452312
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
PROJECT TITLE: Large Aircraft Maintenance Hangar; Al Dhafra Air Base, United Arab Emirates (UAE)
The purpose of this Amendment 0001 is to revise (1) Pre-proposal Conference and Site Visit Information, (2) Specification and Draw ings, (3) Structural Interior Design (SID) (Appendix B), (4) Cover Sheets, (5) Section 00 73 00 Supplementary Conditions, Requirements for Issuance of Notice to Proceed (NTP), and (6) Include FAR Provision 52.222-56 Certification Regarding Trafficking in Persons Compliance Plan (Mar 2015).
See Continuation Page
1. CONTRACT ID CODE PAGE OF PAGES
1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 26-Apr-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912ER19R0001
X 9B. DATED (SEE ITEM 11)
01-Apr-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
26-Apr-2019
CODE
US ARMY CORPS OF ENGINEERS-CETAM-CT
MIDDLE EAST DISTRICT, CETAM-CT
PO BOX 2250
WINCHESTER VA 22604-1450
W912ER 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912ER19R0001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
CONTINUATION PAGE
Amendment 0001 to W912ER19R0001 Large Aircraft Maintenance Hangar; Al Dhafra Air Base, United Arab Emirates (UAE), has been revised as follows:
1. Pre-proposal Conference and Site Visit Information: A pre-proposal conference and a site visit will be conducted on April 30, 2019. An organized site visit has been scheduled for 1000 hours UAE time on 30 April 2019, at Al Dhafra Air Base, UAE. Personnel scheduled to attend the site visit will be picked up and transported via a U.S. Air Force bus from Al Dhafra Air Base Gate No. 1 at 1000 hours. Therefore, those who have requested base access should be at the gate between 0830 - 0900 hours to process through the building to obtain their temporary gate passes.
A pre-proposal conference is scheduled from 1400 to 1800 hours and will be held at the Pearl Rotana Hotel at Capital Centre, Abu Dhabi, UAE. Pearl Rotana is located at Capital Centre Al Khaleej Al Arabi At, Capital Centre Abu Dhabi, UAE. A webinar will take place for the pre-proposal conference at the hotel.
2. Specifications: Revised sections are replaced in their entirety. Revisions to the specification pages are shown on the pages in the following manner: New text is underlined and deleted text is shown using strikeout. The amendment number appears in the bottom margin on all pages of the new or revised sections.
The following have been revised/added:
Section 21 13 25.00 10 Paragraph 1.2.1, page 7 Paragraph 2.14.3, page 19
Section 28 31 76 Paragraph 2.4.1, page 15
Drawings: Drawings are not affected by this amendment.
Cover sheet of drawings replaced in its entirety.
(3) Structural Interior Design (SID) (Appendix B): SID binder Appendix B is deleted from the Solicitation package in its entirety.
(4) Cover Sheet: Cover sheet of the Solicitation has been changed to read as Volume 1 instead of Volume 2.
(5) Section 00 73 00 Supplementary Conditions, Requirements for Issuance of Notice to Proceed (NTP): The Requirements for Issuance of Notice to Proceed (NTP) has been replaced in its entirety to read as below:
Requirements for Issuance of Notice to Proceed (NTP)
The following contract requirements, (a) through (g) below, must be provided to the Contracting Officer and the Contract Specialist. No earlier deadline for meeting any requirement included herein is waived by this clause. The purpose of this clause is specifically to set forth prerequisites for issuance of Notice to Proceed.
FAILURE TO PROVIDE THE FOLLOWING ITEMS TO THE CONTRACTING OFFICER WITHIN TWENTY
(20) DAYS OF CONTRACT AWARD SHALL BE CONSIDERED A MATERIAL BREACH OF CONTRACT
AND COULD CAUSE THIS CONTRACT TO BE TERMINATED FOR DEFAULT. ANY TIME THE NOTICE
TO PROCEED IS DELAYED DUE TO THE CONTRACTOR’S FAILURE TO MEET ANY OF THE
REQUIREMENTS IN THIS CLAUSE SHALL BE DEDUCTED FROM THE CONTRACT PERIOD OF
PERFORMANCE.
