About this file

This section specification outlines temporary construction facilities and controls requirements for the Port Monmouth Hurricane and Storm Damage Reduction Project in Middletown Township, Monmouth County, New Jersey. The specification requires the contractor to submit plans for a construction site plan, traffic control, haul roads, and cybersecurity compliance and to obtain permits from Monmouth County and Middletown Township. It also provides requirements for facilities, utilities, sanitation, safety, security, and cleanup for the contractor's use during the project schedule, as well as specifications for temporary signage, fencing, wiring, and backflow preventers. The government field office requirements include furnishing a lockable field office with specified equipment and services for use by the contracting officer.

View the file

Other files

File Type Posted
Bid Abstract 2022 08 09.pdf PDF
W912DS22B0003 Amendment 0012.pdf PDF
S-004.pdf PDF
Note to Bidders.pdf PDF
S-510.pdf PDF
C-101G.pdf PDF
W912DS22B0003 Amendment 0011.docx DOCX document
Amend 0010 Plans and Specs.pdf PDF
W912DS22B0003 Amendment 0010.pdf PDF
W912DS22B0003 Amendment 0009.pdf PDF
Bid Schedule attachment 1.pdf PDF
Plans and Specs - Amend 0009.pdf PDF
W912DS22B0003 Amendment 0008.pdf PDF
C-203.pdf PDF
C-511.pdf PDF
StandConstDetails 38.pdf PDF
C-203.pdf PDF
01 20 00.pdf PDF
33 30 00.pdf PDF
01 14 00.pdf PDF
01 55 26.pdf PDF
W912DS22B0003-0007 Port Monmouth.pdf PDF
W912DS22B0003 Amendment 0006.pdf PDF
Amendment 0005 Plans and Specs.pdf PDF
W912DS22B0003 Amendment 0005.pdf PDF
W912DS22B0003 Amendment 0004.pdf PDF
Amendment 0003 Attachment.pdf PDF
W912DS22B0003 Amendment 0003.pdf PDF
W912DS22B0003 Amendment 0002.pdf PDF
W912DS22B0003 Amendment 0001.pdf PDF
PRMT C5100 Submission 02182022.pdf PDF
W912DS22B0003.pdf PDF
Port Monmouth Contract 5 -RTA SPECS 2022-03-22.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PORTMONPIICT5 PORT MONMOUTH PHASE II, CONTRACT 5

Amendment 0007

SECTION 01 50 00

TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

11/20

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN WATER WORKS ASSOCIATION (AWWA)

AWWA C511 (2017) Reduced-Pressure Principle Backflow Prevention Assembly

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70 (2020; ERTA 20-1 2020; ERTA 20-2 2020; TIA

20-1; TIA 20-2; TIA 20-3; TIA 20-4)

National Electrical Code

NFPA 241 (2019) Standard for Safeguarding Construction, Alteration, and Demolition Operations

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

U.S. FEDERAL AVIATION ADMINISTRATION (FAA)

FAA AC 70/7460-1 (2016; Rev L; Change 2) Obstruction Marking and Lighting

U.S. FEDERAL HIGHWAY ADMINISTRATION (FHWA)

MUTCD (2009; Rev 2012) Manual on Uniform Traffic Control Devices

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Construction Site Plan ; G, RO

SECTION 01 50 00 Page 1 06/02/22

Traffic Control Plan ; G, RO

Haul Road Plan ; G, RO

Contractor Computer Cybersecurity Compliance Statements ; G, RO

Contractor Temporary Network Cybersecurity Compliance Statements ; G, RO

By-pass roadway plan ; G, RO

SD-07 Certificates

Backflow Tester Certification

Backflow Preventers Certificate of Full Approval

1.3 LAYOUT OF WORK

a. The plane of reference for elevations is in feet and referenced to the North American Vertical Datum (NAVD) of 1988. Grid System is in U.S.

survey feet and is the New Mercator State Plane Coordinate System (NAD83).

b. The Contractor will establish the following baselines and benchmarks at the site of the work: (Monuments and benchmarks as shown on the drawings).

c. From the baseline and benchmarks the Contractor must complete the layout of the work and must be responsible for all measurements that may be required for the execution of the work to the location and limit marks prescribed in the specifications or on the Contract drawings, subject to such modifications as the Contacting Officer may require to meet changed conditions or as a result of necessary modifications to the Contract work.

d. The Contractor must furnish, at his own expense, such stakes, templates, platforms, equipment, tools and material, and all labor as may be required in laying out parts of the work. It is the responsibility of the Contractor to maintain and preserve all stakes and other marks until authorized to remove them. If such marks are destroyed by the Contractor or through his negligence prior to their authorized removal, they may be replaced by the Contracting Officer, at his discretion. The expense of replacement will be deducted from amounts due or to become due to the Contractor. The Contracting Officer may require that work be suspended at any time when location and limit marks established by the Contractor are not reasonably adequate to permit checking of the work.

1.4 CONSTRUCTION SITE PLAN

Prior to the start of work, submit for Government approval a site plan showing the locations and dimensions of temporary facilities (including layouts and details, equipment and material storage area (onsite and offsite), and access and haul routes, avenues of ingress/egress to the fenced area and details of the fence installation. Identify areas which may have to be graveled to prevent the tracking of mud. Indicate if the use of a supplemental or other staging area is desired. Show locations of safety and construction fences, site trailers, construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas.

SECTION 01 50 00 Page 2

1.4.1 ACCESS AREA

Areas designated on the drawings as "Construction Entrance" must be used by the Contractor solely for access to and from the "Contractor Working Limits." The Contractor must arrange his use of these access areas to minimize interference with the property owners' (or user's) access or normal use.

