This technical specification covers requirements for a vehicular dune crossover and split rail fencing to be constructed on Rockaway Beach in Queens County, New York. The specification requires the vehicular crossover to be constructed of a Type 4 subbase or Soil Aggregate Designation 3A base course, overlaid with geotextile and concrete as detailed in the referenced sections. It provides requirements for materials, placement, compaction testing per ASTM standards, and actions required for non-compliance. Split rail fencing must be constructed of pressure-treated cedar or other naturally decay-resistant wood as shown on the contract drawings. The related federal contract opportunity is solicitation number W912DS21B0008 for construction work under the Rockaway Contract 2 in Queens County, New York issued by the Department of the Army Corps of Engineers New York District.

View the file

Other files

File Type Posted
Bid Abstract.pdf PDF
W912DS21B0008Amend0009.pdf PDF
W912DS21B0008Amend0008.pdf PDF
Pages 22 to 42 Rockaway C2_Amendmen 7_Plans.pdf PDF
Pages from Pages 1 to 10 Rockaway C2_Amendmen 7_Plans.pdf PDF
2020_02_26_WQC_Package_0-9999-00228_00001.pdf PDF
B 32 to 117 Boring.pdf PDF
B24-B35 Geotech Memo.pdf PDF
2021_10_13_WQC_Package.pdf PDF
06 13 33.pdf PDF
Pages from Pages 11 to 21 Rockaway C2_Amendmen 7_Plans-2.pdf PDF
Rockaway Structural Drawings 2021-10-13_AMEND 007.pdf PDF
05 52 00.pdf PDF
2021_10_14_Authorization_to Proceed_CONTRACT 2.pdf PDF
W912DS21B0008 Amendment 0007.pdf PDF
01 57 19.pdf PDF
W912DS21B0008 Amendment 0006.pdf PDF
31 62 19.pdf PDF
01 22 00.00 10.pdf PDF
Rockaway C2_Amendmen 5_Plans.pdf PDF
06 13 35.00 18.pdf PDF
Rockaway Structural Drawings - 2021-10-06 - AMEND 5.pdf PDF
W912DS21B0008 Amendment 0005.pdf PDF
32 94 00.pdf PDF
GSD Curves A1 to A17.pdf PDF
GSD Curves A18 to A25.pdf PDF
Weight Percent Passing A.pdf PDF
GSD Curves B.pdf PDF
01 50 00.pdf PDF
W912DS21B0008 Amendment 00004.pdf PDF
Summary Statistics.pdf PDF
EastBorrowArea_90sort_Median xyz.txt TXT text file
5042_EAST-ROCKAWAY-CSRM-2021_MAPPED_NAVD88_ELEV XYZ.txt TXT text file
WestBorrowArea_90sort_Median xyz.txt TXT text file
WestBorrowArea_5x5_Median xyz.txt TXT text file
20200427_rkwyct1_conformed.pdf PDF
W912DS21B0008 Amendment 00003.pdf PDF
EastBorrowArea_5x5_Median xyz.txt TXT text file
W912DS21B0008 Amendment 00002.pdf PDF
Rockaway Sheet Pile Reference Line.pdf PDF
W912DS21B0008 Amendment 00001.pdf PDF
R4 Phase 2 Boardwalk Access Beach 97 to 105.pdf PDF
R5-Phase 3 Boardwalk Access Beach 105 to 126.pdf PDF
R1-3 Survey 2021 Rockaway Inlet sheets 1 to 76.pdf PDF
Rockaway C2 100 pc part 3 of 3.pdf PDF
R2- Rockaway Make Safe -Baffle Wall.pdf PDF
R1-1 Survey 2021 Rockaway Inlet sheets 1 to 76.pdf PDF
Rockaway C2 100 pc part 2-1 of 3.pdf PDF
Rockaway C2 100 pc part 1-1 of 3.pdf PDF
Rockaway C2 100 pc part 2-2 of 3.pdf PDF
Show 40 more

Latest 50 of 58 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ROCKAWAY REINFORCED DUNE AND CROSSOVER

Amendment 004

SECTION 06 13 34.00 18

VEHICULAR DUNE CROSSOVER

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D448 (2012) Sizes of Aggregate for Road and Bridge Construction

1.2 SCOPE OF WORK

The work specified in this section shall be bid upon and executed on a per unit basis and shall include all labor, materials, equipment, and performing all operations required for the complete construction of vehicular dune crossover and split rail fencing.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

Vehicular Crossover; G, DO

Drawings graphically showing the details of the crossover including materials, connections, and details of fabrication and installation.

Locations; G, DO

A separate shop drawing for each location requiring a vehicular crossover including plan views and elevations.

Survey Data; G, RO

Each shop drawing shall include all survey data for connections of the crossover to existing ground.

Split Rail Fencing; G, RO

SD-03 Product Data

SECTION 06 13 34.00 18 Page 1

Concrete; G, RO

Vehicular Crossover; G, RO

Submit information describing the quality and performance of the materials proposed for the crossover.

Split Rail Fencing; G, RO

SD-06 Test Reports

Gradation Test; G, RO

Grain size distribution curves shall be in accordance with ASTM D448 and shall be submitted from the source of the base course materials to be used on the vehicular dune crossover.

Submit 3 copies of each test report within one week of conclusion of physical tests. Reports shall indicate the location of the sample/test, the test data, and a statement of compliance or non-compliance, where applicable.

1.4 DELIVERY AND STORAGE

Materials shall be delivered to the site in undamaged condition, stored off ground in fully covered, well-ventilated areas, and protected from extreme changes in temperature and humidity.

