W912DW24B0Y1Y - Amendment 0006.pdf

PDF 392 KB Posted

Attached to
Repairs to McChord Bridge – Barnes Blvd
Solicitation number
W912DW24B0Y1Y
Issued by

About this file

This document is Amendment 0006 to Solicitation W912DW24B0Y1Y for the "Repair Barnes Blvd. Bridge (J84004)" project on Joint Base Lewis-McChord (JBLM) in Washington. The amendment updates the table of contents and provides several revised drawings as attachments, including updates to the telecom drawings and utility plans. It also clarifies that the period of performance was increased from 360 days to 580 days in a previous amendment, and that the bid due date remains unchanged at April 2, 2024. This is a 100% small business set-aside under NAICS code 237310, with an estimated contract value between $7.5 and $15 million. The solicitation is being issued by the Department of the Army Corps of Engineers, Engineering District Seattle.

View the file

Other files

File Type Posted
OF1419 Abstract of Bids for Barnes Blvd. Bridge Repairs (Signed).pdf PDF
Attachment 19 - Replacement Drawing TO-02 TELECOM SITE PLAN in Attachment 2.pdf PDF
Attachment 18 - Replacement Drawing TO-01 TELECOM LEGEND in Attachment 2.pdf PDF
W912DW24B0Y1Y Amendment 0004.pdf PDF
Attachment 14 - Replacement Drawing CU102 NEC Profile Details in Attachment 2 (Rev 1).pdf PDF
W912DW24B0Y1Y - Repair Barnes Blvd. - IFB Amendment 0006.pdf PDF
W912DW24B0Y1Y Amendment 0003.pdf PDF
W912DW24B0Y1Y Amendment 0002.pdf PDF
Attachment 20 - Replacement Drawing CU101 UTILITIES PLAN in Attachment 2.pdf PDF
W912DW24B0Y1Y Amendment 0001.pdf PDF
Attachment 7 - Barnes Blvd Temporary Bridge Detour Requirements and Details (Rev 1).pdf PDF
Attachment 1 - SPECIFICATIONS Revised Barnes Blvd Bridge McChord IFC 2024-03-15.pdf PDF
W912DW24B0Y1Y - Repair Barnes Blvd. - IFB Amendment 0005.pdf PDF
W912DW24B0Y1Y Amendment 0005.pdf PDF
Attachment 1 - SPECIFICATIONS Revised Barnes Blvd Bridge McChord IFC 2024-03-06.pdf PDF
W912DW24B0Y1Y Amendment 0004.pdf PDF
Attachment 16 - Replacement Drawing S 135 Utility Bridge Typical Section in Attachment 2 (Rev 1).pdf PDF
Attachment 17 - Replacement Drawing S-132 Pedestrian Rail Detail 1 in Attachment 2 (Rev 1).pdf PDF
W912DW24B0Y1Y - Repair Barnes Blvd - IFB Amendment 0004.pdf PDF
W912DW24B0Y1Y - Repair Barnes Blvd - IFB Amendment 0003.pdf PDF
W912DW24B0Y1Y Amendment 0003.pdf PDF
Attachment 17 - Replacement Drawing S-132 Pedestrian Rail Detail 1 in Attachment 2.pdf PDF
Attachment 16 - Replacement Drawing S-135 Utility Bridge Typical Section in Attachment 2.pdf PDF
W912DW24B0Y1Y Amendment 0002.pdf PDF
Attachment 15 - WADOT Aluminum Pedestrian Rail Details.pdf PDF
Attachment 1 - SPECIFICATIONS Revised Barnes Blvd Bridge McChord IFC 2024-02-21.pdf PDF
W912DW24B0Y1Y - Repair Barnes Blvd - IFB Amendment 0002.pdf PDF
Site Visit Sign-In Sheet - Repair Barnes Bridge.pdf PDF
Attachment 14 - Replacement Drawing CU102 NEC ProfileDetails in Attachment 2.pdf PDF
Attachment 10 - Utility Contacts Fees Responsiblities (Rev 01).pdf PDF
W912DW24B0Y1Y Amendment 0001.pdf PDF
W912DW24B0Y1Y - Repair Barnes Blvd - IFB Amendment 0001.pdf PDF
Attachment 1 - SPECIFICATIONS Revised Barnes Blvd Bridge McChord IFC 2024-02-09.pdf PDF
Attachment 3 - 2023-11-14 McChord Field Bridges Stormwater Drainage Plan (Rev 1).pdf PDF
Attachment 1 - SPECIFICATIONS Revised Barnes Blvd Bridge McChord IFC.pdf PDF
Attachment 5 - Stream Work to follow Nationwide USACE Permit 2021-NWP14-Enclosure-20220511.pdf PDF
Attachment 2 - 2023-11-17 100 Series - IFC Plans 11x17 (Rev 01).pdf PDF
Attachment 10 - Utility Contacts Fees Responsiblities.pdf PDF
Submittal Register - Barnes Blvd. Bridge Repairs.xlsx XLSX spreadsheet
Attachment 4 - 2021-12-22 McChord Geotech Bridge Foundation Report.pdf PDF
Attachment 13 - Revised PSE Utility Drawings.pdf PDF
Attachment 7 - Barnes Blvd Temporary Bridge Detour Requirements and Details.pdf PDF
Attachment 12 - FAA Form 7460-1 052026.pdf PDF
Attachment 11 - Draft Property Barnes Blvd 2021-10-12 Form DD 1354.pdf PDF
JA Brand Name - Repair Barnes Blvd Redacted.pdf PDF
W912DW24B0Y1Y - Repair Barnes Blvd - IFB.pdf PDF
Attachment 9 - 2021-11-11 McChord H-H Analysis Report.pdf PDF
Attachment 8 - Temp Stockpile Lining Diagram.pdf PDF
Attachment 6 - Standard Operating Procedures for use of Grays Army Airfield Borrow Source Pit.pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendment 0006 to Solicitation W912DW24B0Y1Y for project entitled, “Repair Barnes Blvd. Bridge (J84004)” on Joint Base Lew is-McChord (JBLM), Washington.

