W912DS22B0003-0007 Port Monmouth.pdf

PDF 1 MB Posted

Attached to
Port Monmouth Hurricane and Storm Damage Reduction Project in Middletown Township, Monmouth County, New Jersey
Solicitation number
W912DS22B0003
Issued by

About this file

This solicitation is for a hurricane and storm damage reduction project in Middletown Township, New Jersey. The Army Corps of Engineers is seeking bids for construction services including building earthen levees and floodwalls, installing steel piles, performing load tests, installing erosion controls, and relocating utilities. The base bid scope covers work from stations 0+00 to 29+80, and there are options that could extend the work to other stations if awarded. Bids are due by June 16, 2022 and the contract completion date is 570 calendar days from notice to proceed, with additional days possible if options are exercised. Pricing must be provided for both the base bid and optional work.

View the file

Other files

File Type Posted
Bid Abstract 2022 08 09.pdf PDF
W912DS22B0003 Amendment 0012.pdf PDF
S-004.pdf PDF
Note to Bidders.pdf PDF
S-510.pdf PDF
C-101G.pdf PDF
W912DS22B0003 Amendment 0011.docx DOCX document
Amend 0010 Plans and Specs.pdf PDF
W912DS22B0003 Amendment 0010.pdf PDF
W912DS22B0003 Amendment 0009.pdf PDF
Bid Schedule attachment 1.pdf PDF
Plans and Specs - Amend 0009.pdf PDF
W912DS22B0003 Amendment 0008.pdf PDF
C-203.pdf PDF
C-511.pdf PDF
StandConstDetails 38.pdf PDF
C-203.pdf PDF
01 20 00.pdf PDF
01 50 00.pdf PDF
33 30 00.pdf PDF
01 14 00.pdf PDF
01 55 26.pdf PDF
W912DS22B0003 Amendment 0006.pdf PDF
Amendment 0005 Plans and Specs.pdf PDF
W912DS22B0003 Amendment 0005.pdf PDF
W912DS22B0003 Amendment 0004.pdf PDF
Amendment 0003 Attachment.pdf PDF
W912DS22B0003 Amendment 0003.pdf PDF
W912DS22B0003 Amendment 0002.pdf PDF
W912DS22B0003 Amendment 0001.pdf PDF
PRMT C5100 Submission 02182022.pdf PDF
W912DS22B0003.pdf PDF
Port Monmouth Contract 5 -RTA SPECS 2022-03-22.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

-- Revise and reissue the Bid Schedule -- Make changes to the Plans (Draw ings) -- Make changes to the Specif ications -- Respond to contractors' RFIs -- FOR INFORMATIONAL PURPOSES ONLY -- Move the bid opening date to 14 July 2022 at 2:00pm EST The Government's responses to contractors' other RFIs are currently being review ed and w ill be published on SAM.gov in the next amendments.

NOTE: Bidders must acknow ledge receipt of this amendment by the date specified in the solicitation (or as amended) by one of the follow ing methods: In the space provided on the SF1442, by separate letter, or by signing Block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH THE LATE BID, LATE

MODIFICATIONS OF BIDS OR LATE WITHDRAWAL OF BIDS (FAR 14.304).

1. CONTRACT ID CODE PAGE OF PAGES

1 74

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 24-Jun-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS22B0003

X 9B. DATED (SEE ITEM 11)

25-Mar-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

23-Jun-2022

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 16-300

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS22B0003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0007

Hurricane and Storm Damage Reduction Project Phase II – Contract 5

Port Monmouth, New Jersey

REVISED AND REISSUED BID SCHEDULE

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job

FFP

MOBILIZATION AND DEMOBILIZATION

FOB: Destination

PSC CD: Y1PZ

NET AMT

0002 1 Job

EARTHEN LEVEE

All work necessary to construct the earthen embankment levee between STA 9+90 to STA 29+80, including but not limited to the embankment, ramps, toe drain, and inspection trench, excavation and shoring, in accordance with the drawings and specifications, but not including Bid Items 0004.

0003 4,400 Linear

Foot

PILES (BUILDINGS)

All work necessary to furnish and install steel piles for buildings in accordance with the drawings and specifications, but not including Bid Items 0008-0011. The Contractor's equipment must be able to drive piles with lengths ranging from 50 feet to 100 feet.

ESTIMATED QUANTITY

0004 1 Job

PUMP STATION AND GENERATOR BUILDING

All work necessary to construct the pump station and generator building including foundation, utility connections, pumps, operations, electrical panels, oil tank distribution, 0005 1 Each

TEST PILES

All work necessary to furnish and install test pile sets consisting of two (one primary and one secondary) piles in each set but not including bid items 0006a, 0006b, and options 0008a and 0008b.

STATIC COMPRESSION LOAD TESTS

*****This line item is NOT PRICED and is for INFORMATIONAL PURPOSES only.

0006AA 1 Each

STATIC COMPRESSION LOAD TESTS FOR PRIMARY TEST PILES

All work to perform static compressive load tests for the primary test piles including calibration of the extensometers, load cell, and hydraulic jack; driving all reaction/support piling; placing and removing load frame for each test; placing and removing test loads and test equipment; extracting reaction or support piles;

backfilling pulled pile holes; submission of load test results/report; and all operations incidental thereto. The number of primary static compressive load tests is three for the entire project.

0006AB 1 Each

STATIC COMPRESSION LOAD TESTS FOR SECONDARY TEST PILES

All work to perform static compressive load tests for the secondary test piles including calibration of the extensometers, load cell, and hydraulic jack; driving all reaction/support piling; placing and removing load frame for each test; placing and removing test loads and test equipment; extracting reaction or support piles;

backfilling pulled pile holes; submission of load test results/report; and all operations incidental thereto.