1.4.2 Ingress and Egress

Areas designated on the drawings as "Construction Entrance" must be used by the Contractor solely for access to and from the "Contractor Working Limits." The Contractor must arrange his use of these access areas to minimize interference with the property owners' (or user's) access or normal use.

1.4.3 Existing Signage

Existing traffic signs and other traffic control devices within the project limits which are to remain must be protected from damage by construction operations. Items lost or damaged because of negligence on the part of the Contractor must be replaced. Should temporary relocation of such items be required because of construction operations, they must be placed as directed.

1.5 COORDINATION OF TRADES

a. The Contract drawings are in part diagrammatic and show the general arrangement of duct, piping, and other mechanical and electrical trades.

The Contractor must have a competent engineer on the project site to coordinate all fieldwork and shop drawings of the various trades prior to installation or submission of field or shop drawings for approval. The Contractor must allot spaces to the various trades prior to installation of the work. In spaces where all the various installations cannot be accommodated, the Contractor must notify the Contracting Officer and must submit alternate solutions as to its solution at no cost to the Government. The decision of the Contracting Officer must be final.

b. The Contractor must be responsible for the coordinated drawings of the various trades showing locations and sizes of all sleeves, electric outlets, inserts, piping, shafts, hangers, lights, ducts, catwalks, pads, chases, sprinklers, smoke detectors, soffits, fascias, steel trusses, etc. Composite signed-off coordinated shop drawings must be developed at 3/8" equals 1'-0 scale showing all mechanical, electrical work in hung ceilings and chases.

1.6 CONNECTION WITH WORK OF OTHER CONTRACTS

During this Contract, other contracts may be in force for the construction of other features of work on or adjacent to the site of work being accomplished under this Contract. The Contractor must arrange his plant and must schedule and perform the work to effectively cooperate with all other contractors and Government agencies. It is the Contractor's responsibility to know the extent of the limits of his Contract. No direct or extra compensation will be allowed on account of the cooperation required.

a. At all points of connection with work of other contracts, the Contractor must have weekly coordination meetings until all connections

SECTION 01 50 00 Page 3 have been completed with the adjoining Contractor (s) to ensure proper and timely connections.

b. Where the work under this Contract is completed before that of the adjoining Contractor, the Contractor must terminate his work in an approved manner ready for future connection by the adjoining Contractor.

Pipes and conduits must be closed with suitable caps or plugs that will prevent dirt or debris entry but are readily removable when final connections are made. For back-filled underground lines, approved type markers that extend above the ground surface must be provided to facilitate the future location of the lines by the adjoining Contract.

c. Where the work of the adjoining Contractor is already in place, the Contractor must perform all work required to effect the necessary connection, including locations of underground lines, removing of caps, providing necessary adapters or joining pieces, and all related incidental work for necessary for a proper, secure connection.

1.7 BACKFLOW PREVENTERS CERTIFICATE

1.7.1 Backflow Tester Certificate

Prior to testing, submit to the Contracting Officer certification issued by the State or local regulatory agency attesting that the backflow tester has successfully completed a certification course sponsored by the regulatory agency. Tester must not be affiliated with a company participating in other phases of this Contract.

1.7.2 Backflow Prevention Training Certificate

Submit a certificate recognized by the State or local authority that states the Contractor has completed at least 10 hours of training in backflow preventer installations. The certificate must be current.

1.8 DOD CONDITION OF READINESS (COR)

DOD will set the Condition of Readiness (COR) based on the weather forecast for sustained winds 50 knots ( 58 mph ) or greater. Contact the Contracting Officer for the current COR setting.

Monitor weather conditions a minimum of twice a day and take appropriate actions according to the approved Emergency Plan in the accepted Accident Prevention Plan, EM 385-1-1 Section 01 Emergency Planning and the instructions below.

Unless otherwise directed by the Contracting Officer, comply with:

a. Condition FOUR (Sustained winds of 58 mph or greater expected within 72 hours): Normal daily jobsite cleanup and good housekeeping practices. Collect and store in piles or containers scrap lumber, waste material, and rubbish for removal and disposal at the close of each work day. Maintain the construction site including storage areas, free of accumulation of debris. Stack form lumber in neat piles less than 3.3 feet high. Remove all debris, trash, or objects that could become missile hazards. Review requirements pertaining to "Condition THREE" and continue action as necessary to attain "Condition FOUR" readiness. Contact Contracting Officer for weather and COR updates and completion of required actions.

SECTION 01 50 00 Page 4

b. Condition THREE (Sustained winds of 58 mph or greater expected within 48 hours): Maintain "Condition FOUR" requirements and commence securing operations necessary for "Condition ONE" which cannot be completed within 18 hours. Cease all routine activities which might interfere with securing operations. Commence securing and stow all gear and portable equipment. Make preparations for securing buildings. Reinforce or remove formwork and scaffolding. Secure machinery, tools, equipment, materials, or remove from the jobsite.

Expend every effort to clear all missile hazards and loose equipment from general base areas. Contact Contracting Officer for weather and COR updates and completion of required actions. Review requirements pertaining to "Condition TWO" and continue action as necessary to attain "Condition THREE" readiness.

c. Condition TWO (Sustained winds of 58 mph or greater expected within 24 hours): Secure the jobsite, and leave Government premises.

d. Condition ONE. (Sustained winds of 58 mph or greater expected within 12 hours): Contractor access to the jobsite and Government premises is prohibited.

