RFP IS-15-0001 Attachment 5 - Special Specification

View the file

Other files

File Type Posted
Amendment_0003_SF30_W912GB-14-R-0030.pdf PDF
Amend_0002_SF30_W912GB-14-R-0030_FY15_Israel_MATOC.pdf PDF
RFP_IS-15-0001_Atch6_KitchenDrawings-276_Facility.zip ZIP file
RFP_IS-15-0001_Atch6_ElecDrawings-276_Facility.zip ZIP file
RFP_IS-15-0001_Atch6_PlumbingDrawings-276_Facility.zip ZIP file
RFP_IS-15-0001_Atch1_Price_Schedule_Site_276_28Sep2014.pdf PDF
RFP_IS-15-0001_Atch6_WaterproofDrawings-Bldg_7_276_Facility.zip ZIP file
RFP_IS-15-0001_Atch6_RoadsDrawings-276_Facility.zip ZIP file
RFP_IS-15-0001_Atch6_AC_Drawings-276_Facility.zip ZIP file
RFP_IS-15-0001_Atch6_StructuralDrawings-276_Facility.zip ZIP file
RFP_IS-15-0001_Atch2_OSP_Worksheet_Directions_Site_276.pdf PDF
RFP_IS-15-0001_Atch6_ElevatorsDrawings-276_Facility.zip ZIP file
RFP_IS-15-0001_Atch9_Key_Personnel_and_Performance_Certificate_Site_276_28Sept14.pdf PDF
RFP_IS-15-0001_Atch4_SRs_Site_276_28Sep14.pdf PDF
RFP_IS-15-0001_Atch7_Soil_Boring_Plan-Logs-276_Facility.pdf PDF
RFP_IS-15-0001_Atch6_FuelDrawings-276_Facility.zip ZIP file
RFP_IS-15-0001_Atch6_ArchDrawings-276_Facility_-_3.zip ZIP file
RFP_IS-15-0001_Atch3_OSP_Worksheet-Site_276_DFAC_and_Energy_Center.xls XLS spreadsheet
RFP_IS-15-0001_Atch8_Submittal_Schedule_Site_276_28Sept14.pdf PDF
RFP_IS-15-0001_Atch6_SiteDrawings-276_Facility.zip ZIP file
RFP_IS-15-0001_Atch6_ArchDrawings-276_Facility_-_2.zip ZIP file
RFP_IS-15-0001_Atch10_USACE_Specs_Site_276_28Sep14.pdf PDF
RFP_IS-15-0001_Atch6_ArchDrawings-276_Facility_-_1.zip ZIP file
RFP_IS-15-0001_Transmittal_Ltr_Site_276_30Sep14.pdf PDF
RFP_IS-15-0001_Atch6_Drawing_List-276_Facility-29Sep2014.pdf PDF
Amend_0001_Atch1_14-R-0030_Revised_Experience_Overview_Sheet_27Sep14.docx DOCX document
Amendment_0001_W912GB-14-R-0030_FY15_Israel_MATOC_30Sep14.pdf PDF
Atch_1_Experience_Overview_Sheet.docx DOCX document
Atch_3_Past_Performance_Questionnaire.docx DOCX document
Atch_10_Host_Nation_Technical_Requirements.zip ZIP file
Atch_7_Contractor_Certification_Key_Personnel_and_Performance.docx DOCX document
W912GB-14-R-0030_FY15_Israel_MATOC_Solicitation_2Sep14.pdf PDF
Atch_8_PriceSchedule.xls XLS spreadsheet
Atch_5_Sample_Off-Shore_Procurement_Worksheet_with_Directions.doc DOC document
Atch_2_Experience_Information_Sheet.docx DOCX document
Atch_4_Letter_of_Commitment.doc DOC document
Atch_11_Sample_Contract_Requirements_-_SRs_29Aug14.pdf PDF
Atch_9__USACE_Specs_29Aug14.pdf PDF
Atch_6_Disclosure_of_Lobbying_Activities.doc DOC document
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Special Specifications for

276 Facilities DFAC & Energy Center

23 SEP 2014

Site 276 DFAC & Energy Center - Israel 23 September 2014

RFP IS-15-0001 FY15 Israel MATOC Attachment 5 - Special Specification

Table of Contents

Chapter No.

Chapter name Page No.

00 General 3

01 Earth Works 5 02 Cast in Situ Concrete works 6 04 Masonry Works 12

05 Sealing Works 14 06 Carpentry and Metal Works 46

07 Sanitary Installation 54 08 Electrical Installations 67

09 Plaster Works 97 10 Flooring and Covering Works 99 11 Painting Works 104

12 Aluminum Metal Works 109 14 Stone Works 115

15 Heating, Ventilation and Air-Conditioning Works 120 17 Requirement For Elevators 179 18 Communications 186

19 Steel Structures Works 223 22 Pre – Fabricated Elements in Building 227

23 Drilling and Casting Piles 236 24 Dismantling Demolition and Preparatory Works 239

30 Furniture and Signage 240 31 Kitchen Equipment 242 32 Test, Evaluation and Quality Assurance Unit for

Generators

33 Synchronization Panel 280 34 Fire Detection and Fire Extinguishing Systems 298

35 Building Control System 372 38 Fuel System for Generators 373 40 Site Development Works 402

49 Installation of Diesel Generators and Mechanical Systems at the Power Station

51 Paving of Roads and Surfaces 413

Site 276 DFAC & Energy Center - Israel 23 September 2014

Chapter 00 General

In case of conflict between the USACE’s General Condition and these Special Specifications, USACE’s General Conditions prevail.

00.01 Scope of Work

This project involves the construction of a structure, installations, and infrastructure work to be executed within site 276, in the central part of Israel.

This work includes the following structures and installations:

1. General Mobilization

a) Fencing the mobilization area and arranging it.

b) Fencing the work areas as well as carrying out defenses, separations, installing safety and caution measures.

c) Connecting and lining infrastructure to the site (water, electricity, phone lines, etc.).

d) Building ensemble offices for the Contracting Officer or their Representative (COR) and for the contractor uses.

e) Installing temporary signposting.

f) Repair works and accommodation to existing guard facility.

2. Building 7- Dining Facility (DFAC)

The scope of works includes construction of a Kitchen and Dining Room Building with a total floor area of about 2000 m² that includes:

a) An approximately 300 m² basement.

b) An approximately 750 m² ground floor that includes a kitchen, office, laboratory, storerooms, elevator, stairwell, service rooms, and lavatories.

c) An approximately 870 m² upper floor that includes dining rooms, food service areas, entrance lobby, rinsing room, elevator, stairwell, service rooms and lavatories.