0007 1 Job

BASE APPURTENANT ITEMS - (INCLUDINING BUT NOT LIMITED TO C3-

4 DRAINAGE STRUCTURE STA. 27+36.50)

All work necessary to construct the drainage swales with erosion control matting, stormwater outlet pipes including motorized sluice gate, concrete structure for the outlet and inlet of the pipes, and electric lines, manholes, manhole covers, removal and plugging of existing culvert and utility mains, clearing, grubbing and stripping, topsoil, planting and seeding, erosion and sediment control measures, levee cellular confinement system, levee and floodwall geotextile separator, and site restoration, in accordance with the drawings and specifications.

0008 1 Job

VIBRATION MONITORING OF STRUCTURES

All work necessary to monitor the vibration of structures, in accordance with the drawings and specifications. This CLIN applies to all vibration and monitoring in the Base.

0009 7 Each

JOB PILE DYNAMIC TESTS

All work for performing dynamic load tests for job piles including calibration of testing equipment; use of testing equipment; use of equipment used to apply the loading; wave equation analysis; CAPWAPC or similar analysis; submission of load test results/report; and all operations incidental thereto.

0010 1 Each

TEST PILE DYNAMIC TESTS FOR PRIMARY TEST PILES

All work for performing dynamic load tests for the test piles including calibration of testing equipment; use of testing equipment; use of equipment used to apply the loading; wave equation analysis; CAPWAPC or similar analysis; submission of load test results/report; and all operations incidental thereto.

0011 1 Each

TEST PILE DYNAMIC TESTS FOR SECONDARY TEST PILES

All work for performing dynamic load tests for the test piles including calibration of testing equipment; use of testing equipment; use of equipment used to apply the loading; wave equation analysis; CAPWAPC or similar analysis; submission of load test results/report; and all operations incidental thereto.

0012 1 Job

EROSION AND SEDIMENT CONTROL

All material and labor required to install erosion and sediment control protection measures including but not limited to silt fence, hay bales, catch basin filters, tree protection, construction entrance, cellular confinement system on the levees in accordance with the drawings and specifications. This CLIN applies to all erosion and sediment control measures in the Base.

LANDSCAPING

All material and labor required to retore all the disturbed area and vegetation along the levees including but not limited to seeding, mulching, planting in accordance with the drawings and specifications.

0013AA 9,150 Each

SHRUBS

All material and labor required for the placement and maintenance of shrubs in accordance with the project specifications and landscape plans.

0013AB 14.99 Acre

SEEDING

All material and labor required for the seeding, maintenance, and mowing of the seeding areas in accordance with the project specifications and landscape plans.

0013AC 2.86 Acre

HERBIVORY FENCE

All material and labor required for the fabrication, installation, and maintenance of a temporary herbivory fence around the cell perimeter of the restored planting areas in accordance with the project specifications and landscape plans.

PLANTING AREA

0014AA .37 Acre

DUNES NORTH OF PORT MONMOUTH RD. (FORMER CONTRACT 3

AREA)

All material and labor required for the seeding, maintenance, and mowing of the seeding areas in accordance with the project specifications and landscape plans.

0014AB .64 Acre

PLANTING AREA - SOUTH OF OLD PORT MONMOUTH RD. (FORMER

CONTRACT 3 AREA)

All material and labor required for the seeding, maintenance, and mowing of the seeding areas in accordance with the project specifications and landscape plans.

0014AC .63 Acre

PLANTING AREA - NORTH OF PUMP STATION (FORMER CONTRACT 2

AREA)

All material and labor required for the seeding, maintenance, and mowing of the seeding areas in accordance with the project specifications and landscape plans.

0014AD .10 Acre

SOUTH OF PUMP STATION (FORMER CONTRACT 2 AREA)

All material and labor required for the seeding, maintenance, and mowing of the seeding areas in accordance with the project specifications and landscape plans.

0015 1 Job

SURCHARGE FILL

All work necessary to construct the surcharge fill at STA 27+36.5, including but not limited to surcharge fill, temporary rerouting of existing sewer line, temporary drainage line, excavation, shoring, undercutting and replacement of 5 ft thick unsuitable material within the surcharge footprint with levee material, dewatering, geotextile installation, two settlement monitoring plates, surcharge fill compaction inspection, various relevant laboratory tests in accordance with the drawings and specifications

0016 1 Job

AS BUILTS

Contractor shall complete the “Record Drawing As-Builts" CAD submittal as required by Specification Section 01 78 00 CLOSEOUT SUBMITTALS for Record Drawings Files and for CAD standards and compliance requirements.

THIS CLIN IS NOT TO EXCEED $80,000.

OPTION OPTION 1

FFP

All material and labor required to construct from STA 1+20BA through STA 6+20BA. This option may be exercised within 18 months after Notice to Proceed of the Base Contract.

0017AA 1 Job

OPTION OPTION 1

FFP

VIBRATION MONITORING OF STRUCTURES

All work necessary to monitor the vibration of structures, in accordance with the drawings and specifications. This CLIN applies to all vibration and monitoring in Option 1.

0017AB 1 Job

OPTION OPTION 1

FFP

EROSION AND SEDIMENT CONTROL

All material and labor required to install erosion and sediment control protection measures including but not limited to silt fence, hay bales, catch basin filters, tree protection, construction entrance, cellular confinement system on the levees in accordance with the drawings and specifications. This CLIN applies to all erosion and sediment control measures in Option 1.

0017AC 1 Job

OPTION OPTION 1

FFP

CONSTRUCTION ELEMENTS

All other material and labor not captured in 0017AA and 0017AB required to construct from STA 1+20BA through STA 6+20BA.

OPTION OPTION 2

FFP

All material and labor required to construct from STA 29+80 through STA 37+30 and STA 0+00RR through STA 12+54RR. This option may be exercised within 18 months after Notice to Proceed of the Base Contract. If Option 2, CLIN 0018, is exercised, so will all subCLINs 0018AA through 0018AD.

