This document summarizes an amendment to a solicitation for the Rockaway Contract 2 project in Queens County, New York. The amendment provides revisions to drawings and specifications including changes to archaeological monitoring requirements, work restrictions, and clarifications to bid items and project scope. It also includes responses to contractor questions on topics such as liquidated damages, dredging sequencing, and testing requirements for timber piles.
View the file
Other files
Show 40 more
Latest 50 of 58 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
1. Answ er questions to prospective bidders for informational purposes only
2. Revise and re-issue specs
NOTE: Bidders must acknow ledge receipt of this amendment by the date specif ied in the solicitation (or as amended) by one of the follow ing Methods: In the space provided on the SF1442, by separate letter, or by signing the block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH THE LATE BID, LATE
MODIFICATIONS OF BIDS OR LATE WITHDRAWAL OF BIDS (FAR 14.304).
1. CONTRACT ID CODE PAGE OF PAGES
1 10
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 04-Oct-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS21B0008
X 9B. DATED (SEE ITEM 11)
16-Aug-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
04-Oct-2021
CODE
US ARMY CORPS OF ENGINEERS, NEW YORK
26 FEDERAL PLAZA, RM 16-300
NEW YORK NY 10278-0090
W912DS 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DS21B0008
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0004
W912DS-21-B-0008
Amendment No.4
To Bidders The following changes shall be made to the drawings and specifications.
DRAWINGS
1. The following DRAWINGS have been REVISED and REISSUED:
-None
2. The following DRAWINGS have been ADDED:
-None
3. The following DRAWINGS have been REVISED but NOT REISSUED:
-None
SPECIFICATIONS:
1. The following SPECIFICATION SECTIONS have been ADDED and are provided in their entirety herein:
-None
2. The following SPECIFICATIONS SECTIONS have been DELETED in their entirety:
-None
3. The following SPECIFICATION SECTIONS have been REVISED and REISSUED in their entirety:
-Section 06 13 34.00 18 -Section 32 94 00 -Section 01 50 00
4. The following SPECIFICATION SECTIONS have been REVISED but NOT REISSUED:
-Section 35 31 29.40
REVISED SPECIFICATIONS:
-Section 06 13 34.00 18– Part of Paragraph 3.4.3 “Preservation and Recovery of Archaeological Resources” was revised to state “Monitoring will be required where soil will require excavation prior to the placement of the reinforced dune stones. Placement of other stones that do not require the earth beneath to be excavated or disturbed will not require monitoring. The contractor will provide a qualified archaeologist, who meets the standards of 36 CFR Part 61 (Appendix A) to monitor excavations.”
-Section 32 94 00– first sentence revised to “There shall be no work nor access between Memorial Day and Labor Day, unless coordinated with the COR, between streets B108th and B90th.”
-Section 01 50 00- added hard copy requirement to par 3.7.1
-Section 35 31 29.40 – added the following sentence to par 3.13.1 “Dune reinforcement shall not be left exposed without backfill for lengths greater than 500-feet.”
Questions and Answers:
The following questions and answers are provided for information only. Nothing contained below amends or revises any provision of the solicitation.
This is for bidder’s reference only, and is not to be considered as a part of the Contract Documents.
Contract award will be based on what is contained in the printed Plans and Specifications in a hard copy format or Electronic Bid Set if provided and as posted in the FBO.
RFI SET #1:
Question 8. Section 00 90 06 “Character of Material Within Borrow Area” in the specifications provides geological logs for the borrow areas.
a. Can the USACE please provide the sieve analysis curves from these logs as well?
Response: Information provided with this amendment.
RFI SET #2:
Question 1. The item 0007 calls for the demolition and re-construction of existing S-type concrete ramps;
CO 28, 34, 38, 44, 50, 53, 58, 61, 65, all of which have a designation of "Demo C". Item 004AC calls for the demolition and reconstruction of Type C demolition ramps. Question, is this a duplication of payment items, i.e., do you get paid under item 004AC AND item 0007?
Response: Item Number 0004AC is for only demolition of the Type C structures. Item Number 0007 is for rebuild of the type P5 structures. Refer to plan sheet SD-203.
Question 2. What are the payment limits for excavation under item 0002AA? What are the side slopes in the excavation prism?
Response: Side slopes in excavation prism was assumed 1:1 using surveys.
Question 6. Is the loading of the boardwalk H20 or greater? If not, what is the loading capacity?
Response: Boardwalk was designed by others for H20 loading; contractor to verify loading of boardwalk prior to use.
Question 7. The access points given for this project show the contractor going over the elevated boardwalk.
Will any additional support be needed to handle all the deliveries that will be coming to this project?
Response: Prior to using access points at existing boardwalk, Contractor is to verify loading capacity.