1.9 CYBERSECURITY DURING CONSTRUCTION

{For Reference Only: This subpart (and its subparts) relates to AC-18, SA-3, CCI-00258.} Meet the following requirements throughout the construction process.

1.9.1 Contractor Computer Equipment

Contractor owned computers may be used for construction. When used, Contractor computers must meet the following requirements:

1.9.1.1 Operating System

The operating system must be an operating system currently supported by the manufacturer of the operating system. The operating system must be current on security patches and operating system manufacturer required updates.

1.9.1.2 Anti-Malware Software

The computer must run anti-malware software from a reputable software manufacturer. Anti-malware software must be a version currently supported by the software manufacturer, must be current on all patches and updates, and must use the latest definitions file. All computers used on this project must be scanned using the installed software at least once per day.

1.9.1.3 Passwords and Passphrases

The passwords and passphrases for all computers must be changed from their default values. Passwords must be a minimum of eight characters with a minimum of one uppercase letter, one lowercase letter, one number and one special character.

1.9.1.4 Contractor Computer Cybersecurity Compliance Statements

Provide a single submittal containing completed Contractor Computer Cybersecurity Compliance Statements for each company using Contractor

SECTION 01 50 00 Page 5 owned computers. Contractor Computer Cybersecurity Compliance Statements must use the template published at http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs/forms-graphics-tables . Each Statement must be signed by a cybersecurity representative for the relevant company.

1.9.2 Temporary IP Networks

Temporary Contractor-installed IP networks may be used during construction. When used, temporary Contractor-installed IP networks must meet the following requirements:

1.9.2.1 Network Boundaries and Connections

The network must not extend outside the project site and must not connect to IP networks other than IP networks provided under this project or Government furnished IP networks provided for this purpose. Any and all network access from outside the project site is prohibited.

1.9.3 Government Access to Network

Government personnel must be allowed to have complete and immediate access to the network at any time in order to verify compliance with this specification.

1.9.4 Temporary Wireless IP Networks

In addition to the other requirements on temporary IP networks, temporary wireless IP (WiFi) networks must not interfere with existing wireless network and must use WPA2 security. Network names (SSID) for wireless networks must be changed from their default values.

1.9.5 Passwords and Passphrases

The passwords and passphrases for all network devices and network access must be changed from their default values. Passwords must be a minimum 8 characters with a minimum of one uppercase letter, one lowercase letter, one number and one special character.

1.9.6 Contractor Temporary Network Cybersecurity Compliance Statements

Provide a single submittal containing completed Contractor Temporary Network Cybersecurity Compliance Statements for each company implementing a temporary IP network. Contractor Temporary Network Cybersecurity Compliance Statements must use the template published at http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs/ forms-graphics-tables . Each Statement must be signed by a cybersecurity representative for the relevant company. If no temporary IP networks will be used, provide a single copy of the Statement indicating this.

PART 2 PRODUCTS

2.1 TEMPORARY SIGNAGE

2.1.1 Bulletin Board

Prior to the commencement of work activities, provide a clear weatherproof covered bulletin board not less than 36 by 48 inches in size for displaying the Equal Employment Opportunity poster, a copy of the wage

SECTION 01 50 00 Page 6 decision contained in the Contract, Wage Rate Information poster, Safety and Health Information as required by EM 385-1-1 Section 01 and other information approved by the Contracting Officer. Coordinate requirements herein with 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS. Locate the bulletin board at the project site in a conspicuous place easily accessible to all employees, and in location as approved by the Contracting Officer.

2.1.2 Project Identification Signs

The requirements for the signs, their content, and location are as specified in Section 01 58 00 PROJECT IDENTIFICATION. Erect signs within 15 days after receipt of the notice to proceed. Correct the data required by the safety sign daily, with light colored metallic or non-metallic numerals.

2.1.3 Warning Signs

Post temporary signs, tags, and labels to give workers and the public adequate warning and caution of construction hazards according to the EM 385-1-1 Section 04. Attach signs to the perimeter fencing every 150 feet warning the public of the presence of construction hazards. Signs must require unauthorized persons to keep out of the construction site.

Correct the data required by safety signs daily. Post signs at all points of entry designating the construction site as a hard hat area.

2.2 TEMPORARY TRAFFIC CONTROL

2.2.1 Haul Roads

Construct access and haul roads necessary for proper prosecution of the work under this Contract in accordance with EM 385-1-1 Section 04.

Construct with suitable grades and widths; avoid sharp curves, blind corners, and dangerous cross traffic. Submit haul road plan for approval. Provide necessary lighting, signs, barricades, and distinctive markings for the safe movement of traffic. The method of dust control, although optional, must be adequate to ensure safe operation at all times. Location, grade, width, and alignment of construction and haul roads are subject to approval by the Contracting Officer. Lighting must be adequate to assure full and clear visibility for full width of haul road and work areas during night work operations.

2.2.2 Barricades

Erect and maintain temporary barricades to limit public access to hazardous areas. Barricades are required whenever safe public access to paved areas such as roads, parking areas or sidewalks is prevented by construction activities or as otherwise necessary to ensure the safety of both pedestrian and vehicular traffic. Securely place barricades clearly visible with adequate illumination to provide sufficient visual warning of the hazard during both day and night.

2.2.3 Materials

Traffic control devices must conform to the design, materials, colors, fabrication, and installation requirements specified by NJDOT Specifications and the applicable specification as may be modified by this Section. Whether new or used, traffic control devices must be in good working condition and must be subject to approval. Reflective sheeting of

SECTION 01 50 00 Page 7 the encapsulated lens grade must be used on all devices requiring reflectorization.