0018AA 1 Job

OPTION OPTION 2

FFP

ROAD RAISING AND SHEET PILE RETAINING WALL

All work necessary to construct the road raising including the sheet pile retaining wall between STA 30+70 to STA 34+15 and between STA 4+80RR to STA 9+20RR, including but not limited to excavation, earthen fill, grading, underground utilities and its appurtenances, road pavement and its appurtenances

0018AB 1 Job

OPTION OPTION 2

FFP

EARTHEN LEVEE

All work necessary to construct the earthen embankment levee between STA 29+80 to STA 31+00 and STA 33+85 to STA 37+30, including but not limited to the embankment, ramps, toe drain, and inspection trench, excavation and shoring, in accordance with the drawings and specifications, but not including Bid Items 0004.

0018AC 1 Job

OPTION OPTION 2

FFP

VIBRATION MONITORING OF STRUCTURES

All work necessary to monitor the vibration of structures, in accordance with the drawings and specifications. This CLIN applies to all vibration and monitoring in Option 2.

0018AD 1 Job

OPTION OPTION 2

FFP

EROSION AND SEDIMENT CONTROL

All material and labor required to install erosion and sediment control protection measures including but not limited to silt fence, hay bales, catch basin filters, tree protection, construction entrance, cellular confinement system on the levees in accordance with the drawings and specifications. This CLIN applies to all erosion and sediment control measures in Option 2.

0018AE 1 Job

OPTION OPTION 2

FFP

UTILITY: AMERICAN WATER

All material and labor required to restore/relocate AMERICAN WATER owned utilities in accordance with the drawing C-102 and specifications.

0018AF 1 Job

OPTION OPTION 2

FFP

CONSTRUCTION ELEMENTS

All other material and labor not captured in 0018AA through 0018AD required to construct from STA 29+80 through STA 37+30 and STA 0+00RR through STA

12+54RR.

OPTION OPTION 3

FFP

All material and labor required to construct from STA 00+00 through STA 9+90.

This option may be exercised within 18 months after Notice to Proceed of the Base Contract. If Option 3, CLIN 0019, is exercised, so will all subCLINs 0019AA through 0019AN.

0019AA 1 Job

OPTION OPTION 3

FFP

FLOODWALL

All work necessary to construct the reinforced concrete T-wall between STA 0+00 and STA 9+75 including but not limited to concrete wall foundation, sheet pile cut-off wall, toe drain, excavation, shoring, dewatering, and backfill with satisfactory material in accordance with the drawings and specifications, but not including Bid Items 0001, 0003, and Option 0002a.

0019AB 24,000 Linear

Foot

OPTION OPTION 3

PILES (FLOODWALL)

All work necessary to furnish and install steel piles for floodwall in accordance with the drawings and specifications, but not including Bid Items 0008-0011. The Contractor's equipment must be able to drive piles with lengths ranging from 50 feet to 100 feet.

ESTIMATED QUANTITY

0019AC 2 Each

OPTION OPTION 3

FFP

TEST PILES

All work necessary to furnish and install test pile sets consisting of two (one primary and one secondary) piles in each set but not including bid items 0006a, 0006b, and options 0008a and 0008b.

0019AD 2 Each

OPTION OPTION 3

FFP

STATIC COMPRESSION LOAD TESTS FOR PRIMARY TEST PILES

All work to perform static compressive load tests for the primary test piles including calibration of the extensometers, load cell, and hydraulic jack; driving all reaction/support piling; placing and removing load frame for each test; placing and removing test loads and test equipment; extracting reaction or support piles;

backfilling pulled pile holes; submission of load test results/report; and all operations incidental thereto. The number of primary static compressive load tests is three.

0019AE 2 Each

OPTION OPTION 3

FFP

STATIC COMPRESSION LOAD TESTS FOR SECONDARY TEST PILES

All work to perform static compressive load tests for the secondary test piles including calibration of the extensometers, load cell, and hydraulic jack; driving all reaction/support piling; placing and removing load frame for each test; placing and removing test loads and test equipment; extracting reaction or support piles;

backfilling pulled pile holes; submission of load test results/report; and all operations incidental thereto. The number of secondary pile tests that will be performed are not fixed and are up to the discretion of the Contracting Officer. The quantity shown is the maximum number of tests that may be performed on the secondary piles.

0019AF 33 Each

OPTION OPTION 3

FFP

JOB PILE DYNAMIC TESTS

All work for performing dynamic load tests for job piles including calibration of testing equipment; use of testing equipment; use of equipment used to apply the loading; wave equation analysis; CAPWAPC or similar analysis; submission of load test results/report; and all operations incidental thereto.

0019AG 2 Each

OPTION OPTION 3

FFP

TEST PILE DYNAMIC TESTS FOR PRIMARY TEST PILES

All work for performing dynamic load tests for the test piles including calibration of testing equipment; use of testing equipment; use of equipment used to apply the loading; wave equation analysis; CAPWAPC or similar analysis; submission of load test results/report; and all operations incidental thereto.

0019AH 2 Each

OPTION OPTION 3

FFP

TEST PILE DYNAMIC TESTS FOR SECONDARY TEST PILES

All work for performing dynamic load tests for the test piles including calibration of testing equipment; use of testing equipment; use of equipment used to apply the loading; wave equation analysis; CAPWAPC or similar analysis; submission of load test results/report; and all operations incidental thereto.

0019AJ 82 Each

OPTION OPTION 3

FFP

SPLICING

All work necessary to splice steel piles within the Option 3 in accordance with the drawings and specifications.

0019AK 1 Job

OPTION OPTION 3

FFP

EARTHEN LEVEE

All work necessary to construct the earthen embankment levee between STA 9+30 to STA 9+95 including but not limited to the embankment, ramps, toe drain, and inspection trench, excavation and shoring, in accordance with the drawings and specifications, but not including Bid Items 0004.

