W912DS21B0008 Amendment 0006.pdf
PDF 856 KB Posted
- Attached to
- Rockaway Contract 2, Queens County, New York
- Solicitation number
- W912DS21B0008
About this file
This document is an amendment to a solicitation for the Rockaway Contract 2 project in Queens County, New York. The amendment provides revised drawings and specifications, answers bidders' questions, and adds a new clause.
The project involves beach and dune restoration along Rockaway Beach, including excavation, backfill, dune reconstruction with vegetation and sand fencing, dune reinforcement with armor stone and sheetpile walls, demolition and rebuilding of pedestrian and vehicular crossovers, construction of a concrete walkway, vibration monitoring, and record drawing preparation. The solicitation is open to all responsible bidders and offers optional additional work for aluminum railings, reinforced plastic lumber, a seabeach amaranth pilot study, additional hydraulic fill, and timber groin removal. Bids are due by August 16, 2021 and the contract is to be awarded by the U.S. Army Corps of Engineers, New York District.
View the file
Other files
Show 40 more
Latest 50 of 58 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
1. Answ er questions to prospective bidders for informational purposes only
2. Revise and re-issue specifications and draw ings
3. Revise the bid schedule
4. Add Clause 252.223-7999 NOTE: Bidders must acknow ledge receipt of this amendment by the date specif ied in the solicitation (or as amended) by one of the follow ing Methods: In the space provided on the SF1442, by separate letter, or by signing the block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH THE LATE BID, LATE
MODIFICATIONS OF BIDS OR LATE WITHDRAWAL OF BIDS (FAR 14.304).
1. CONTRACT ID CODE PAGE OF PAGES
1 28
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 13-Oct-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS21B0008
X 9B. DATED (SEE ITEM 11)
16-Aug-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
13-Oct-2021
CODE
US ARMY CORPS OF ENGINEERS, NEW YORK
26 FEDERAL PLAZA, RM 16-300
NEW YORK NY 10278-0090
W912DS 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DS21B0008
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
AMENDMENT 0006
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
MOBILIZATION & DEMOBILIZATION
FFP
INFORMATIONAL PURPOSES ONLY
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001AA 1 Job Mob/Demob Reinforced Dune & Crossovers
FFP
FOB: Destination
PSC CD: Y1KZ
0001AB 1 Job Mob/Demob Hydraulic Beachfill
FFP
EXCAVATION BACKFILL& DUNE RECONSTRUCTION
0002AA 842,170 Cubic
Yard
Excavation, Stockpiling and backfill
ESTIMATED QUANTITIES
0002AB 30,000 Cubic
Disposal of Unsuitable Fill and Debris
ESTIMATED QUANTITIES
0002AC 2,585,900 Cubic
Hydraulic Fill
ESTIMATED QUANTITIES
0002AD 70 Acre Vegetation
FFP
ESTIMATED QUANTITIES
0002AE 43,200 Square
Coir Blankets
ESTIMATED QUANTITIES
0002AF 110,000 Linear
Foot
Sand Fence
(dune, crossovers and walkway)
ESTIMATED QUANTITIES
0002AG 400 Short Ton Removal & Disposal of Timber Piles
FFP
ESTIMATED QUANTITIES
0002AH 268,000 Cubic
Regradiing Hydraulic Fill
Post Reinforced Dune Construction
ESTIMATED QUANTITIES
DUNE REINFORCEMENT
0003AA 385,000 Short Ton Type A Armor Stone
FFP
ESTIMATED QUANTITIES
0003AB 177,000 Short Ton Core Stone
FFP
ESTIMATED QUANTITIES