1.5 MEASUREMENT AND PAYMENT

1.5.1 Measurement

The quantity to be measured for payment will be the one unit complete.

1.5.2 Payment

Payment for the contract unit price shall include the all labor, materials, equipment, and performing all operations required for the complete construction of the work.

PART 2 PRODUCTS

2.1 VEHICULAR CROSSOVER

2.1.1 Base Course

The base course shall be Type 4 subbase material having a gradation in accordance with TABLE 733-04A Subbase Gradation as determined by ASTM D448, or the base course shall be a Soil Aggregate, Designation 3A, conforming to the NYSDOT Standard Specification. Recycled materials are not acceptable.

2.1.2 Geotextile

Underlying geotextile shall be as specified in Section 31 05 22 GEOTEXTILES

USED AS FILTERS

SECTION 06 13 34.00 18 Page 2

2.2 CONCRETE

Concrete shall be constructed as indicated on the contract drawings and specified in Sections 03 11 13.00 10 STRUCTURAL CAST-IN-PLACE FORMING

03 20 00.00 10 CONCRETE REINFORCING, 03 31 01.00 10 CAST-IN-PLACE

STRUCTURAL CONCRETE FOR CIVIL WORKS, and 03 31 30 MARINE CONCRETE.

2.3 SPLIT RAILING FENCING

Drawings graphically showing the details of the split rail fencing including materials, connections, and details of fabrication and installation. Submit information describing the quality and performance of the materials proposed for the split rail fencing.

2.3.1 Material

Split rail fence (posts and rails) shall be No. 1 cedar, pressure-treated lumber, or other naturally decay-resistant wood.

PART 3 EXECUTION

3.1 DUNE CROSSOVERS

The dune crossovers shall be constructed in the locations and in the manner indicated on the contract drawings. The geotextile shall be placed as specified in Section 31 05 22 GEOTEXTILES USED AS FILTERS.

3.1.1 Placing, Spreading, Moisture Control and Compaction

Excavate or place sand and subbase course materials in maximum 6 inch lifts to the lines and grades shown on the contract drawings. Compact by the controlled use of the hauling and spreading equipment. Movement of the equipment shall be distributed as much as practicable over the surface to provide uniform compaction and complete coverage of the fill. Compaction shall be performed prior to placement of geotextile and repeated following placement of the base course on top of the geotextile.

3.1.2 Testing

The Contractor shall be wholly responsible for furnishing materials meeting the requirements specified herein, for placing the materials within the limits of moisture suitable for proper compaction, and for compacting the materials in accordance with the requirements of this section. The Contractor shall also be responsible for performing laboratory tests as required to control the work and demonstrate compliance with material specifications. Field in-place density shall be determined in accordance with ASTM D 6938. ASTM D 6938 results in wet unit weight of soil shall be used to determine the moisture content of the soil. The calibration curves furnished with the moisture gauges shall also be checked along with density calibration checks as described in ASTM D 6938; the calibration checks of both the density and moisture gauges shall be made at the beginning of a job on each different type of material encountered and at intervals as directed by the Contracting Officer. When test results indicate, as determined by the Contracting Officer, that compaction is not as specified, the material shall be removed, replaced and recompacted to meet specification requirements. Tests on compacted areas shall be performed to determine conformance with specification requirements. The following number

SECTION 06 13 34.00 18 Page 3 of tests, if performed at the appropriate time, will be the minimum acceptable for each type of operation.

a. During the course of construction, if the source, appearance or performance of the crossover materials noticeably changes in the opinion of the Contracting Officer, the appropriate index testing, described herein, of the materials shall be repeated to ensure specification compliance and re-establish moisture/density relationships for compaction.

b. Three moisture-density points shall be determined from one compaction text, in accordance with ASTM D 1557, for each type of material used as crossover material to determine the optimum moisture and laboratory maximum density value.

c. One in-place nuclear density test shall be performed per vehicular crossover.

d. In-place densities shall be checks using ASTM D 1556 a minimum of one

(1) time during placement of the crossover materials for every crossover constructed. Additional checks shall be performed as requested by the Contracting Officer.

3.1.3 Action Required for Non-Compliance

Whenever testing specified in this section indicates material non-compliance, the Contractor shall be required to remove all material not meeting the specification requirements. The Contracting Officer shall require as many additional tests as necessary to identify the limits of unsuitable material. No additional payment will be made for tests required to determine the limits of unsuitable material or for the cost or removal and replacement with suitable material.

3.2 SPLIT RAILING FENCING

The split rail fence shall be constructed as indicated on the contract drawings. The Contractor shall excavate for the posts to the depths indicated. Remove debris encountered when excavating to install posts.

Moisten backfill to optimum condition and compact with hand tampers or other approved methods. Set posts plumb and in proper alignment.

-- End of Section --

SECTION 06 13 34.00 18 Page 4

06 13 34.00 18 - VEHICULAR DUNE CROSSOVER
PART 1 GENERAL
1.1 REFERENCES
1.2 SCOPE OF WORK
1.3 SUBMITTALS
1.4 DELIVERY AND STORAGE
1.5 MEASUREMENT AND PAYMENT
1.5.1 Measurement
1.5.2 Payment
PART 2 PRODUCTS
2.1 VEHICULAR CROSSOVER
2.1.1 Base Course
2.1.2 Geotextile
2.2 CONCRETE
2.3 SPLIT RAILING FENCING
2.3.1 Material
PART 3 EXECUTION
3.1 DUNE CROSSOVERS
3.1.1 Placing, Spreading, Moisture Control and Compaction
3.1.2 Testing
3.1.3 Action Required for Non-Compliance

3.2 SPLIT RAILING FENCING