3. Building 8- Energy Building

The scope of works includes construction of an Energy Center with a total floor area of approximately 200 m².

General

a) The structure's frames shall be built using standard concrete and block construction with pre-stressed panels.

b) The work includes all finish works, among which are included:

waterproofing, carpentry and metal works, plastering, painting, flooring and cladding, aluminum works, structural steel works, suspended ceilings, prefabricated toilet stalls, fixtures, kitchen equipment, etc.

c) The work also includes building utilities, among which are included:

sanitary installations, electric, air-conditioning, communications, fire detection and extinguishing, elevator, generators, etc.

4. Site Development Works around the buildings.

23 September 2014

The scope of works includes site and infrastructure that surrounds the buildings and around the base.

5. Dismantling of existing structures and facilities

a) The contractor will be required to reroute existing services before commencement of construction The contractor shall provide and connect these consumers to alternative lines, infrastructure and facilities, permanent or temporary, No disconnections will be made before the connection of alternatives as mentioned above.

b) Lavatory structure to be dismantled and moved within the base

c) Dismantling of an approximately 2 x 2 m precast structure and its moving and re-installation within the base, including disconnection of water and sewage systems and re-connection to water, sewage and electricity.

d) Antenna tower concrete base – to be dismantled and removed

e) Demolition and removal of an array of structures and installations on the site

f) Demolition and removal of an array of 7 structures, built using precast, light and rigid construction, having a total area of approximately 1000 m², partially roofed with

g) Careful disconnection of active water, electric, sewage, communications and other systems.

h) Removal from site of underground ( empty) 20,000litre fuel tank

The work also includes the dismantling of all of the utilities, installations, retaining walls, fences, foundations, slabs, etc. on the site for purposes of execution of the new project.

00.02 USACE General Conditions

The USACE General Conditions provided with the solicitation are applicable to this project. The contractor shall be responsible to execute all requirements of this Technical Specification, drawings and those required of the USACE General Conditions. The Host Nation Technical Requirements are included in the Base Contract.

00.03 Order of Precedence

Refer to USACE Specification Section 00 73 16.01 Special Conditions for Projects in Israel and the Federal Acquisition Regulation (FAR) Clauses in the base MATOC Contract in the event of inconsistencies between this Technical Specification, Technical Drawings, Special Contract Requirements (SRs), Host Nation Technical Requirements (HNTRs) and any other documents provided with the solicitation as amended.

00.04 Brand Names or Equal

Any reference to brand names within this specification shall be read as brand name or equal and handled in accordance with FAR Clause 52.211-6 – Brand Name or Equal.

End of Chapter 00

23 September 2014

Chapter 01 — Earth Works

Remark: In case of conflict, these special specifications shall prevail over the HNTR.

10.10 General

The term excavation mentioned in this tender/contract refers in all cases to excavations in all types of soil as well as cutting in rock, even if rock-breaking is not specifically mentioned.

Full and exclusive responsibility for the stability of the excavations and for the safety of the earthworks being performed at the site in accordance with laws and regulations is imposed on the Contractor.

10.10 Removal of excavated material

Excavated material shall be removed from the worksite to a disposal site approved by the local authority, subject to that stated in the other contract documents.

10.10 Compaction of the bottom of the excavation

The bottom of the excavation shall be compacted to a density exceeding 95% of maximum density according to modified American Association of State Highway and Transportation Officials (AASHTO). Depth shall be at least 15 cm.

10.10 Excavations for thickened areas

Excavation for thickened areas in the floor, foundation beams, etc. shall be performed after completion of all of the compaction works. The Contractor shall perform spot excavations with maximum care in order to avoid disturbing the fill near the excavation.

Supplements of over-excavation shall be provided using lean concrete only.

10.10 Work in stages

The Contractor shall take into consideration that the excavation work will be performed near and adjacent to existing structures and installations, requiring careful work in stages while providing temporary support, with all which this entails.

10.10 Scope of the work

The earthworks shall be considered as also including everything specified above and in the drawings, including: use of all types of equipment and manually, bracing of the excavation sidewalls, filling of over-excavation with lean concrete, compaction of the bottom of the excavation and controlled compaction as required for filling of trenches within the structure, foundations, shaft walls, payment of fees to authorities for removal of waste, etc.

End of Chapter 01

23 September 2014

Chapter 02 — Cast in Situ Concrete works

02.01 Type of concrete

Unless noted otherwise in the drawings, the type of concrete used in the building shall be B-30.

02.02 Control conditions

Control conditions shall be good for all types of concrete.

02.03 Preparation for casting

Quick drying of the concrete shall be avoided on hot and dry days. Steps shall be taken to protect the concrete from rapid evaporation immediately after its casting in order to avoid plastic cracking. Casting will not be permitted in temperatures exceeding 30°C.

Dowels, anchoring devices, sleeves, bolts, passageways, etc. in the concrete elements shall be covered before casting of the concrete. This shall also be performed for drainage accessories, floor traps and the like.

The position of the reinforcement in the cross-section shall be secured with the use of suitable prefabricated spacers, stabilized in the location and at the level as determined in the drawings.

02.04 Passageways, sleeves, holes etc.

Prior to casting of the concrete works, the Contractor shall clarify all of the details associated with the preparations required for these concrete works. The Contractor shall be responsible for preparing drawings of all passageways, grooves, openings, recesses, sleeves, straight edges, profiles, anchors/bolts embedded in the concrete, etc., all so that the Contractor will be able to fit them and/or install them in the formwork in advance.

The Contractor shall verify that all of the information that it needs is indeed in its possession and that it has taken all of the steps necessary to execute all of the previously mentioned without the need for demolition or cutting into parts of the cast concrete works.

02.05 Casting breaks

A. Casting breaks shall be provided in the locations as indicated in the drawings.

02.06 Precision of the work

The required level of tolerance if not indicated otherwise in one of the contract documents shall be in accordance with the table of tolerances in Israel Standard 789 (Part 1).

Permissible deviations, if not otherwise required for them, shall be half of the tolerance value as specified above (plus or minus).

Site 276 DFAC & Energy Center - Israel 23 September 2014

Maximum vertical deviation in the elevator shaft for the entire height of the shaft shall not exceed 25 mm.