0019AL 1 Job

OPTION OPTION 3

FFP

APPURTENANT ITEMS - C3-1 DRAINAGE STRUCTURE (STA. 5+45)

All work necessary to construct the drainage swales with erosion control matting, stormwater outlet pipes including motorized sluice gate, concrete structure for the outlet and inlet of the pipes, and electric lines, manholes, manhole covers, removal and plugging of existing culvert and utility mains, clearing, grubbing and stripping, topsoil, planting and seeding, erosion and sediment control measures, levee cellular confinement system, levee and floodwall geotextile separator, and site restoration, in accordance with the drawings and specifications.

0019AM 1 Job

OPTION OPTION 3

FFP

VIBRATION MONITORING OF STRUCTURES

All work necessary to monitor the vibration of structures, in accordance with the drawings and specifications. This CLIN applies to all vibration and monitoring in Option 3.

0019AN 1 Job

OPTION OPTION 3

FFP

EROSION AND SEDIMENT CONTROL

All material and labor required to install erosion and sediment control protection measures including but not limited to silt fence, hay bales, catch basin filters, tree protection, construction entrance, cellular confinement system on the levees in accordance with the drawings and specifications. This CLIN applies to all erosion and sediment control measures in Option 3.

0019AP 1 Job

OPTION OPTION 3

FFP

CONSTRUCTION ELEMENTS

All other material and labor not captured in 0020AA through 0020AN required to construct from STA 00+00 through STA 9+90.

0020 10 Each

OPTION OPTION 4

FFP

SPLICING

All work necessary to splice steel piles within the Base in accordance with the drawings and specifications. This option may be exercised within 18 months after Notice to Proceed of the Base Contract.

0021 2,750 Cubic

Yard

OPTION OPTION 5

CONTAMINATED NON-HAZARDOUS MATERIAL

All work for handling, transport, treatment, and off-site disposal of upland material exceeding NJDEP non-residential soil cleanup criteria and classified as contaminated non-hazardous (ID 27 Waste) suitable for landfill cover, roadway subbase and recycling facilities, complete. Quantities are estimated. This option may be exercised within 18 months after Notice to Proceed of the Base Contract.

ESTIMATED QUANTITY

0022 2,750 Cubic

Yard

OPTION OPTION 6

HAUL AND DISPOSE OF EXCESS OR UNSATISFACTORY MATERIAL AT

OFFSITE LOCATION

All work necessary to haul and dispose of excess or unsatisfactory material at an approved off-site location in accordance with the drawings and specifications.

Quantities are estimated. This option may be exercised within 18 months after Notice to Proceed of the Base Contract.

ESTIMATED QUANTITY

0023 1 Job

OPTION OPTION 7

FFP

LIABILITY INSURANCE

NJDEP, Monmouth County, and Middletown Township Liability Insurance. The amount bid will be the maximum amount payable. Actual payment will be based on actual costs up to bid amount. This option may be exercised within 90 days after Notice to Proceed of the Base Contract.

OPTION OPTION 8

FFP

STATIC TENSION LOAD TESTS If Option 8, CLIN 0024, is exercised, so will all subCLINs 0024AA through 0024AB.

0024AA 2 Each

OPTION OPTION 8

FFP

STATIC TENSION LOAD TESTS FOR PRIMARY TEST PILES

All work to perform static tension load tests for the primary test piles including calibration of the extensometers, load cell, and hydraulic jack; driving all reaction/support piling; placing and removing load frame for each test; placing and removing test loads and test equipment; extracting reaction or support piles;

backfilling pulled pile holes; submission of load test results/report; and all operations incidental thereto. The number of primary static tension load tests is two. These tests apply to Option 3 scope only. This option may be exercised within 18 months after Notice to Proceed of the Base Contract.

0024AB 2 Each

OPTION OPTION 8

FFP

STATIC TENSION LOAD TESTS FOR SECONDARY TEST PILES

All work to perform static tension load tests for the secondary test piles including calibration of the extensometers, load cell, and hydraulic jack; driving all reaction/support piling; placing and removing load frame for each test; placing and removing test loads and test equipment; extracting reaction or support piles;

backfilling pulled pile holes; submission of load test results/report; and all operations incidental thereto. These tests apply to Option 3 scope only. This option may be exercised within 18 months after Notice to Proceed of the Base Contract.

OPTION OPTION 9

UTILITY: VERIZON

0025AA 1 Job

OPTION OPTION 9

FFP

UTILITY: VERIZON

Utility provided material and labor required to retore/relocated Verizon owned utilities in accordance with the drawings and specifications including cable materials, cable placing and splicing, pole removal labor, conduit inspection during construction, and construction engineering. Contractor is to verify that the work is performed by an approved contractor. This option may be exercised within 18 months after Notice to Proceed of the Base Contract. Not to exceed allowance amoiunt of $175,000 to be included in bid as shown and not changed. Actual payment will be based on actual costs up to the not to exceed amount.

*****This CLIN is not to exceed $175,000.00.

0025AB 1 Job

OPTION OPTION 9

FFP

UTILITY: VERIZON

All Contractor material and labor required to retore/relocated Verizon owned utilities in accordance with the drawings and specifications. This option may be exercised within 18 months after Notice to Proceed of the Base Contract.

OPTION OPTION 10

FFP

COMCAST

0026AA 1 Job

OPTION OPTION 10

FFP

RE-ROUTE UTILITY: COMCAST

Utility material and labor required to retore/relocated Comcast owned utilities in accordance with the drawings and specifications. Contractor is to verify that the work is performed by an approved contractor. This option may be exercised within 18 months after Notice to Proceed of the Base Contract. Not to exceed allowance amoiunt of $20,000 to be included in bid as shown and not changed. Actual payment will be based on actual costs up to the not to exceed amount.

