task Order under the FY19 Italy Design Build / Design Bid Build MATOC resulting from RFP W912GB19R0031;
Buildings 6A and 6B Renovations Caserma Ederle, Vicenza, Italy (DC-19-0062) - SEED Project #1
5. Design-Build Responsibility. This project is design-build in nature. The contractor is responsible for verifying the requirements of the specifications and drawings provided by the Corps of Engineers. The contractor shall be responsible for providing the certificate of compliance for the design, specifications, and drawings furnished thereby under the contract. Designer of record approval is required for changes to the drawings, specifications, solicitation, accepted proposal, equipment compatibility, and materials required. Additionally, Federal Acquisition Regulation (FAR) Clauses 52.236-23, Responsibility of the Architect-Engineer Contractor (Apr 1984), and 52.244-4, Subcontractors and Outside Associates and Consultants (A-E Services) (Aug 1998), are applicable to this project.
6. Basis for Award. The basis for award for the seed task orders will be best value tradeoff and will use the same non-price evaluation criteria and relative importance as the MATOC award decision, and the Contracting Officer will individually select the awardee that presents the best value to the Government for each seed project. See Phase II of the FY 19 DB / DBB Italy MATOC Solicitation, W912GB-19-R-0031.
7. Evaluation Factors. See Phase II of the FY 19 DB / DBB Italy MATOC Solicitation, W912GB-19-R-0031, Factor 4 and 5 for Evaluation Criteria.
8. Contract Type. The resulting contract will be firm-fixed-price, payable entirely in Euro. The contract price will not be adjusted on account of fluctuations in the currency exchange rates. No additional sums will be payable due to any escalation in the cost of labor, materials, or equipment. Changes in the contract price and / or completion date will be made only via contract modification signed by the Contracting Officer.
9. Availability of Funds. Funds are not presently available for this acquisition. No contract award will be made until appropriated funds are made available.
10. Disclosure of Contract Magnitude. Per FAR 36.204, Disclosure of the Magnitude of Construction Projects, the estimated price range of this task order is between $1,000,000.00 and $5,000,000.
11. Price Schedule. (See attachment) Your proposal shall be submitted using the attached price schedule. Do not break out the price or provide any other pricing detail, except as noted in the price schedule, unless otherwise requested by the Contracting Officer.
12. Base and Optional Bid Items. (See FAR 52.217-5 and 52.217-7). The Government may require the delivery of optional items identified in the price schedule.
13. Notice to Proceed (NTP) and Contract Completion Date. (See FAR 52.211-10) A single notice to proceed will be issued for the design and construction, after receipt and approval of the BLG and DBA insurance certificates. The contractor shall commence work within 7 days following the NTP and complete the entire work for use not later than 635 calendar days following the NTP. Any option items exercised by the Government must be completed no later than 635 days following the NTP for the base items (option items do not have their own separate completion dates).
14. Liquidated Damages. (See FAR 52.211-12) If the Contractor fails to complete the work within the time specified in this contract, the Contractor shall, in place of actual damages, pay to the Government liquidated damages in the amount of €605.00 per day.
15. Acceptance Period. All proposals shall be valid for 120 calendar days after the proposal due date.
16. Defense Base Act (DBA) Insurance Coverage. (See FAR 52.228-3) DBA coverage is required for work performed on this project by all contractors and subcontractors. You will be required to provide the insurance certificate prior to receiving the Notice to Proceed (NTP) but no later than 14 calendar days after award.
The DBA Defense Base Act (DBA) insurance is commercially available from carriers and self-insured employers authorized by the Department of
17. Societa Organismo di Attestazione (SOA): Reference is made to clause 52.000- 4090 Qualification of Firms Pursuant to Italian Decree DPR 00/34 (Decreto Del Presidente Della Republica, January 25, 2000, No. 34. The Work Category for this project is OG1 Civil Buildings. Work Classification is I. This task order will be awarded to a contractor who has the required SOA, which must be submitted with the proposal, even if provided previously. Failure to submit the required SOA at the time of proposal will result in disqualification of the offeror from further consideration.
18. Anti-Mafia Clause: In accordance with Contract Clause 52.000-4091 Compliance with Italian Decree DPR 554/99, as amended by Article 2 of DPR 412/00, if the contractor intends to use subcontractors for performance of the task order, the contractor is required to certify, in writing, to the Contracting Officer that no disciplinary actions or proceedings for Mafia related matters against such subcontractors have occurred or are presently occurring. Failure to provide this documentation within the time specified may result in termination of the contract for default, in accordance with contract clause 52.249-10 Default.
19. Bank Letter of Assurance (BLA) and Bank Letter of Guaranty (BLG). A BLA that specifies the Contractor can furnish a BLG in the amount of 10% is required WITH PROPOSAL SUBMISSION. The successful Offeror shall furnish the BLG (original hard copy) to the Contracting Officer within 14 days of task order award.
20. Inquiries. Offerors shall submit inquiries in writing via “Bidder Inquiry” in ProjNet at www.projnet.org\projnet. The bidder inquiry key is RH675A-FFGS94, this is the same key utilized for the MATOC solicitation. Please ensure to being your inquiry with the project number (DC-19-0062) to ensure inquiries are handled properly.
Your point of contact for this contract action is contact Mr. Jason Malak, Contract
Specialist (+49 611 9744 2278 / jason.r.malak@usace.army.mil). As an alternate, please feel free to contact the undersigned (+49 611 9744 2127 / joshua.d.mueller@usace.army.mil).
