QA_Parts Kit Hydraulic Pump.xlsx

XLSX spreadsheet 13 KB Posted

Attached to
Solicitation: Parts Kit, Hydraulic Pump ( NSN: 4320-01-086-6793)
Solicitation number
W912CH-26-B-0009
Issued by

About this file

This file is a Questions and Answers (Q&A) document related to Solicitation W912CH-26-B-0009 for a Parts Kit, Hydraulic Pump (NSN 4320-01-086-6793, Part Number 12284862). The Q&A addresses procedural and technical clarifications that arose during the solicitation period. Key issues resolved include completion of the Technical Data Package (TDP) with nine missing prints (various harnesses, covers, cables, and hose assemblies), which were subsequently added to SAM. The government also addressed bidder requests for deadline extensions and clarified that the initial September 18, 2026 closing date was extended to October 9, 2026, with bid opening moved to October 20, 2026, following Amendment 0001. Technical documentation challenges were resolved, including the addition of missing Drawing 12347278 and reupload of Drawing 12273456 to address file access issues.

Amendment 0002, issued September 23, 2026, clarified the delivery schedule confusion regarding First Article Testing (FAT) requirements. The clarification specified that the initial delivery of 50 units shall occur 600 calendar days after receipt of order, with subsequent deliveries of 50 units every 30 calendar days thereafter, rather than the conflicting 300-day start date mentioned in earlier solicitation language. This is a five-year Firm-Fixed-Price Indefinite-Delivery Indefinite-Quantity (IDIQ) contract with estimated quantities of 106 units in year one and 125 units in years two through five, with a five-year minimum guarantee of 15 units and maximum of 625 units. The procurement is full and open competition, and bidders require TDP access (Distribution Statement D, limited to Department of War and contractors) prior to bid submission.

View the file

Other files

File Type Posted
QA_Parts Kit Hydraulic Pump.xlsx XLSX spreadsheet
W912CH26B0009 AMD 0002.pdf PDF
W912CH26B0009 AMD 0001.pdf PDF
QA_Parts Kit Hydraulic Pump.xlsx XLSX spreadsheet
QA_Parts Kit Hydraulic Pump.xlsx XLSX spreadsheet
QA_Parts Kit Hydraulic Pump.xlsx XLSX spreadsheet
QA_Parts Kit Hydraulic Pump.xlsx XLSX spreadsheet
W912CH26B0009.pdf PDF
First Article Waiver Worksheet.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

NumberQUESTIONANSWER
1Please be advised that the TDP for subject solicitation is incomplete.

Our initial review shows that the following prints are missing from the current TDP:

•HARNESS, PN 12284943
•HARNESS, PN 12284944
•HARNESS, PN 12284988
•COVER, PN 12284990
•CABLE, PN 12284992
•CABLE, PN 12311974
•CABLE, PN 12311975
•HOSE, PN 12387220
•CABLE, PN 12387571

All of the above are called out on the solicited kit 12284862 print.

Will you please update the TDP on SAM to include the above prints? The TDP has been updated in SAM with the requested prints and should now be complete. We apologize for any inconvenience this may have caused.

Please let us know if you have any further questions.

2 We would like to request an extension for solicitation W912CH-26-B-0009 (Parts Kit, Hydraulic Pump), as we are still awaiting quotes from several vendors. Granting an extension would allow us to remain competitive and provide the government with the best possible pricing. Thank you for your interest in Solicitation W912CH-26-B-0009 (Parts Kit, Hydraulic Pump) and for bringing your request to our attention.

Please note that the solicitation remains open until September 18, 2026. As standard procedure, the Government assesses submission timelines closer to the closing date before making a determination regarding an extension.

At this time, the deadline remains unchanged. We encourage your team to continue preparing your proposal in the interim, as an extension may be evaluated and considered at a later date if deemed necessary. Any official changes or extensions will be posted via formal amendment.

3 After reviewing the TDP, please be advised that Drawing 12347278 is missing, and Drawing 12273456 is unable to be opened. Drawing 12347278 is referenced in the following sub-assemblies: 12284943, 12284944, 12284988, 12284945, 12284992, 12387571, 12311974, and 12311975. Drawing 12273456 is referenced in the following sub-assemblies: 12284943, 12284944, 12284988, 12284945, and 12284992. Drawing 12347278 has been successfully included in the Technical Data Package TDP 1 of 2 Drawings zip file.

Regarding your access issues with drawing 12273456, we have verified that the file is fully functional and opens correctly on our end. To assist with any potential file corruption during transmission, I have removed and re-uploaded the drawing to the zip file.

Please attempt to redownload the package. If the technical issue persists on your network, we recommend contacting your local IT support to ensure there are no local firewall or file compatibility restrictions 4 Does USG anticipate releasing an amendment to extend the due date, given that the current due date is this Friday and the drawings are still unavailable? Thank you for your continued interest in the Sealed Bid Solicitation W912CH-26-B-0009.

At this time, we will be extending the solicitation deadline to 09 October 2026. A formal amendment has been posted. Please be aware that circumstances can change, and an further extension may be considered at a later date. Therefore, we highly recommend that you continue to develop your proposal to be in the best position possible should the opportunity for a later submission arise.

5 Our SDVOSB would like to request for our response to this bid until 9 October 2026.

Thank you for your time and consideration.

6 Line F.2.1 Start deliveries 600 calendar days ARO, while Line F.2.2 outlines that 50 units need to be delivered 300 calendar days ARO and that every 30 days 50 units are to be delivered.

The two starting points of 600 and 300 seem to be at odds with each other.

Can you help clarify this for our team? Amendment 0002 to Solicitation W912CH-26-B-0009 has been issued.

The purpose of this amendment is to clarify the Government-required delivery schedule when First Article Testing (FAT) is required.

7
8
9
10