Contractor also has two access point options that do not cross over the boardwalk.
Question 9. Can construction of the dune reinforcement structure begin prior to any dredging work, in the event that no dredge subcontractors are available until August of 2022?
Response: Yes, pending work plan/contractor’s schedule approvals and if contractor adheres to specification requirements, such as, but not limited to, the following specifications -
Section 31 23 00.00 20 par 1.5 c - Suitable backfill in the quantities required is not available at the project site; hydraulic fill from borrow area is needed in addition to material on site.
Section 35 31 29.40
3.13 ACCEPTANCE SECTIONS
3.13.1 Section Designations
Completed work on the rock reinforcement shall be accepted in 100-foot sections. The accepted sections may be backfilled to its design dune grade with sand. Dune reinforcement shall not be left exposed without backfill for lengths greater than 500-feet.
RFI SET #3:
Question 8. Sand Fence material-The Current market shows Aspen as the available wood slat Sand fencing option. Is the intent to utilize current available market products for this project?
Response: Yes.
Question 9. Please provide the specification for the “Sumac” as designated “S” on the Planting plan (page 7 of Spec 32 94 00). This species is not identified under 32 94 00 paragraph 2.1. Please advise if this item should be removed from the planting plan and indicate its substitution if this is in error.
Response: Added the following language to section 32 94 00 - Sumac (Rhus aromatic): plant size 1 quart, planted 36" off center with staggered rows, each plant planted 7"-9" deep. Each plant shall be hand planted.
All areas stated in paragraph 1.2 above and shown on planting plan attachment at the end of this section.
Planting shall occur between April 15 and June 1.
Question 10. Marine Concrete 03 31 30- Supplemental Corrosion Protection- No mention is given in plan set, please confirm that this is not to be included in cost of concrete cap?
Response: Confirmed, no supplemental corrosion protection.
RFI SET #4:
Question 5. Clause 52.211-12 Liquidated Damages -- Construction (SEP 2000) states that “if the contractor fails to complete the work within the time specified in the contract the contractor shall pay liquidated damages to the Government in the amount of $6,593 for the first tier for each calendar day of delay until the work is completed or accepted and of $1648 for the second tier of each calendar day of delay until the work is completed or accepted”. Please clarify what is considered first tier and what is considered second tier with regard to assignment of liquidated damages.
Response: Response: “First tier” demurrage is based upon costs incurred in administration of the contract past the completion date. This amount does not include any liquidated damages for each day of delay that would accrue to the using service from exclusion of beneficial occupancy. The “second tier” demurrage is if the contractor fails to complete documented punchlist items after the date of beneficial occupancy.
Question 6. The installation of the Core Stone and Armor stone against the new NZ14 sheetpile wall/concrete cap will require significant excavation and stockpiling of material to be used for backfill. During the armor stone installation, while the fill is stockpiled, if a storm event occurs and washes away the stockpile, will the contractor be reimbursed for importing additional fill to replenish the material that was lost?
Response: The contractor shall take all reasonable precautions to protect the excavated sand, as required by the contract. In the event that a storm is forecast that may be severe enough to cause significant loss of material, it should be predictable with enough lead time to allow the contractor to take extra steps to secure the sand – which is also required by the contract.
RFI SET #5:
Question 1. We were looking at the documents and there is not a DIVISION 9 section, but the scope says there is. Please advise. Thank you.
Response: There is no Division 09 listed in specifications table of contents.
RFI SET #6:
Question 3. Clarification of Bid Items scope, For when a bid item appears to contain other bid items embedded with in, please clarify the following:
a. On the various cross overs: Does Snow Fence shown in sections on C-503, C-504, get Billed under its line item 0002AF, or is it included in crossover type P1, P3, P4 and v2 ?
Response: Sand fence shown on C-503 & C-504 gets billed under Item Number 0002AF Sand Fence.
b. Dwg C-508 shows Concrete Walkway Details, is the sand fence, part of the item 00010 Concrete Walkway or will it be compensated under item 0002AAF sand fence? Is excavation and base course included in the Walkway 00010 item?
Response: Sand fence billed under Item Number 0002AF Sand Fence.
Question 4. Please provide Specification for Split Rail Fence shown for Vehicle Access Crossovers.
Response: Specification for split rail fence added to section 06 13 34.00 18 Vehicular Dune Crossover.
Question 5. Notes on S-507 and S508 describing VA32 work call out for epoxy coated rebar, S509 which shows Dune Cap does not mention rebar type, Is the Concrete Dune Cap to be reinforced with Epoxy coated rebar ?
Response: Yes, reinforcing in dune concrete cap shall be epoxy-coated rebar. A note will be incorporated into next Amendment package.