Sincerely, Joshua Mueller Contracting Officer
Enclosures:
SEED #1 Statement of Work SEED #1 Att #1 - Location Map SEED #1 Att #2 - Conceptual Site Plan SEED #1 Att #3 - FuncLayout SEED #1 Att #4 - AsBuilt Floor Plan SEED #1 Att #5 - Utility AsBuilts SEED #1 Att #6 - Structural Calculations Guidelines SEED #1 Att #7 - Additional Requirements USAG Italy SEED #1 Att #8 - Draft Structural Assessments SEED #1 Att #9 - Hazmat Survey Bid Schedule Price and Payment Procedures
US Army Corps of Engineers Europe District
APO AE 09049
it48 6AB
Statement of Work Project Number:
E8-41100-8J
Buildings 6A and 6B Renovations Caserma Ederle, Vicenza, Italy
Prepared by:
Design Section
Engineering Branch 04 June 2019
01 10 10 Statement of Work Buildings 6A and 6B Renovations
4-Jun-19 Page 2 of 76
SECTION 01 10 10
STATEMENT OF WORK
SECTION TABLE OF CONTENTS:
1 GENERAL
2 CIVIL AND GEOTECHNICAL
3 ARCHITECTURAL
4 STRUCTURAL
5 ELECTRICAL & COMMUNICATIONS
6 MECHANICAL
7 FIRE PROTECTION
8 SUSTAINABILITY
ATTACHMENTS
Att. # 1 Location Map Att. # 2 Conceptual Site Plan Att. # 3 Functional Layout Att. # 4 As-Built Floor Plan Att. # 5 Utility As-Builts Att. # 6 Structural Calculations Guideline Att. # 7 Additional Requirements for USAG Italy Att. # 8 Draft Structural Assessment Att. # 9 Hazmat Survey
1.0 GENERAL
1.1 PROJECT DESCRIPTION
The Request for Proposal (RFP) provides parameters for a design-build project for renovation of buildings 6A and 6B in Caserma Ederle, Vicenza.
The project includes the following general items of work, detailed requirements are contained elsewhere in this Statement of Work:
a. Civil Improvements
b. Buildings renovation work;
c. Complete interior upgrade of mechanical, electrical, communications and plumbing systems and fixtures;
d. New fire suppression system and new fire alarm and mass notification system.
1.2 GENERAL REQUIREMENTS
The Contractor must deliver fully functional, turnkey type facilities (without furniture) as described in this document. The work includes - but is not limited to - design, demolition, fabrication, delivery, installation, construction, and site work. The facility and the installed equipment must be permanent construction.
The facility in this project must be complete and usable to meet codes and technical and functional requirements per this Statement of Work (SOW). The proposal price must include all design, calculations, approvals, certificates, fees, labor, material, equipment, direct overhead, indirect overhead, general and administrative expenses (G&A) and general conditions to complete this project as described in the SOW.
These design and product requirements are minimum requisites. Compliance with the provisions of this section by subcontractors is the responsibility of the Contractor.
4-Jun-19 Page 3 of 76
1.2.1 BASE BID ITEMS AND OPTIONAL BID ITEMS
This Statement of Work addresses the technical requirements necessary to complete all work associated with this project. For information and requirements regarding the allocation of pricing between elements of the work, refer to the Bid Schedule included as a separate document. The Bid Schedule identifies the breakdown between the individual base bid and optional items for all work identified in this Statement of Work, associated drawings, and attachments. All work as described in these documents is included in either the Base Bid or Optional Items: consider all items not specifically identified in the Optional Items as part of the Base Bid Items.
1.3 FUNCTIONAL AREAS
Renovation work of the existing barracks. Existing functional areas must remain.
The following rooms and areas must be renovated:
1.3.1 Building 6A
101 ELEC. 8.61 sqm
102 MECH 28.03 sqm
103 BEDRM 24.76 sqm
104 ENTRY 2.16 sqm
105 BATHRM 7.88 sqm
106 BEDRM 24.76 sqm
107 ENTRY 2.16 sqm
108 BATHRM 8.47 sqm
109 BEDRM 38.18 sqm
110 ENTRY 2.16 sqm
111 BATHRM 5.27 sqm
112 BEDRM 37.94 sqm
113 ENTRY 2.16 sqm
114 BATHRM 5.25 sqm
115 BEDRM 39.10 sqm
116 ENTRY 2.16 sqm
117 BATHRM 5.40 sqm
118 BEDRM 37.67 sqm
119 ENTRY 2.16 sqm
120 BATHRM 5.21 sqm
121 BEDRM 38.35 sqm
122 ENTRY 2.16 sqm
123 BATHRM 5.30 sqm
124 BEDRM 38.29 sqm
125 ENTRY 2.16 sqm
126 BATHRM 5.81 sqm
127 BEDRM 25.43 sqm
128 ENTRY 2.16 sqm
129 BATHRM 5.59 sqm
130 BEDRM 25.43 sqm
131 ENTRY 2.16 sqm
132 BATHRM 5.61 sqm
4-Jun-19 Page 4 of 76
133 BEDRM 22.85 sqm
134 ENTRY 2.16 sqm
135 BATHRM 5.61 sqm
136 CORR. 27.27 sqm
137 CORR. 43.96 sqm
138 EL. 1.18 sqm
139 BEDRM 27.81 sqm
140 BATHRM 5.63 sqm
141 STOR. 18.92 sqm
142 ABA.WC.UNI 4.31 sqm
143 WC.M 9.27 sqm
144 CORR. 3.20 sqm
145 LAUND. 33.88 sqm
146 KITCH. 35.68 sqm
147 LOUNGE 80.94 sqm
148 STOR. 42.80 sqm
149 JAN. 3.43 sqm
150 BEDRM 38.35 sqm
151 ENTRY 2.16 sqm
152 BATHRM 5.30 sqm
153 BEDRM 37.67 sqm
154 ENTRY 2.16 sqm
155 BATHRM 5.21 sqm
156 BEDRM 39.10 sqm
157 ENTRY 2.16 sqm
158 BATHRM 5.40 sqm
159 BEDRM 37.94 sqm
160 ENTRY 2.16 sqm
161 BATHRM 5.25 sqm
162 BEDRM 38.18 sqm
163 ENTRY 2.16 sqm
164 BATHRM 5.28 sqm
165 BEDRM 24.72 sqm
166 ENTRY 2.16 sqm
167 BATHRM 8.47 sqm
168 BEDRM 24.72 sqm
169 ENTRY 2.16 sqm
170 BATHRM 7.88 sqm
171 BEDRM 25.35 sqm
172 ENTRY 2.16 sqm
173 BATHRM 9.49 sqm
Building 6A total net area: 1,152.42 sqm (approximately 1,358.67 sqm gross area).
