Bid Abstract 11 17 2022.xls

XLS spreadsheet 40 KB Posted

Attached to
8-Bed Level 1 Confinement Facility, Joint Base-MDL (McGuire AFB), New Jersey
Solicitation number
W912DS22B0021
Issued by

About this file

This document contains bid abstract information for an invitation for bids to construct an 8-bed confinement facility at Joint Base-MDL in New Jersey. The U.S. Army Corps of Engineers, New York District intends to issue an IFB seeking a firm-fixed price construction contract. Bids were due on November 17th, 2022 for construction of a 4,607 square foot single story, 8-cell facility including security fencing, lighting, a recreation area, site work and parking lot. The project also requires a generator hook-up, administrative area, visitation room, training room, waiting room, day room and all building utilities, communications, electrical, mechanical and fire protection systems. The period of performance is 540 calendar days from notice to proceed. The IFB will be restricted to a small business set-aside and have an estimated cost between $5-10 million.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1st Proposal

8-Bed Confinement Facility
W912DS22B0021 (6 Amendments)
Bid Opening Date: 17 November 2022
12345678910
CLINDESCRIPTIONIGEKLK ElectricDelta to IGEAll Aces Corp.Delta to IGENutmeg CompaniesDelta to IGERanco Const.Delta to IGEEastern Const.Delta to IGEIntercontinental Const.Delta to IGEMagnum Inc.Delta to IGEUSA Environmental Mgmt.Delta to IGEBenaka Inc.Delta to IGESand Point Svcs.Delta to IGE
Base Bid
0001All work (includes all plant, labor, and material) for the construction of 8-bed confinement facility as described in the plans and specifications except for work included in items below.$5,588,885$7,209,160$6,881,890$6,366,520$6,364,000$6,251,078$6,966,000$6,481,500$5,698,900$7,200,000$7,304,744
0002All work (includes all plant, labor, and material) for the site work, all work outside the five-foot line of the Confinement facility perimeter, excluding items below, as described in plans and specifications.$1,042,151$1,111,132$1,771,440$516,520$1,350,000$727,062$1,615,425$472,900$537,000$1,100,000$755,109
0003All work for the Final Record Drawing Submission (See Section 01 78 00).$30,000$30,000$30,000$30,000$30,000$30,000$30,000$30,000$30,000$30,000$30,000
0004All work (includes all plant, labor, and material) associated with construction of Parking Lot Expansion as described in the plans and specifications (Drw: CS-100)$185,136$91,176$165,079$113,520$227,000$165,331$188,100$101,600$135,000$180,000$94,736
0005All work (includes all plant, labor, and material) associated with adding prime coat on asphalt as described in the plans and specifications.$1,604$6,253$62,031$17,520$22,500$2,076$24,354$15,700$15,000$25,000$3,606
0006All work (includes all plant, labor, and material) associated with installing Manual (non-automatic) transfer switch.$37,850$100,040$15,850$27,520$99,000$58,708$54,000$25,000$25,000$40,000$26,740
0007All work (includes all plant, labor, and material) for procurement and Installation of backup Generator with Automatic Transfer Switch to include concrete pad, generator enclosure, grounding, as described in the plans and specification.$239,010$275,110$225,000$175,520$332,000$140,187$186,660$158,000$170,000$380,000$212,369
0008All work (includes all plant, labor, and material) for material cost of upsizing the Fire Protection Line and valves from 6 inch to 8 inch.$30,795$20,071$96,081$12,520$15,000$5,765$45,990$11,400$12,000$21,500$51,071
0009All work (includes all plant, labor, and material) for construction of walkway lighting along new pedestrian walkways as noted on Drw ES-101.$79,201$93,788$343,049$38,520$96,000$34,888$88,911$34,900$38,000$52,000$39,258
0010All work (includes all plant, labor, and material) for reduction in domestic water line connection as described in Note 10 on CU-100.-$11,546$12,505$79,097-$8,500-$9,000-$7,400$126,000-$10,300-$11,000-$15,300$11,695
0011All work (includes all plant, labor, and material) for purchase, delivery and installation of furnishings and equipment as outlined in the FF&E Package, except those items identified as included part of facility construction.$214,885$70,466$126,039$89,520$102,000$70,545$90,000$65,000$69,000$95,000$74,448
0012All work (includes all plant, labor, and material) for purchase, delivery and installation of electronic equipment (i.e. cameras, mounts, wiring) as outlined in “CLIN 0012 - Electronic Equipment SOW 8 Bed Confinement JBMDL,” except those items identified as included part of the confinement facility construction.$162,475$750,300$69,079$100,520$133,000$199,714$101,160$90,000$81,000$160,000$105,785
Total Base Bid Items (CLINs 0001 to 0003)$6,661,036$8,350,29225.36%$8,683,33030.36%$6,913,0403.78%$7,744,00016.26%$7,008,1405.21%$8,611,42529.28%$6,984,4004.85%$6,265,900-5.93%$8,330,00025.06%$8,089,85321.45%
Total Option Bid Items (CLINs 0004 to 0012)$939,410$1,419,70951.13%$1,181,30525.75%$566,660-39.68%$1,017,5008.31%$669,814-28.70%$905,175-3.64%$491,300-47.70%$534,000-43.16%$938,200-0.13%$619,708-34.03%
Total Base plus Option Items (CLINs 0001 to 0012)$7,600,446$9,770,00028.55%$9,864,63529.79%$7,479,700-1.59%$8,761,50015.28%$7,677,9541.02%$9,516,60025.21%$7,475,700-1.64%$6,799,900-10.53%$9,268,20021.94%$8,709,56114.59%

&C&"Arial,Bold Italic"* SOURCE SELECTION SENSITIVE * &C&"Arial,Bold Italic"* FOR OFFICIAL USE ONLY *&RPage &P of &N

File details come from the government source that posted it. Updated .