AMD_1_SPECIFICATIONS_DOC.pdf

PDF 860 KB Posted

Attached to
Award for Contract W912ER19C0015 Large Aircraft Maintenance Hangar, UAE Federal contract opportunity
Solicitation number
W912ER-19-R-0001
Issued by
Department of the Army Corps of Engineers Engineering District Middle East

About this file

Amendment 0001 Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Award for Contract W912ER19C0015 Large Aircraft Maintenance Hangar, UAE, newest first.
File Type Posted
Amendment_0005_Specifications_Document.pdf PDF
A154_Amendment_0005_W912ER19R0001_Large_Aircraft_Maintenance_Hangar,_UAE.pdf PDF
Amendment_0005_Drawing_Document.pdf PDF
A154_Amendment_0004_W912ER19R0001_Large_Aircraft_Maintenance_Hangar,_UAE.pdf PDF
Amendment_0003_Specifications_W912ER19R0001_Large_Aircraft_Maintenance_Hangar,_UAE.pdf PDF
A154_Amendment_0003_W912ER19R0001_Large_Aircraft_Maintenance_Hangar,_UAE.pdf PDF
Amendment_0003_Drawings_W912ER19R0001_Large_Aircraft_Maintenance_Hangar,_UAE.zip ZIP file
A154_Amendment_0002_W912ER19R0001_Large_Aircraft_Maintenance_Hangar,_UAE.pdf PDF
AMENDMENT_0002_SPECIFICATIONS_DOCUMENT_-_LAMH.pdf PDF
DRAWING_FILE_COVER_PAGE.pdf PDF
Cover_Vol_1_for_Contracting.pdf PDF
A154_Amendment_0001_W912ER19R0001_Large_Aircraft_Maintenance_Hangar,_UAE.pdf PDF
A153_Attachment_B_-_W912ER19R0001_Large_Aircraft_Maintenance_Hangar,_Al_Dhafra_UAE.docx DOCX document
A153_Attachment_C_-_W912ER19R0001_Large_Aircraft_Maintenance_Hangar,_Al_Dhafra_UAE.docx DOCX document
Drawings_2018-10-12_Corrected_Final_Updated_03-15-19.pdf PDF
VOL_3_OF_3_LAMH_DIV_21-43.pdf PDF
A153_Solicitation_W912ER19R0001_Large_Aircraft_Maintenance_Hangar,_Al_Dhafra_UAE.pdf PDF
A153_Attachment_D_-_W912ER19R0001_Large_Aircraft_Maintenance_Hangar,_Al_Dhafra_UAE.docx DOCX document
A153_Attachment_F_-_W912ER19R0001_Large_Aircraft_Maintenance_Hangar,_Al_Dhafra_UAE.docx DOCX document
Attachment_G_UAE_Large_AirCraft_Hangar_Proposal_Schedule__2-4-19.pdf PDF
VOL_2_OF_3_LAMH_DIV_01-13.pdf PDF
A153_Attachment_A_-_W912ER19R0001_Large_Aircraft_Maintenance_Hangar,_Al_Dhafra_UAE.docx DOCX document
A153_Attachment_E_-_W912ER19R0001_Large_Aircraft_Maintenance_Hangar,_Al_Dhafra_UAE.docx DOCX document
Appendix_A_Furniture,_Fixtures,_and_Equipment_(FFE).pdf PDF
Appendix_B_Structural_Interior_Design_(SID).pdf PDF
Attachment_G_UAE_Large_AirCraft_Hangar_-_Cost_Breakdown_2-4-19.pdf PDF
Attachment_1_DRAFT_Solicitation_Large_Aircraft_Maintenance_Hanger,_UAE.PDF PDF
Presolicitation_Notice_Advisory_Multi-Step_Process_(FAR_15.202),_Large_Aircraft_Maintenance_Hangar,_UAE.pdf PDF
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LARGE AIRCRAFT MAINTENANCE HANGAR, AL DHAFRA, UAE 452312

