W912DS-14-B-0007-AMENDMENT 0002 REVISED BID SCHEDULE

View the file

Other files

File Type Posted
FY14_Thule_Consolidation_2_-_Bid_Abstract_-_30_Apr_14_(2).pdf PDF
W912DS-14-B-0007-Amendment_0012_.pdf PDF
W912DS-14-B-0007-Amendment_0011.pdf PDF
Plans_-_Amendment__10.pdf PDF
W912DS-14-B-0007_AMENDMENT_0010.pdf PDF
Plans_-_Amendment_9.pdf PDF
W912DS-14-B-0007_AMENDMENT_0009.pdf PDF
Plans_-_Amendment_8.pdf PDF
W912DS-14-B-0007_Amendment_0008.pdf PDF
W912DS-14-B-0007-0007.pdf PDF
W912DS-14-B-0007-AMENDMENT_0006.pdf PDF
W912DS-14-B-0007_AMENDMENT_0005.pdf PDF
Plans_-_Amendment__5.pdf PDF
W912DS-14-B-0007_Amendment_0004.pdf PDF
W912DS-14-B-0007_AMENDMENT_0003.pdf PDF
Bid_Schedule_-_Thule_Consolidation_2_-_Amendment__3.pdf PDF
Appendix_T_-_FY14__FY15_Sealift_Rates.pdf PDF
W912DS-14-B-0007-AMENDMENT_0002.pdf PDF
W912DS-14-B-0007-AMENDMENT_0002_Plans.pdf PDF
W912DS-14-B-0014-AMENDMENT_0001.pdf PDF
Package_1_-_100_Thule_Consolidation_2_-_Plans.pdf PDF
Appendix_U_-_DBA_Waiver.pdf PDF
Appendix_I_-_Slug_Mgmt_Plan.pdf PDF
Appendix_V_-_Project_Site_Survey.dwg DWG drawing
Appendix_J_-_Installation_HAZMAT_Management_Plan.pdf PDF
Appendix_L_-_Affirmative_Proc_Plan.pdf PDF
Package_2_-_100_Thule_Consolidation_2_-_Specifications.pdf PDF
Package_3_-_100_Thule_Consolidation_2_-_SID-CID.pdf PDF
Appendix_D_-_HWM_Plan.pdf PDF
Appendix_M_-_PCB_Replacement_Plan.pdf PDF
Appendix_E_-_Spill_Prevention-Response_Plan.pdf PDF
Appendix_F_-_PPM_Plan.pdf PDF
Appendix_A_-_Active_Landfills.pdf PDF
Appendix_B_-_NFS_Material_Borrow_Site.pdf PDF
Appendix_N_-_Asbestos_Management_Plan.pdf PDF
Appendix_S_-_Pacer_Goose_Shipping_Instructions.pdf PDF
Appendix_P_-_Demo_As-Built_and_Asbestos_Surveys.pdf PDF
Appendix_K_-_FGS-GL_(Environmental_Protection).pdf PDF
Appendix_O_-_Lead_Paint_Management_Plan.pdf PDF
W912DS-14-B-0007_SOLICITATION.pdf PDF
Appendix_C_-_Conservation_Mgmt_Plan.pdf PDF
Appendix_H_-_Storm_Water_Mgmt_Plan.pdf PDF
Appendix_G_-_Solid_Waste_Mgmt_Plan.pdf PDF
Appendix_R_-_Geotechnical_Investigation.pdf PDF
Appendix_Q_-_Shipping_Rates_Gov_Furnished_Transport.pdf PDF
Appendix_T_-_FY14_Sealift_Rates.pdf PDF
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912DS-14-B-0007- AMENDMENT 0002

BID SCHEDULE

FY14 Thule Consolidation 2 Thule AB, Greenland

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Base Bid Item Construction of FY 14

FFP

Consolidated 2 Facility, Thule Air Base: All work (includes all plant, labor, and material) for the FY14 Thule Consolidation 2 as described in the plans and specifications except for work included in the other Line items.

FOB: Destination

MILSTRIP: W16ROE40080817

PURCHASE REQUEST NUMBER: W16ROE40080817

NET AMT

0002 1 Job Base Bid Item Construction of FY 14

FFP

Consolidated 2 Facility, Thule Air Base: Site work, all work outside the five-foot line of the building perimeter.