0003AC 7,100 Short Ton Gravel Base Course
FFP
ESTIMATED QUANTITIES
0003AD 120,000 Square
Geotextile
ESTIMATED QUANTITIES
0003AE 1,128,900 Square
NZ14 Sheetpile
ESTIMATED QUANTITIES
0003AF 35,000 Cubic
Concrete Cap
ESTIMATED QUANTITIES
DEMOLITION & DISPOSAL EXISTING CROSSOVER
0004AA 1 Job Demolition Type A
FFP
0004AB 1 Job Demolition Type B
FFP
0004AC 1 Job Demolition Type C
FFP
0004AD 1 Job Demolition Type D
FFP
0005 12,000 Square
PEDESTRIAN CROSSOVER TYPES P1, P3 AND P4
Stabilization Mats
ESTIMATED QUANTITIES
0006 9 Each
PEDESTRIAN ADA COMPLIANT CROSSOVERS TYPE
FFP
Construction of Type P2 Crossovers
0007 9 Each
PEDESTRIAN CROSSOVERS TYPE P5 REBUILD
FFP
Re-build Type P5 Crossovers
VEHICULAR CROSSOVERS TYPE V1
0008AA 6 Each Construction of Type V1 Crossovers
FFP
(VA25, VA37, VA75, VA86, VA97, VA101)
0008AB 1 Each Construction of Type V1 Crossovers
FFP
(VA32)
0009 5 Each Construction of Type V2 Crossovers
FFP
(VA41, VA49, VA57, VA67, VA69)
0010 3,580 SY
Walkway
FFP
5’ wide Stabilization Mat
0011 1 Job Vibration Monitoring
FFP
0012 1 Job As Built Record Drawing
FFP
PRE-PRICED CLIN $100,000.00
$100,000.00
0013 1 Job OPTION Option 1 - Additional Insurance
FFP
in accordance with specifications section 01 30 00 paragraph 1.8
0014 3,880 Linear
OPTION Option 2 - Aluminum Railings
For CO3, CO8, C015 & CO19
ESTIMATED QUANTITIES
0015 14,300 Square
OPTION Option 3 -Reinforced Plastic Lumber
For CO3, CO8, C015 & CO19
ESTIMATED QUANTITIES
0016 3,300 Linear
OPTION Option 4 - Aluminum Railings
For CO71, CO83, C098, CO99 & CO100
ESTIMATED QUANTITIES
0017 12,160 Square
OPTION Option 5 - Reinforced Plastic Lumber
For CO71, CO83, C098, CO99 & CO100
ESTIMATED QUANTITIES
0018 1 Job OPTION Option 6 - Seabeach Amaranth Pilot Study
FFP
(0.5 acre pilot study between STA 207+00 to STA 245+50)
0019 367,400 Cubic
OPTION Option 7- Hydraulic Fill
(STA-45+00 to STA 0+00)
ESTIMATED QUANTITIES
0020 5 Each OPTION Option 8 - Timber Groin Removal
FFP
Existing timber groins must be removed or cut 5 feet below existing grade .
The existing timber groins consist of timber piles, timber wales and timber sheet piles, and are approximately 250ft to 300ft. in length.
TOTALS:
TOTAL BASE – NO OPTIONS (ITEMS 0001 thru 0012) $________________
TOTAL OPTIONS (ITEMS 0013 thru 0020) $_________________
TOTAL BASE PLUS OPTION (ITEMS 0001 thru 0020) $_________________
NOTES:
1.Low bidder for the purpose of award will be the conforming bidder offering the lowest amount for the total base bid and optional bid items.
2. Any bid which is materially unbalanced as to prices for the Base Bid Items may be rejected. An unbalanced bid is one, which is based on the prices significantly less than cost for some work and prices, which are significantly overstated for other work.
3. Bidders are required to bid on all items or their bids will be rejected.
4. Bidders are reminded that they must bid on the issued plans and specifications as amended. Any deviations, conditions, or attachments made by the bidder himself thereto may render the bid non-responsive and may be caused for its rejection.
5. Tapering are included in the items and exact locations are on the plan sheets.
6. The Government is under no obligation to award any option. If Options are exercised, Bid items 0013-0020) will be exercised by December 31, 2024. No additional days will be added to the contract duration period .