Question 6. The Recycled Plastic Lumber, is this option in lieu of the wood decking for crossover P2 ? Is there a specification ? If not please provide.
Response: Recycled Plastic Lumber (RPL) is an option for the wood decking of P2, the elevated ADA crossovers. A paragraph in section 06 13 33 shall be included in the next Amendment specification package regarding the RPL option.
Question 7. Ref Plan S 507, S 508 VA 32, shows Concrete Cap on Crossover Sheet Pile, are these items paid under the item 003AE Sheet pile and 003AF Concrete Cap or are they part of Cross over item 0008AB? What happens where the Concrete Cap of the crossover Sheet pile meets the Dune Concrete Cap ? Please provide detail plan view.
Response: This should be under the cross over item 008AB as they are referring to the cross over concrete cap. Crossover sheet pile caps shall have the respective rebar extend into the dune concrete cap and bend at far side of the dune cap reinforcement or at the dune sheeting if it obstructs. An additional detail will be provided for clarification in the next Amendment package.
Question 8. Where is the marine concrete as per the Marine Concrete spec used ? The definition in the spec calls for there to be contact with seawater or brackish water, as the concrete cap varies in elevation above sea level please confirm if the Concrete Cap in the Dune is to be Marine concrete.
Response: Concrete cap in the dune shall be the marine concrete.
Question 9. On S-501 Detail 1 and 2 there is no clear connection detail for the Bottom Chord and the 6x8 Truss Bracings. Are the 6x8 alongside, above, or below the floor beam members?
Response: Bracing is in line with the floor beams, above the bottom chords of the truss. See connection details 4, 5, and 6 on page S-504. A clarifying note will be added to S-501 with next Amendment package.
Question 10. On S-504, is the USACE able to provide angles for each of the steel plate details?
Response: Angles of the bracing members shall be indicated on detail 2 of S-501 in next Amendment package. Plates shall ensure min edge distance requirements as indicated.
Question 11. There are conflicting screw lengths for the decking boards. On S-502 the plan calls for 2.5” screws. However, in the timberworks spec under decking (Section 06 13 33 Page 4 - 3.1.4) The spec calls for 4 Inches greater than the thickness of the board. That would be 5.5” Screws. What length screws should be used for the 2x6 decking boards?
Response: 2.5” screws shall be used. Specification section will be updated to match structural drawings in next Amendment package.
RFI SET #7:
Question 2. Please provide any grain size analysis that was taken on projects in the past.
Response: Information provided with this amendment.
Question 3. The specifications state that if the Options are exercised, Bid items 0013-0020 will be exercised within three years of the contract period of performance. If exercised, when does the Government anticipate Option 0019 – Hydraulic Fill taking place?
Response: Optimally it would take place right after base fill, if exercised.
Question 4. The specifications state, “No construction activities associated with this project may take place from March 21 – September 1 from Beach 6th Street to Beach 85th Street.” Please provide the beach stationing where this work restriction applies.
Response: Approximately STA 351+58 (eastern end of project area) to STA 160+00. Also note the rest of the specifications section par 01 57 19 par 3.5.1.1 1 - “Pre-construction surveys shall be undertaken in the remainder of the project area by an approved qualified biologist (on the basis of behavioral observations regarding territorial, courtship, nest building, egg laying, and brood rearing). If located, their breeding areas will be protected and no construction activities shall occur within 1,000 m of the delineated breeding area.”
Question 5. The specification state, “Proceed with the placement of the beachfill in a continuous manner along the shoreline moving generally east to west, starting at Beach 9th Street, or as directed by the COR.”
Due to the Time of Year Work Restrictions along with the December 1, 2022 completion requirement, this requirement will greatly limit the sequencing of potential dredging Contractors and will force the work to be done in less favorable weather conditions. In order to provide the best value for the Government, we would like to request that Contractors be able to define their order of work and commence in the western portion of the project if deemed beneficial.
Response: Beachfill deadline extended to March 14, 2023. Sand placement must be east to west along the shoreline, the starting point is flexible if deemed beneficial to start elsewhere.
RFI SET #8:
The following questions reference Rockaway Contract 2 Specification Section 32 94 00
Question 1. Paragraph 1.2 Area to be Vegetated, identified the Beach grass quantity of 13552 culms, however a quantity of 4840 plants without a description of if the word plants, units and/or culms. Please define and clarify if Plants refers to goldenrod, beach rose, bayberry, and beach plum, or if it is inclusive of beach grass and should be added to 13552.
Response: The numerical number presented in the spec are just a reference number of plants per acer depending on the requested spacing of the plants which ranges form 18-36 inch on center. The plant species are reference in the spec to define the plant spacing.
Question 2. Paragraph 2.1 Plant Material Cape American Beach grass quantifies 19,360 planting units per acre. Please clarify if this language is interchangeable with culms, and the term “plants” utilized in paragraph 1.2.