1.3.2 Building 6B
201 ELEC. 8.40 sqm
4-Jun-19 Page 5 of 76
202 MECH 27.30 sqm
203 BEDRM 24.72 sqm
204 ENTRY 2.12 sqm
205 BATHRM 8.39 sqm
206 BEDRM 24.72 sqm
207 ENTRY 2.12 sqm
208 BATHRM 8.39 sqm
209 BEDRM 37.57 sqm
210 ENTRY 2.12 sqm
211 BATHRM 5.22 sqm
212 BEDRM 37.56 sqm
213 ENTRY 2.13 sqm
214 BATHRM 5.22 sqm
215 BEDRM 37.57 sqm
216 ENTRY 2.12 sqm
217 BATHRM 5.22 sqm
218 BEDRM 37.56 sqm
219 ENTRY 2.13 sqm
220 BATHRM 5.22 sqm
221 BEDRM 37.57 sqm
222 ENTRY 2.12 sqm
223 BATHRM 5.22 sqm
224 BEDRM 37.56 sqm
225 ENTRY 2.13 sqm
226 BATHRM 5.81 sqm
227 BEDRM 24.72 sqm
228 ENTRY 2.12 sqm
229 BATHRM 5.50 sqm
230 BEDRM 24.72 sqm
231 ENTRY 2.13 sqm
232 BATHRM 5.50 sqm
233 BEDRM 24.72 sqm
234 ENTRY 2.13 sqm
235 BATHRM 5.50 sqm
236 CORR. 26.75 sqm
237 CORR. 43.95 sqm
238 LAUND. 35.27 sqm
239 NBC 17.49 sqm
240 ABA.WC.UNI 4.41 sqm
241 WC.M 8.94 sqm
242 CORR. 2.78 sqm
243 ARMS 35.67 sqm
244 LOUNGE 35.31 sqm
245 LOUNGE 74.23 sqm
246 STOR. 41.64 sqm
247 JAN. 3.25 sqm
4-Jun-19 Page 6 of 76
248 BEDRM 37.57 sqm
249 ENTRY 2.12 sqm
250 BATHRM 5.22 sqm
251 BEDRM 37.57 sqm
252 ENTRY 2.12 sqm
253 BATHRM 5.22 sqm
254 BEDRM 37.57 sqm
255 ENTRY 2.12 sqm
256 BATHRM 5.22 sqm
257 BEDRM 37.57 sqm
258 ENTRY 2.12 sqm
259 BATHRM 5.22 sqm
260 BEDRM 37.57 sqm
261 ENTRY 2.12 sqm
262 BATHRM 5.22 sqm
263 BEDRM 24.72 sqm
264 ENTRY 2.12 sqm
265 BATHRM 8.39 sqm
266 BEDRM 24.72 sqm
267 ENTRY 2.12 sqm
268 BATHRM 8.39 sqm
269 BEDRM 24.72 sqm
270 ENTRY 2.12 sqm
271 BATHRM 8.40 sqm
Building 6B total net area: 1,133.23 sqm (approximately 1,321.80 sqm gross area).
1.3.3 Total usable area to be provided must be approximately 2,285.65 sqm net.
1.4 SUBMITTALS
Government approval is required for submittals with “G” designation; submittals not having a “G” are for Contractor Quality approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Pre-construction Submittals
Demolition Plan; G
Security Plan; G
Inspection Plan; G
SD-05 Design Data
35% Design; G, DO
65% Pre-Final Design; G, DO
95% Final Design; G, DO
4-Jun-19 Page 7 of 76
100% Corrected Final Design; G, DO
Draft DD Form 1354; G
1.4.1 DESIGN SUBMITTALS
Provide a complete design package at each milestone, as described in Specification Section 01 33 16 DESIGN AFTER AWARD. The milestones for this project are indicated above in Section 1.4 SUBMITTALS. The specific requirements of each milestone are described in each discipline-specific section of this Specification.
Contractor must provide a DRAFT DD Form 1354 in accordance with UFC 1-300-08 CRITERIA FOR TRANSFER AND ACCEPTANCE OF DoD REAL PROPERTY.
Submit all documents in electronic format (.pdf for text and calculations, .pdf and .dwg (AutoCAD, latest version) for drawings). See Specification 01 33 00 SUBMITTAL PROCEDURES for additional information.
