This document contains bid abstract information for an invitation for bids to construct an 8-bed confinement facility at Joint Base-MDL in New Jersey. The U.S. Army Corps of Engineers, New York District intends to issue an IFB seeking a firm-fixed price construction contract. Bids were due on November 17th, 2022 for construction of a 4,607 square foot single story, 8-cell facility including security fencing, lighting, a recreation area, site work and parking lot. The project also requires a generator hook-up, administrative area, visitation room, training room, waiting room, day room and all building utilities, communications, electrical, mechanical and fire protection systems. The period of performance is 540 calendar days from notice to proceed. The IFB will be restricted to a small business set-aside and have an estimated cost between $5-10 million.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1st Proposal
| 8-Bed Confinement Facility | ||||||||||||||||||||||
| W912DS22B0021 (6 Amendments) | ||||||||||||||||||||||
| Bid Opening Date: 17 November 2022 | ||||||||||||||||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | |||||||||||||
| CLIN | DESCRIPTION | IGE | KLK Electric | Delta to IGE | All Aces Corp. | Delta to IGE | Nutmeg Companies | Delta to IGE | Ranco Const. | Delta to IGE | Eastern Const. | Delta to IGE | Intercontinental Const. | Delta to IGE | Magnum Inc. | Delta to IGE | USA Environmental Mgmt. | Delta to IGE | Benaka Inc. | Delta to IGE | Sand Point Svcs. | Delta to IGE |
| Base Bid | ||||||||||||||||||||||
| 0001 | All work (includes all plant, labor, and material) for the construction of 8-bed confinement facility as described in the plans and specifications except for work included in items below. | $5,588,885 | $7,209,160 | $6,881,890 | $6,366,520 | $6,364,000 | $6,251,078 | $6,966,000 | $6,481,500 | $5,698,900 | $7,200,000 | $7,304,744 | ||||||||||
| 0002 | All work (includes all plant, labor, and material) for the site work, all work outside the five-foot line of the Confinement facility perimeter, excluding items below, as described in plans and specifications. | $1,042,151 | $1,111,132 | $1,771,440 | $516,520 | $1,350,000 | $727,062 | $1,615,425 | $472,900 | $537,000 | $1,100,000 | $755,109 | ||||||||||
| 0003 | All work for the Final Record Drawing Submission (See Section 01 78 00). | $30,000 | $30,000 | $30,000 | $30,000 | $30,000 | $30,000 | $30,000 | $30,000 | $30,000 | $30,000 | $30,000 | ||||||||||
| 0004 | All work (includes all plant, labor, and material) associated with construction of Parking Lot Expansion as described in the plans and specifications (Drw: CS-100) | $185,136 | $91,176 | $165,079 | $113,520 | $227,000 | $165,331 | $188,100 | $101,600 | $135,000 | $180,000 | $94,736 | ||||||||||
| 0005 | All work (includes all plant, labor, and material) associated with adding prime coat on asphalt as described in the plans and specifications. | $1,604 | $6,253 | $62,031 | $17,520 | $22,500 | $2,076 | $24,354 | $15,700 | $15,000 | $25,000 | $3,606 | ||||||||||
| 0006 | All work (includes all plant, labor, and material) associated with installing Manual (non-automatic) transfer switch. | $37,850 | $100,040 | $15,850 | $27,520 | $99,000 | $58,708 | $54,000 | $25,000 | $25,000 | $40,000 | $26,740 | ||||||||||
| 0007 | All work (includes all plant, labor, and material) for procurement and Installation of backup Generator with Automatic Transfer Switch to include concrete pad, generator enclosure, grounding, as described in the plans and specification. | $239,010 | $275,110 | $225,000 | $175,520 | $332,000 | $140,187 | $186,660 | $158,000 | $170,000 | $380,000 | $212,369 | ||||||||||
| 0008 | All work (includes all plant, labor, and material) for material cost of upsizing the Fire Protection Line and valves from 6 inch to 8 inch. | $30,795 | $20,071 | $96,081 | $12,520 | $15,000 | $5,765 | $45,990 | $11,400 | $12,000 | $21,500 | $51,071 | ||||||||||
| 0009 | All work (includes all plant, labor, and material) for construction of walkway lighting along new pedestrian walkways as noted on Drw ES-101. | $79,201 | $93,788 | $343,049 | $38,520 | $96,000 | $34,888 | $88,911 | $34,900 | $38,000 | $52,000 | $39,258 | ||||||||||
| 0010 | All work (includes all plant, labor, and material) for reduction in domestic water line connection as described in Note 10 on CU-100. | -$11,546 | $12,505 | $79,097 | -$8,500 | -$9,000 | -$7,400 | $126,000 | -$10,300 | -$11,000 | -$15,300 | $11,695 | ||||||||||
| 0011 | All work (includes all plant, labor, and material) for purchase, delivery and installation of furnishings and equipment as outlined in the FF&E Package, except those items identified as included part of facility construction. | $214,885 | $70,466 | $126,039 | $89,520 | $102,000 | $70,545 | $90,000 | $65,000 | $69,000 | $95,000 | $74,448 | ||||||||||
| 0012 | All work (includes all plant, labor, and material) for purchase, delivery and installation of electronic equipment (i.e. cameras, mounts, wiring) as outlined in “CLIN 0012 - Electronic Equipment SOW 8 Bed Confinement JBMDL,” except those items identified as included part of the confinement facility construction. | $162,475 | $750,300 | $69,079 | $100,520 | $133,000 | $199,714 | $101,160 | $90,000 | $81,000 | $160,000 | $105,785 | ||||||||||
| Total Base Bid Items (CLINs 0001 to 0003) | $6,661,036 | $8,350,292 | 25.36% | $8,683,330 | 30.36% | $6,913,040 | 3.78% | $7,744,000 | 16.26% | $7,008,140 | 5.21% | $8,611,425 | 29.28% | $6,984,400 | 4.85% | $6,265,900 | -5.93% | $8,330,000 | 25.06% | $8,089,853 | 21.45% | |
| Total Option Bid Items (CLINs 0004 to 0012) | $939,410 | $1,419,709 | 51.13% | $1,181,305 | 25.75% | $566,660 | -39.68% | $1,017,500 | 8.31% | $669,814 | -28.70% | $905,175 | -3.64% | $491,300 | -47.70% | $534,000 | -43.16% | $938,200 | -0.13% | $619,708 | -34.03% | |
| Total Base plus Option Items (CLINs 0001 to 0012) | $7,600,446 | $9,770,000 | 28.55% | $9,864,635 | 29.79% | $7,479,700 | -1.59% | $8,761,500 | 15.28% | $7,677,954 | 1.02% | $9,516,600 | 25.21% | $7,475,700 | -1.64% | $6,799,900 | -10.53% | $9,268,200 | 21.94% | $8,709,561 | 14.59% |