*****This CLIN is not to exceed $20,000.00.

0026AB 1 Job

OPTION OPTION 10

FFP

UTILITY: COMCAST

All Contractor material and labor required to retore/relocated Comcast owned utilities in accordance with the drawings and specifications. This option may be exercised within 18 months after Notice to Proceed of the Base Contract.

OPTION OPTION 11

FFP

UTILITY: JCP&L

0027AA 1 Job

OPTION OPTION 11

FFP

UTILITY: JCP&L

Utility material and labor required to retore/relocated JCP&L owned utilities in accordance with the drawings and specifications. Contractor is to verify that the work is performed by an approved contractor. This option may be exercised within 18 months after Notice to Proceed of the Base Contract. Not to exceed allowance amoiunt of $250,000 to be included in bid as shown and not changed. Actual payment will be based on actual costs up to the not to exceed amount.

*****This CLIN is not to exceed $250,000.00.

0027AB 1 Job

OPTION OPTION 11

FFP

UTILITY: JCP&L

All Contractor material and labor required to retore/relocated JCP&L owned utilities in accordance with the drawings and specifications. This option may be exercised within 18 months after Notice to Proceed of the Base Contract.

0028 0.79 Credit

OPTION OPTION 12

FFP

Wetland Mitigation Bank Credits

Purchase credits from a NJDEP approved wetland mitigation bank certified to sell credits in Watershed Management Area 12 for project impacts to freshwater wetlands. This option may be exercised within 6 months after Notice to Proceed of the Base Contract.

*****THIS LINE ITEM IS FOR 0.79 CREDIT.

0029 2 Each

OPTION OPTION 13

FFP

Portable Eye Wash Station

Purchase of specified equipment for the former Contract 2 facility. This option may be exercised within 18 months after Notice to Proceed of the Base Contract.

TOTAL BASE CLINs 0001-0016 $_______________

TOTAL OPTION CLINs 0017-0029 $_______________

TOTAL BASE AND OPTION CLINs 0001-0029 $_______________

Hurricane and Storm Damage Reduction Project Phase II – Contract 5

Port Monmouth, New Jersey

AMENDMENT 0007 for Port Monmouth Contract 5 Port Monmouth, NJ

TO BIDDERS:

The following changes shall be made to the drawings and specifications.

DRAWINGS:

1. The following DRAWINGS have been REVISED and REISSUED:

a. C-203

b. C-511

2. The following DRAWINGS have been REVISED but NOT REISSUED:

a. None

3. The following NEW DETAILS have been ADDED:

4. The following DRAWINGS have been DELETED:

SPECIFICATIONS:

1. The following SPECIFICATION SECTIONS have been ADDED and are provided in their entirety herein:

2. The following SPECIFICATIONS SECTIONS have been DELETED in their entirety:

3. The following SPECIFICATIONS SECTIONS have been REVISED and REISSUED:

a. 01 14 00

b. 01 20 00

c. 01 50 00

d. 01 55 26

e. 33 30 00

4. The following SPECIFICATIONS have been REVISED but NOT REISSUED:

a. None.

BIDDERS’ QUESTIONS AND GOVERNMENT REPLY:

(Questions that may be of general interest to all Bidders and/or the Government and that are not readily answered by the proceeding changes will appear below. These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question(s).

Questions and answers are issued to the bidders “For Information Only” and do not revise the solicitation, plans or specifications.)

Bidder Inquiry 01: Dwg C-101B: Water tap diameter and pipe size and material is needed.

Government Response: ¾” Type-L Copper pipe as shown on Detail 6 sheet C-507.

Bidder Inquiry 02: Dwg C-101C: Please indicate the sizes of the proposed elliptical pipe class IV (20LF and

216LF)

Government Response: The elliptical pipe shall be the same as coming from the road and shown on plan and the profile sheet 38”span x 24”rise. C-101C and C-203 shall be updated to show the size and class.

Bidder Inquiry 03: Dwg C-102:

a) Existing poles BT40988MDT and 216108-58450 (AKA BT40987) are to be removed by Contractor or by utility company.

b) What Option # the removal falls under. Same with the overhead utility associated with these two poles.

Government Response:

a) Pole removal is to be done by the owner, some of the poles are owned by either JCP&L or Verizon.

b) The poles fall in Option 2.

Bidder Inquiry 04: Dwg C-103: The note “Provide Cellular confinement system on both sides and on top of levee” appears to apply only to the base contract and the Option 2 areas. Please confirm.

Government Response: Concur, the cellular confinement system is on the levee which shall be constructed in Base and Option 2.

Bidder Inquiry 05: Dwg C-503, detail 4, Road Rising Cross sections: Please confirm if the existing asphalt pavement is to be removed.

Government Response: Yes, the existing pavement shall be removed. After pavement removal, the compaction of existing subgrade, placing fill, etc., should be done according to the project specifications.

Bidder Inquiry 06: Item No. 20, Option 4 – Splicing: Please point to the drawing sheet/ and details where this work is indicated.

Government Response: Field locations of pile splicing are to be coordinated with the COR during construction.

Bidder Inquiry 07: Please advise the bidders as to how the Government will be addressing the current and foreseeable volatile market conditions that are causing Force Majeure conditions for contractors who are incurring daily and weekly price increases on the types of materials and services that are major cost components for this project such as: Fuel, Trucking, Asphalt, Cement, Concrete, Steel, etc. The Government needs assure the Bidders that the Contractor for this project will be compensated for cost increases that can be documented and attributed to these unprecedented Force Majeure market conditions over which the Contractor has no control.

Government Response: The bids submitted shall be a firm fixed price bid.

Bidder Inquiry 08: Sheets C-509 and C-510 show a PZ22 Sheet Pile Cut-Off Wall under the Headwalls of Drainage Structure C3-1 & C3-4. The Cut-Off Wall details show a Tip Elevation of Minus 25 feet, which conflicts with the 10 foot depth that is also shown. Please clarify which is correct: the tip elevation or the 10’ depth.