1.4.2 DRAFT DD FORM 1354
Provide a Draft DD Form 1354 “Transfer and Acceptance of DoD Real Property” with the 100% Final Design Submittal. Complete the Draft DD Form 1354 in accordance with the instructions contained in UFC 1-300-08 CRITERIA FOR TRANSFER AND ACCEPTANCE OF DoD REAL PROPERTY.
1.5 MATERIALS AND EQUIPMENT
Materials and products used must be durable, heavy duty, industry standard. The equipment must be the manufacturer’s standard quality and must be compatible with all other equipment and materials within the system or assembly. Equipment and materials must include all connections and accessories necessary to ensure operability and correct installation according to manufacturer’s requirements.
Provide a nameplate secured to each major piece of equipment. Each nameplate must have the manufacturer’s name, address, contact information, type or style, model or serial number, and catalog number. The definition of a “major piece of equipment” is at the discretion of the COR.
1.5.1 LIFE-SPAN
Construction must have an expected life span of 25 years.
1.5.2 MAINTAINABILITY
Provide low maintenance materials and systems appropriate for the project climate and location.
1.5.3 OPERABILITY
Systems (including but not limited to architectural, electrical, communications, and mechanical systems) must be simple to operate and easy to maintain.
1.5.4 STANDARDIZATION
Provide standardized materials, products, equipment, and systems to minimize the requirements for replacement parts, storage facilities, and service requirements.
1.6 DESIGN DIMENSIONS
Develop the design using the metric system.
1.7 DESIGN CRITERIA
Project design, site facilities, utility systems and material standards must be in accordance with the latest editions of the Host Nation and US building codes and following codes / criteria:
a. NFPA 101 Life Safety Code
b. International Building Code (IBC)
4-Jun-19 Page 8 of 76
c. Host Nation Building Codes and Standards
d. Unified Facilities Criteria (UFC) 1-200-01 DoD Building Code (General
Building Requirements)
e. UFC 1-200-02 High Performance and Sustainable Building Requirements
f. UFC 3-101-01 Architecture
g. UFC 3-110-03 Roofing
h. UFC 3-301-01 Structural Engineering
i. UFC 3-600-01 Fire Protection Engineering for Facilities
j. UFC 4-010-01 DoD Minimum Antiterrorism Standards for Buildings
k. Engineering Manual (EM) 385-1-1 USACE Safety and Health Requirements.
l. Environmental Final Governing Standards for Italy.
While this RFP references various source standards and specifications, all design documents are to meet US and Host Nation codes and requirements. It is the designer's responsibility to demonstrate that the Host Nation standard is equal to the US cited standard or specifications being supplanted. The more restrictive standards apply when conflicts arise between the requirements of this RFP and any referenced or other applicable codes, standards or regulations. If equivalency cannot be met, use the more stringent requirement and quote both codes verbatim in correspondence to the COR. The designer is responsible to determine the required material and execution standards where specific standards are not indicated.
Provide an electronic copy of the local Host Nation standards and building codes in their original language as related to facility design and construction.
1.8 DESIGN CONFERENCES AND MEETINGS
The Contractor and the entire design team are required to participate in a design review conference for each design submittal. The Contractor may request a review conference, but the Government is under no obligation to conduct or participate in a review conference unless specifically identified in the contract documents. The Contractor must bring the personnel that developed the design submittal to any review conference.
All design review conferences must be held via teleconference or be reviewed and comments resolved via email.
The Contractor is responsible for taking meeting minutes during each design review conference and submitting to the COR for information and approval.
The Contractor is responsible for evaluating all Government comments prior to each design review conference. The Contractor is responsible for resolving all Government comments from each design phase. The Contractor must provide annotated responses to each design review comment with the subsequent design submittal packages. Construction may not begin until all Government comments from all design phases have been resolved.
1.9 SPECIAL CONSTRUCTION REQUIREMENTS
1.9.1 AT LEVEL I TRAINING
All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, controlled access areas, or require network access, must complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Upon request, the Contractor must submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the
4-Jun-19 Page 9 of 76 following website: http://jko.jten.mil/courses/atl1/launch.html; or it can be provided by the RA ATO in presentation form which will be documented via memorandum.
1.9.2 ACCESS AND GENERAL PROTECTION/SECURITY POLICY AND PROCEDURES
All contractor and all associated sub-contractors employees must comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The Contractor must also provide all information required for background checks or background investigation and to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.
1.9.2.1 ACCESS TO DEPARTMENT OF DEFENSE FACILITIES WITHOUT COMMON ACCESS CARD
(CAC)
Contractor and all associated sub-contractors employees must comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
1.9.3 SUSPICIOUS ACTIVITY REPORTING TRAINING
The Contractor and all associated sub-contractors must receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training must be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.
1.9.4 OPSEC LEVEL I TRAINING
All new contractor employees must complete Level I OPSEC Training within 30 calendar days of their reporting for duty. Additionally, all contractor employees must complete annual OPSEC awareness training. The Contractor must submit certificates of completion for each affected contractor and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training. OPSEC awareness training is available at the following websites: https://www.iad.gov/ioss/ or http://www.cdse.edu/catalog/operations-security.html; or it can be provided by the RA OPSEC Officer in presentation form which will be documented via memorandum.
END OF SECTION
4-Jun-19 Page 10 of 76
2.0 CIVIL AND GEOTECHNICAL
Provide and perform civil engineering design and construction services as required to provide a complete, accessible, functional and usable project. The Contractor is required to extensively coordinate civil design and construction work with the scope of the other disciplines described in this SOW.