Response: Yes when the word plant refers to Beach grass.
Question 3. One acre in Paragraph 1.2, adding 13,552 culms with 4,840 plants, equals 18,392.
One acre in Paragraph 2.1 indicates 19,360 planting units of Only Beach grass.
Manual counting of beach grass in the “enclosed basic planting plan” as referred to in 1.2, and as shown on the last page of 32 94 00, provides a quantity of 14,794 per acre.
All bold numbers were within 32 94 00.
Please advise the intent of the quantity of beach grass on this project per acre.
Response: The intent is to plant beach grass 18 in oc. The total numbers per acer are just for reference.
Question 4. 32 94 00 Paragraph 1.2 describes species locations and refers to a planting plan. Both conflicts.
Scenario 5 plants South side:
- beachgrass Crest:
- goldenrod
- beach rose
- beach grass
North side
- beach grass
- bayberry
- beach plum
Conflict:
Planting plan shows 6 plants and introduces Sumac (also does not specify type of species), all plants appear on all sides of dune, not isolated as described above to sides of the dune.
Response: The figure is just an example of the planting scheme; plant sumac specifications were added to section 32 94 00.
Question 5. Please advise layout of crest, and layout of Northside if the intent is not the planting plan provided within spec 32 94 00. Also advise where Sumac is to be planted if the intent is not to utilize the provided planting plan. Additionally, please provide the species of Sumac.
Response: Sumac specifications added to section 32 94 00.
RFI SET #9:
Question 1. Upon review of the plans, there are cross sections that show the new reinforced dune, then the dune berm that goes out at elevation 8, approximately 240’ from the baseline depending on location.
Then there is a note at the bottom of the plan stating “ 3 FILL AREAS WHERE EXISTING GRADE IS
ABOVE THE DESIGN TEMPLATE, THOSE AREAS SHALL NOT DISTURBED. THESE AREAS SHALL
BE VERIFIED WITH SURVEY ON FIELD BY THE CONTRACTOR”. Is it up to the contractor to assume that any area after the dune crest at elevation 18 that is higher than the proposed grade that we are not going to touch it? It is not really clear with having that note, but still showing a proposed grade line that is below the existing grade line. It also makes excavation difficult to attempt to not damage any existing dune that is above the proposed grade location outside of the immediate work area. Also how are the As-builts going to be accepted? Will they be accepted based on proposed grades or based on the preliminary survey grades that were taken?
Response: Contractor to place fill between existing beach and proposed template, and not disturb sand above the proposed template. This only applies for fill, and not for the excavation required to construct the reinforced dune. After the construction of the reinforced dune, sand shall be placed to the proposed template. Refer to section 01 22 00.00 10 Price and Payment Procedures for as-builts/acceptance/payment/measurement.
Question 2. For timber pile driving the testing requirements and quantities were not specified. Is PDA testing acceptable? What quantity of piles required testing? Please advise, thank you.
Response: PDA testing is acceptable and shall be performed on 14” diameter piles supporting the ends of the truss span. Clarifying notes will be added to the structural drawings and specification section 31 62 19 will be revised to include testing requirements in the next Amendment package.
Question 3. Just received Addm #3. . please look at the files that end with .txt all look like IP Addresses?
Please advise.
Response: All the .txt files provided in Amendment 3 are XYZ survey data for the beach placement area and borrow areas. The .txt file is just easting (x), northing (y) and elevation (z) coordinates.
RFI SET #10:
Question 2. Amend 3 -Question #6- Does the response infer a separate NTP for the dredging contractor?
As opposed to the prime contractor? Please clarify?
Response: Only the prime contractor will receive NTP.
Question 3. Section 01 14 00 Work Restrictions- 1.3.1 Order of Work references “Hydraulic beachfill placement must be constructed prior to reinforced dune and crossover construction, and base hydraulic fill must be completed by December 1, 2022”. The date has changed (per Amend 3), however is the order of work mandatory. Will the USACE consider reinforced dune construction starting before Hydraulic beachfill commences?
Response: Yes, pending work plan/contractor’s schedule approvals and if contractor adheres to specification requirements, such as, but not limited to, the following specifications -
Section 31 23 00.00 20 par 1.5 c - Suitable backfill in the quantities required is not available at the project site; hydraulic fill from borrow area is needed in addition to material on site.
Section 35 31 29.40
3.13 ACCEPTANCE SECTIONS
3.13.1 Section Designations
Completed work on the rock reinforcement shall be accepted in 100-foot sections. The accepted sections may be backfilled to its design dune grade with sand. Dune reinforcement shall not be left exposed without backfill for lengths greater than 500-feet.
(End of Summary of Changes)