02.07 Chamfering of corners

The Contractor shall chamfer all concrete elements using straight triangles with two 1.5 cm sides or by using a concave corner piece (in order to obtain a rounded corner) using strips that will be introduced in the forms prior to casting, all as detailed in the architectural drawings and details. These chamfers shall also be made in all locations where door frames are assembled in the concrete walls (on both sides)

02.08 Casting of a waterproof belt

A waterproof belt shall be constructed around wet areas that are intended to be sealed such as lavatories, kitchenettes, open balconies and roofs, the function of which shall prevent the passage of water in the fill around the tiling between the “wet” area and the “dry” area.

The belt shall be anchored into the structural concrete of the floor with dowels.

The waterproofing system shall come up over the belt and shall cover it and connect with the existing waterproofing.

The height of the belt under walls shall be 7 cm above the height of the flooring.

The height of the belt at door thresholds shall reach the underside of the flooring.

The waterproofing shall be separated in the area of the door using a brass threshold. The waterproofing shall come up over the threshold and connect with it. A cant strip shall be constructed under the belt.

This belt shall be constructed between the flooring of the roofs and balconies and the interior flooring.

02.09 Concrete surfaces planned for an epoxy coating

A. General

The works in this section shall be performed in accordance with Section 50 of the HNTR for concrete surfaces and as detailed in this specification.

The surfaces shall be cast following installation of sub base and the placement of polyethylene sheets while paying particular attention to the installation of casting breaks, joints, and concrete curing. Joints in the concrete surfaces shall be placed at distances as detailed in the drawings.

0.3 mm thick, polyethylene sheets shall be deployed prior to casting on the ground.

B. Type of floor

The floor shall be Type 02 – Casting Method 001 –”uniform layer” method.

Site 276 DFAC & Energy Center - Israel 23 September 2014

C. Type of concrete

The layer shall be cast using B-40 concrete with a smooth finish. The concrete shall include additives as recommended by the concrete supplier to prevent cracking, including plastic cracks.

D. Preparation and determination of mix ratios

The mix ratios shall be determined based on preliminary testing at a certified laboratory at the Contractors' expense. Compressive and flexural strength of the concrete shall be determined by laboratory testing as required in Israel Standard 118.

E. Level of precision and maximum allowable tolerances

The average tolerance in the planned level and the average tolerance in flatness shall be compatible with a standard level of precision as defined in Table No. 1 of Subsection 50096 of the HNTR. That shall say, a level of precision of ±10 mm in level and 10 mm in average flatness.

F. Formwork

Forms shall be made from sheet steel that are stable during application, compaction and troweling.

Leveling and the determination of heights of the forms shall be performed using survey instruments such as a level with a millimetric scale staff. Leveling and the determination of heights with the use of a leveling tube or water level will not be allowed.

G. Setting of reinforcing web and dowels

Reinforcing webs (both lower and upper) and dowel bars shall be set in advance using stable supports in a quantity that ensures their position within the hardened concrete according to the heights as indicated in the drawings.

The final distance of the webs from the various joints shall be as indicated in the drawings. The dowel bars shall be perpendicular to the forms in all directions.

H. Casting of concrete

The concrete shall be applied and compacted using a vibrating beam. Additional vibrating shall be performed next to the forms using a needle vibrator.

Compaction of the concrete surface and its leveling in order to obtain the final level shall be performed by the cutting action of a light metal straightedge supported by the forms in order to obtain the required height.

I. Troweling of the concrete surface

1. Leveling, compacting and preliminary troweling

Upon completion of vibrating, the surface of the concrete shall be leveled and compacted with the use of a suitable metal straightedge. Following completion of the

Site 276 DFAC & Energy Center - Israel 23 September 2014 leveling, the height of the concrete surface shall be checked. All recesses shall be filled with more concrete and vibrated and any surplus concrete shall be removed.

2. Final troweling

The Contractor shall take into consideration that the toweling activity requires time, experience, and it shall be performed using a well-trained crew several hours after completing the casting. After leveling as described above, any other activity shall be deferred until a time when the sheen disappears from the water secreting from the surface of the concrete, but before the concrete hardens to such an extent that the final toweling cannot be performed. Final toweling shall be performed with the use of a rotary toweling machine (“helicopter”) by tradesmen skilled in this work. In narrow areas that are difficult to reach, the troweling shall be performed using a plasterer's trowel by a skilled tradesman.

J. Curing

Curing shall begin immediately after the finishing activity and with suitable care in order to avoid damaging the surface of the troweled concrete.

Curing shall be performed by covering [the concrete] with sheets of geotechnical cloth clad with polyethylene sheets to prevent evaporation from the surface. Geotechnical cloth sheets clad in a thermal adhesion process with polyethylene sheets [shall be] as for example TC sheets fabricated for this purpose. The cloth [when] coming into contact with the concrete surface shall be wetted lightly before the sheet is rolled onto the concrete surface. Minimum curing time shall be 10 days. The use of a vapor barrier material will not be permitted.

K. Joints

Joints shall be formed in accordance with the details as required in the drawings and in conformance with all requirements of Subsection 5004 of the HNTR.

Types of joints: longitudinal and transverse casting joints, transverse dummy joints and isolation joints next to columns and walls.

The location of transverse dummy joints shall be marked clearly on the forms prior to casting.

Prior to cutting the joints, the Contractor shall mark the alignment with paint with a straight line perpendicular to the troweling. Cutting shall be performed with the use of a concrete cutting machine with a diamond blade that includes a control device that allows cutting in a straight line.

The cutting of dummy joints shall be performed as soon as possible the day after casting but in any case with high precision so that the edges of the joint will not crumble or become damaged.

The cutting of casting break joints shall be performed at a time as close as possible to their filling with filler.

The joints shall be filled in for their entire length with fire-resistant and oil-resistant

Site 276 DFAC & Energy Center - Israel 23 September 2014 elastomeric material.

The filler shall be applied so that the top face of the filler will be flush with the top surface of the slab while taking care not to spill the material beyond the sides of the joint. Leaks and stains shall be cleaned immediately on the day of application using materials recommended by the supplier.

L. Order of casting

Casting shall be performed in large strips (fields), one after the other with casting break joints between them.

02.10 Finish of exposed concrete

A. General

1. All exposed concrete shall be prepared having a standard exposed concrete finish. Concrete surfaces shall be painted.

2. Exposed concrete shall be prepared in accordance with Subsection 0208 of the HNTR for Construction Works in accordance with the following classification:

3. Conditions of service and exposure to atmospheric conditions shall be standard exposure as defined in the HNTR.

4. The concrete surface shall be flat and smooth without any bubbles or segregation. Joints between forms shall be sealed and placed together in a manner such that it will not enable leaking of cement water during casting and vibration.