2.2.4 ROADWAY MAINTENANCE

Existing and temporary pavements must be kept in good repairs using the same or materials compatible with the pavement. In general, plant-mixed bituminous concrete is suitable for all pavement surfaces. Other suitable materials may be used if approved.

2.3 FENCING

Provide fencing along the construction site and at all open excavations and tunnels to control access by unauthorized personnel. Safety fencing must be highly visible to be seen by pedestrians and vehicular traffic.

All fencing must meet the requirements of EM 385-1-1 . Remove the fence upon completion and acceptance of the work.

2.3.1 Polyethylene Mesh Safety Fencing

Temporary safety fencing must be a high visibility orange colored, high density polyethylene grid, a minimum of 48 inches high and maximum mesh size of 2 inches . Fencing must extend from the grade to a minimum of 48 inches above the grade and be tightly secured to T-posts spaced as necessary to maintain a rigid and taut fence. Fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection.

2.3.2 Chain Link Panel Fencing

Temporary panel fencing must be galvanized steel chain link panels 6 feet high. Multiple fencing panels may be linked together at the bases to form long spans as needed. Each panel base must be weighted down using sand bags or other suitable materials in order for the fencing to withstand anticipated winds while remaining upright. Fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection.

2.3.3 Post-Driven Chain Link Fencing

Temporary post-driven fencing must be galvanized chain link fencing 6 feet high supported by an tightly secured to galvanized steel posts driven below grade. Fence posts must be located on minimum 10 foot centers.

Posts may be set in various surfaces such as sand, soil, asphalt or concrete as necessary. Chain link fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection. Completely remove fencing and posts at the completion of construction and restore surfaces disturbed or damaged to its original condition. Locate and identify underground utilities prior to setting fence posts. Equip fence with a lockable gate. Gate must remain locked when construction personnel are not present.

2.4 TEMPORARY WIRING

Provide temporary wiring in accordance with EM 385-1-1 Section 11, NFPA 241 and NFPA 70 . Include monthly inspection and testing of all equipment and apparatus.

SECTION 01 50 00 Page 8

2.5 BACKFLOW PREVENTERS

Certificate of Full Approval from FCCCHR List, University of Southern California, attesting that the design, size and make of each backflow preventer has satisfactorily passed the complete sequence of performance testing and evaluation for the respective level of approval. Certificate of Provisional Approval is not acceptable.

Reduced pressure principle type conforming to the applicable requirements AWWA C511. Provide backflow preventers complete with 150 pound flanged cast iron, brass mounted gate valve and strainer, 304 stainless steel or bronze, internal parts.

PART 3 EXECUTION

3.1 EMPLOYEE PARKING

Construction Contract employees must park privately owned vehicles in an area designated by the Contracting Officer. Employee parking must not interfere with existing and established parking requirements at the project site.

The Contractor must not permit his employees to park their vehicles nor may he store equipment or materials adjacent to the traveled way or NJDOT rights-of-way where it may be a hazard to traffic. Normally, a clear distance of at least 30 feet from the edge of pavement must be kept free of such obstacles unless otherwise authorized.

Provide parking areas with adequate outdoor lighting in accordance with E.M. 385-1-1, TABLE 7-1. Provide a minimum of 15 vehicle parking spaces adjacent to the office with chain link fence enclosure and 2 gates for 12' electro/mechanical opening by electronic card reader at the gate (15 cards).

3.2 AVAILABILITY AND USE OF UTILITY SERVICES

3.2.1 Temporary Utilities

No utility services will be provided by the Government. The Contractor must provide in accordance with regulatory requirements at his expense.

3.2.2 Sanitation

Provide and maintain within the construction area minimum field-type sanitary facilities in accordance with EM 385-1-1 Section 02. Locate the facilities behind the construction fence or out of the public view. Clean units and empty wastes at least once a week or more frequently into a municipal, district, or station sanitary sewage system, or remove waste to a commercial facility. Obtain approval from the system owner prior to discharge into a municipal, district, or commercial sanitary sewer system. Penalties or fines associated with improper discharge will be the responsibility of the Contractor. Coordinate with the Contracting Officer and follow station regulations and procedures when discharging into the station sanitary sewer system. Maintain these conveniences at all times.

Include provisions for pest control and elimination of odors. Government toilet facilities will not be available to Contractor's personnel.

SECTION 01 50 00 Page 9

3.2.3 Telephone

Make arrangements and pay all costs for landline phone with full conferencing features.

3.2.4 Obstruction Lighting of Cranes

Provide a minimum of 2 aviation red or high intensity white obstruction lights on temporary structures (including cranes) over 100 feet above ground level. Light construction and installation must comply with FAA AC 70/7460-1 . Lights must be operational during periods of reduced visibility, darkness, and as directed by the Contracting Officer.

3.2.5 Fire Protection

Provide temporary fire protection equipment for the protection of personnel and property during construction. Remove debris and flammable materials daily to minimize potential hazards.

3.3 TRAFFIC PROVISIONS

3.3.1 Traffic Regulations

Highway ramps, crossings, approaches to crossings, and NJDOT and local rights-of-way used by the Contractor's equipment, must be kept clear of debris and excavated material resulting from the Contractor's operations.

Ramps must be constructed approaching and leaving the highway pavement.

The gross weight of each loaded vehicle using roadways and crossing must not exceed State and local limits. The roadway at the ramp and crossing sites must be restored to conditions existing before hauling operations started. If the highway pavement has been damaged as a result of the Contractor's operations, the pavement must be reconstructed to the proper line and grade in conformance with NJDOT Specifications .