2.1 SCOPE SUMMARY
Civil works for this project include, but are not limited to, site survey, site layout, demolition, earthwork, pavement, outdoor furnishings, and landscaping. Refer to the bid schedule for which of these are base bid or optional.
2.2 EXISTING CONDITIONS
The proposed project is located on the Camp Ederle in Vicenza, Italy. See Att#1- Location Map.
2.2.1 TOPOGRAPHY
There is no known topographic survey for the project site. The existing site contains buildings, pavement, utilities, and vegetation as shown on Att#2-Conceptual Site Plan. The site is relatively flat. The existing information shown on Att#2- Conceptual Site Plan was compiled from google earth and site photos.
2.2.2 UTILITIES
There are existing utilities connected to the building as shown on Att#5-Utility As-builts. Contractor to verify actual utility locations in the field.
2.2.3 GEOTECHNICAL
There is no geotechnical information provided for the project site.
2.2.4 ENVIRONMENTAL
See Att#7-Additional Requirements.
2.2.5 UNEXPLODED ORDNANCE (UXO) CLEARANCE
There is no prior knowledge of UXO in the site’s soil. However, the site has historically been a military base.
2.2.6 EXISTING CONDITIONS INVESTIGATION
Prior to bid, investigate the general and local conditions which can affect the work and/or its cost, including but not limited to:
a. Weather, river stages, tides, or similar physical conditions at the site;
b. Surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site and due diligence research of as-built drawings, geotechnical reports, environmental reports, and publicly available information on the site.
c. Mobilization and staging constraints.
2.3 DESIGN SUBMITTALS
Provide civil design submittals in accordance with RFP Section 01 33 16, DESIGN AFTER AWARD and SOW Section 1.0 – GENERAL.
35% Design Submittal:
a. Preliminary Design Analysis of civil features.
b. Final Existing Conditions Plan.
c. Preliminary Demolition Plan and details.
d. Preliminary Pavement Plans and details.
e. Preliminary Outdoor Furnishings Plans and details.
f. Preliminary Civil Specifications
65% Design Submittal:
4-Jun-19 Page 11 of 76
a. Update all items from the 35% Design Submittal to 65% (Pre-Final) Design.
Incorporate all 35% design comments.
95% Design Submittal:
a. Update all items from the previous Design Submittal to 95% (Final) Design.
Incorporate all previous design comments.
100% Submittal:
The 100% Submittal provides a complete and final set of contract documents ready for construction. Update all Final submittals from 95% to a corrected Final submittal.
Address all previous government review comments before submitting.
2.3.1 DESIGN ANALYSIS
Provide a Design Analysis for all Civil features that documents significant design choices and substantiates design compliance with contract requirements, applicable codes and standards. Documentation includes narrative, calculations, photographs, sketches, and catalog cut sheets. Reference all applicable regulations, standards, and criteria for the design. Reference sources are subject to Government approval.
Provide design assumptions. For design choices, discuss alternative systems considered, and provide rationale for the selected alternative.
The Design Analysis includes but is not limited to:
a. Discussion of Pavement constraints and design decisions. Provide calculations for the pavement section.
2.3.2 DESIGN DRAWINGS
Provide Civil design drawings of sufficient detail to address the requirements of each design submittal. Civil drawings include plans, profiles, cross sections, and details of Civil features for the project. Design drawings include all necessary information (labeling, dimensioning, legend, details, notes, etc.) to allow for complete understanding and constructability of all proposed features. Provide comprehensible differentiation between features that are proposed, existing, future, or proposed to be demolished by use of appropriate choice of line styles, line weights, and/or colors. Reference USACE A/E/C Graphics Standard for graphic requirements.
2.3.3 SPECIFICATIONS
Provide Civil specifications of sufficient detail to address the requirements of each design submittal. Specifications, when combined with the design drawings, allow for complete understanding and constructability of all proposed Civil features. See Specification Section 01 33 16-DESIGN AFTER AWARD for specification requirements.
2.4 DESIGN CRITERIA
Provide civil design in accordance with Host Nation codes, and the latest release of the International Building Code (IBC), SOW Section 1.0-GENERAL, and the following codes and technical standards:
a. Uniform Facility Criteria (UFC) 3-201-01, Civil Engineering
b. UFC 3-220-01, Geotechnical Engineering
c. USACE A/E/C Graphics Standard (ERDC/ITL TR-12-1)
d. Military Surface Deployment and Distribution Command Transportation Engineering
Agency (SDDCTEA) Pamphlet 55-17, Better Military Traffic Engineering
2.5 GEOTECHNICAL INVESTIGATION AND REPORT
Geotechnical investigation and report is not a direct requirement for this project.
In the absence of geotechnical investigations performed on-site, an allowable soil bearing pressure is discussed in STRUCTURAL section 4.0.
4-Jun-19 Page 12 of 76
For Construction, perform field and laboratory geotechnical work required for earthwork (i.e. compaction tests, inspection of structure foundation excavations).
In the absence of Host Nation standards, perform the geotechnical work per UFC 3- 220-01, Geotechnical Engineering and IBC.
2.6 TOPOGRAPHIC SURVEY
Site information provided to the Contractor by the Government is not to be considered accurate Site Survey information. Utility field locates and as-built research are the responsibility of the Contractor.
2.7 SITE LAYOUT
Locate the proposed Civil improvements as indicated on Att#2 – Conceptual Site Plan.
Amend the site layout as determined by site-specific constraints, code requirements, the owner’s preferences, future expansion, and opportunities that are identified and evaluated as part of the Contractor’s scope of work. The Contractor is responsible for all aspects of the project whether they are shown on the conceptual plan or not.