5. Casting breaks shall be treated with special profiles integrated into the forms.

All of the corners shall be chamfered using 50 x 50 mm cross-section triangular strips, which shall be installed in the forms prior to casting.

B. Formwork

1. Forms shall be made from steel or plywood.

2. Forms shall be tied using a compatible steel tie-bolts in a manner by which the surface of the steel following dismantling of the forms and breaking of the bolts will be at least 1.5 cm beneath the surface of the concrete. The recess that is left shall be filled with mortar

3. The form builder shall prepare everything required to integrate openings and passageways for various systems in the forms.

C. Test casting

Prior to casting exposed concrete, the form builder shall execute a test casting of the exposed concrete as specified above. The casting area shall be 10 m². Only following inspection of the casting will be form builder be permitted to begin the exposed concrete works. The mockup will remain until completion of all of the works for purposes of

Site 276 DFAC & Energy Center - Israel 23 September 2014 comparison. The exposed concrete shall be identical to the approved mockup. The form builder shall protect the mockup from damage and soiling.

D. Leaks, protrusions, roughness, etc. that have been formed, if formed, between the panels or in any other location shall be abraded and polished with a disk grinder by the form builder following dismantling of the forms in order to obtain a uniform and smooth texture on the concrete surface.

E. Segregation, holes or any other defects requiring filling shall be repaired using a modified polymeric plaster

F. The wall shall be rinsed prior to painting with water and detergent to remove the oily layer that is left following spreading of the forms.

02.11 Reinforcing steel

A. Deformed steel bars shall be compatible with Israel Standard 4466, Parts 3 and 5.

Round steel bars shall be compatible with Israel Standard 4466, Part 2. Welded webs shall be anchoring webs in accordance with Israel Standard 4466, Parts 4 and 5, made from steel bars having an improved adhesive ability (ribbed steel) and high-strength, with the designation 50. Overlap between grids, if not required in other drawings, shall be at least three grid squares or 50 cm (whichever is larger). In slabs and beams with large spans, the Contractor shall use full-length steel up to 24 m long in order to avoid excess steel within the concrete due to overlap.

C. Where welding to reinforcing bars is required, the steel shall be classified as suitable for welding.

D. The thickness of the concrete covering on the reinforcing bars shall be 5 cm for components that come into contact with the ground or with water and 3 cm for other components, if not indicated otherwise in the drawings.

02.12 Materials

A. A list of the materials is attached to this section that comprise the standard for all the works at the site.

B. Some of the materials in this section may also apply to the execution of works connected with other sections; the Contractor shall refer to the materials as they apply in this section.

C. All the works shall be implemented in accordance with the HNTR, unless otherwise stated in the special specification.

C-1 – Smooth cast-in-place concrete floor C-2 – Cast-in-place concrete C-3 – Architectural cast-in-place concrete C-4 – Cast-in-place concrete with double component epoxy coat gray color

End of Chapter 02

23 September 2014

Chapter 04 – Masonry works

04.01 General

Partitions in the structure shall be constructed with hollow blocks in the thicknesses as indicated in the drawings.

04.02 Concrete tie beams

Concrete tie beams, if not indicated specifically otherwise in the drawings, shall be at a height of 2.10 m above the height of the doors and windows for the entire length of the walls, including walls without openings.

An additional tie beam shall be constructed under the windows between columns.

04.03 Connections

A vertical corner post shall be constructed at every free corner, at every intersection between planes of walls and partitions and at the intersection between walls and partitions with concrete elements.

The masonry construction shall end approximately 10 cm from the intersection in an offsetting block pattern.

Dowels shall protrude from the concrete elements during casting. The gap shall be filled with concrete after arranging the dowels in the space between the blocks and the concrete, adding of reinforcing to the corner posts and connection of the horizontal tie beams.

04.04 Placement and concreting of frames

A. Accessory frames made from 1.5 mm thick galvanized sheet metal shall be constructed for all of the aluminum and steel doors and windows.

Accessory frames in stone surfaces shall be placed at a distance of about 8 cm from the concrete castings (thickness of the stone + thickness of the plaster). The accessory frame shall thus be anchored to the concrete.

This anchoring shall be provided using 8 [mm] diameter dowels every 20 cm, which shall be inserted into the concrete to a depth of at least 10 cm with chemical dowels. The gap between the accessory frame and the concrete shall be filled with a supplementary concrete casting. The thickness of the concrete casting shall in no case be less than 5 cm.

Application of the concrete shall be performed in a casting between forms. Spreading like plaster will not be permitted. The concrete shall be minimum B-20 and the Contractor shall perform laboratory testing to prove the type of concrete as in the structural components of the building.

B. The placement of frames in the masonry work shall be performed while strictly adhering to height and alignment with the use of a level and plumb bob. The frame shall be supported against deviation. If the surface of the frame shall be aligned with the

Site 276 DFAC & Energy Center - Israel 23 September 2014 plaster, a gap of at least 15 mm shall be left for the plaster. In other cases, the frame shall be assembled as required in the drawings and in consideration of the thickness of the plaster.

C. The Contractor shall strictly verify filling of the frame space with concrete with pea aggregate, with the addition of an anti-moisture additive. In any case in which the frame will not be filled, the Contractor shall dismantle it and reassemble it.

D. Frames on the same floor shall be placed in a uniform horizontal alignment.

Frames between floors shall also be aligned in vertical lines and no protrusions or deviations from the standard will be permitted.

E. During casting of the grout, the frame shall be supported on the inside for its entire length so that no warping will be caused to it during the support and/or casting.

04.05 Waterproof stop

A waterproof stop shall be constructed around wet areas as specified in Section 02 above.

04.06 Materials

A. A list of materials is attached to this section that comprise the standard for all the works in the site.

B. Some of the materials in this section will also apply in the execution of works connected with other sections; the Contractor shall refer to the materials as they apply in this section.

C. All the works shall be implemented in accordance with the HNTR, unless otherwise stated in the special specification.

CMU-7 7 cm thick

CMU-10 10 cm thick

CMU-15 15 cm thick

CMU-20 20 cm thick

PB-1 Decorative concrete block 40/40/12. light color.