3.3.2 Traffic Control Standards

Updated NJDOT Standard Specifications for Road and Bridge Construction, Section 159 Traffic Control and associated sections must also be considered as required and necessary.

3.3.3 Maintenance of Traffic

a. Conduct operations in a manner that will not close thoroughfares or interfere with traffic on railways or highways except with written permission of the Contracting Officer at least 15 calendar days prior to the proposed modification date, and provide a Traffic Control Plan for Government approval detailing the proposed controls to traffic movement for approval. The plan must be in accordance with State and local regulations and the MUTCD, Part VI. The Plan must be in written form and must indicate the type and location of all signs, lights, barricades, striping, and barriers to be used for safe passage of vehicular traffic through the project and for the protection of construction traffic and workers through the project, including traffic along levees, berms, and the borrow and disposal areas. The Plan must include specific details addressing ingress and egress at all access points with public right of way. The Plan must indicate conditions and setups for each phase of the Contractor's activities.

The Contractor must not begin work until the Plan has been approved.

Modifications to the Plan that become necessary must be submitted in

SECTION 01 50 00 Page 10 writing for approval. Modifications to the approved Plan cannot be implemented on the project until the Contractor submits and receives approval of such modification, except in an emergency. Contractor may move oversized and slow-moving vehicles to the worksite provided requirements of the highway authority have been met.

b. Conduct work so as to minimize obstruction of traffic, and maintain traffic on at least half of the roadway width at all times. Obtain approval from the Contracting Officer prior to starting activities that will obstruct traffic.

c. Provide, erect, and maintain, at Contractor's expense, lights, barriers, signals, passageways, detours, and other items, that may be required by the Life Safety Signage, overhead protection authority having jurisdiction.

d. Provide cones, signs, barricades, lights, or other traffic control devices and personnel required to control traffic. Do not use foil-backed material for temporary pavement marking because of its potential to conduct electricity during accidents involving downed power lines.

e. For roadway closures with appropriate temporary signs, provide a By-pass roadway plan .

f. During construction, the Contractor must provide a right-of-way for roads and intersecting access roads. In addition, the Contractor must provide temporarily relocated roads as necessary to provide the required right-of-way. The Contractor must maintain and protect traffic on existing adjacent roadways until the completion of the work along local streets connected to Campbell Avenue and Broadway, including Creek Road, Church Street, and Main Street, which may or may not be inclusive of project requirements. Temporary, limited additional lane closures are subject to approval of the submitted Traffic Control Plan and By-pass roadway plan and obtaining required permits in accordance with the paragraph of this Section titled PERMIT REQUIREMENTS. Traffic will be maintained continuously for the duration of the Contract and the traveling public must be protected from all damage to person and property. At least one lane of traffic must be maintained on either Campbell Avenue or Broadway at all times. The Contractor must develop temporary total closure to traffic and public access for the work areas at Campbell Avenue and Broadway subject to the traffic control plan as approved by the Contracting Officer. Campbell Avenue and Broadway cannot have total closure to traffic at the same time.

3.3.4 Protection of Traffic

Maintain and protect traffic on all affected roads during the construction period except as otherwise specifically directed by the Contracting Officer. Measures for the protection and diversion of traffic, including the provision of watchmen and flagmen, erection of barricades, placing of lights around and in front of equipment the work, and the erection and maintenance of adequate warning, danger, and direction signs, will be as required by the State and local authorities having jurisdiction. Provide self-illuminated (lighted) barricades during hours of darkness.

Brightly-colored (orange) vests are required for all personnel working in roadways. Protect the traveling public from damage to person and property. Minimize the interference with public traffic on roads selected

SECTION 01 50 00 Page 11 for hauling material to and from the site. Investigate the adequacy of existing roads and their allowable load limit. Contractor is responsible for the repair of damage to roads caused by construction operations.

Flagmen must be trained and certified by NJDOT, they must wear orange vest and helmets and operate the traffic in conformance with the procedure and requirements of NJDOT Specifications . Police traffic directors must be assigned according to the Middletown Township requirements and approved by the Contracting Officer.

ASSIGNMENT OF POLICE

TRAFFIC DIRECTOR, POC

NAME: LIEUTENANT HANSEN

TITLE: TRAFFIC BUREAU COMMANDER

ADDRESS: ONE KINGS HIGHWAY, MIDDLETOWN, NJ 07748

PHONE NUMBER: 732-615-2100 X 2045

3.3.5 construction signs

Provide, erect, maintain, move and remove signs as required and as directed to adequately and safely inform and direct the traveling public.

The number of signs indicated in the MUTCD, Part VI is a minimum, and the Contracting Officer may require additional signs. The Contractor must have an adequate quantity of these signs on hand prior to starting construction operations for use as required. Sign sizes and details must conform to the MUTCD, Part VI or standard models. Signs and markers must indicate actual existing conditions and must be moved, removed, relocated, or changed as directed. Signs must be kept clean and in good condition for the duration of the Contract. They must be mounted at the required height on the adequate supports and placed in proper position and alignment so as to give maximum visibility both day and night. During non-working hours and following the completion of a particular construction operation, all warning signs, except those required to remain for the safety of the public, must be removed or covered.

3.3.6 Rush Hour Restrictions

Do not interfere with the peak traffic flows preceding and during normal operations for more than 5 minutes without notification to and approval by the Contracting Officer.

