W9128F25Q0016 P00001.pdf

PDF 974 KB Posted

Attached to
Elmendorf AFB FY25 CMP Tank Inspection
Solicitation number
W9128F25Q0016
Issued by

About this file

This is a Request for Quotes (RFQ) issued by the U.S. Army Corps of Engineers, Omaha District for API 653 internal tank inspection services at Joint Base Elmendorf-Richardson (JBER), Alaska. The solicitation (W9128F25Q0016) is set aside 100% for Service-Disabled Veteran-Owned Small Businesses under NAICS code 541990 with a size standard of $19.5 million. Quotes are due by February 19, 2025 at 2:00 PM CST.

The scope of work includes performing an API 653 internal inspection on tank facility 738, replacing wiper seals and penetration seals, ultrasonic testing, coating condition survey by a NACE Level II certified inspector, and testing of secondary containment areas. The contractor must provide all personnel, equipment, supplies, and materials necessary to complete the work. Key deliverables include a Project Inspection Management Plan, Health and Safety Plan, inspection reports (draft and final), and coating condition survey report. The period of performance is 182 days after contract award. The contract will be awarded as a firm-fixed-price contract based on technical capability, experience, and price. Questions must be submitted 7 days before the quote due date to the Contract Specialist Ryan Saville and Contracting Officer Brent Bertrand.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ADDENDUM

(No Collect Calls)

W9128F25Q0016 12-Feb-2025

b. TELEPHONE NUMBER

8. OFFER DUE DATE/LOCAL TIME

02:00 PM 19 Feb 2025

5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA – FAR (48 CFR) 53.212

(TYPE OR PRINT)

(SIGNATURE OF CONTRACTING OFFICER)

ADDENDA ARE

26. TOTAL AWARD AMOUNT (For Gov t. Use Only )

23.

CODE 10. THIS ACQUISITION IS

SUCH ADDRESS IN OFFER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT

BELOW IS CHECKED

TELEPHONE NO.

W9128F9. ISSUED BY

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

RYAN L SAVILLE

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER

(TYPE OR PRINT)

30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA

0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.

25. ACCOUNTING AND APPROPRIATION DATA

1. REQUISITION NUMBER

20.

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

. YOUR OFFER ON SOLICITATION

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

% FOR:SET ASIDE:UNRESTRICTED OR X

SMALL BUSINESS

17a.CONTRACTOR/ CODE FACILITY

OFFEROR CODE

U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST

CONTRACTING OFFICE

1616 CAPITOL AVENUE

OMAHA NE 68102-4901

18a. PAYMENT WILL BE MADE BY CODE

RATED ORDER UNDER

DPAS (15 CFR 700)

13a. THIS CONTRACT IS A

13b. RATING

CODE15. DELIVER TO CODE 966752 16. ADMINISTERED BY

12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

14. METHOD OF SOLICITATION

RFQ IFB RFPX

COE PROGRAMS MANAGEMENT BRANCH

LAURA STEPHENS

USA, OMAHA CENWO-PM-P

1616 CAPITOL AVE

OMAHA NE 68102-4901

TEL: 402-995-2802 FAX:

FAX:

TEL: SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

X 8(A)

HUBZONE SMALL

BUSINESS

SIZE STANDARD:

$19,500,000

NAICS:

541990

OFFER DATED

29. AWARD OF CONTRACT: REF.

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

EMAIL:

TEL:

31c. DATE SIGNED

SEE SCHEDULE

SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT

24.22.21.19.

WOMEN-OWNED SMALL BUSINESS (WOSB)

ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

(CONTINUED)

PAGE 2 OF57

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

37. CHECK NUMBER

FINALPARTIALCOMPLETE

36. PAYMENT35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER

FINAL

33. SHIP NUMBER

PARTIAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV. 2/2012) BACK

Prescribed by GSA – FAR (48 CFR) 53.212

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

SEE SCHEDULE

20.

SCHEDULE OF SUPPLIES/ SERVICES

21.

QUANTITY UNIT

22. 23.

UNIT PRICE

24.

AMOUNT

19.

ITEM NO.

W9128F25Q0016

Section SF 1449 - CONTINUATION SHEET

PERFORMANCE WORK STATEMENT

SP-POL-CMP-INSPECT-PWS-ELM

Joint Base Elmendorf-Richardson, AK

Part 1 General Information

1. GENERAL:

1.1. Scope: This is a non-personnel services contract to perform inspections on

Department of Defense fuel tanks. This service entails replacing wiper seals and providing an aboveground storage tank (AST) Inspection on tank(s) listed in Attachment B.