Government Response: Sheets C-509 and C-510 have been corrected and will be issued in the upcoming Amendment 5.

Bidder Inquiry 09: Please confirm our interpretation that the costs of the Sheet Pile Cut-Off Walls are to be included in the price for Drainage Structure C3-1 and C3-4.

Government Response: Yes, the sheet pile cut off wall for the headwalls shall fall under the drainage structure. Cut off wall with levee or flood shall fall under the respective structure

Bidder Inquiry 10: Please note that the Headwalls shown on Sheet C-509 & C-510 cannot be Precast Concrete as detailed on those drawings, and these structures will need to be cast-in-place. Therefore, we request that the reference to a Precast Headwall be removed from those two drawings.

Government Response: The structures are permitted to be cast in place. The word precast in the section titles will be revised to read “concrete.”

Bidder Inquiry 11: Item 0017 - Option 1: Note stating that “This line item is NOT PRICED and is for INFORMATIONAL PURPOSES only.” Does it mean that none of the work shown on drawing C-101C and related, such as the swale excavation, headwall BA-1, manhole BA-1 among others are to be performed under this Contract? If that’s the case, it makes little sense for items 0017AA and 0017AB. Please confirm.

Government Response: All work from STA 1+20BA through STA 6+20BA is part of Option 1 of this contract. The Government will amend the bid schedule to add a CLIN 0017AC to bid on all other material and labor not included in 0017AA 0017AB required to construct from STA 29+80 through STA 37+30 and STA 0+00RR through STA 12+54RR.

Bidder Inquiry 12: In a related issue, there is a net amount blank field under option 17, does it mean that bidders have to enter an amount for this item in spite of the note cited above? This situation repeats itself through several bid items. Please clarify.

Government Response: Similar to the above response, an additional sub clin will be added to 0018 and 0019 to allow for bidding of all other material and labor not included in current sub clins.

Bidder Inquiry 13: Drawing C-101G: There is an note “End Retaining Wall” at Sta 34+15. Please provide cross sections and details of said retaining wall.

Government Response: Refer to Sheet C-205.

Bidder Inquiry 14: Soil analytics are needed for a proper characterization of the soil disposal per items 0021 and 0022. Please provide.

Government Response: CLIN 0021 and 0022 are for soil characterization found during construction which are not current captured in the boring reports.

Bidder Inquiry 15: Due to the significant and complex nature of the scope of the work on the project, the time required for contractor design of temporary works, and the time required to coordinate with specialty subcontractors and material suppliers, please provide an extension to the bid of at least three (3) weeks until May 17, 2022.

Government Response: Please see Amendment 4 extending bid opening to 16-JUN-22.

Bidder Inquiry 16: From the PDF document titled “W912DS22B0003.PDF” included in this Solicitation, please confirm that the SF 1442 (Pages 1 & 2 of 81), Section 00 10 00 (Pages 3 to 35 of 81), and Section 00 20 00 (Page 36 of 81) are “Provided by the Contracting Division” for inclusion in Section 00 10 00 of “Division 00 – Procurement and Contracting Requirements” of the “Specifications”.

Government Response: Yes.

Bidder Inquiry 17: From the PDF document titled “W912DS22B0003.PDF” included in this Solicitation, please clarify if Section 00 21 00 (Page 37 &38 of 81) is being “Provided by the Contracting Division” for inclusion in Section 00 21 16 of “Division 00 – Procurement and Contracting Requirements” of the “Specifications”.

Bidder Inquiry 18: The PDF document titled “W912DS22B0003.PDF” included in this Solicitation does not include a Section 00 22 10 as stated will be “Provided by the Contracting Division” for inclusion in Section 00 22 10 of “Division 00 – Procurement and Contracting Requirements” of the “Specifications”. Please confirm that Section 00 22 10 of the “Specifications” is not applicable to this Contract.

Government Response: Yes.

Bidder Inquiry 19: The PDF document titled “W912DS22B0003.PDF” included in this Solicitation does not include a Section 00 24 00 “Evaluation for Award” as stated will be “Provided by the Contracting Division” for inclusion in Section 00 24 00 of “Division 00 – Procurement and Contracting Requirements” of the “Specifications”. Please provide this specification section as it is critical to the preparation of the Contractor’s Bid.

Government Response: This Section 00 24 00 “Evaluation for Award” is intentionally not included in this solicitation as it is an Invitation for Bid (IFB) not a Best Value Trade Off (BVTO).

Bidder Inquiry 20: From the PDF document titled “W912DS22B0003.PDF” included in this Solicitation, please clarify if Section 00 70 00 (Page 44 to 70 of 81) and Section 00 73 00 (Page 71 of 81) are being “Provided by the Contracting Division” for inclusion in Section 00 72 00 of “Division 00 – Procurement and Contracting Requirements” of the “Specifications”.

Bidder Inquiry 21: From the PDF document titled “W912DS22B0003.PDF” included in this Solicitation, please clarify if Section 01 00 00 (Page 72 to 81 of 81) is being “Provided by the Contracting Division” for inclusion in Section 00 90 00 of “Division 00 – Procurement and Contracting Requirements” of the “Specifications”.

Bidder Inquiry 22: In Section 00 10 00 – Solicitation, there are no CLINs included in the Bidding Schedule for the work to be performed for Option 1 from STA 1+20BA to STA 6+20BA other than Vibration Monitoring and E & S Control. Please revise the Bidding Schedule to include the appropriate CLINs as it is critical to the preparation of the Contractor’s Bid.

Government Response: All work from STA 1+20BA through STA 6+20BA is part of Option 1 of this contract. The Government will amend the bid schedule to add a CLIN 0017AC to bid on all other material and labor not included in 0017AA 0017AB required to construct from STA 29+80 through STA 37+30 and STA 0+00RR through STA 12+54RR.