2.8 DEMOLITION
Remove existing structures, utilities, pavement, vegetation, and any other features to construct the proposed improvements. Provide straight, neat sawcuts at limits of pavement removal. Any contaminated soils discovered require special testing and disposal per Host Nation requirements. Reference RFP Section 00 74 00-SPECIAL CONDITIONS, 00 74 17-SUPPLEMENTAL CONDITIONS FOR PROJECTS IN ITALY, Att#7-Additional Requirements, and 01 30 00-GENERAL REQUIREMENTS for additional demolition, protection, and permitting requirements.
2.8.1 CONSTRUCTION LIMITS
Do not disturb any areas outside the boundary shown on Att#2-Conceptual Site Plan, with the exception of utility trenches. Show demolition work and limits of disturbance in the drawings. Stake-out the limits of disturbance on-site with temporary fencing before beginning construction.
2.8.2 ITEMS TO REMAIN IN PLACE WITHIN CONSTRUCTION LIMITS
Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the COR. Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the COR prior to performing said work.
2.8.3 TREE DEMOLITION
Unless otherwise noted, protect all trees within the project site which might be damaged during construction. Provide a temporary fence, 1.8 m high, around the dripline of the tree(s), which is assumed to be the extent of the tree’s roots. If tree removal is necessary for construction, request authorization from the COR. The Contractor is responsible for permitting and mitigation for tree removal per Host Nation and Installation requirements.
2.8.4 UTILITY DEMOLITION
Any existing utilities encountered within the site boundary that are impacted by this project must be protected, or relocated if protection is not feasible. Relocate existing utility mains outside the structural zone of influence of proposed buildings and structures. Utilities impacted by this project that require decommissioning, or that are already out of service, must be removed up to the utility main and capped. Manholes or underground structures to be abandoned must be removed to a minimum depth of 50 centimeters below finish grade. Fill abandoned manhole or structure per Section 2.9-EARTHWORK requirements.
4-Jun-19 Page 13 of 76
2.8.5 DUST, DEBRIS, AND EROSION CONTROL
Prevent the spread of dust, debris, and erosion from the project site. Install erosion control measures before beginning construction. Sweep pavements as often as necessary to control the spread of debris. When using water for dust control, do not cause hazardous or objectionable conditions such as, but not limited to, ice, flooding, erosion, or pollution. Remove snow, dust, dirt, and debris from work areas daily. Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply Host Nation regulations regarding hauling and disposal.
2.8.6 SPECIAL DEMOLITION REQUIREMENTS
Remove abandoned chiller structure located near the northwest corner of Building 6A.
Remove piping back to the interior of the building.
2.9 EARTHWORK
Perform all earth work necessary for the installation of the proposed improvements.
2.9.1 PLANS AND SPECIFICATIONS
Define earthwork requirements in the plans and specifications. Include requirements for satisfactory material, borrow material, structural fill, topsoil, utility trenches, replacement and improvement of on-site soils, soil compaction (for subgrades of structures, paving, and landscaped areas), compaction for utility trenches, maximum lift depths, density testing frequency, maximum temporary and permanent slopes, and engineered support systems.
2.9.2 UNEXPLODED ORDNANCE (UXO) CLEARANCE
UXO clearance is not required on Camp Ederle.
2.9.3 CONTAMINATED SOIL
Inspect and test all soil according to Host Nation requirements. If hazardous materials are discovered, cease excavation, secure the area, and notify the COR for further guidance.
2.9.4 CULTURAL RESOURCES
Cultural resources, such as archaeological remains, may be uncovered during excavation operations. If suspected cultural remains are found, cease excavation, secure the area, and notify the COR for further guidance.
2.9.6 SATISFACTORY MATERIAL
Excavated material (below topsoil), if satisfactory for reuse per the Contractor’s Geotechnical Engineer, may be used on the project site where fill is required.
Unsatisfactory material, and surplus excavated material not required for fill, must be disposed of offsite, and is the responsibility of the Contractor. Borrow material may be required for construction from sources off site. Borrow materials are to be free of hazardous materials and contaminants. Any soil brought in from off-site sources must be certified clean. All tests and certifications require COR approval.
2.9.7 BACKFILL COMPACTION
In the absence of Host Nation requirements and geotechnical recommendations, fill and backfill must be placed in layers of 20 centimeters loose thickness and compacted to a minimum 95% of the maximum dry density as determined by Host Nation test method equivalent to ASTM D-1557 (Modified Proctor test). Provide density tests on all lifts at a frequency of 1 test per 40 square meters for foundations and parking, and 1 test per 30 meters of road and utility trench. Round up to nearest whole number (i.e. a 25 square meter foundation requires one test). The location of all tests must be selected by the Contractor’s Geotechnical Engineer, and copies of all test results must be furnished to the COR. All structure foundation excavations must be
4-Jun-19 Page 14 of 76 inspected and approved by the Contractor’s Geotechnical Engineer prior to placing concrete. Repair earthwork areas as recommended by the Contractor’s Geotechnical Engineer, and approved by the COR.
2.9.8 ENGINEERED SOIL SUPPORT SYSTEMS
Provide engineered soil support systems (i.e. shoring) as required for the construction of the proposed improvements. The Contractor is responsible for all dewatering necessary for earthwork.
2.9.9 SITE GRADING
Provide site grading per UFC 3-201-01, Civil Engineering guidelines.