See Continuation Page for Amendment details.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 28-Mar-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DW24B0Y1Y

X 9B. DATED (SEE ITEM 11)

01-Feb-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 0 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

28-Mar-2024

CODE

USA ENGINEER DISTRICT, SEATTLE

ATTN: CENWS-CT

4735 EAST MARGINAL WAY SOUTH, BLDG. 1202

SEATTLE WA 98134-2388

W912DW 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DW24B0Y1Y

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

Amendment 0006:

The purpose of Amendment 0006 is to incorporate the following into Solicitation W912DW24B0Y1Y, for project entitled, “Repair Barnes Blvd. (J84004),)” on Joint Base Lewis-McChord (JBLM), Washington:

1. Update the Table of Contents to display revised/added attachment(s)

2. Provide the following updated/added attachments:

- Attachment 14 - Replacement Drawing CU102 NEC Profile Details in Attachment 2 (Rev 1)

- Attachment 18 - Replacement Drawing TO-01 TELECOM LEGEND in Attachment 2

- Attachment 19 - Replacement Drawing TO-02 TELECOM SITE PLAN in Attachment 2

- Attachment 20 - Replacement Drawing CU101 UTILITIES PLAN in Attachment 2

3. Update clerical error within block 11 of the 1442. Amendment 0004 increased the period of performance from

360 to 580 days, block 11 was not updated to reflect this change and is being done so with the issuance of Amendment 0006. Note: Amendment 0004 stated the period of performance changed from 300 days to 580 days. 300 days was inadvertently input within Amendment 0004 and should have stated a period of performance of 360 days to 580 days.

Note to Bidders: The due date for receipt of bids in response to this solicitation remains unchanged, with bids due 2 April 2024 at 10:00AM., the ProjNet window for questions will remain open for inquiries until the close of business on 26 March 2024.

All other terms and conditions of this Solicitation remain unchanged.

NOTICE TO BIDDERS: Bidders must acknowledge receipt of this amendment, and any previous amendments, by number and date on the Standard Form 1442, Back, Block 19.