SECTION TABLE OF CONTENTS

DIVISION 21 - FIRE SUPPRESSION

SECTION 21 13 25.00 10

HIGH EXPANSION FOAM (HI EX. HEF) FIRE PROTECTION SYSTEM REVISED BY AMENDMENT

PART 1 GENERAL

1.1 REFERENCES

1.2 SYSTEM DESCRIPTION

1.2.1 Design Requirements

1.2.2 System Operation

1.2.2.1 Related Systems

1.2.2.2 Hose System

1.3 CONTRACTOR RESPONSIBILITIES

1.4 SUBMITTALS

1.5 QUALITY ASSURANCE

1.5.1 Fire Protection Specialist

1.5.2 Installer's Qualifications

1.5.3 Foam System Testing

1.6 EXTRA MATERIALS

1.7 PERFORMANCE REQUIREMENTS

1.8 CALCULATIONS

PART 2 PRODUCTS

2.1 STANDARD PRODUCTS

2.2 NAMEPLATES

2.3 REQUIREMENTS FOR FIRE PROTECTION SERVICE

2.4 PRESSURE RATINGS

2.5 ABOVEGROUND PIPING SYSTEMS FOR WATER OR FOAM/WATER SOLUTION

2.5.1 Pipe

2.6 ABOVEGROUND PIPING SYSTEMS FOR HEF CONCENTRATE

2.6.1 Pipe

2.6.2 Fittings

2.6.3 Gaskets

2.6.4 Pipe Hangers

2.6.5 Control Valves

2.7 AUTOMATIC WATER FLOW CONTROL VALVE ASSEMBLY (DELUGE VALVE)

2.8 BASKET STRAINER

2.9 HIGH EXPANSION FOAM LIQUID CONCENTRATE

2.10 FOAM TANK

2.11 HIGH EXPANSION FOAM INDUCTOR

2.11.1 Proportioning Equipment

2.12 HYDRAULIC SURGE SUPPRESSOR

2.13 HIGH EXPANSION FOAM GENERATORS

2.14 ALARM INITIATING DEVICES

2.14.1 Waterflow Pressure Alarm Switch

2.14.2 Foam Test Header

2.14.3 Foam System Control Panel

2.14.3.1 Primary Power Supply

SECTION 21 13 25.00 10 Page 1

Amendment 0001 W912ER19R0001

2.14.3.2 Emergency Power Supply

2.14.3.2.1 Storage Batteries

2.14.3.2.2 Battery Charger

2.15 ALARM INITIATING DEVICES

2.15.1 Waterflow Pressure Alarm Switch

2.15.2 Manual Foam Discharge Stations

2.15.3 Multi-Sprectrum (Triple) IR (Infrared) Flame Detectors

2.15.4 Signal Line and Initiating Device Circuits

2.16 FOAM SYSTEM ABORT SWITCHES

2.16.1 Foam Stop/Abort Switches

2.16.2 Operation

2.16.3 Automatic Reset

2.17 NOTIFICATION APPLIANCES

2.18 OVERVOLTAGE AND SURGE PROTECTION

2.18.1 Signaling Line Circuit Surge Protection

2.18.2 Sensor Wiring Surge Protection

PART 3 EXECUTION

3.1 INSTALLATION

3.1.1 Aboveground Piping

3.1.2 Foam Inductor Installation

3.1.3 Joints

3.1.4 Reducers

3.1.5 Pipe Supports and Hangers

3.1.6 Pipe Penetrations

3.1.7 Piping Pitch

3.1.8 Escutcheons

3.1.9 Drains

3.1.10 Painting

3.1.11 Identification Signs

3.2 PIPE AND LABELING

3.2.1 Pipe Identification

3.3 ELECTRICAL WORK

3.3.1 Overcurrent and Surge Protection

3.3.2 Grounding

3.3.3 Foam System Control Panel (FSCP)

3.3.4 Manual Release/Discharge Stations

3.3.5 Dead-man style foam abort switches

3.3.6 Notification Appliances

3.3.7 Wiring

3.4 TESTING PROCEDURES

3.4.1 Automatic Flow Control Valve (FCV) Functional Testing

3.4.2 Preliminary Tests

3.4.2.1 Hydrostatic Tests

3.4.2.2 Automatic Water Flow Control Valves

3.4.2.3 Foam Generators

3.4.2.4 Concentrate System

3.4.3 Final Test

3.4.3.1 Requirements

3.4.3.1.1 Pretest Requirements

3.4.3.1.2 Videotaping

3.4.3.1.3 Manufacturer's Services

3.4.3.1.4 Materials and Equipment

3.4.3.1.5 Facility and Environmental Protection

3.4.3.2 Proportioning System Tests

3.4.3.3 Post-discharge Test Requirements

3.5 POSTED INSTRUCTIONS

3.6 TRAINING

SECTION 21 13 25.00 10 Page 2

3.7 ADDITIONAL TESTING INFORMATION

-- End of Section Table of Contents --

SECTION 21 13 25.00 10 Page 3

SECTION 21 13 25.00 10

HIGH EXPANSION FOAM (HI EX. HEF) FIRE PROTECTION SYSTEM

REVISED BY AMENDMENT 0001

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASME INTERNATIONAL (ASME)

ASME A13.1 (2015) Scheme for the Identification of Piping Systems

ASTM INTERNATIONAL (ASTM)

ASTM A312/A312M (2017) Standard Specification for Seamless, Welded, and Heavily Cold Worked Austenitic Stainless Steel Pipes

ASTM A351/A351M (2016) Standard Specification for Castings, Austenitic, for Pressure-Containing Parts

ASTM A403/A403M (2016) Standard Specification for Wrought Austenitic Stainless Steel Piping Fittings

FM GLOBAL (FM)

FM APP GUIDE (updated on-line) Approval Guide http://www.approvalguide.com/

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 11 (2016) Standard for Low-, Medium- and High- Expansion Foam

NFPA 13 (2016) Standard for the Installation of Sprinkler Systems

NFPA 16 (2015) Standard for Installation of Foam-Water Sprinkler and Foam-Water Spray Systems

NFPA 70 (2017) National Electrical Code

NFPA 72 (2016) National Fire Alarm and Signaling Code

SECTION 21 13 25.00 10 Page 4

U.S. DEPARTMENT OF DEFENSE (DOD)

UFC 3-600-01 (2016; Change 1 2016) Fire Protection Engineering For Facilities

UFC 4-211-01 (2017; with Change 1, November 2017) Aircraft Maitenance Hangars

UNDERWRITERS LABORATORIES (UL)

UL Fire Prot Dir (2012) Fire Protection Equipment Directory

1.2 SYSTEM DESCRIPTION

1.2.1 Design Requirements

Design and provide a new automatic high expansion foam (HEF) system consisting of an automatic deluge foam-water fire protection system for the area indicated on the drawings. The system shall provide uniform distribution of aerated high expansion solution to provide complete coverage throughout the areas indicated. The design, equipment, materials, installation, and workmanship shall be in strict accordance with the required and advisory provisions of UFC 3-600-01 , UFC 4-211-01 , Air Force Criteria Change, NFPA 11 , NFPA 13 , and NFPA 72 , except as modified herein.

The system shall include all materials, accessories and equipment necessary to provide the system complete and ready for use.

Design and install the system to give full consideration to blind spaces, piping, electrical equipment, ductwork, and all other construction and equipment to provide complete coverage in accordance with the drawings to be submitted for approval. Devices and equipment for fire protection service shall be of a make and type listed by the Underwriter's Laboratories Inc. in the UL Fire Protection Equipment Directory or approved by the Factory Mutual System in FM APPROVAL GUIDE, unless otherwise specified. In the publications referred to herein, the advisory provisions shall be considered to be mandatory, as though the word "shall" had been substituted for "should" wherever it appears; reference to the "authority having jurisdiction" shall be interpreted to mean US Army Corps of Engineers Center of Expertise for Aircraft Hangar Fire Protection.