3.3.7 Debris

The traveled way must be maintained free of foreign objects such as spilled earth, rocks, timber, and other items that may fall from transporting vehicles. Materials spilled by or dropped from vehicles used in the Contractor's hauling operations along or across public traveled way, both within and outside the project limits, must be removed immediately.

3.3.8 Dust Control

Dust control methods and procedures must be approved by the Contracting Officer. Coordinate dust control methods with 01 57 19 TEMPORARY

ENVIRONMENTAL CONTROLS.

3.4 PERMIT REQUIREMENTS

The Contractor is responsible for acquiring permits and paying fees required for portable variable message signs (VMS), road closure, or

SECTION 01 50 00 Page 12 opening from Monmouth County or Middletown Township. Point of contact (POC) information is provided below. No work must be commenced without an approved permit. Road opening permit required for Main St.,Port Monmouth Rd. and Brainard Ave. must be obtained from Monmouth County Middletown Township . The Contractor must allow a minimum of 30 calendar days from the date of a written application to receive permission to close the road.

MONMOUTH COUNTY POC NAME: ROBERT E. DICKERSON (HIGHWAY)

PHONE NUMBER: 732-431-6550 X7572

EMAIL: ROBERT.DICKERSON@CO.MONMOUTH.NJ.US

MIDDLETOWN TOWNSHIP POC NAME: TED MALONEY

PHONE NUMBER: 732-615-2259

EMAIL: TMALONEY@MIDDLETOWNNJ.ORG

3.5 PORTABLE VARIABLE MESSAGE SIGN (VMS)

Provide at least two portable variable message signs (VMS) during the construction phase. The COR/ACO must approve the location of the VMS signs. The VMS signs must be in accordance with NJDOT Specifications for Road and Bridge Construction, Division 1000-Equipment, Section 1001.02 Portable Variable Message Sign. Verify that the VMS signs are operating at all times and providing sufficient information to control and direct the vehicular traffic.

3.6 CONTRACTOR'S TEMPORARY FACILITIES

3.6.1 Administrative Field Offices

Provide and maintain administrative field office facilities within the construction area at the designated site. Government office and warehouse facilities will not be available to the Contractor's personnel.

In the event a new building is constructed for the temporary project field office, it must be a minimum 12 feet in width, 16 feet in length and have a minimum of 7 feet headroom. Equip the building with approved electrical wiring, at least one double convenience outlet and the required switches and fuses to provide 110-120 volt power. Provide a work table with stool, desk with chair, two additional chairs, and one legal size file cabinet that can be locked. The building must be waterproof, supplied with a heater, have a minimum of two doors, electric lights, a telephone, a battery-operated smoke detector alarm, a sufficient number of adjustable windows for adequate light and ventilation, and a supply of approved drinking water. Provide approved sanitary facilities. Screen the windows and doors and provide the doors with deadbolt type locking devices or a padlock and heavy-duty hasp bolted to the door. Door hinge pins must be non-removable. Arrange the windows to open and to be securely fastened from the inside. Protect glass panels in windows by bars or heavy mesh screens to prevent easy access. In warm weather, provide air conditioning capable of maintaining the office at 50 percent relative humidity and a room temperature 20 degrees F below the outside temperature when the outside temperature is 95 degrees F . Unless otherwise directed by the Contracting Officer, remove the building from the site upon completion and acceptance of the work.

3.6.2 Storage Area

Construct a temporary 6 foot high chain link fence around trailers and materials. Include plastic strip inserts, colored brown, so that

SECTION 01 50 00 Page 13 visibility through the fence is obstructed. Fence posts may be driven, in lieu of concrete bases, where soil conditions permit. Do not place or store trailers, materials, or equipment outside the fenced area unless such trailers, materials, or equipment are assigned a separate and distinct storage area by the Contracting Officer away from the vicinity of the construction site but within the municipality's boundaries. Trailers, equipment, or materials must not be open to public view with the exception of those items which are in support of ongoing work on the current day.

Do not stockpile materials outside the fence in preparation for the next day's work. Park mobile equipment, such as tractors, wheeled lifting equipment, cranes, trucks, and like equipment within the fenced area at the end of each work day.

Keep fencing in a state of good repair and proper alignment. Grassed or unpaved areas, which are not established roadways, and will be traversed with construction equipment or other vehicles, must be covered with a layer of gravel as necessary to prevent rutting and the tracking of mud onto paved or established roadways, should the Contractor elect to traverse them with construction equipment or other vehicles. Mow and maintain grass located within the boundaries of the construction site for the duration of the project. Grass and vegetation along fences, buildings, under trailers, and in areas not accessible to mowers must be edged or trimmed neatly.

3.6.3 Supplemental Storage Area

Upon request, and pending availability, the Contracting Officer will designate another or supplemental area for the use and storage of trailers, equipment, and materials. This area may not be in close proximity of the construction site but will be within the municipality's boundaries. Maintain the area in a clean and orderly fashion and secured if needed to protect supplies and equipment. Utilities will not be provided to this area by the Government. Coordination with local Government is required for approval.

3.6.4 Appearance of Trailers

a. Trailers must be roadworthy and comply with all appropriate state and local vehicle requirements. Trailers which are rusted, have peeling paint or are otherwise in need of repair will not be allowed on the project site. Trailers must present a clean and neat exterior appearance and be in a state of good repair.

b. Maintain the temporary facilities. Failure to do so will be sufficient reason to require their removal at the Contractor's expense.

3.6.5 Safety Systems

Protect the integrity of all installed safety systems or personnel safety devices. Obtain prior approval from the Contracting Officer if entrance into systems serving safety devices is required. If it is temporarily necessary to remove or disable personnel safety devices in order to accomplish Contract requirements, provide alternative means of protection prior to removing or disabling any permanently installed safety devices or equipment and obtain approval from the Contracting Officer.