(a) Signed acknowledgement of the Notice of Award. You must provide a complete and signed copy of the Notice of Award to the Contracting Officer.
(b) Proof of a valid DBA Insurance policy with Department of Labor’s (DOL) DBA insurance carriers for the Prime and all Subcontractors at every tier for performance of this contract. This is a contract requirement in accordance with FAR clause 52.228-3 “Worker’s Compensation Insurance (Defense Base Act)”. Proof of this insurance policy may be in the form of a paid invoice for DBA Insurance or an email from a DOL insurance carrier sent to the Contracting Officer.
(c) Provide original and fully executed performance and payment bonds supported by acceptable security in accordance with FAR Clause 52.228-15 PERFORMANCE AND PAYMENT BONDS--CONSTRUCTION. The Contracting Officer has not determined it to be impracticable to provide bonds from U.S. Treasury-listed sureties, so any commercial surety bonds used to meet this requirement must be issued by U.S. Treasury-listed sureties.
(d) Notice of Application of U.S. Criminal Jurisdiction. In accordance with DFARS clause 252.225-7995 “Contractor Personnel Authorized to Accompany U.S. Armed Forces Deployed Outside the United States”, you are required to notify any employee working on this contract who is a U.S. National about the overseas application of U.S. Criminal Jurisdiction. You must provide the Contracting Officer a copy of the “Notice of Application of U.S.
Criminal Jurisdiction” that you will provide to your employees. If you will not employ US Nationals on this contract, you must provide a statement of non-applicability to the Contracting Officer. Either the notice or statement of non-applicability shall be in the form of a memorandum on your company letterhead that has been signed by an authorized representative of your company.
(e) Travel Warning Notifications. In accordance with DFARS clause 252.225-7043 “Antiterrorism/Force Protection Policy For Defense Contractors Outside the United States,” you are required to provide antiterrorism/force protection awareness information (i.e. Travel Warnings) to all employees performing work under this contract. You must provide the Contracting Officer a copy of these travel warnings that you will issue to your employees on your company letterhead, which has been signed by an authorized representative of your company.
(f) Proof of SPOT entry of employees performing work under this contract. In accordance with DFARS clause 252.225-7995 “Contractor Personnel Performing in the United States Central Command Area of Responsibility”, you are required to record all personnel working under this contract in the Synchronized Pre-Deployment Operational Tracker (SPOT) system. The SPOT system is found at https://spot.dmdc.mil. This requirement is for all employees of the Prime and their Subcontractors at every tier of performance of this contract. You are required to input personnel into the SPOT system and maintain this data during the entire performance period of the contract.
If your company is not already registered in SPOT, Contractor company administrators should register for a SPOT account at https://spot.dmdc.mil; and the customer support team must validate user need. This process may take two business days. Company supervisors will be contacted to validate Contractor company administrator account requests and determine the appropriate level of user access. Once you are registered you must input at least five (5) personnel into the SPOT system. All employees assigned to the job under the contract should be entered as soon as possible and the list maintained in a current status whenever personnel changes occur.
When a contractor employee is required to have a visa to perform work in a particular country, the company must enter the visa details (visa number, expiration date, sponsor name, location where employee will perform work) into
SPOT.
(g) EFT Wire Transfer Form. If this is your first contract with the United States Corps of Engineers (USACE) Transatlantic Middle East District (TAM), you must complete the EFT Wire Transfer Form and return to the Contracting Officer. The EFT Wire Transfer Form will be provided per request. All contracts with USACE-TAM are paid by electronic funds transfer.
(End of Requirement)
(6) Included is the FAR Provision 52.222-56 Certification Regarding Trafficking in Persons Compliance Plan (Mar 2015) into the Solicitation. The certification is required by FAR 52.222-56 Certification Regarding Trafficking in Persons Compliance Plan (Mar 2015) prior to Award.