SUMMARY OF CHANGES

SECTION 00 01 10 - TABLE OF CONTENTS

The following have been modified:

Section 00 10 00 Solicitation

- Contract Line Item Number (CLIN) Schedule

- Authority to Bind

Section 00 21 00 Instructions

- Provisions

Section 00 45 00 Representations and Certifications

- Pre-Award Information

Section 00 72 00 General Conditions

- Contract Clauses

Section 00 73 00 Supplementary Conditions

- Davis Bacon and Related Acts Wage Determination

Section 01 00 00 General Requirements

- Statement of Work Dated 11 January 2024

Submittal Register (PROVIDED UNDER SEPARATE COVER)

- 01 33 00_Submittal Register

Attachments (PROVIDED UNDER SEPARATE COVER)

- Attachment 1 - SPECIFICATIONS Revised Barnes Blvd Bridge McChord IFC 2024-03-15

- Attachment 2 - 2023-11-17 100 Series - IFC Plans 11x17 (Rev 01)

- Attachment 3 - 2023-11-14 McChord Field Bridges Stormwater Drainage Plan (Rev 1)

- Attachment 4 - 2021-12-22 McChord Geotech Bridge Foundation Report

- Attachment 5 - Stream Work to follow Nationwide USACE Permit 2021-NWP14-Enclosure-20220511

- Attachment 6 - Standard Operating Procedures for use of Grays Army Airfield Borrow Source Pit

- Attachment 7 - Barnes Blvd Temporary Bridge Detour Requirements and Details (Rev 1)

- Attachment 8 - Temp Stockpile Lining Diagram

- Attachment 9 - 2021-11-11 McChord H&H Analysis Report

- Attachment 10 - Utility Contacts Fees Responsibilities (Rev 01)

- Attachment 11 - Draft Property Barnes Blvd 2021-10-12 Form DD 1354

- Attachment 12 - Attachment 12- FAA Form 7460-1 052026

- Attachment 13 - Revised PSE Utility Drawings

- Attachment 14 - Replacement Drawing CU102 NEC Profile Details in Attachment 2

- Attachment 14 - Replacement Drawing CU102 NEC Profile Details in Attachment 2 (Rev 1)

- Attachment 15 - WADOT Aluminum Pedestrian Rail Details

- Attachment 16 - Replacement Drawing S 135 Utility Bridge Typical Section in Attachment 2 (Rev 1)

- Attachment 17 - Replacement Drawing S-132 Pedestrian Rail Detail 1 in Attachment 2 (Rev 1)

- Attachment 18 - Replacement Drawing TO-01 TELECOM LEGEND in Attachment 2

- Attachment 19 - Replacement Drawing TO-02 TELECOM SITE PLAN in Attachment2

- Attachment 20 - Replacement Drawing CU101 UTILITIES PLAN in Attachment 2

Attachment 14 - Replacement Drawing CU102 NEC Profile Details in Attachment 2 (Rev 1)

Attachment 14, bottom left of drawing, the following verbiage was added:

SEE DRAWING PAGE TO-04 FOR DUCT TRENCH DETAIL. REFER TO TELECOMMUNICATION

DRAWINGS TO-XX FOR ADDITIONAL INFORMATION.

ALL OUTSIDE PLANT (OSP) TELECOMMUNICATIONS INFRASTRUCTURE DESIGNS AND

INSTALLATION SHALL COMPLY WITH THE CRITERIA SPECIFIED IN THE I3A.

Attachment 14, bottom right of drawing, the TYPICAL TRENCH DETAIL diagram was removed.

Attachment 14, Profile Drawing, changed from:

New 38Y-312 ACCES VAULT RIM EL. = 278.3 FT.

TO:

New 38Y-612 ACCES VAULT RIM EL. = 278.3 FT.

The following attachments supersede their corresponding drawings within Attachment 2 - 2023-11-17 100 Series - IFC Plans 11x17 (Rev 01) (Upon award, a finalized version of Attachment 2 will be provided):

- Attachment 18 - Replacement Drawing TO-01 TELECOM LEGEND in Attachment 2

- Attachment 19 - Replacement Drawing TO-02 TELECOM SITE PLAN in Attachment 2

- Attachment 20 - Replacement Drawing CU101 UTILITIES PLAN in Attachment 2

SECTION 00 10 00 - SOLICITATION

The contractor period of performance end date has increased by 220 days from 360 days to 580 days.

(End of Summary of Changes)

File details come from the government source that posted it. Updated .