ITEMS 13-17 (options 1-5) is the additional cost to replace timber decking and railings for the crossovers listed.
W912DS-21-B-0008
Amendment No.5
To Bidders The following changes shall be made to the drawings and specifications.
DRAWINGS
1. The following DRAWINGS have been REVISED and REISSUED:
-G-002, C-101, C-102, C-103, C-112, C-113, C-129, C-200, C-202, C-301, C-302, C-303, C-306, C-312, C-501, C-503, C-506, S-101, S-102, S-103, S-104, S-201, S-202, S-203, S-204, S-501, S-508, S-509
2. The following DRAWINGS have been DELETED:
-C-508
3. The following DRAWINGS have been REVISED but NOT REISSUED:
-None
SPECIFICATIONS:
1. The following SPECIFICATION SECTIONS have been ADDED and are provided in their entirety herein:
-None
2. The following SPECIFICATIONS SECTIONS have been DELETED in their entirety:
3. The following SPECIFICATION SECTIONS have been REVISED and REISSUED in their entirety:
-Section 06 13 35.00 18 -Section 01 22 00.00 10 -Section 31 62 19 -Section 01 57 19
4. The following SPECIFICATION SECTIONS have been REVISED but NOT REISSUED:
REVISED SPECIFICATIONS:
- Section 06 13 35.00 18– revised sizes in paragraph 2.1 (a)
- Section 01 22 00.00 10– revised multiple paragraphs and added paragraphs for seabeach amaranth pilot study.
- Section 31 62 19- revised multiple paragraphs and added language for test piles.
- Section 01 57 19- added seabeach amaranth pilot study paragraph to par 3.5.2
Questions and Answers:
The following questions and answers are provided for information only. Nothing contained below amends or revises any provision of the solicitation.
This is for bidder’s reference only, and is not to be considered as a part of the Contract Documents.
Contract award will be based on what is contained in the printed Plans and Specifications in a hard copy format or Electronic Bid Set if provided and as posted in the FBO.
RFI SET #2:
Question 3. Can the design shape of the core and armor stone be modified to have a continuous slope instead of a vertical face on the seaside of the structure?
Response: Yes, updated drawings to be posted with next amendment.
RFI SET #4:
Question 4. Drawing C-507, note 5 indicates that groins are to be removed East of 32nd street but upon inspection of the site there does not appear to be any timber groins at that location? Does this work get paid for under item No. 0002AG – Removal & Disposal of Timber Piles or Option Item 0020 – Timber Groin Removal?
Response: That work is under option Item No. 0020 – timber groin removal. Some photos, for information only, of exposed timber groins near B30/31, B29 and B28 –
RFI SET #6:
Question 12. The Mobi Mat width is called out in the 061335.0018 spec section as a minimum of 66” which is 5.5”. However, on the crossover schedule (C-200) it shows 6’6” Walking Width. Please clarify the width of the Mobi Mats.
Response: Revised section 06 13 35.00 18.
RFI SET #9:
Question 4. The existing baffle wall appears to extend to the southern (ocean) side of concrete walkway, with the portions of baffle wall extending on the beach side of the walkway being demoed at B147th St. and B142nd St. With sand fence on either side of the walkway this will result in 200’+ “dead end” at each street.
The call-outs indicate “5’ wide concrete walkway connecting street entries at baffle wall entrance (Typ).”
If the baffle wall remains across the walkway there will not be “connecting street entries”.
Are there any other sections of baffle wall to be demoed other than at B147th and B142nd Streets?
Response: No other sections of baffle wall to be demoed other than at B147th and B142nd.
Question 5. Can USACE please confirm treatment types for timber members, and piles. Typically CCA is used on the east coast and more accessible via treatment plants as well as MCA for timbers that come in contact with pedestrians. Currently AZCA is called out for some timbers.