Foam Concentrate Storage Tank must be a vertical, closed cell double-walled , high density cross-linked polyethylene storage tank compatible with the required concentrate. Tank capacity must be the volume required to fully submerge the inductor dip tube plus the design volume to operate the foam generators for not less than 15 minutes or discharge at the hydraulically calculated waterflow rate and 130% of the nominal concentrate injection rate. Design the inductor to 115% of the nominal injection rate. The inductor dip tube must enter through the top of the tank, and no taps are permitted in the bottom or sides of the tank. Provide a closeable fill opening and vent assembly. Provide either a translucent shell or clear vertical window to indicate fill level with permanent capacity markings at least every 50 gallons. The capacity markings will not include the unsuckable amount of concentration at the bottom of the tank. Mount concentrate tank on a 2 inch concrete housekeeping pad. The double wall tank does not require spill or secondary containment. A second foam concentrate tank or reserve concentrate supply is not required.

The foam proportioning must be by a single foam inductor for each foam-water riser. Inductor must, through a venturi, take concentrate and

SECTION 21 13 25.00 10 Page 5 proportion such concentrate into the flow steam reliably at the designed system flow rate. Inductor must be specifically tuned for the system required flow rate, inlet pressure, back pressure, concentrate type, proportioning ratio, and lift height (at the near empty tank level). The inductor must be equipped with the exact orifice at the entry of the foam pipe. Off the shelf pre-tuned generic model inductors are not permitted.

Shop drawings must be accompanied with an inductor datasheet fully annotated with the flow rate, inlet pressure, back pressure, and concentrate lift height (at the near empty tank level). Inductor will be fitted with a low loss bronze or brass check valve assembly by the manufacturer that is included in the device's hydraulic design.

An automatic flow control valve must be provided with trim package for electric releasing, remote re-setting, and opening/closing speed control.

Provide flow control vavle in accordance with UFC 4-211-01. In addition to automatic operation, arrange each valve for manual release at the valve.

Pressure gages and other appurtenances shall be provided at the flow control valve as required by NFPA 13 . All trim piping must be brass with compatible fittings. Trim piping must be factory configured and installed. The manual release for the flow control valve shall be installed no higher than 1.5 m above finished floor. Flow control valve provided must include the manufacturer's minimum pressure drop across the valve for the features indicated in UFC 4-211-01.

Prepriming of any foam solution piping is NOT acceptable. All solution piping must be slopped to be self-draining back to the riser. During commissioning, the responsible FPE must seal or otherwise install tamper proof guards on the pressure regulator adjusting stem and the two small globe valves on the speed control assembly. It is crucial these settings not be changed after commission; least the system may be impaired.

Safety-wire these devices in those positions and label them "DO NOT ADJUST". Any other trim valves which must be open or closed for the automatic flow control valve to function also must be safety wired in position.

Provide foam stop stations of the "dead-man" type. The stop stations must be used in conjunction with valves and equipment that will prohibit or stop the discharge of foam/water from the foam suppression system. The stations must have distinctive signage at each device. Provide a red mushroom type push button and include the word "PUSH". Colored portions of tamper cover must be blue and lettering on the cover must be "STOP"; the words "FIRE", "ALARM", or "AGENT" must not appear on the cover. A manual foam stop station will be provided at each manual foam releasing station. Once depressed, and so long as the button is held down, the stop station will prevent/stop discharge from the foam system regardless of whether or not the foam system was activated automatically or manually and whether or not the activation occurs prior to or after the stop station is pressed and held. Unless the foam system control panel (FSCP) has been reset and all activation alarms (manual and automatic) have been cleared; when the foam stop station button is released, the FSCP will instantaneously restore system operation and foam discharge. When the foam stop station button is depressed under full flow, the time to fully close the flow control valve will not exceed 15 seconds. The time for the flow control valve to fully open upon release of the foam stop station button will not exceed 5 seconds. Manual foam stop stations will be protected from mechanical damage and water infiltration (minimum NEMA 4). Manual foam stop stations will be provided with a clear plastic tamper cover that must be lifted prior to actuating the station. Conduits will enter the station back box from the bottom. Back box and conduits will not be placed in front of

SECTION 21 13 25.00 10 Page 6 signage, and a breather and drain (at the low point in the conduit) will be provided. Where manual stop stations and foam releasing stations are provided at an exit door, they will be located on opposite sides of doorway from fire alarm manual pull station. Where not located at an exit door opening, the manual stop stations and foam releasing stations will be located at least 1524 mm apart from the manual fire alarm pull station.

Provide two separate but adjacent 610 mm high by 508 mm wide metal signs.

There will be no more than 304 mm of separation between the two signs. The words "FIRE", "ALARM", or "AGENT" will not appear on these signs. The sign for the manual releasing station will have a yellow or lime-yellow background with "START FOAM SYSTEM" in red lettering not less than 76 mm high. The manual release station with tamper cover will be located on the lower center portion of the sign. The word "START" will be written in minimum 1 inch high green lettering placed directly above the activation station. The sign for the manual stop station will have a white background with a minimum 1/2 inch wide blue border with "STOP FOAM SYSTEM" in blue lettering not less than 3 inches high. The manual stop station with tamper cover will be located on the lower center portion of the sign. The word "STOP" will be written in minimum 1 inch high red lettering placed directly above the manual stop station.

FSCP FSCP must be Det-Tronics Eagle Quantum Premier Fire Detection/ Releasing System, must be furnished complete with Safety Systems Software (S3) configuration/logic programming/diagnostic tools software package including USB dongle key and RS232 cable. FSCP alarm, supervisory, and trouble signal reporting to the Fire Alarm Control Panel must be via discrete dry contact output points. Modular type panel installed in a surface mounted NEMA 4 painted steel cabinet with hinged door and cylinder lock. All detectors must be listed for use with that panel. IR detectors must be networked with the panel so that during commission IR detectors can be calibrated from the releasing panel. The FSCP must provide a real time display of current IR levels at any detector, have the ability to set the detector sensitivity for each detector from the panel, be able to download detector level log history, have remote test and diagnostics capability (manual self-test, lens dirty, sensor failure, power out of tolerance, device non-responsive), and remote setup and programing of detector options (lens heater power level, detector alarm LED function, alarm latching or non-latching, device address, sensitivity level, timing and gate count for alarm). FSCP must be electro-magnetic interference/radio frequency interference (EMI)/(RFI) tolerant and rated to SIL level 2 capability (IEC 61508), a safety assessment evaluation which evaluates critical fault paths, redundancies, and statistical measurement/prediction to ensure a specific level of long term reliable performance and stability to co-exist with aircraft radar systems.