BU-1 Continuous wall bumper for kitchen ramp made of molded rubber according to Detail 01-213

BU-2 Wall Guard for dining halls made of continuous aluminum profile with PVC cover, including end plugs and corner accessory

End of Chapter 04

23 September 2014

Chapter 05 – Sealing Works

05.01 Materials technical data sheet

Type 1 - Hydraulic cement

Technical Data

Chemical Base Part A: liquid polymer and additive

Part B: Portland cement selected aggregate and admixtures

Density Fresh mortar density: ~ 2.00 kg/l

Layer Thickness 0.75 mm min.-1.5 mm max.

Thermal Expansion 13 x 10-6 per °C

Carbon Dioxide Diffusion Coefficient (μCO2) μCO2 ~ 35.000

Water Vapor Diffusion Coefficient (μH2O) μH2O ~ 500

Mechanical / Physical Properties

(According to EN 196-1)

Compressive Strength- 3 days ~ 20 N/mm2; 28 days ~ 35 N/mm2

Flexural Strength- 3 days ~ 6 N/mm2; 28 days ~ 10 N/mm2

Tensile Strength:

Cured in water: ~ 3.2 N/mm2 after 14 days exposure

(According to DIN 53455)

Cured in air: ~ 4.5 N/mm2 after 14 days exposure

Bond Strength 2.0 to 3.0 N/mm2 (failure in substrate)

E-Modulus Static: ~ 8.4 kN/mm2

Type 2 – Solvent base bitumen primer

Bitumen primer required by manufacturer of solvent base bitumen brush coat.

Type 3 – Solvent base bitumen brush

Site 276 DFAC & Energy Center - Israel 23 September 2014

Description Property Standard

Appearance Black paste

Specific gravity 0.94

Solid content >57%

Coverage 2.5-3.0 kg/m2 (6.3-7.6 gal/100 sq.ft)

Dry film thickness 1.4-1.7 mm

(56-68 mils)

Service temperature -10?C to +60C (14°F to 140°F)

Application temperature +5?C to 40?C (41°F to 104°F)

Heat stability >100°C (212°F) ASTM D 2939

Cold flexibility <-5°C (<8 °F) ASTM D 522

Tensile Strength > 0.8 MPa (> 116 psi ) ASTM D 412

Elongation at break > 1200% ASTM D 412

Resistance to water pressure > 0.5 atm, 24 hr (>7.3 psi, 24 hr) DIN 52123

Recovery 85% ASTM D 412

Resistance to water Passed ASTM D2939

Type 4 – Water base bitumen primer

Bitumen primer required by manufacturer of water base bitumen brush coat.

Site 276 DFAC & Energy Center - Israel 23 September 2014

Type 5 – Water base bitumen brush

Description Property Standard

Appearance Brown paste (dries to black membrane)

Specific gravity 1.16

Solid content 65% +/- 2% (wt)

Coverage 3.0-5.0 kg/m2 (6.1-10 gal/100 sq.ft)

Dry film thickness 1.5-2.5 mm (60-100 mils)

Flashpoint Non flammable

Service temperature: -10?C to +60?C (14°F to 140°F)

Application temperature: +5?C to 40C (41°F to 104°F)

Heat stability >90°C (194°F) ASTM D 2939

Cold flexibility <-13°C (<8 °F) ASTM D 522

Low temperature flexibility and crack bridging Pass Conduct @-26°C ASTM C 836

Tensile Strength > 0.5 MPa (> 71 psi ) ASTM D 412

Elongation at break > 600% ASTM D 412

Resistance to water pressure > 0.5 atm, 24 hr (>7.3 psi, 24

hr) DIN 52123

Water Vapor Permeance 0.45 perms ASTM E 96

Water vapor transmission 2.0 m SI 1731

Recovery 85% ASTM D 412

Creep AT 80?C No creep DIN 52123

Resistance to water Passed ASTM D2939

Bacterial attack in soil 30 days 40?C Passed ASTM D 3083

Crack bridging > 5 mm (>0.2 inch) SI 1731

Site 276 DFAC & Energy Center - Israel 23 September 2014

Type 6 – Self-adhesive membrane

Thickness 25 mils

Sealant Material Modified Butyl

Peel Strength 17 lbs. per linear inch

Tensile Strength 790 psi avg.

Elongation 560% avg.

Flexibility Excellent, no cracking

Bonding Time Intermediate aggressive grip, full bond 24 hours

Service Temperature -20°F. to 200°F.

Surface Burning Flame Spread 15

Smoke Developed15

Type 7 – Swelling profile

Change of Volume Hydrophilic swelling red part:

7 days in tap water: ≥100% (DIN 53521)14 days in tap water: ≥150% 10 dry-wet cycles in tap water: ≥100% (DIN 53521)(1 cycle = 7 days dry and 7 days in tap water)

Swelling Pressure ≤ 15 bar after 7 days stored in tap water Mechanical / Physical Properties

Tensile Strength Hydrophilic swelling red part:

≥ 2.5 N/mm2 (DIN 53504) EPDM black part:

≥ 7.0 N/mm2 (DIN 53504)

Shore A Hardness Hydrophilic swelling red part:

75 +/- 5 (DIN 53505)

EPDM black part:

80 +/- 5 (DIN 53505)

Elongation at Break Hydrophilic swelling red part:

≥ 250% (DIN 53504)

EPDM black part:

≥ 100% (DIN 53504)

Type 8 – Sealing accessory for cable/pipe passage

Cables penetration-sealed accessory.

Type 9 – sealant for cable/pipe penetration

Site 276 DFAC & Energy Center - Israel 23 September 2014

Sealed sealant for filling gap around cables penetration

Density approximate 1.2 g/cm³ (NEN 1183)

Water absorption 5% - 20% (ASTM D 570)

Temperature Ranges: Application: +20°C to +35°C

Service: -20°C to +35°C

Type 10 – Polyurethane sealant

Chemical Base 1-part polyurethane, moisture curing.

Density ~ 1.3 kg/l (color concrete grey) (DIN 53 479)

Skinning Time ~ 60 - 120 minutes (+23°C / 50% r.h.)

Curing Rate ~ 2 - 3 mm/24 h (+23°C / 50% r.h.)