Bidder Inquiry 23: In Section 00 10 00 – Solicitation, many of the CLINs required to construct Option 2 are not included in the Bidding Schedule. Please revise the Bidding Schedule to include the appropriate CLINs as it is critical to the preparation of the Contractor’s Bid.

Government Response: Similar to the above response, an additional sub clin will be added to 0018 and 0019 to allow for bidding of all other material and labor not included in current sub clins.

Bidder Inquiry 24: The NJDEP DLRP Letter included in Section 00 31 24.01 indicates “A timing restriction from March 1 through June 30 is imposed on all in water work for each given year for the protection of anadromous species”. Please advise as to what specific features of work and what specific work areas on the site are considered to be “in water” (if any).

Government Response: Any channel that is inundated during the tide cycle will be subject to that restriction. These areas are the Proposed Outlet Swale C3-1OUT, the PROPOSED TRAPEZOIDAL PUMP STATOIN OUTLET SWALE, and the PROPOSED OUTLET SWALE C3-4.

Bidder Inquiry 25: The NJDEP Permit included in Section 00 31 46 indicates that the permittee shall submit proof of purchase for 1.70 mitigation credits if it is purchasing credits from a mitigation bank to satisfy a mitigation requirement. Its appears as though this is USACE’s strategy as evidenced by Item No. 0028 for Option

12. However, the in the Bidding Schedule is 1.04 Job. Please clarify the purpose and quantity for Item No. 0028.

Government Response: CLIN 0028 - Wetland Mitigation Bank Credits, has been revised to CLIN 0029.

The quantity has also been revised to .79 credits.

Bidder Inquiry 26: Please confirm that the Contract is Tax Exempt.

Government Response: The offeror's attention is directed to FAR 52.229-3, Federal State and Local Taxes. Determination of the applicability of taxes is the offeror's responsibility, and offerors are responsible for including all applicable taxes in their proposal. After award, the Contracting Officer may be able to assist with obtaining tax exempt certificates, however, assistance with provision of a form is not an assurance that the contractor will be able to purchase materials that are tax exempt.

Bidder Inquiry 27: Rightfully so, the NAICS Code for this Solicitation is 237990 – Other Heavy and Civil Engineering Construction. However, the Wage Rates included in Section 00 90 00 (or 01 00 00) of the Specifications via the PDF document titled “W912DS22B0003.PDF” indicates the Construction Type as “Heavy Dredging” and provides Wage Rates accordingly. Heavy Dredging is not applicable to this Contract. Therefore, Wage Rates should be provided for Heavy and Civil Engineering Construction such as Dockbuilders, Crane Operators, Excavator Operators, other Heavy Equipment Operators, Ironworkers, Carpenters, Laborers, Truck Drivers, etc. Please provide the appropriate Wage Rates for this Contract.

Government Response: Wage rates NJ20210058 are to be used for this contract, this has been corrected via Amendment 0002.

Bidder Inquiry 28: In Section 01 11 00 of the Specifications, are the Calendar Day durations listed for Options 1, 2, and, 3 (194, 305, and 336 Days) in addition to or included in the 570 Calendar Days required for Completion? Please advise as to when Contract Time will start for each Option and how the overall Contract Time will be calculated with each Option if all or some of the Options are awarded by USACE.

Government Response: Calendar Days for Options 1, 2, and, 3 (194, 305, and 336 Days) are from the exercise of each Option which may or may not be included in the base 570 Calendar Days.

Bidder Inquiry 29: Section 01 11 00 indicates that “development of permit applications” is a part of the work in the Project Description. No further detail or Specification is provided for “development of permit applications”. Please provide.

Government Response: All permits (other than environmental) needed to complete the construction of this scope shall be developed by the contractor (including but not limited to road opening permit, building permit, fuel oil tank permit, etc.)

Bidder Inquiry 30: In Section 01 14 00 Work Restrictions under “Special Scheduling Requirements”, 1.3(a) is left incomplete. Please provide the proper detail for this Specification.

Government Response: Section 01 14 00 paragraph 1.3.a will be revised as follows under Amendment 0006.

“The construction of the tie-in floodwall located at station xxxx 0+00 must be completed xx 180 days from the issuance/award of Option 3.”

Bidder Inquiry 31: Please confirm that all the Piles listed in the “Pile Schedule” Table on Plan Sheet S-004 for the Floodwall, Generator Building, Fuel Storage Tank, and Pump Chamber are all to be Measured and Paid under Base Bid Item No. 0003.

Government Response: Confirmed.

Bidder Inquiry 32: Please confirm that the entirety of the Traffic Control Plan as shown on Plan Sheet G-102 may be implemented for the Base Bid work and regardless of what Options (1, 2, or 3) may or may not be awarded by

USACE.

Government Response: Traffic Control Plan will be implemented on the Base and as necessary on the options as awarded. The entire Traffic Control Plan shall be prepared by the contractor within the specified window.

Bidder Inquiry 33: Please confirm that the entirety of the Soil Erosion and Sediment Control Plan as shown on Plan Sheet C-103 may be implemented for the Base Bid work and regardless of what Options (1, 2, or 3) may or may not be awarded by USACE.

Government Response: Soil Erosion and Sediment Control Plan will be implemented on the Base and as necessary on the options as awarded. The entire Soil Erosion and Sediment Control Plan shall be prepared by the contractor within the specified window.

Bidder Inquiry 34: Please confirm that the Staging Area adjacent to Port Monmouth Road as shown on Plan Sheet C-103 is available for the Contractor’s use for the Base Bid work and regardless of what Options (1, 2, or 3) may or may not be awarded by USACE.

Government Response: Confirmed.

Bidder Inquiry 35: Please provide an Existing Conditions Plan. It is difficult to see the existing topographic lines and survey notes on the Bid Document Plans Sheets.