Optical flame detection system shall be the X3301 Multi-spectrum IR Flame Detector manufactured by Det-Tronics and will use triple infrared (IR) flame detectors listed/approved for the expected fuel hazards in the hangar bay. The detectors will be immune to radar and radio frequency emissions.

Provide shielding for the detectors and their circuits from radio frequency interference. All circuiting from the FACP or FSCP to the detectors will be shielded, and shielding will be grounded at one end. A single optical flame detector alarm signal shall result in a latched fire alarm output to the fire alarm notification system. Any two optical flame detectors in alarm simultaneously shall result in a latched foam suppression release.

Detectors must be mounted in accordance with their listing at approximately 2440 mm above the finished floor of the hangar. The specifics for each design must take into account facility construction, type of aircraft, SECTION 21 13 25.00 10 Page 7 aircraft configuration and positioning, fixed and mobile equipment within the aircraft servicing area, and all other relevant factors. Do not mount optical detectors in inaccessible locations. The detectors will be angled and blinds will be provided such that the cone-of-vision does not extend more than 1524 mm outside the hangar bay. The horizontal and vertical axis of the detector determined during commissioning will be permanently marked on each detector. The optical flame detectors will be installed with 1524 mm of flexible conduit to allow for any minor adjustments during testing or changes in mission of the hangar. Provide a sufficient number of optical flame detectors such that a fire at any position within the hangar bay will be within the range and cone-of vision of at least two detectors. With the exception of a manual foam release station, the cross-zoning of two optical flame detectors in the hangar bay is required to release the foam suppression system.

Provide blue beacons not less than 400 cd (208/120VAC) powered from a dedicated emergency panel provided in accordance with UFC 3-520-01. The FSCP will control beacon initiation. A backup power supply or supervision of the power supply feeding the beacons is not required when fed from the dedicated emergency panel. Beacons will be mounted 6.1 m to 9.1 m above the floor of the hangar bay. Provide additional beacons where at least one beacon is not viewable from normally occupied areas of the hangar bay.

Design will take into account facility construction, type of aircraft, aircraft configuration and positioning, fixed and mobile equipment within the aircraft servicing area.

Provide a 2-position non-key operated switch located within the FSCP enclosure, that when activated disables the releasing function of all optical flame detectors in the hangar bay through programming at the FSCP.

When the switch is placed in inhibit mode, only the releasing functions of the optical flame detectors are disabled while leaving all other functions of the FSCP operational. Monitor the inhibit switch at the FSCP. Provide supervisory signal to the receiving station indicating the optical flame detectors are inhibited, a trouble signal is not permitted. Label the switch "INHIBIT OPTICAL FLAME DETECTION". Provide engraved labels on the inhibit switch indicating when the optical flame detectors are in "NORMAL" or "INHIBIT" mode.

Installing contractor shall ensure that all drawings of the FSCP and Flame Detectors must come from the manufacturer.

1.2.2 System Operation

The systems shall be designed to support the flow of all foam generators, plus the flow of the overhead system.

Actuation of two multi-spectrum IR detectors, or manual release shall cause the automatic water flow control valve to open, foam concentrate to drawn through the foam inductor from the atmospheric foam concentrate storage tank, and foam-water solution to be discharged from all foam generators of the respective system. Use of motor-operated valves is prohibited. Once activated, the system shall employ alarm components and a flow control valve such the system flow can be stopped and restarted by pressing and releasing dead-man type buttons located near the manual activation stations.

1.2.2.1 Related Systems

In addition, refer to the following sections for related work and

SECTION 21 13 25.00 10 Page 8 coordination:

Section 21 30 00 FIRE PUMPS

Section 28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM

1.2.2.2 Hose System

Hose systems including hose reels shall not be provided.

1.3 CONTRACTOR RESPONSIBILITIES

The Contractor is responsible for the full design, installation, testing, and acceptance of the high expansion foam system as required by this performance based specification. The drawings indicate general arrangement of piping, equipment, appurtenances, and other system components but are provided for "Information Only". The Contractor is solely responsible for selecting the quantity and location of foam generators to satisfy the performance requirements. The Contractor shall:

a. Verify that the selected equipment will perform as herein required or make all associated changes required to provide a complete operating system.

b. Provide shop drawings and detailed calculations showing that all components of the system proposed will meet the criteria required by these documents.

c. Follow the drawings except to make adjustments to accommodate the selected equipment and verified water supply. General deviations from these drawings will not be allowed just for the Contractor's convenience or preference.

d. Determine pipe and valve sizes by hydraulic analysis.

e. Design any portion of the foam system not shown on the foam system drawings.

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES.

A designation following the "G" designation identifies the office that will review the submittal for the Government.

"G" Designation shall include submission to Air Force Civil Engineer Center (AFCEC) and U.S. Army Corps of Engineers Middle East District (TAM) for final approval after review by qualified fire protection engineering retained by general contractor.

Submittal shall be a single package combined with the fire sprinkler system, fire pumps and tanks and include required criteria of NFPA 13 .

Partial submittals will be returned without review.

Via U.S. Postal Service:

U.S. Army Corps of Engineers

SECTION 21 13 25.00 10 Page 9

Middle East District ATTN: CETAM-EN-B (Dipert) P.O. Box 2250 Winchester, Virginia 22604-1450

Submittals to the AFCEC shall include the 4025(s) for the submittal and a packing slip including POC(Name, Phone Number, Title) for both the contractor and the USACE representative for the project. Packing slip shall list all submittals included in the submission.