Movement Capability 25%

Joint Dimensions Min. width = 10 mm / max. width = 40 mm

Sag Flow 0 mm, very good (DIN EN ISO 7390)

Service Temperature -40°C to +70°C

Mechanical / Physical Properties

Tear Strength ~ 7 N/mm (+23°C / 50% r.h.) (DIN 53 515)

Shore A Hardness ~ 25 after 28 days (+23°C / 50% r.h.) (DIN 53 505)

E-Modulus ~ 0.3 N/mm2 at 100% elongation (+23°C / 50% r.h.) (DIN EN ISO 8340) ~

0.6 N/mm2 at 100% elongation (-20°C)

Elongation at Break ~ 800% (+23°C / 50% r.h.) (DIN 53 504)

Elastic Recovery > 80% (+23°C / 50% r.h.) (DIN EN ISO 7389 B)

Type 11 – Bitumen base sealant for high density polyethylene pipes (HDPE) pipes

Site 276 DFAC & Energy Center - Israel 23 September 2014

Type 12 – Two component bitumen brush

Viscosity: Over 40,000 Cps.

Solid contents (%): 65

Fluidity at 80°c: Non-skid, non-fluid

Flexibility at –15°c: Does not crack

Resistance to water spray: No noticeable change in the film. After subjection to water spraying for 72 hours.

Resistance to ponding water: resistant to ponding water maintaining

Bonding to infrastructure for 36 hours from completing the application.

Resistance to water pressure: A dry 3mm film resist water pressure of 1atmosphere for 72 hours.

Elongation: 1000%

Recovery: after 500% elongation 58%

Resistance to impact: Good

Site 276 DFAC & Energy Center - Israel 23 September 2014

Type 13 – Bitumen sealant

Description Property

Density (gr/cm2) 1.25

Viscosity (cPs) 140,000-180,000

Flash Point (ºC) >27ºC

Solid Content (%) >80%

Type 14 – Hot bitumen

Hot bitumen 75/25

Type 15, type 16 – bitumen membranes

Nominal Thickness Minimum (mil)

4(160) 5(200) EN 1849-1ASTM D

Length,m (ft) 10(33) 10(33) EN 1848-1

Width ,m (ft) 1(3.3) 1(3.3) EN 1848-1

Upper Surface Sand/ Mineral/PE Sand/ Mineral/PE

Tensile strength , LD/TD/N/5cm (ibf/in)

600/400(67/45) 600/400(67/45) EN 12311-1ASTM D

Elongation at break , LD/TD ,%

30/30 35/35 EN 12311-1ASTM D

Cold Flexibility ,cº (f) -20(-4) -25(-13) -20(-4) -25(-13) EN 1109ASTM D

Heat stability ,cº (f) 100(212) 110(230) 100(212) 110(230) EN 1110ASTM D

Water tightness ,kPa (Ibf/in2)

>200(>29) >200(>29) EN 1928

Shear resistance of joint N/Scm (Ibf/in)

>400(>45) >400(>45) EN 12317-1

Resistance to impact , h=300mm,mm (in)

>12.7(>0.5) >12.7(>0.5) EN 12691

Resistance to static loading ,kg (Ibf)

>20(>44) >20(>44) EN 12730

Site 276 DFAC & Energy Center - Israel 23 September 2014

Type 17 – Sealed mortar

Ready-made sealed mortar

Type 18 – Vapor barrier

Reinforced non-woven glass felt and 25µ Aluminum foil

Thickness mm 1.4 min.

Tensile strength LD/TD, min. N/5cm 300/140 ASTM D 5147

Elongation at break, LD/TD, %, min. 5.855.8 ASTM D 5147

Cold Flexibility, °C < 0 ASTM D 5147

Heat stability, °C > 100 ASTM D 5147

Type 19 – Acrylic paint

Description Property Standard

Appearance White paste

Specific gravity 1.5

Solid content >70%

Coverage 3.5-4.5 kg/m2 (5.5-7.0 gal/100 sq.ft)

Dry film thickness 1.3-1.7 mm (52-68 mils)

Application temperature +5?C to 40?C

Heat stability >120 °C (>248°F) ASTM D 2939 cold flexibility < -15 °C (< 5 °F) ASTM D 522

Tensile Strength >1.0 Mpa (>145 psi) ASTM D 412

Elongation at break >150% ASTM D 412

Resistance to water pressure >0.5 atm, 24 hr (> 7.35 psi, 24 hr) DIN 52123

UV Resistance Resistant to UV and the influence of Oxygen and Ozone ASTM D 4799

Adhesion Excellent to: Concrete, Bituminous membrane, bitumen, Aluminum, Galvanized steel, asbestos, etc.

ASTM C 794

Site 276 DFAC & Energy Center - Israel 23 September 2014

Type 20 – EPDM glue

Shear Strength ~ 1.15 N/mm2; 1 mm adhesive thickness (+23°C / 50% r.h) (DIN 52 283)

Tensile Strength ~ 1.6 N/mm2 (+23°C / 50% r. h) (DIN 53 504)

Tear Strength ~ 5.5 N/mm2 (+23°C / 50% r. h.) (DIN 53 515)

Shore a Hardness ~ 38 (after 28 days) (DIN 53 505)

E-Modulus 0.7 N/mm2 at 100% elongation (+23°C / 50% r. h) (DIN EN ISO 8340) Elongation at Break ~ 420% (+23°C / 50% r. h) (DIN 53 504)

Elastic Recovery > 70% (+23°C / 50% r. h) (DIN EN ISO 7389 B)

Type 21 – EPDM membrane

Technical Specification

General

Section 05 of the Host Nation Technical Requirements (HNTR) shall be read in Conjunction with this Special Specification that constitutes an extent to the work with regard to Waterproofing Works.

This specification shall be read in conjunction with the drawings of waterproofing details number:

9877-007-05-KP1, 9877-007-05-KP2, 9877-007-05-KP3, 9877-007-05-KP4.

Waterproofing of single piles cap in direct contact to the concrete slab.

See detail 109

1.1 Surface Preparation

The surface shall be cleaned properly of any dirt, dust, unbound material residues etc.

All steel bars or wires protruding from the walls shall be cut inside the concrete.

Segregation pockets shall be plugged with a mixture of 1 part cement, 3 parts sand, and water with latex additives (15% of cement weight).

1.2 Hydraulic cement

Site 276 DFAC & Energy Center - Israel 23 September 2014

The waterproofing area shall include the pile surface and their periphery to a height of about 30 cm. Two coats of hydraulic cement type 1 shall be applied. 1 kg per m² each coat, a total of 2 kg per m². The second coat shall be applied after the first has already started to dry. Care shall be taken that the coating does not dry and therefore the area shall be moistened as necessary.

1. Waterproofing concrete beams

This clause includes the internal and the external side of the concrete beam.