Government Response: Please plan sheets 144 of 154 through 154 of 154 for the topographic/utility survey sheets.

Bidder Inquiry 36: Sheet C-205 shows the Road Raising Retaining Walls having a stepped top profile, yet, there is a fence to be mounted on the sheet cap. Is the intent to have a stepped series of fence panels?

Government Response: The fence shall follow the sheet pile profile. The height of the fence shall be from the top of the sheet pile as shown in the detail. Therefore, if the sheet pile steps, the fence shall step as well

Bidder Inquiry 37: The bid proposal for this contract includes numerous Optional Bid Items that cover a significant amount of work that may or may not be awarded, and the current wording allows the Government up to 18 Months to decide if the Optional Work will be awarded. Please be advised that this approach to awarding the Optional Work is not an acceptable contracting approach and it needs to be revised. The Government needs to provide the Contractor with a go/no-go decision on the Optional Work within 30 days of making an award of the base contact so that the Contractor and its Subcontractors can properly plan and schedule the work, and so that they can secure the necessary resources to execute the work. Also, the Government needs to recognize that the current unprecedented and volatile market conditions prevent most manufacturers, suppliers, trucking companies, and subcontractors from holding or forecasting their prices for more than a month, let alone 18 months. Therefore, it is extremely important for this issue to be promptly addressed, and we request that a revised bid proposal be issued ASAP to revise the Optional Work award language accordingly.

Government Response: To continue to move forward with this project, the current time to award options will not change. Please bid on the bid schedule options based on the allowable award timeframes.

Bidder Inquiry 38: With regard to Optional Item #0028 – Wetlands Mitigation Bank Credits, the current wording allows the Government to take up to 18 Months to decide if this Optional Item will be awarded. Please be advised that it is not possible for the Contractor to obtain firm pricing at bid time from Wetland Banks that would remain firm for that 18-month period of time. Therefore, we request that one of the two following revisions be made to the bid proposal: (a) either remove this Optional Work Item from the bid proposal, or (b) make the go/no-go decision on the award of this Optional Item within 30 days of making an award of the base contract

Government Response: The time to exercise this Optional Item #0028 – Wetlands Mitigation Bank Credits has been reduced to 6 months.

Bidder Inquiry 38: Please clarify the bidding quantity for Optional Item #0028 – Wetlands Mitigation Bank Credits. The bidding quantity is shown as 1.04, but the Unit is shown as “JOB”. We assume that the Unit is supposed to be “ACRE”. Please clarify.

Government Response: The unit is not ACRE but CREDIT.

Bidder Inquiry 39: Please note that the following bid items in the bid proposal contain the following wording “This line item is NOT PRICED and is for INFORMATIONAL PURPOSES only”. We find this language to be very confusing because each one of these bid items appears to cover work that should be priced-out, and each one of these bid items has space to under the Amount Column for pricing to be provided. Please issue a revised bid proposal ASAP to correct this confusing language so that the bidders know what should be done with these bid items.

0006 – Static Compression Load Tests 0013 – Landscaping 0014 – Planting Area 0017 – Work from STA 1+20BA to STA 6+20BA 0018 – Work from STA 29+80 to STA 37+30, etc.

0019 – Work from STA 00+00 to STA 9+90 0024 – Static Tension Load Tests 0025 – Reroute Verizon 0025AB – Reroute Verizon 0026 – Reroute Comcast

0027 – Reroute JCP&L

Government Response: The following CLINs are for informational purposes only and are not separately priced: 0006, 0013, 0014, 0017, 0018, 0019, 0024, 0025, 0026, and 0027. All bids shall be placed on the respective subCLINs.

CLIN 0025AB is a separately priced line item.

Bidder Inquiry 40: Optional Item #0023 that covers Liability Insurance. Please clarify the purpose of making Liability Insurance an Optional Bid and explain why it would take the Government up to 90 days to determine whether or not the Contractor needs to provide this insurance.

Government Response: The purpose is to provide exact pricing to the Non-Federal Sponsor for their insurance. The time to exercise this option is not for determining whether or not the Contractor needs to provide this insurance, this option may be exercised, instead it is the time provided to formally exercise the option.

Bidder Inquiry 41: Specification Section 00 24 00 “Evaluation Factors For Award”, part 1.1 states “to be provided by the Contracting Division”. No further information has been provided within this section. Please indicate what these factors will be.

Government Response: There are no evaluation factors for award, this is an Invitation for Bid.

Bidder Inquiry 42: Specification Section 01 11 00 “Scope of Work” part 1, paragraph 1.1a, states that the total contract time is 570 calendar days (19 months). If the Options are selected, they can be exercised within 570 calendar days of the NTP. Options 1, 2, and 3, if chosen, could require 6, 9 and 11 months respectively in order to complete. The last sentence of this section states that no additional days shall be added to the contract duration.

a. Please clarify whether the USACE can exercise the options within 570 calendar days from NTP per paragraph 1.1a, or within 18 months of NTP per subsection 1.4.

b. Regardless of either case, please confirm that in order not to exceed the 570 calendar days for completion, that Options 1 thru 3 would need to be exercised 13, 10, and 8 months respectively from the NTP.

Government Response: The last sentence of the referenced section which read ““No additional days will be added to the contract duration period” has been deleted under Amendment 05.

a. USACE can exercise the options within 570 calendar days from NTP, subsection 1.4 will be amended to state as such.

b. Calendar Days for Options 1, 2, and 3 (194, 305, and 336 Days respectively) are from the exercise date of each Option. which may or may not be included as part of the base 570 Calendar Days. The specifications statement “no additional days shall be added to the contract duration” shall be removed in an amendment to avoid confusion.

Bidder Inquiry 43: Traffic Control Spec 01.55.26, page 5, refers to Maintenance of Traffic using either…

This is the start of the file's text. The full file is on GovTribe.