Submittal shall also be submitted directly to AFCEC/East:

Judy Biddle, GS-13, DAF Mechanical & Fire Protection Engineer

HQ AFCEC/COSM

139 Barnes Drive, Suite 1 Tyndall AFB, FL 32403 judy.biddle.1@us.af.mil

SD-02 Shop Drawings

Six copies of the shop drawings, no later than 21 days prior to the start of system installation.

Detail drawings conforming to the requirements prescribed in NFPA 13 ; drawings shall be minimum 841 mm by 594 mm . Drawings shall include plan and elevation views which establish that the equipment will fit the allotted spaces with clearance for installation and maintenance. Each set of drawings shall include the following:

a. A descriptive index with drawings listed in sequence by number. A legend sheet identifying device symbols, nomenclature, and conventions used in the package.

b. Floor plans drawn to a scale not less than 1:100 clearly showing locations of devices, equipment, risers, electrical power connections, areas covered by each foam generator, and other details required to clearly describe the proposed arrangement.

c. Piping plan for each foam generator system. Each type of fitting used and the location of bushings, reducing fittings, and welded joints shall be identified.

d. Piping plan of the high-expansion foam concentrate system and details of all associated valves, fittings, and other components.

e. Location of control panels, multi-spectrum IR (infrared) flame detectors, manual stations, supervisory switches, dead-man style abort switches, solenoids, notification appliances, and other electrical devices. In addition, conduit routing and sizes, and the number of conductors contained in each shall be indicated.

Drawings reflecting the coverage area to prove the double coverage all the floor area shall be provided for the multi-sprectrum IR detection for each bay.

f. Equipment room layout drawings drawn to a scale of not less than 1:20 to show details of each system component, clearances

SECTION 21 13 25.00 10 Page 10 between each other and from other equipment and construction in the room.

g. Details of each type of pipe hanger, sway bracing for earthquake protection, foam inductors, foam generators and mounting details, high-expansion foam system control valve header and related components.

h. Connection drawings and control diagrams indicating overall electrical and mechanical operation of the high-expansion system.

This shall include identification and operation of each major component of the system. Diagrams shall be supplemented with a narrative description of the system. Point-to-point wiring diagrams shall indicate foam system control panel wiring and make and model of devices and equipment connected thereto.

As-built Drawings; G M

Submit as-built shop drawings on 20lb engineering bond, white, minimum 91% brightness and electronic in PDF, AutoCAD, and original drawing file formats, within 14 calendar days after successful completion of required testing. A separate set of approved submittal drawings of the overall system, marked up to indicate as-built conditions, shall be maintained on site. These drawings shall be maintained in a current condition at all times and shall be made available for review immediately upon request during normal working hours. Variations from the approved drawings, for whatever reason, including those occasioned by modifications, change orders, optional materials, and/or required for coordination between trades shall be indicated in sufficient detail to accurately reflect the as-built conditions.

SD-03 Product Data

Materials and Equipment

Manufacturer's catalog data for each separate piece of equipment proposed for use in the system. Data shall indicate the name of the manufacturer of each item of equipment, with data highlighted to indicate model, size, options, etc. proposed for installation.

In addition, a complete equipment list with equipment description, model number, and quantity shall be provided. This shall include the following:

a. Pipe, fittings, and mechanical coupings

b. FLow control valve

c. Valves, including gate, check, and globe

d. Pipe hangers and supports

e. Pressure switches

f. Foam concentrate storage tank

g. Proportioning equipment - foam inductor

h. Foam concentrate

SECTION 21 13 25.00 10 Page 11

i. Strainers

j. Laminated sign layout/graphics

k. Foam generators

l. Hydraulic surge suppressor

Spare Parts

Installer's Qualifications

Post-discharge Test Requirements

SD-05 Design Data

Hydraulic Calculations; G M

SD-06 Test Reports

Preliminary Test Report Procedures; G M

Preliminary Test Report; G M

Final Acceptance Test Report Procedures; G M

Final Acceptance Test Report; G M

SD-07 Certificates

Materials and Equipment

SD-10 Operation and Maintenance Data

Operation and Maintenance Manuals; G R

1.5 QUALITY ASSURANCE

Compliance with referenced NFPA standards is mandatory. This includes advisory provisions listed in the appendices of such standards, as though the word "shall" had been substituted for the word "should" wherever it appears. In the event of a conflict between specific provisions of this specification and applicable NFPA standards, this specification shall govern. Reference to "authority having jurisdiction" shall be interpreted to mean the Contracting Officer.

1.5.1 Fire Protection Specialist

Perform the work specified in this section under the supervision of and certified by the Fire Protection Specialist (FPS). Submit the name and documentation of certification of the proposed FPS, no later than 14 days after the Notice to Proceed and prior to the submittal of the sprinkler system shop drawings and hydraulic calculations. The Fire Protection Specialist shall serve as the project's Qualified Fire Protection Engineer. A Qualified Fire Protection Engineer is defined as an individual who has passed the fire protection engineering written examination administered by the National Council of Examiners for Engineering and Surveying (NCEES) and has relevant fire protection engineering experience.

SECTION 21 13 25.00 10 Page 12

The Qualified Fire Protection Engineer shall be an integral part of the design team, and must be involved in every aspect of the design and construction as it relates to fire protection for this project. The FPS shall prepare and submit a list of submittals related to Fire Protection from the Contract Submittal Register that verify the successful installation of the sprinkler systems(s), no later than 7 days after the approval of the FPS. The submittals identified on this list shall be accompanied by a letter of approval signed and dated by the FPS when submitted to the Government. The FPS shall be regularly engaged in the design and installation of the type and complexity of system specified in the Contract documents, and shall have served in a similar capacity for at least three systems that have performed in the manner intended for a period of not less than 6 months.

1.5.2 Installer's Qualifications

Work specified in this section shall be performed by the Sprinkler System Installer who is regularly engaged in the installation of the type and complexity of system specified in the contract documents, and who has served in a similar capacity for at least three systems that have performed in the manner intended for a period of not less than 6 months. Submit the name and documentation of certification of the proposed Sprinkler System Installer, concurrent with submittal of the Fire Protection Specialist Qualifications.