See details 101, 104, 105, 108,110,112,201

1.3 Surface Preparation

The surface shall be cleaned properly of any dirt, dust, unbound material residues etc. all steel bars or wires protruding from the walls shall be cut inside the concrete and plugged with a mixture of 1 part cement, 3 parts sand and water with Latex SBR or equivalent (15% of cement weight).

At the threshold door on ground level, the contractor shall install an aluminum strip directly to the side of the concrete beam.

The temporary protection done in the protruding area of the floor shall be removed carefully to prevent waterproofing damaging.

1.4 Primer

On clean, dry surface of the concrete beam, the contractor shall apply bitumen primer type 2, 300 gram/m².

1.5 Modified Bitumen Brush

The contractor shall apply coats of modified bitumen type 3, 4 mm dry coat layer.

In the upper area: the coats will reach the bottom level of the slab. Later, the waterproofing from the slab will overlap this layer.

On the external side of the parametrical beam: the coat will be applied 10 cm above the final level of the landscape around or overlap the threshold door aluminum bar.

At the bottom: the coats will be applied 30 cm deep or the concrete beam bottom.

1.6 Waterproofing protection

The contractor shall cover the bitumen coat with polystyrene boards 30 kg/m³, 3 cm thick, to protect the waterproofing. The boards will be stuck to the bitumen by polystyrene glue.

1.7 Backfilling soil

The backfilling soil will be done carefully in order to avoid damage.

Site 276 DFAC & Energy Center - Israel 23 September 2014

2. Waterproofing of elevator shaft slab, basement slab, ground level slab, etc.

(suspended)

See details 101, 102, 103, 104, 105, 106, 107, 108, 109, 110, 112, 202

This clause includes all the slabs cast above separation boxes, such an elevator shaft slab, basement slab for pipes (-7.875), basement slab level -5.25 and -4.33

1.1 Polyethylene sheet

Above the separation box, the contractor shall place a layer of 0.3 mm. polyethylene sheet. The overlapping between the sheets will be 10 cm.

1.2 Reinforce concrete

The contractor shall cast a reinforce lean concrete layer, 6 cm thickness.

The concrete will include reinforce mesh 6 mm, 20 x 20 cm + bent iron figures (like bench) every 60 cm, in order to hang the waterproofing coat attached to the foundation beam.

The top reinforce concrete level will be 5 cm under the bottom level of the foundation beam.

The concrete surface finish shall be smooth and continuous; no aggregates shall protrude over the surface.

Under concrete beams shorter than 50 cm: the lean concrete will continue under the concrete beam.

Around foundation pile caps and concrete beams: The top level of the lean concrete will be 5 cm under the bottom level of the slab.

Towards elevator shaft walls, underground cast walls, etc.: 30 cm along the vertical elements, the lean concrete will be cast 15 cm deeper in order to increase the overlapping area.

Around the slab: The leveling concrete plate shall protrude 30 cm outside the cast walls in order to join the waterproofing of the floor to the waterproofing of the wall.

1.3 Surface Preparation

Prior to commencing sealing works, all the details and elements that may affect the sealing shall be completed. The surface shall be cleaned of dirt, dust, stones, oils, steel wires etc. The surface shall be smooth, clean and straight.

1.4 Primer

Above the reinforce concrete the contractor shall apply a coat of bitumen primer type 4, 300 grms/m².

1.5 Bitumen spray

Above the primer, the contractor shall apply a one component bitumen spray coat, type 5.

At elevator shaft and basement 5 mm dry coat.

At ground level slab 4 mm dry coat.

Around metal bars / bend figures: The coat will be applied as a thick cove.

Around foundation pile caps and concrete beams: The bitumen coats will vertically overlap the hydraulic cement 5 cm (higher than the future protection concrete).

Towards elevator shaft walls, underground cast walls, etc: The bitumen coats will vertically overlap the hydraulic cement 15 cm (higher than the future protection concrete in this area).

Around the slab: The bitumen coats shall protrude 30 cm outside the cast walls in order to join the waterproofing of the floor to the waterproofing of the wall.

1.6 Waterproofing around pipes in underground walls

Around “HDPE pipes penetrating through the slab, the contractor shall wrap a self adhesive membrane that includes a fabric side type 6.

On top of the patch, the pipe and the wall sealing, the contractor shall apply coats of liquid bitumen brushed in the form of a cove.

In the case of suspended pipes under the slab, around each supporting metal bar the contractor shall apply a thick layer of the coat.

1.7 Temporary protection layer

On top of the bitumen sealing, on the protruding area of 30 cm, outside the place of the future cast beam, the contractor shall place a layer of 0.2 mm. polyethylene sheets and a polystyrene board 2 cm. thick, as a temporary protection system.

1.8 Protective coating

Cast of a protective concrete B-20, 5 cm thick to protect the bitumen coat. The layer shall be accomplished by using semi-liquid mixture to avoid the use of tools that may cause damage to the sealing coat. The layer shall cover the protruding sealing beyond the beam.

1.9 Water stop swelling profile

At each cast interruption, between floor and wall, around pipes, etc., the contractor shall apply a swelling profile type 7, size 20 x 5 mm. The strip shall be applied at the center of the wall and glued swelling glue.

1.10 Slab casting

The slab will be cast according to structural engineer details

3. Waterproofing of elevator shaft walls, basement underground walls

See details 101, 102, 103, 104, 105, 107, 108, 111, 112, 201, 203, 204, 205

1.11 Water stop swelling profile

At each cast interruption, between floor and wall, around pipes, etc., the contractor shall apply a swelling profile type 7, size 20 x 5 mm. The strip shall be applied at the center of the wall and glued swelling glue.

1.12 Surface Preparation

The surface shall be cleaned properly of any dirt, dust, unbound material residues etc. all steel bars or wires protruding from the walls shall be cut inside the concrete and plugged with a mixture made 1 part cement, 3 parts sand and water with Latex SBR or equivalent (15% of cement weight)

Large segregation areas shall plug with a non-shrink mortar.

At the threshold door, the contractor shall install an aluminum strip.

The temporary protection done in the protruding area of the floor shall be removed carefully to prevent waterproofing damaging.

1.13 Primer

Above the reinforce concrete the contractor shall apply a coat of bitumen primer type 4, 300 grms/m².

1.14 Bitumen spray

Above the primer, the contractor shall apply a bitumen spray coat, type 5, 5 mm thick.

Towards the elevator shaft slab: The bitumen coats shall be applied to the 30 cm area that protrude of the waterproofing of the slab for overlapping.