FOB: Destination

ITEM NO

SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0003 1 Job Base Bid Item Construction of FY 14

FFP

Consolidated 2 Facility, Thule Air Base: All work for the Final Record Drawing Submission (See paragraph 11 of Section 00800). THIS LINE ITEM IS PRE-

PRICED AT 300,000 DKK. THIS LINE ITEM IS A FIRM FIXED PRICE LINE

ITEM AND THE PRICE SHOWN MAY NOT BE CHANGED, SEE

PARAGRAPH 11(i) of Section 00 80 00.00 18

Construction of FY 14

FFP

Consolidated 2 Facility, Thule Air Base: Transportion: All Government Furnished Transportation From Norfolk, Virginia to Thule Air Base. This Line Item is for Informational Purposes Only. This Line Item is not Priced.

0004AA 1 Job Base Bid Iem Construction of FY 14

FFP

Consolidated 2 Facility, Thule Air Base: Transportation: all Government Furnished Transportation From Norfolk, Virginia to Thule Air Base.

0004AB 1 Job Base Bid Item Construction of FY 14

FFP

Consolidated 2 Facility, Thule Air Base: Transportation: All Government Furnished Transportation from Thule Air Base to Norfolk, Virginia. TONNAGE

(VOLUME)

0005 1 Job Base Bid Item Construction of FY 14

FFP

Consolidated 2 Facility, Thule Air Base Transportation: Furnished From Denmark to Thule Air Base.

0006 1 Job Base Bid Item Construction of FY 14

FFP

Construction of FY14 Consolidated 2 Facility, Thule Air Base: Defense Base Act (DBA) Insurance if required. Refer to Appendix U - DBA Waiver, Paragraph D, and Section 00 80 00.00 18 Paragraph 76 - DBA Insurance Rates, for applicability.

The amount listed by the bidder on this CLIN is the estimated DBA insurance premium (estimated payroll of the bidder and its subcontractors, multiplied by the applicable rate(s)).

The actual amount paid by the Government under this CLIN will be based on the amount of the Rutherfoord invoice submitted by the bidder after contract award. In the event of recalculation of the premium by CNA based on actual payroll amounts, the Contracting Officer will adjust this CLIN by contract modification to reflect actual premium amounts paid.

NOTE: IF NOT REQUIRED BID must be 0.00 DKK

0007 1 Job OPTION Optional Bid Item No. 1

FFP

Construction of FY14 Consolidated 2 Facility, Thule Air Base: All work (includes all plant, labor, and material) for the FY14 Thule Consolidation 2 Snow Removal portion of the facility inclusive of site work as described in the plans and specifications. Inclusive of transportation from Norfolk, Virginia and/or Denmark to Thule AB and return to Norfolk, Virginia and/or Denmark.

If using Government provided Transportation, provide Tonnage:

Volume from Norfolk, Virginia to Thule Air Base

___________________(MT)

Volume from Thule Air Base to Norfolk, Virginia

___________________(MT

0008 1 Job OPTION Optional Bid Item No. 2

FFP

Construction of FY14 Consolidated 2 Facility, Thule Air Base: All work (includes all plant, labor, and material) for the connection of Thermistor Strings to the Building Automation System (BAS) as described in the plans and specifications.

0009 1 Job OPTION Optional id Item No. 3

FFP

Construction of FY14 Consolidated 2 Facility, Thule Air Base: All work (includes all plant, labor, and material) for providing and installing BACnet Networked Thermostat for Hot Water Unit Heaters and Panel Radiators for remote monitoring and control by the BAS as described in the plans and specifications.

0010 1 Job OPTION Optional Bid Item No. 4

FFP

Construction of FY14 Consolidated 2 Facility, Thule Air Base: All work (includes all plant, labor, and material) for the demolition of Building 1090 as described in the plans and specifications.

0011 1 Job OPTION Optional Bid Item No. 5

FFP

Construction of FY14 Consolidated 2 Facility, Thule Air Base: All work (includes all plant, labor, and material) for the demolition of Building 563 as described in the plans and specifications.

0012 1 Job OPTION Optional Bid Item No. 6

FFP

Construction of FY14 Consolidated 2 Facility, Thule Air Base: All work (includes all plant, labor, and material) for the demolition of Building 836 as described in the

0013 1 Job OPTION Optional Bid Item No. 7

FFP

Construction of FY14 Consolidated 2 Facility, Thule Air Base: All work (includes all plant, labor, and material) for the demolition of Building 580 as described in the

0014 1 Job OPTION Optional Bid Item 8

FFP

Construction of FY14 Consolidated 2 Facility, Thule Air Base: All work (includes all plant, labor, and material) for the demolition of Building 630 as described in the

0015 1 Job OPTION Optional Bid Item No 9

FFP

Construction of FY14 Consolidated 2 Facility, Thule Air Base: Additional Demolition Equipment inclusive of transportation from Norfolk, Virginia and/or Denmark to Thule AB and return to Norfolk, Virginia and/or Denmark for completing demolition work as outlined in Options No 4 thru No 8.