1.5.3 Foam System Testing

Details of method proposed for required tests for Preliminary and Final Acceptance, including step-by-step test procedures; list of equipment to be used; names, titles, and affiliations and qualifications of personnel who will participate in the tests; methods for protecting the facility and equipment during testing; means for containing the foam solution during discharge tests. Test plan shall include a drawing showing proposed number and arrangement of fire hoses and nozzles proposed for use in testing foam inductors. Blank forms the Contractor plans to use to record test results shall be included. See also section 3.7 of this specification for the additional information and requirements for testing requirements of the U.S. Army Corps of Engineers Center of Excellence.

Provide clean up and disposal plans to the Contracting Officer's Representative and Al Dhafra Air Base for approval. Plans are the sole responsibility of the Specialist.

1.6 EXTRA MATERIALS

Submit spare parts data for each different item of material and equipment specified. The data shall include a complete list of parts and supplies, with current unit prices and source of supply, and a list of parts recommended by the manufacturer to be replaced after 1 year and 3 years of service. Include a list of special tools and test equipment required for maintenance and testing of the products supplied by the Contractor.

1.7 PERFORMANCE REQUIREMENTS

Failure to achieve these requirements during acceptance testing will indicate a system failure. Contractor shall make modifications to obtain acceptable operations with no additional cost to the Owner.

SECTION 21 13 25.00 10 Page 13

Low-level high-expansion foam system must cover 90 percent of the aircraft silhouette area projected on the floor in one minute or less from the activation of manual foam discharge station. The area under engines extend beyond the wing edge and under rear elevators is not to be considered in the aircraft's silhouette area.

Low-level high-expansion foam systems must cover the aircraft servicing area and adjacent accessible areas to a depth of 1000 mm(3.2 feet) in four minutes or less.

The test shall start form the initiation of a manual foam pull station and shall include delay times such as FSCP control delay time, fire pump start delay time, foam solution transit time and fall time, etc.

1.8 CALCULATIONS

a. Provide a combined demand calculation of the high expansion foam system and the most hydraulically demanding area of the fire sprinkler system protecting the hangar bay. Theses demand calculations shall demonstrate the combined fire water demand does not exceed the available supply with the applicable safety factor applied at the fire pump outlet. Multiple calculations may be required to demonstrate the most demanding area has been met.

b. Provide a combined supply calculation of the high expansion foam system and the least hydraulically demanding area of the fire sprinkler system protecting the hangar. The least demanding area of the sprinkler system is typically the design area near the top of the system riser.

This design area shall be a nominal rectangle utilizing the shape factors of NFPA 13 for length along the branch line. This supply calculation shall not include a safety factor. The fire water flow calculated for the overhead system in this supply calculation shall be used for the high expansion foam breakdown factor. Velocity limits do not apply to supply calculations.

c. Provide a high expansion foam only supply calculation. Theses supply calculations shall not include the applicable safety factor. The results of these calculations shall establish the minimum foam concentrate storage. Velocity limits do not apply to supply calculations. Hydraulic calculations must include a minimum pressure drop across the automatic flow control valve of 69 kPa (10 psi), or the listed pressure drop, whichever is greater.

d. Provide foam spread calculations or diagrams showing the performance requirements to cover the plane silhouette are met for calculation 'a' above.

e. Provide a demand calculation of the most hydraulically demanding area for the fire sprinkler system in the shop/support areas. Multiple calculations may be required to demonstrate the most demanding area has been met.

PART 2 PRODUCTS

2.1 STANDARD PRODUCTS

Provide materials and equipment which are standard products of a manufacturer regularly engaged in the manufacture of such products and that essentially duplicate items that have been in satisfactory use for at least

SECTION 21 13 25.00 10 Page 14

2 years prior to project start date. Submit manufacturer's catalog data for each separate piece of equipment proposed for use in the system. Data shall indicate the name of the manufacturer of each item of equipment, with data highlighted to indicate model, size, options, etc. proposed for installation. In addition, provide a complete equipment list with equipment description, model number, and quantity and certificates from manufacturers to substantiate that components, equipment and material proposed for installation and use meet requirements as specified.

2.2 NAMEPLATES

Major components of equipment shall have the manufacturer's name, address, type or style, model or serial number, and catalog number on a plate permanently affixed to the item of equipment.

2.3 REQUIREMENTS FOR FIRE PROTECTION SERVICE

All equipment and material shall have been tested by Underwriters Laboratories, and listed in UL Fire Prot Dir or approved by Factory Mutual and listed in FM APP GUIDE. Where the terms "listed" or "approved" appear in this specification, such shall mean listed in UL Fire Prot Dir or FM APP GUIDE. The omission of these terms under the description of any item of equipment described shall not be construed as waiving this requirement.

2.4 PRESSURE RATINGS

Valves, fittings, couplings, proportioners, alarm switches, strainers, and similar devices shall be rated for the maximum working pressures that can be experienced in the system, but in no case less than.

2.5 ABOVEGROUND PIPING SYSTEMS FOR WATER OR FOAM/WATER SOLUTION

2.5.1 Pipe

Foam solution piping shall be balck steel schedule 40 pipe.

2.6 ABOVEGROUND PIPING SYSTEMS FOR HEF CONCENTRATE

2.6.1 Pipe

Pipe shall be standard weight stainless steel conforming to ASTM A312/A312M , Grade TP 304L. Foam concentrate pipe shall also be fitted with capped tee-fitting as surrogate foam concentrate test connection.

2.6.2 Fittings

Seamless socket weld type or flanged type fittings shall conform to ASTM A403/A403M , Grade WP 304L, and shall be compatible with the pipe.

Grooved type fittings and couplings shall be of Type 316 Stainless Steel conforming to ASTM A351/A351M .

2.6.3 Gaskets

Gaskets material shall be approved by the manufacturer for use with the foam concentrate.