In the upper area: the coats will reach the bottom level of the slab. Later, the waterproofing from the slab will overlap this layer.

Towards threshold door of the lobby: The bitumen coats will vertically overlap the profile that will be placed on the concrete beam of the threshold door.

1.15 Waterproofing protection

The contractor shall cover the bitumen coat with polystyrene boards 30 kg/m³, 3 cm thick, to protect the waterproofing. The boards will be stuck to the bitumen by polystyrene glue.

1.16 Backfilling soil

The backfilling soil will be done carefully in order to avoid damage.

4. Waterproofing of pipes penetration through underground walls (representative clause)

See detail 111

This clause is a representative spec. for different types of pipe penetration. In the project are different types of penetration, sleeves, pipes, cables, elements (walls, drainage pit, etc.).

This clause shall be adapted for each penetration.

1.17 Waterproofing around pipes in underground walls

Around PVC or metal pipes the contractor shall do a thickening of the bitumen sealing in the form of a thick cove corner.

In the case of multiple pipe penetration made, metal, PVC or HDPE pipes the contractor shall leave at least 10 cm between each pipe.

Around HDPE pipes the contractor shall apply a thick coat of sealant.

At cable penetration the contractor shall install a sealed accessory type 8.

In the case of metal, PVC or HDPE pipes feeding through metal or PVC sleeves in an underground wall, when the sleeve diameter exceeds the pipe diameter by a maximum of 5 cm: After the cables or pipes are inserted into the sleeves, fire resistant, swell polyethylene sponge shall be wrapped at both the internal side and the external side of the wall, 15 cm apart from each other, in order to create a gap for sealing sealant filler.

In the space left between the sleeve and the pipe, the contractor shall inject sealant type 9, approximately 15 cm deep; width equal to the remaining space.

Through the external edge of the pipe the contractor shall install an approved factory made sealing accessory type roof drain outlet. Between the sleeves of the accessory to the bitumen of the wall, additional bitumen coats will be applied.

5. Internal waterproofing of drainage pit

1.18 Surface Preparation

The surface shall be cleaned properly of any dirt, dust, unbound material residues etc.

All steel bars or wires protruding from the walls shall be cut inside the concrete.

Concrete residues shall be cut

Holes and segregation areas shall be plugged with a mixture made 1 part cement, 3 parts sand and water with latex additive (15% of cement weight)

Site 276 DFAC & Energy Center - Israel 23 September 2014

Large segregation areas shall plug with a non-shrink mortar.

In the concrete, on the internal side of the wall, around pipe penetration the contractor shall wrap a polyethylene backer rod 1cm Ø.

After casting the wall, the backer rod will be removed in order to create a gap at the internal surface of the concrete around the pipe.

1.19 Hydraulic cement coat

Above prepared surface the contractor shall apply 3 coats of hydraulic cement brush type 1. Each layer will be 1 kg/m², (3 kg/m² in total). The applications shall entirely cover the internal area of the pit, includes floor, wall and ceiling.

1.20 Waterproofing of pipe passage

After removing the backer rod around the pipe, the gap shall be plugged with a polyurethane sealant type 10.

Around HDPE pipes the sealant shall be type 11.

6. Waterproofing of sunken yard

See detail 101

1.21 Slope concrete

The contractor shall cast slope concrete layer improved by latex additive. The layer casting shall be a minimum of 1 cm thick. The casting shall have a minimum slope of 1%.

1.22 Surface Preparation

The surface shall be cleaned properly of any dirt, dust, unbound material residues etc. all steel bars or wires protruding from the walls shall be cut inside the concrete and plugged.

At the threshold door, the contractor shall cast concrete beams and install an aluminum strip to finish the top edge of the waterproofing at doors.

The aluminum strip will be included in the main contractor scope of work and will be priced together with the surface preparation clause.

1.23 Drainage System

Drainage elements shall have a rim that protects against any return flow and collect water from both the sealing level and the flooring surface level.

The gutter rim or channel frame shall be positioned at the lowest point so that the entry of the waterproofing coat into the gutter or channel rim is smooth and continuous with the slope direction to avoid water accumulation around the gutter or channel entry.

Site 276 DFAC & Energy Center - Israel 23 September 2014

The gutter or channel model, grilles, drains outlets and the entire drain system shall comply with the sanitary installation designer specifications

1.24 Primer

Above the reinforce concrete the contractor shall apply a coat of bitumen primer type 4, 300 grms/m².

1.24 Bitumen Brush

Above the primer, the contractor shall apply coats of bitumen type 12, 4 mm dry layer.

The waterproofing shall include the floor area and will be applied above walls 10 cm above the level of the paving (same high of the threshold door concrete beam).

1.25 Protective coating

Cast of a protective concrete B-20, 5 cm thick to protect the bitumen coat. The layer shall be accomplished by using semi-liquid mixture to avoid the use of tools that may cause damage to the sealing coat. The layer shall cover the protruding sealing beyond the beam.

1.26 Paving

Paving will be done according to architectural details.

7. Waterproofing of service yard

See detail 201

1.27 Surface Preparation

The surface shall be cleaned properly of any dirt, dust, unbound material residues etc. all steel bars or wires protruding from the walls shall be cut inside the concrete and plugged.

At the threshold door, the contractor shall cast concrete beams and install an aluminum strip to finish the top edge of the waterproofing at doors.

The aluminum strip will be included in the main contractor scope of work and will be priced together with the surface preparation clause.

1.28 Hydraulic cement coat

Above the slab the contractor shall apply 3 coats of hydraulic cement brush type 1. Each layer will be 1.5 kg/m², (4.5 kg/m² in total). The applications shall entirely cover the high concrete ramp and will be applied in vertical areas, 10 cm above the final level of the finishing layers.

1.29 Stabilized sand coat

Above the waterproofing, the contractor shall apply a stabilized sand coat mixture of 1 m³ of clean sand for each100 kg cement. The coat will be 5 cm. After watering and drying the layer, the contractor shall wait until the layer is stable.

1.30 Paving

Paving will be done carefully in order to prevent damage to the waterproofing.

8. Waterproofing of kitchens floor

See details 105, 201, 301,302, 303, 304, 305, 307, 309

This clause includes the entire area of the kitchen at level -5.50 and the dish washing area at level 0.00.

1.31 Concrete beam

On the Perimeter of the kitchen the contractor shall cast a concrete belt, before the building of the walls, to create a “sealed bath”. The concrete belt will be 10 cm height of the final paving of the floor.