Response: In the event that ACZA cannot be sourced, Chromated Copper Arsenate (CCA) pressure treated wood may be used under the condition that it must be clean and free of CCA surface deposits.
Wood with CCA surface deposits must be washed for at least 5 minutes under running water prior to use.
The washing must occur greater than 100 feet landward of any regulated wetland and/or water body. Any wood debris such as sawdust or wash waster must not enter any water body, including wetlands or protected buffer areas. The Contractor must be responsible for the quality of treated wood products.
Specification sections will be updated with these requirements in Amendment 7.
Question 6. For timber pile driving; Are piles driven to ultimate strength prior to embedment depth acceptable? If not is the intention to pre-auger all piles to achieve embedment depth? Please advise, thank you.
Response: Piles shall be driven to the specified embedment depth on the design drawings. Refer to specification section 31 41 16 and 31 62 19 for pile driving process.
RFI SET #10:
Question 1. Sheet C-508 and S-508 reference epoxy bar for the sidewalk and VA 32 crossover concrete.
No epoxy bar is referenced for the concrete cap at the sheetpile wall. Please confirm?
Response: Epoxy coated bar shall be used for the concrete cap at the sheet pile wall. A clarifying note will be incorporated into the Amendment 6 drawing set.
Question 5. Sheet S-504- Are the plates to be on both sides of the connection (2 ea./per connection)?
Assumed NS and FS are a reference to both sides.
Response: Confirmed. Plates will be on both sides of the connection.
Question 6. ACZA is a Douglas Fir treatment for the west coast. The east coast is predominantly Southern Yellow Pine treated with CCA. In addition to that, the timberworks specification (061333) and the Timber Marine Piles specification (316219) calls for Southern Yellow Pine. SYP is not treated with ACZA, only Douglas Fir.
Please see notations from suppliers:
“This preservative treatment is only used on the West Coast to the West Coast Forest products. Southern Yellow Pine is an East Coast Forest product and is used heavily for marine and foundation use. Under the AWPA Book of Standards regarding the application use a specifier chooses CCA for the East coast not a Douglas Fir ACZA West Coast Forest product. Both CCA & ACZA products are considered equal in the AWPA US5A application.”
“Please can you inform USACE that unfortunately treating the piling, lumber and timbers with ACZA is not an option. CCA is the industry standard and is what has been used in all their most recent contracts”
We request that CCA treatment be used for pilings and non-human contact timbers. We have had significant success in the region on USACE marine jobs with the use of CCA treatment.
Response: In the event that ACZA cannot be sourced, Chromated Copper Arsenate (CCA) pressure treated wood may be used under the condition that it must be clean and free of CCA surface deposits.
Wood with CCA surface deposits must be washed for at least 5 minutes under running water prior to use.
The washing must occur greater than 100 feet landward of any regulated wetland and/or water body. Any wood debris such as sawdust or wash waster must not enter any water body, including wetlands or protected buffer areas. The Contractor must be responsible for the quality of treated wood products.
Specification sections will be updated with these requirements in Amendment 7.
RFI SET #11:
Question 1. On Dwg S-509, Detail 1 call-out indicates “#6 ties @ 12” Max. Typ.”; Detail 3 call-out (apparently for the same bars) indicates “#4 bar, Typ.”. The overlap indicated ln Detail 1 (1’6”) is more consistent with a #4 bar than a #6. What size bar is to be used for the bent ties?
Response: Ties in the dune concrete cap are to be #6 bar. Overlap has been increased to 3’-0” and updates to drawings will be issued with Amendment 6 package.
Question 3. Lumber, including timber piles, is specified as being treated with ACZA (Ammoniacal Copper Zinc Arsenate). We are unable to find a timber supplier able to supply timber with that type of treatment.
Will the Corps accept an alternate treatment for those timbers?
What type of treatment was used on the Long Beach/Pt. Lookout crossovers? Will that same type of treatment be acceptable at Rockaway?