3.6.6 Weather Protection of Temporary Facilities and Stored Materials

Take necessary precautions to ensure that roof openings and other critical

SECTION 01 50 00 Page 14 openings in the building are monitored carefully. Take immediate actions required to seal off such openings when rain or other detrimental weather is imminent, and at the end of each workday. Ensure that the openings are completely sealed off to protect materials and equipment in the building from damage.

3.6.6.1 Building and Site Storm Protection

When a warning of gale force winds is issued, take precautions to minimize danger to persons, and protect the work and nearby Government property.

Precautions must include, but are not limited to, closing openings;

removing loose materials, tools and equipment from exposed locations; and removing or securing scaffolding and other temporary work. Close openings in the work when storms of lesser intensity pose a threat to the work or any nearby Government property.

3.7 GOVERNMENT FIELD OFFICE

3.7.1 Resident Engineer's Office Requirements

a. The Contractor must furnish, prior to the start of work, a lockable field office and equipment for the use of the Contracting Officer.

b. A lease commercial office space is acceptable as the field office.

c. The office must be located in close proximity to the project site as directed by the Contracting Officer.

d. The following must be submitted for approval:

Equipment and Services:

No separate payment shall be made for providing the items below and all costs in connection therewith will be considered the obligation of the Contractor.

1. Office space shall be a minimum of 2,000 SF, with lockable interior doors. The space (if rented in a building) shall be in good condition. The office shall contain at least two operable windows with screens.

2. Two enclosed bathrooms with hot and cold water.

3. Two enclosed office of minimum dimensions of 12 feet x 12 feet. NJDEP State Inspector shall be allowed access to one of the office.

4. Partitioned open flat area to accommodate three (3) office cubicles and meeting area having a minimum of 1,400 SF.

5. Five office desks with lockable drawers (60 inches x 30 inches) laminated top and high-back cloth swivel chairs. NJDEP State Inspector shall be allowed access to one of the desk.

6. Four fire-proof, 4-drawer, legal-size lockable filing cabinets.

7. Two shelf sets, four-shelves high x 12 inches deep x 3 feet long (attachable to wall).

8. One 21" Color TV with basic cable service with the Weather Channel

SECTION 01 50 00 Page 15 included.

9. Wall TV swivel mount with outlet surge protector.

10. Three office conference tables, 2-1/2 feet by 8 feet with laminated top oval configuration.

11. Eight straight high back office chairs with wheels.

12. One bulletin board, 3 feet x 5 feet.

13. Four wastebaskets with supply of bags.

14. One vertical filing plan rack for twelve sets of E-size plans.

15. One drafting table for E-size drawings and chair.

16. Three office tables, 3 feet x 8 feet with laminated top.

17. Two coat racks.

18. One paper towel dispenser with towels.

19. One paper cup dispenser with cups.

20. One water cooler/heater with water.

21. Toilet facilities as specified.

22. One steel locking storage cabinet.

23. All structures installed under this paragraph FIELD OFFICE shall be provided with, as a minimum, the following services:

a. Lighting: electric light, non-glare types luminaries to provide a minimum illumination level of 50-foot candles at desk height level.

b. Heating and Cooling: adequate equipment to maintain an ambient air temperature of 70 degrees F +/- 3 degrees.

c. Window Blinds.

d. Potable bottled water- Provide sufficient supply of bottled 16.9oz water for field office.

e. Fire Extinguisher - Provide two : non-toxic, dry chemical, fire extinguishers meeting Underwriters Laboratories, Inc. approval for Class A, Class B and Class C fires with a minimum rating of 10A;

20B, 10C.

f. For each bathroom: power-ventilated, heated and complying with applicable sanitary codes including hot and cold running water and flush-type toilet.

g. 24-hour electronic security alarm system with direct feed to local police.

h. DSL or Cable Modem Service: Business DSL or cable modem service with all required equipment (modems, filters, Ethernet NIC cards, SECTION 01 50 00 Page 16 etc.) shall be provided for the entire duration of the contract.

DSL service shall be 940 Mbps downstream/ upstream. Service shall utilize a Static IP address for the connection. Contractor shall pay all costs associated with this service including ISP fees.

DSL or Cable Modem service shall be a 'dedicated' service, and this line shall not be shared with other Users (i.e., Contractors Field Office Trailer and USACE Field Office Trailer shall not utilize the same DSL or Cable Modem line via an Ethernet Switch/Hub). The Contractor shall provide and install all required equipment (i.e., Switch, Hub, Ethernet NIC Cards, modems, etc.)

for use with Government-furnished field office computers.

i. If contractor utilizes VHF or similar radio communication, provide base station and two (2) portable units on the Contractor's frequency, all with desk chargers.

j. The contractor shall be responsible for the monthly utility and telephone payment and installation cost of the above service and equipment.

k. The Contractor shall provide conference phone similar to Polycom VoiceStation 100 at his own expense.

l. The Contractor shall provide Bluetooth compatible speakers for use during all meetings and conference calls

m. Janitorial services on a daily basis including, but not limited to, sweeping, emptying baskets, weekly mopping, dusting all surfaces, servicing of toilets and washing and waxing floors, cleaning all windows (inside and out) and re-supply of paper goods and soap.

o. Snow and ice removal in the vicinity of the field office may be required during and after storm events.