1.2. Background: See Attachment J for previous inspection report(s).

1.3. Objectives: The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items. The contractor shall also provide non-personnel services necessary to replace wiper seals and perform an AST Internal inspection on the tank(s), as applicable, at the location and for the tanks specified in Attachment B, as defined in this Performance Work Statement (PWS), except for those items specified as government furnished property and services.

1.4. General Information

1.4.1. Recognized Holidays:

New Year’s Day Martin Luther King Birthday President’s Day Memorial Day Juneteenth National Independence Day Independence Day Labor Day Columbus Day Veteran’s Day Thanksgiving Christmas

1.4.2. Hours of Operation: The contractor is responsible for conducting business, between the hours of 0730-1630 Monday through Friday, except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. Other than normal duty hours, work must be coordinated with the Contracting Officer (KO) or his/her designated representative. The Contractor must always maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall maintain stability and continuity of the workforce.

1.4.3. Place of Performance: The work to be performed under this contract will be performed at the installation and facilities identified in Attachment B.

1.4.4. Type of Contract: The government will award a Firm Fixed Price Contract

1.4.5. Security Requirements: Reference Attachment A – General Installation Security Requirements

1.4.6. Site Access: Contractor shall coordinate with Installation personnel for access to the site. Points of contact for the installation will be provided upon award.

1.4.7. Meetings/Kick-Off Meetings: The Contractor shall coordinate with the USACE Project Manager (PM) and conduct a kickoff meeting prior to field activities.

This can be accomplished either prior to mobilization and inspection activities or onsite prior to commencement of inspection activities. The Work Plan shall be discussed, and further coordination and scheduling shall be accomplished at this meeting. These meetings shall be at no additional cost to the government.

1.4.8. The Contractor shall call the installation 72 hours prior to mobilization to verify tank fuel quantities are at the quoted/verified amount as stated in Attachment B as the contractor is not authorized to remove/transfer or dispose of more fuel than what is stated in the contract per Attachment B.

1.4.9. The Contractor shall be responsible to establish a report of findings and coordinate a teleconference after the inspection is complete and at least 24 hours prior to placing tank back into service. This teleconference will review deficiencies found during the inspection with the Government making the final decision on whether or not to place this tank back into service. The Contractor can use Attachment E - API INTERNAL INSPECTION TELECON BRIEFING TEMPLATE or their own format however this document shall include the next recommended inspection intervals for both External and Internal Inspection, and State regulated inspection intervals, if applicable. Also, when listing the findings, they shall be categorized as either “Mandatory” or “Recommended”.

Coordinate with POC’s, individuals to be identified after project award, from Service Control Point (SCP), Defense Logistics Agency (DLA), and USACE.

1.4.10. Key Personnel: Certified API 653 Inspector and Project Manager.

1.4.11. Organizational Conflict of Interest: Contractor and subcontractor personnel performing work under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications, or work statements, etc.) or perform evaluation services which may create a current or subsequent Organizational Conflict of Interests (OCI) as defined in FAR Subpart 9.5. The Contractor shall notify the Contracting Officer immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the Contracting Officer to avoid or mitigate any such OCI.

The Contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the Contracting Officer and in the event the Contracting Officer unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the Contracting Officer may affect other remedies as they deem necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.

1.4.12. Suitability For Service: Evaluate inspection data to determine suitability for continued use. Identify conditions which pose a risk to integrity. Determine a metal loss threshold for mandatory repairs. In the determination of mandatory repairs:

Use a "first, do no harm" approach to classifying tank repairs.

Use Desired Service Interval as the time to next inspection unless notified otherwise by the Contracting Officer.

Use minimum remaining thickness (MRT) no less than 100 mils at the next inspection.

Do not classify as mandatory repair of conditions which are noncompliant with current standards but are un-related to structural or hydraulic integrity (e.g., gouge, improper weld spacing, weld profile).

Apply repair determination to individual indications. Do not average across an entire plate or course.

PART 2

GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND

SERVICES

2. GOVERNMENT FURNISHED ITEMS AND SERVICES:

2.1. Services: No Government furnished items or services are required.

PART 3

CONTRACTOR FURNISHED ITEMS AND SERVICES

3. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:

3.1. General: The Contractor shall furnish all supplies, equipment, facilities, and services required to perform work under this contract that are not listed under Section 2 of this PWS.