Response: In the event that ACZA cannot be sourced, Chromated Copper Arsenate (CCA) pressure treated wood may be used under the condition that it must be clean and free of CCA surface deposits.
Wood with CCA surface deposits must be washed for at least 5 minutes under running water prior to use.
The washing must occur greater than 100 feet landward of any regulated wetland and/or water body. Any wood debris such as sawdust or wash waster must not enter any water body, including wetlands or protected buffer areas. The Contractor must be responsible for the quality of treated wood products.
Specification sections will be updated with these requirements in Amendment 7.
RFI SET #12:
Question 1. Reference Addendum 04, RFI Set #8 from contractor: Question 4 identifies the conflict with Sumac.
Addendum 04 Provides Sumac specifies under 2.1 and advises to install based on 1.2, however 1.2 does not state Sumac in this paragraph. Please specify where Sumac will be planted. Will it be planted on Crest, North side or South side? Furthermore, the planting plan does not match the written spec in 1.2.
Response: Added the following language to section 32 94 00 - Sumac (Rhus aromatic): plant size 1 quart, planted 36" off center with staggered rows, each plant planted 7"-9" deep. Each plant shall be hand planted.
Planting shall occur between April 15 and June 1. The Planting plan is just a reference for the bidder. The sumac should be planted on the northside of the dune.
Question 6. Spec 32 94 00 paragraph 3.2 states nursery must be within 125 miles from site. Was the intent to also require genetics of plants within the same distance?
Response: There is no intent for genetics to be done on the plants.
Question 8. Is the planting plan intended to go over the entire 70 acres?
Response: Yes, planting shall take place on the entire dune (both slopes and crest).
RFI SET #13:
Question 1. The measurement of Crossovers ITEM 0005 for payment is in area (SY) so for types P1,P3 and P4 is the width measured from Sand fence to Sand fence or is just the surface of Mobi mat ?
Response: Surface of mobi mat.
Question 2. The Concrete Cap on drawing 1/S-509 typical section points to the bands as #6 rebar 12" OC. It calls out an overlap of 1'6" (24 diameters), this seems light. Typical Expansion joint detail 2/S-509 details same rebar as #4 @12" OC. Please clarify.
Response: Ties in the dune concrete cap are to be #6 bar. Overlap has been increased to 3’-0” and updates to drawings will be issued with Amendment 6 package.
252.223-7999 Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009) As prescribed in Class Deviation 2021-O0009, Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors, use the following clause:
ENSURING ADEQUATE COVID-19 SAFETY PROTOCOLS FOR FEDERAL
CONTRACTORS (DEVIATION 2021-O0009) (OCT 2021)
(a) Definition. As used in this clause –
United States or its outlying areas means—
(1) The fifty States;
(2) The District of Columbia;
(3) The commonwealths of Puerto Rico and the Northern Mariana Islands;
(4) The territories of American Samoa, Guam, and the United States Virgin Islands; and
(5) The minor outlying islands of Baker Island, Howland Island, Jarvis Island, Johnston Atoll, Kingman Reef, Midway Islands, Navassa Island, Palmyra Atoll, and Wake Atoll.
(b) Authority. This clause implements Executive Order 14042, Ensuring Adequate COVID Safety Protocols for Federal Contractors, dated September 9, 2021 (published in the Federal Register on September 14, 2021, 86 FR 50985).
(c) Compliance. The Contractor shall comply with all guidance, including guidance conveyed through Frequently Asked Questions, as amended during the performance of this contract, for contractor or subcontractor workplace locations published by the Safer Federal Workforce Task Force (Task Force Guidance) at https:/www.saferfederalworkforce.gov/contractors/.
(d) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (d), in subcontracts at any tier that exceed the simplified acquisition threshold, as defined in Federal Acquisition Regulation 2.101 on the date of subcontract award, and are for services, including construction, performed in whole or in part within the United States or its outlying areas.
(End of clause)