24. Sufficient supply of electrical outlets meeting NEC code for residential construction.

25. First Aid Kit: Provide two kits. As a minimum, each kit shall include antiseptic kit, eyewash solution, bandages, insect sting medication, aspirin and acetaminophen, and cold pack, and at the minimum shall conform to ANSI Z308.1

26. The field office shall be removed from the project site when and as directed by the Contracting Officer. Secure the trailer complex by an 8- foot high chain link fence topped by 3 rows of barb wire. The secured area shall be able to accommodate at least 15 vehicles.

Provide a lockable gate with the fence and security lighting in the trailer complex.

27. Provide one (1) Combination Smoke/Carbon Monoxide Alarm with battery back-up.

28. Provide two vehicles with 4-wheel drive, less than 3 years old (minimum 6 passengers) with gas cards sufficient to cover the duration of the project for Government’s official use.for Government's use.

Maintenance of the vehicles including all fuel, insurance, registration, and fuel and maintenance of the vehicle including State Inspections shall be the contractor’s responsibility.

SECTION 01 50 00 Page 17

29. Printer: Provide two Laserjet Printers with 10,000 sheets of 8-1/2 11 laser-type print paper. Must have at minimum 2 Hi-Speed USB 2.0 Host; 1 Hi-Speed USB 2.0 Device; 1Ethernet 10/100 Base-TX network; 1 RJ-11 modem port; 802.11 b/g/n Station; 802.11 b/g Access Point.

Replacement ink Cartridges shall be supplied as needed.

30. Digital Camera: Digital Camera: Provide two Black 12 MP 4X Optical Zoom Waterproof Shockproof Wide Angle Digital Camera HDTV Output, 028 to 105 zoom compact with propriety software established to be legal court documents with case, spare battery and memory card, computer interface and program and desk charger. It is necessary to have one

(1) camera per field office.

31. Copier: One heavy duty, digital dry process photocopying machine, with auto document feeder, sorter, collator, enlarging/reduction ability, 8.5 x 11, 8.5 x 14 and 11 x 17 paper trays and adequate supply of copy paper and printing supplies. The supply of copy paper shall be replenished by the Contractor regularly as required by the Contracting Officer.

32. Telephone: Two telephones: one for phone service and one for fax service. Telephone shall be capable of conference calling and have two lines with twenty number memories. Phone service shall be applied in the Contractor's name and itemized bills paid by the Contractor.

Telephone service shall be provided by "landline" to the office space. Installation and phone company fees shall be paid by the Contractor. The Contractor shall arrange for the telephone service and instrument as follows:

a. 2 lines with 4 instruments, 5 jacks, for voice communication and intercom.

b. 1 line dedicated for use by fax machines.

c. 1 line dedicated for use by 2 computer modems.

d. 1 TCIP modem line for the network computer.

33. Telephone Answering Machine: One 2-line digital telephone answering machine with remote answering and access capability and voice time/day stamp.

34. Rechargeable Flashlight Systems: Four (4) heavy-duty Rechargeable flashlights, charging cradle, rechargeable NiMH battery (or equivalent), 12 volt adapter, and 120 volt A/C converter with a minimum output of 240 Lumens.

3.8 PLANT COMMUNICATIONS

Whenever the individual elements of the plant are located so that operation by normal voice between these elements is not satisfactory, install a satisfactory means of communication, such as telephone or other suitable devices and make available for use by Government personnel.

3.9 TEMPORARY PROJECT SAFETY FENCING

As soon as practicable, but not later than 15 days after the date established for commencement of work, furnish and erect temporary project safety fencing at the work site. Maintain the safety fencing during the life of the Contract and, upon completion and acceptance of the work, SECTION 01 50 00 Page 18 remove from the work site.

3.10 CLEANUP

Remove construction debris, waste materials, packaging material and the like from the work site daily. Dirt or mud which is tracked onto paved or surfaced roadways must be cleaned away. Store all salvageable materials resulting from demolition activities within the fenced area described above or at the supplemental storage area. Neatly stack stored materials not in trailers, whether new or salvaged.

3.11 RESTORATION OF STORAGE AREA

Upon completion of the project remove the bulletin board, signs, barricades, haul roads, and all other temporary products from the site.

After removal of trailers, materials, and equipment from within the fenced area, remove the fence. Restore areas used during the performance of the Contract to the original or better condition. Remove gravel used to traverse grassed areas and restore the area to its original condition, including top soil and seeding as necessary.

3.12 UTILITIES

All work involving storm and sanitary sewer facilities must be performed by the Contractor. All work involving New Jersey Natural Gas, Comcast Cable and Verizon facilities must be performed by the respective utility companies.

Company Name: New Jersey American Water

Point of Contact (POC): George Bauer

POC Tittle: Superintendent Field Operation

Address: 661 Shrewsbury Ave Shrewsbury, NJ 07702

Phone Number: 732-933-5913

Email Address: George.Bauer@amwater.com

Company Name: New Jersey Natural Gas

Point of Contact (POC): Marc Panaccione

POC Tittle:

Address: 1415 Wyckoff Road P.O. Box 1468 Wall, NJ 07719

Phone Number: 732-919-8140

Email Address: MPanaccione@NJNG.com

SECTION 01 50 00 Page 19

Company Name: Township of Middletown Sewerage Authority

Point of Contact (POC): Brian Rischman, P.E.

POC Tittle:

Address: P.O. Box 205 100 Beverly Way Belford, NJ 07718

Phone Number: (732) 495-1010 (Office) ; (732) 495-4565 (Fax)

Email Address: BRischman@tomsanj.com

Company Name: Verizon Communications - NJ Centralized Engineering Services