SECTION 21 13 25.00 10 Page 15

2.6.4 Pipe Hangers

Hangers shall be listed in UL Fire Prot Dir or FM APP GUIDE and be of the type suitable for the application, construction and size pipe involved.

2.6.5 Control Valves

Valve shall be indicating type with full port ball and operating handle that indicates the on/off position of the valve. Unit shall be socket weld or flanged type. Valve body and ball shall be of 316 stainless steel complying with ASTM A351/A351M . The valve handle shall be provided with a suitable and substantial means for securing the valve open with a key-operated locking device. Valve must also be equipped with a tamper switch for electric supervision and labeled with permanent tags indicating normally open or closed.

2.7 AUTOMATIC WATER FLOW CONTROL VALVE ASSEMBLY (DELUGE VALVE)

Provide flow control valve meeting requirements of UFC 4-211-01. Valve shall be operated by a control system listed for releasing service and independent of the building fire alarm system. Flow control valve shall have the following features, electric release, remote resetting, speed control and pressure reducing trim packages or approved equal. Provide smoothly tapered connections where valve is a different size than riser.

In addition to automatic operation, arrange each valve for manual release at the valve. Provide pressure gages and other appurtenances at the flow control valve as required by NFPA 13 . All trim piping must be brass with compatible fittings. Trim piping must be factory configured and installed.

Gaskets shall be made of EPDM.

a. Water control valve must be an electrically actuated type. Valve must be re-settable without opening the valve. Electrical solenoid valve used to actuate the water control valve must be an integral component of the valve releasing control panel manufacturer. Solenoid valve must be of the normally closed, de-energized type, which opens when energized upon receipt of an electrical signal from the releasing control panel to which it is connected. Solenoid valves used with diaphragm-type valves must be rated for a maximum pressure differential of 175 psi. Electronic solenoids used for high expansion foam release must be listed for fire service applications and approved by the flow control valve manufacturer for use with the specific valve. Water control valve must be capable of recycling to the closed position at an adjustable speed. Assembly must be complete with the gauges and other required appurtenances. Flow control valve provided must include the manufacturer's minimum pressure drop across the valve for the features indicated by UFC 4-211-01.

b. Provide manufacturer's optional valve opening speed control. Flow control valves must gradually open upon receipt of power from the foam system releasing panel and must slowly close upon interruption of power. The time for the flow control valve to fully open upon release of the foam stop station button must not exceed 5 seconds. When the foam stop station button is depressed under full flow, the time to fully close the flow control valve must not exceed 15 seconds. Valve must be equipped with a pressure-reducing trim component.

2.8 BASKET STRAINER

Unit shall have cast iron flanged body and cover flanges. The strainer

SECTION 21 13 25.00 10 Page 16 basket shall be formed of perforated brass or stainless steel sheet with perforations. Assembly shall allow access to the strainer basket by removing the flange on the strainer.

2.9 HIGH EXPANSION FOAM LIQUID CONCENTRATE

Foam concentrate shall be approved for use with all selected components.

Concentrate shall be the product of one manufacturer and shall not contain PFOS/PFOA components. Concentrate shall have a minimum 20-year shelf life. Manufacture date shall be no more than six months before ship date to site. Mixing of non-identical brands of concentrate will not be permitted. Provide concentrate for primary tank based on the design as specified herein adequate to support not less than 15 minutes of continuous system discharge.

2.10 FOAM TANK

Foam Concentrate Storage Tank shall be a vertical, double-walled, high density cross-linked polyethylene storage tank. Tank capacity shall be the volume required to fully submerge the inductor dip tube plus the design volume to operate the foam generators for not less than 15 minutes of discharge at the hydraulically calculated waterflow rate at 130% of the nominal concentrate injection rate. There shall be no taps in the bottom or sides of the tank. Inductor dip tube(s) shall enter through the top of the tank. Provide a closeable fill opening and vent assembly. Permanently label each tank with its capacity, type and percentage of concentrate. The label must specifically identify the required concentrate manufacturer’s name, concentrate name, concentrate identifying product numbers/codes, concentrate manufacturer’s contact information including process to obtain 24-hour concentrate re-supply. The label must include a “Warning” indicating only this specific concentrate is permitted to be used in this system.

2.11 HIGH EXPANSION FOAM INDUCTOR

2.11.1 Proportioning Equipment

Foam proportioning shall be in accordance with UFC 4-211-01, by a single foam inductor per foam/water riser. Inductor shall be a model indicated by the potential manufacturers noted in UFC 4-211-01. Inductor shall, through a venturi, take concentrate and proportion such concentrate into the flow steam reliably at the designed system flow rate. Inductor shall be specifically tuned for the system flow rate, inlet pressure, back pressure, and concentrate lift height (at the near empty tank level). Off the shelf pretuned models are not permitted. Shop drawings shall be accompanied with an inductor datasheet fully annotated with the flow rate, inlet pressure, back pressure, inlet K-factor, and outlet K-factor to which the inductor will be calibrated. The inductor shall be elevated above the maximum fill level of the concentrate tank and have no automatic control valves in the concentrate line. Provide gauge cocks with oil-filled gauges (0-200 psi,

2.5 percent accuracy) a minimum of 610 mm before and after the inductor.

Provide permanent engraved rigid plastic or corrosion-resistant metal constructed label for each control device. A minimum of 10 pipe diameters of straight run of pipe shall be provided upstream and downstream of the inductor.

2.12 HYDRAULIC SURGE SUPPRESSOR

Furnish and install hydraulic surge suppressor for high-expansion foam

SECTION 21 13 25.00 10 Page 17 riser and each sprinkler system riser associated with the Maintenance Bay.

Each hydraulic surge suppressor shall have a minimum 10 gallon capacity.

Hydraulic surge suppressors are not required to be sized by the manufacturer as distances noted in UFC 4-211-01, Section 3-6.5.1 are not exceeded. Each hydraulic surge suppressor shall be seismically braced in accordance with NFPA 13.