If using Government provided Transportation, provide Tonnage:

Volume from Norfolk, Virginia to Thule Air Base

___________________(MT)

Volume from Thule Air Base to Norfolk, Virginia

___________________(MT)

W912DS-14-B-0007-AMENDMENT 0002

TOTAL BID

TOTAL BASE BID PRICE FOR LINE ITEMS 0001- 0006

TOTAL OPTIONS BID PRICE FOR LINE ITEMS 0007- 0015

TOTAL BASE BID WITH OPTIONAL BID LINE ITEMS 0001 – 0015

NOTES:

1. All goods must be wrapped accordingly. It should be protected to withstand handling as well as storage and transportation by sea. Due to packing in containers, in warehouse and on ship every package must be able to withstand a pressure from above of at least it's own weight. If you have any questions please contact Royal Arctic Line Helle Christensen by phone: 99 30 32 26 or by e-mail: hch@ral.dk.

2. “Transportation from Denmark” means that the U.S. Embassy will provide a ship from Denmark to Thule AB,GL; however, it is not free. The Contractor shall reimburse the U.S. Embassy in Denmark the actual carrier cost for the transportation. This is not considered Government Furnished Transportation.

3. Bids must be in Danish Kroners.

4. Construction Award will not include Government Furnished Transportation.

5. Contractors not utilizing Government Furnished Transportation shall include shipping costs in their Base Bid Items, as applicable. In such cases, the applicable transportation price schedule should be marked “NOT APPLICABLE” or “0.”.

6. All pallets and containers used for the transportation of contractor’s cargo from Denmark shall be the contractor’s responsibility and the contractor’s expense.

7. The Contractor shall be billed for all quantities over the amount stated in the bid items for Government Furnished Transportation or shall ship at his own expense through private carrier all items over the amounts stated in the bid items.

8. The Basis of evaluation will be the lowest responsive/responsible bidder calculated based on ABSOLUTE VALUES of each CLIN: Base Bid (sum of CLIN 0001 thru 0006) plus Option No 1 thru Option No 9 (CLIN 0007 thru CLIN 0015).

9. Bidders are required to bid on the Base Bid and all Optional Bid Items or their bids will be rejected.

10. Bidders are reminded that they must bid on the issued plans and specifications as amended. Any deviations, conditions or attachments made by the bidder himself thereto may render the bid non-responsive and be cause for its rejection.

11. Option #1, #2, #3, #9: At any time prior to 90 calendar days after award of the contract, the Government at its option, may execute these Options. Execution of these options will not alter the project completion date of the contract.

12. Option #4 thru #8: At any time prior to 90 calendar days after award of the contract, the Government at its option, may execute these Options. Execution of these options will extend the contract duration by 120 calendar days.

13. Option #9 shall be executed if and only if any option(s) #4 thru #8 is/are executed.

14. Line Item Number 0003 is pre-priced at 300,000DKK, it’s a firm fixed line item, and the price shown may not be changed, see paragraph 11(i) of Section 00800.

15. Bid Acceptance Period: Bidders Bids are to be valid for 90 calendar days for bid acceptance from the Bid Opening.

mailto:hch@ral.dk

16. NOTE: The items mentioned in the CID package under paragraphs 2.2 and 2.3 are NOT IN CONTRACT: i.e. refrigerators, microwaves, dishwashers, washers, dryers, furniture (tables, chairs, office shelving, desks, computers and computer equipment, non-built in work surfaces, trash bins).

17. Line Item Number 0006: Defense Base Act (DBA) Insurance if required. Refer to Appendix U

- DBA Waiver, Paragraph D, and Section 00 80 00.00 18 Paragraph 76 - DBA Insurance Rates, for applicability.

IF NOT REQUIRED BID 0.00 DKK for this CLIN

W912DS-14-B-0007-AMENDMENT 0002
W912DS-14-B-0007-AMENDMENT 0002
W912DS-14-B-0007-AMENDMENT 0002

File details come from the government source that posted it. Updated .