W912DS-16-B-00070005.pdf
PDF 25 KB Posted
- Attached to
- Green Brook Segment B3 Federal contract opportunity
- Solicitation number
- W912DS-16-B-0007
About this file
Amendment 0005
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W912DS-16-B-0007_Bid_Abstract.pdf | ||
| W912DS-16-B-00070009.PDF | ||
| W912DS-16-B-00070008.pdf | ||
| 16-0258.pdf | ||
| W912DS-16-B-00070007.pdf | ||
| W912DS-16-B-00070006.pdf | ||
| W912DS-16-B-00070004.pdf | ||
| W912DS-16-B-0007-0003.pdf | ||
| W912DS-16-B-0007-Amendment_0002.pdf | ||
| GB_SEG_B3_C-101WCB_REV1.pdf | ||
| 4-STRUCT_A W_100__NPS_4-28-2016_-_modified_drwgs_only.pdf | ||
| GB_SEG_B3_SB101WCB_REV1.pdf | ||
| GB_SEG_B3_C-102WCB_REV1.pdf | ||
| EM_1110-2-6056.pdf | ||
| GB_SEG_B3_SS709WCB_REV1.pdf | ||
| GB_SEG_B3_C-503WCB_REV1.pdf | ||
| W912DS-16-B-0007-Amendment_0001.pdf | ||
| GB_SEG_B3_C-501WCB_REV1.pdf | ||
| GB_SEG_B3_C-104WCB_REV1.pdf | ||
| final-report-URS-geotech.pdf | ||
| Segment_B3_(NPS)_Drawings_-_4-15-2016.pdf | ||
| Specifications_-_B3_100__NPS_4-12-2016.pdf | ||
| W912DS-16-B-0007.pdf |
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W16ROE60531834
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
Revise spec section 35 41 00 Answ er questions to prospective bidders for informational purposes only Extend Bid Opening Date to 12-July-2016 at 2:00 P.M. est.
NOTE: Bidders must acknow ledge receipt of this amendment by date specified in the bid (or as amended) by one of the follow ing methods:
In the space provided on the SF 1442, by separate letter, or by signing block 15 below .
FAILURE TO ACKNOWLEDGE AMENDMENT BY DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH THE
LATE BID, LATE MODIFICATION OF BID, OR LATE WITHDRAWAL OF BID (FAR 14.304)
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 23-Jun-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DS-16-B-0007
X 9B. DATED (SEE ITEM 11)
06-May-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
22-Jun-2016
CODE
US ARMY CORPS OF ENGINEERS, NEW YORK
26 FEDERAL PLAZA, RM 1843
NEW YORK NY 10278-0090
W912DS 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DS-16-B-0007
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 28-Jun-2016 02:00 PM to 12-Jul-2016 02:00 PM.
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0005
1. The following changes shall be made to the specifications and plans.
1) SPECIFICATIONS:
1-Section 35 41 00
a. Delete the following in paragraph 3 17 1.1:
All stones and rock fragments larger than 3 inches in any dimension shall be removed at the source prior to hauling to the fill.
b. Replace in its entirety in paragraph 3 17 1.1 with the following:
All stones and rock fragments larger than 4 inches in any dimension shall be removed at the source prior to hauling to the fill.
2) QUESTIONS AND ANSWERS
(Questions that may be of general interest to all Offerors and/or the Government and that are not readily answered by the proceeding changes will appear below. These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question(s). Questions and answers are issued to the Offerors “for information only ”and do not revise the solicitation, plans or specifications.).
Bullet 1: The plans do not specify what type of coating the reinforcing steel is required to have (if any) for the Flood Wall, Culverts, Headwalls and Drainage Chamber Sections. Please specify the type of coating required for the reinforcing steel in those concrete structures or if it is uncoated, black steel.
Corps Response: Drawing SF-801, note 3 under the Reinforcement heading mentions for all reinforcing steel for the wet well to be galvanized. Specification 03 20 00.00 10, paragraph 2.2.1 mentions the galvanizing requirement for the wet well. Specification 03 20 00.10 10 covers "floodwalls, culverts, headwalls, and drainage chambers". Paragraph 2.1 mentions reinforcing steel meeting ASTM A615 or A706. No coating is listed and no coating is required.
W912DS-16-B-0007
Bullet 2: Specification 35 41 00, Section 2.1.1 allows particles up to 4” in levee embankment material. Section 3.17.1.1 requires all stones larger than 3” be removed from levee embankment materials. Please resolve this difference in requirements.
Corps Response: Paragraph 3.17.1.1 stone size revised.
Bullet 3: Can excavated material be used to refill / backfill the levee inspection trench?
Corps Response: Specification 35 41 00, paragraph 1.2.6 includes inspection trench fill material in the same category as the rest of the levee embankment. Paragraph 3.9.2 requires compaction requirements for the trench to be the same as for the levee. Paragraph 3.16.1 similarly requires the inspection trench to be filled with the same material type as is to be placed immediately above, i.e., in the levee embankment. The trench shall be backfilled and compacted to the same requirements as the levee embankment using only materials satisfying the embankment requirements, i.e., select material as specified in paragraph 2.1.1. If the material excavated from the inspection trench satisfies this requirement, then it can be used.
Bullet 4: Are keyways and waterstops required for construction joints between the footing and stem of the floodwall? If so, can you please provide a detail?
Corps Response: No keyways or waterstops are required between the footing and the stem of the floodwall.
Bullet 5: Please provide a basis of design manufacturer(s) for the segmental block retaining wall.
Corps Response: Reference details on the plans and specification for the block retaining wall.
Contractor to research manufacturers.
(End of Summary of Changes)
File details come from the government source that posted it. Updated .