The hydraulic surge suppressor shall be welded steel, constructed, tested in accordance with Section VIII, Division 1 of the ASME Code for a working pressure of 175 PSIG, factory pre-charged and field adjustable. All welds conforming to ASME Section IX. Must be UL (Underwriters' Laboratory) Listed and FM approved for use with Fire Protection Systems per NFPA 13.

2.13 HIGH EXPANSION FOAM GENERATORS

Water powered type; UL listed or FM Approved and listed for use with type of foam concentrate used.

Provide Ansul Jet-X-27 Foam Generators, or an equal item. For the purpose of this solicitation, an "equal" item must meet the following requirements:

produce at least 20,295 CFM of 2% foam while operating at a minimum of 40 psi 40psi, and capable of providing at least a 84 ft. diameter foam spread after 60 seconds of discharge. If the offeror proposes an equal item, its proposal must clearly identify the item by brand name (if any), and make/model number. In addition, the proposal must include descriptive literature such as illustrations, drawings, or a clear reference to previously furnished descriptive data or information available to the Contracting Officer, and clearly describe any modifications the offer plans to make in a product to make it conform to the solicitation requirements.

Generator discharge characteristics shall not result in any foam solution being discharged on aircraft fuselage and wing components from direct impingement or misting. Generator operations pressure shall be such that high pressure fittings and system components must not be required.

2.14 ALARM INITIATING DEVICES

2.14.1 Waterflow Pressure Alarm Switch

Pressure switch shall include a metal housing with a neoprene diaphragm, SPDT snap action switches and a 13 mm NPT male pipe thread. The switch shall have a maximum service pressure rating of 1207 kPa. There shall be two SPDT (Form C) contacts factory adjusted to operate at 28 to 55 kPa.

The switch shall be capable of being mounted in any position in the alarm line trim piping of the alarm check valve.

2.14.2 Foam Test Header

A foam test header shall be provided in the hangar bay within 6.1 m of an exterior door in accordance with UFC 4-211-01 . Refer to drawings for number of test header outlets and manifold sizing . Provide one 2 1/2-inch hose valve for each 375 gallons per minute of flow, rounding up. Control valves shall be provided at the point of connection to the system piping to isoloate the overhead system from the test header during testing. The isolation control valves shall be provided with valve tamper switches and be monitored by the releasing control panel in thier normal operating positions. The foam/water test system header and fire pump test header will be combined, as valving shall be provided to permit independent testing of each foam/water riser and each fire pump.

SECTION 21 13 25.00 10 Page 18

2.14.3 Foam System Control Panel

FSCP shall be Det-Tronics Eagle Quantum Premier Fire Detection/Releasing System, and no other and shall be furnished complete with minimum 60 node Safety Systems Software (S3) configuration/logic programming/diagnostic tools software package including USB dongle key and RS232 cable. FSCP alarm, supervisory, and trouble signal reporting to the Fire Alarm Control Panel shall be via discrete dry contact output points. Modular type panel installed in a surface mounted painted steel cabinet with hinged door and cylinder lock. Finish and lock shall match FACP. Switches and other controls shall not be accessible without the use of a key. The control panel shall be a neat, compact, factory wired assembly containing all parts and equipment required to provide specified operating and supervisory functions of the system. Panel cabinet shall be finished on the inside and outside with factory applied enamel finish. Provide main annunciator located on the exterior of the cabinet door or visible through the cabinet door. Provide audible trouble signal. Provide prominent engraved rigid plastic or metal identification plates, or silk-screened labels attached to the rear face of the panel viewing window, for all lamps and switches.

System power shall be 230 volts AC service, transformed through a two winding isolation transformer and rectified to 24 volts DC for operation of all system initiating, actuating, signal sounding, trouble signal and fire alarm tripping circuits. System shall be electrically supervised on all circuits. A ground fault condition or a single break in any circuit which prevents the required operation of the system shall result in the operation of the system trouble signal. Loss of AC power, a break in the standby battery power circuits, or abnormal AC power or low battery voltage shall result in the operation of the system trouble signals. The abnormal position of any system switch in the control panel shall result in the operation of the system trouble signals. Trouble signals shall operate continuously until the system has been restored to normal at the control panel. System trouble shall also be annunciated on the appropriate zone of the building fire alarm and mass notification control panel. The foam system manual releasing stations, abort stations, optical flame detectors, and all associated wiring shall be connected to and supervised by the releasing system control panel. System control panel shall be UL listed or FM approved for extinguishing system control (releasing device service).

Permanently label all switches. Provide panel with the following switches:

a. Trouble silencing switch which transfers audible trouble signals (including remote trouble devices, if provided) to an indicating lamp.

Upon correction of the trouble condition, audible signals will again sound until the switch is returned to its normal position, or the trouble signal circuit shall be automatically restored to normal upon correction of the trouble condition. The silencing switch may be a momentary action, self-resetting type.

b. Alarm silencing switch which when activated will silence all associated alarm devices without resetting the panel, and cause operation of system trouble signals.

c. Individual zone disconnect switches which when operated will disable only their respective initiating circuit and cause operation of the system and zone trouble signals.

d. Reset switch which when activated will restore the system to normal standby status after the cause of the alarm has been corrected, and all

SECTION 21 13 25.00 10 Page 19 activated initiating devices reset.

e. Lamp test switch.

f. System release disable switch to disable the releasing functions of the panel while leaving all detection and other functions of the panel operational. Activation of this switch must transmit a non latching supervisory alarm signal to the building fire alarm control panel.

Switch must be provided within a lockable control panel.

2.14.3.1 Primary Power Supply

Primary power and trouble alarm power to Control Panel shall be supplied from two 230 VAC circuits. Power to the control panel shall from the existing building electrical distribution panel. Panel shall be equipped with two 20 amp circuit breakers for each control panel and with key lock.

Circuit breakers shall be permanently marked "FOAM FIRE PROTECTION SYSTEM".

2.14.3.2 Emergency Power Supply

Emergency power shall be provided for system operation in the event of failure of the primary power supply and shall consist of rechargeable storage battery system.