Site grading around the building must meet ABA and Host Nation accessibility guidelines. The Contractor must limit proposed landscape slopes to a maximum 4H:1V for grass areas requiring mowing and 2H:1V for non-grass areas, which will require non-erodible surface (i.e. rock, shrubs with mulch).
2.10 UTILITIES
This section applies to all project underground utilities located outside the building, including but not limited to, sanitary sewer, water supply, storm drainage, electrical, communications, gas, liquid fuel, and heat. See Sections 5.0-ELECTRICAL, Section 6.0-MECHNICAL, and Section 7.0-Fire Protection for additional utility requirements.
Provide utility materials per IBC requirements. Proposed utility main alignments must be at least 3.0 meters from facility or building foundations, except for building connections. Provide horizontal and vertical separation between new and existing utilities for rehabilitation, maintenance, repair or replacement. Provide utility line depths, bedding, and backfill as required by applicable requirements and geotechnical recommendations. Minimum cover over pipes is 0.6 meters; greater than frost penetration; or sufficient to support imposed dead and live loads for the pipe materials used; whichever is more stringent. Place plastic warning tape along the route of the buried pipe after installation at a height of 0.3 meters above the pipe.
Coordinate all required installation, relocation, improvement and protection of utilities held by third party (e.g. public or private utility). This includes coordination of any work to be performed by the utility owner. Choice of materials and products for utility installation must be coordinated with the utility owner (customer or third party) to ensure proper integration and compliance with existing systems and allow for easy maintenance and repair of the utilities in the future.
2.11 PAVEMENT
Proposed pavements for the project include:
a. ABA ramps, landings, stairs, and handrails to the buildings’ main entrances.
Provide ABA access to both buildings’ main entrains coming from Roeder Avenue, and ABA access to both buildings’ main entrances coming from the interior parking area. Provide direct access from the buildings’ main entrances to each other without having to go down and up a ramp. Ramps must not block the maintenance and access of existing utilities. Surface materials must be Portland cement concrete (PCC). Handrails must be galvanized steel. Provide expansion joint between building and apron. Provide medium broom finish on PCC concrete.
b. Replace existing pavement in kind where the trenching occurs for utility installation. Sawcut a minimum 30 centimeters beyond edge of trench.
For asphalt concrete, provide compaction and pavement density tests, as well as thickness and evenness tests, at the frequency listed in Section 2.9 - EARTHWORK.
4-Jun-19 Page 15 of 76
For PCC, reference SOW Section 4.0 - STRUCTURAL for concrete requirements. Perform subgrade tests for all pavements as described in Section 2.9 - EARTHWORK.
2.12 OUTDOOR FURNISHINGS
2.12.3 BIKE RACKS
Provide bicycle rack(s) for 10 bicycles near the buildings’ main entrances. Material must be galvanized steel.
2.13 LANDSCAPING
Provide grass seed and 20 centimeters of topsoil on the site in areas that do not have pavement or a building within the limits of disturbance. Seeds must be locally sourced from a certified plant nursery, and native to the area. Provide seed coverage density per manufacturer/supplier’s recommendations. Provide watering, weeding, and any other necessary care to establish growth. Limit planting to times of the year per Host Nation codes and/or manufacturer/supplier’s recommendations.
Replace topsoil and seeds, at Contractor’s expense, in areas which do not have new growth coverage of 75% before the warranty period ends. The Contractor is responsible for providing irrigation water from off-base.
2.14 MOBILIZATION / STAGING / PERMITS
Locate mobilization and staging within the limits of disturbance shown on Att#2- Concpetual Site Plan. Do not block adjacent sidewalks and streets. Reference RFP Section 00 74 00-SPECIAL CONDITIONS for other mobilization, access, and permit requirements.
4-Jun-19 Page 16 of 76
3.0 ARCHITECTURAL
3.1 PROJECT DESCRIPTION
Design and renovation work of Buildings 6A and 6B at Caserma Ederle, Vicenza, Italy. Existing barracks must be renovated.
Design and then perform the renovation work of single-story, solid masonry / concrete building that will serve as barracks.
Extensive coordination is required between the architectural work and the civil, geotechnical, structural, fire protection, mechanical, and electrical requirements of this project.
3.1.1 DESIGN
Provide a design and construction package that uses the space allocations, functional adjacencies, design details, and features given or referenced in this RFP. The design must incorporate all referenced codes and regulations. The Contractor is responsible for creating additional details as required to complete a full design. All details must conform to the requirements of this RFP and are subject to the approval of the COR. A schematic design has been attached for reference. The schematic plans are provided for diagrammatic purposes only and do not necessarily represent an approved floor plan or design. The Contractor is responsible for providing a design that meets all requirements of the User and the codes and criteria referenced in this Statement or Work.
3.1.2 DESIGN SUBMITTALS
Provide all architectural submittals after contract award in accordance with Section 01 33 16 DESIGN AFTER AWARD and Section 01 33 00 SUBMITTAL PROCEDURES.
Prepare and submit the documents listed below at the submittals indicated.
3.1.2.1 35% DESIGN SUBMISSION
Include the following drawings and reports as applicable to the project:
a. Code Summary – Provide a tabular code compliance summary per UFC 3-600-01.
b. Life Safety Plans – Provide plans depicting smoke/fire resistance ratings, egress routes, dead-end corridors, exits, and other aspects of life safety pertaining to the design.
c. Demolition Plans – Provide existing floor plans, indicating all demolition required.
d. Floor Plans – Provide all floor plans, indicating room names, areas, and basic dimensions, scale 1:50.
e. Ceiling Plans – Provide reflected ceiling plans for all rooms, indicating ceiling materials and fixtures, scale 1:50.
f. Building Elevations – Provide all building elevations indicating all exterior materials.
g. Roof Plan – Provide a plan of all roof areas, indicating direction of slope and method of drainage.
h. Building Section – Indicate heights of critical building elements.
i. Wall Section - Provide a typical interior and exterior wall section for each building – describe wall materials.
j. Preliminary Design Analysis – Provide a narrative explaining the design and indicating how the design and materials meet the requirements of this SOW.
k. Preliminary Specifications – List the technical titles and short text descriptions for all performed work.
3.1.2.2 65% DESIGN SUBMISSION
Include the following drawings and reports as applicable to the project:
a. All documents from the 35% submittal updated to incorporate 35% review comments.
b. Code Summary – Provide a tabular code compliance summary per UFC 3-600-01.
4-Jun-19 Page 17 of 76
c. Life Safety Plans – Provide plans depicting smoke/fire resistance ratings, egress routes, dead-end corridors, exits, and other aspects of life safety pertaining to the design.
d. Demolition Plans – Provide existing floor plans, indicating all demolition required.
e. Floor Plans – Provide all floor plans, indicating room names, areas, and basic dimensions, scale 1:50.
f. Ceiling Plans – Provide reflected ceiling plans for all rooms, indicating ceiling materials and fixtures, scale 1:50.
g. Building Elevations – Provide all building elevations indicating all exterior materials.
h. Roof Plan – Provide a plan of all roof areas, indicating direction of slope and method of drainage.
i. Building Section – Indicate heights of critical building elements.
j. Wall Section - Provide a typical interior and exterior wall section for each building – describe wall materials.
k. Interior Elevations – Provide interior elevations of all bathrooms and built-in casework and kitchenettes, indicate critical heights of surfaces and plumbing fixtures and describe all materials and finishes.
l. Pre-Final Design Analysis – Provide a narrative explaining the design and indicating how the design and materials meet the requirements of this SOW.
m. Pre-Final Specifications – Provide detailed explanations of requirements for all performed work and provide product specific manufacturer information (brochures, technical information, cut sheets) for all materials and products to be provided/installed.
3.1.2.3 95% DESIGN SUBMISSION
The 95% Submittal provides a complete and final set of contract documents essentially ready for construction by the D/B Contractor. All previous government review comments must have been addressed. Include the following drawings and reports as applicable to the project:
a. All documents from the 65% submittal updated to incorporate 65% review comments.
b. Floor Plans – Provide all floor plans, indicating room names, areas, and dimensions, scale 1:50.
c. Building Elevations – Provide all building elevations indicating all exterior materials.
d. Roof Plan – Provide a plan of all roof areas, indicating direction of slope and method of drainage.
e. Building Section – Indicate heights.
f. Wall Sections – Provide sufficient wall section(s) to indicate all materials and different conditions.
g. Section and Plan Details – Provide details of critical building intersections.
h. Window and Door Schedule – Provide a schedule of all windows and doors, indicating sizes, hardware, and operation.
i. Stair Section and Details.
j. Finish Schedule – Indicate all proposed finishes.
k. Final Design Analysis – Provide a finalized narrative describing all work to be performed on the project and how it meets the functional and code requirements of the project. Provide product specific manufacturer information (brochures, technical information, cut sheets) for all materials and products to be provided/installed.
l. Final Specifications – Provide line items and detailed descriptions of all work to be performed.
3.1.2.4 100% DESIGN SUBMISSION
4-Jun-19 Page 18 of 76
The 100% Submittal provides a complete and final set of contract documents ready for construction by the D/B Contractor. All previous government review comments must have been addressed. Include all drawings, specifications and calculations from the 95% Submittal updated to incorporate all previous review comments.
3.2 TECHNICAL CRITERIA AND STANDARDS
Design and construct the project in accordance with the requirements outlined in Section 1.7 DESIGN CRITERIA.
3.2.1 LIFE SAFETY REQUIREMENTS
The Design must meet all Host Nation and local life safety and fire suppression system codes and requirements as well as the International Building Code (IBC) and NFPA 101 Life Safety Code as required by UFC 1-200-01 DoD Building Code and UFC 3- 600-01 Fire Protection Engineering.
3.2.2 HANDICAPPED ACCESSIBILITY REQUIREMENTS
The facility will be used by able-bodied US personnel. Per Army Standard for Unaccompanied Enlisted Personnel Housing (UEPH) and Architectural Barriers Act (ABA) Handicapped accessibility requirements apply to building lobby area that include following rooms and areas: 137, 142, 144, 237, 240 and 242.
The facility must meet all applicable Host Nation handicapped accessibility requirements.
3.3 GENERAL SCOPE OF WORK
Design the architectural elements of this facility to withstand all site-specific environmental conditions such as wide seasonal temperature swings, local wind, rain, snow and earthquake conditions. All architectural features must be appropriately braced for anticipated seismic activity. The Contractor may propose alternate building materials to meet the facility’s requirements, but final selection of materials is subject to the approval of the COR. Consider economics not only in the initial acquisition, but also in the future maintenance of the materials, when selecting materials and building systems to be incorporated into the project. When requested, the Contractor must provide documentation demonstrating that a chosen alternative material is life cycle cost effective.
3.4 DETAILED SCOPE OF WORK
The Contractor is responsible for the following specific tasks required for the construction of this facility.
3.4.1 DEMOLITION
The Contractor is responsible for all required demolition as indicated in this scope.
Demolition work includes, but is…