3.2. Equipment: The Contractor shall provide all tools and inspection equipment needed to perform the inspection and other services to be performed under the PWS.

3.2.1. Precision Equipment: Contractor is responsible to ensure all equipment to be used is certified and calibrated to the parameters and tolerances of the required equipment.

3.2.2. Gaskets: Composition ring, one piece factory cut, compliant with ASME

B16.21, Buna-N. Gaskets must be composed of either graphite or synthetic fibers in a nitrile binder and must be resistant to the effects of aviation hydrocarbon fuels and manufactured of fire-resistant materials. Use full-faced gaskets for flat-face flanged joints. Buna-N material must conform to SAE

AMS3275.

3.2.3. Flange Bolts, Nuts, and Washers: Bolts for manway covers must conform to

ASME B18.2.1. Bolts must be of sufficient length to obtain full bearing on the nuts and must project no more than three full threads beyond the nuts with the bolts tightened to the required torque. Bolts must be regular hexagonal bolts conforming to ASME B18.2.1 with material conforming to ASTM A193/A193M, Class 2, Grade B8. Bolts must be threaded in accordance with ASME B1.1, Class 2A fit, Coarse Thread Series, for sizes one inch and smaller and Eight-Pitch Thread Series for sizes larger than one inch. Use stainless steel washers dimensioned in accordance with ASTM F436 flat circular and fabricated from the same grade of stainless steel as the bolt.

3.2.4. Periphery Double Wiper Seal and Penetration Seals: Periphery seals must be flexible wiper squeegee and made of closed cell cast urethane. The periphery seal must fit the space between the tank shell and the outer edge of the floating pan with two flexible seals, a primary and a secondary. The seals, primary and secondary as a unit, must accommodate a deviation between the path of the floating pan relative to the tank shell of an additional 4 inches of compression and an additional extension of 2 inches from its normal compressed position at any fluid level. The primary seal must be above the liquid level. Foam filled coated-fabric seals must not be accepted.

The secondary seal must be above the primary seal. Seals must be capable of being replaced during tank operations, be durable in the tank's environment, be abrasion resistant, and not discolor or contaminate the liquid stored in the tank. Seals must be manufactured in the United States and must be provided in minimum continuous lengths of 28 feet with no factory splices.

Seals must be compatible with avgas, fuel oil, gasoline/ethanol, gasoline/MTBE 80/20, gasoline (unleaded), aviation turbine fuels, kerosene, and sea water. Material must be compliant with UFGS 33 56 21.17. The wiper seal product data specification sheets from the manufacturer must be submitted for review with the contractor’s proposal.

3.3. Project Inspection Management Plan (PMP): As part of the initial PMP, the

Contractor shall prepare and include a brief (< 10 pages) Work Plan, as an attachment, which will include proposed schedule, inspection activities, personnel performing inspection, required training certificates, and additional data or support requests.

3.4. Health and Safety Plan (HSP) and Accident Prevention Plan (APP): The

Contractor will prepare a Health and Safety Plan (HSP) to comply with 29 Code of Federal Regulations (CFR) 1910 and 1926 as well as applicable Military Service (Army, Air Force, or Navy), OSHA, state, host nation, and local and installation health and safety regulations regarding the proposed work effort. Qualifications for individuals who will be on-site for safety shall be submitted in the HSP.

3.4.1. The Accident Prevention Plan (APP) is required by FAR clause 52.236-13.

The APP describes the methods by which the contractor or USACE personnel will meet the safety and health requirements listed in EM 385-1-1. Entry into Confined Spaces shall comply with the requirements of 29 CFR 1910.146.

Provide additional monitoring for toxic (petroleum) vapors in addition to normal air monitoring requirements.

3.4.2. Abbreviated Accident Prevention Plans may be developed and submitted per

Form A-01 Abbreviated Accident Prevention Plan Checklist Page A-13 of the EM 385-1-1. This may be submitted to develop a plan more specific to the work performed under this PWS but shall still comply as indicated above.

PART 4

SPECIFIC TASKS

4. Specific Tasks: Per each tank as identified in attachment B

4.1. Basic Services.

API Internal:

4.1.1. Perform a Tel-con kick-off meeting either prior to mobilization or the morning of the commencement of work on-site.

4.1.2. Remove, transfer, and/or dispose of remaining fuel quantities as stated in

Attachment B. The contractor will be responsible to coordinate with environmental and safety authorities having jurisdiction to obtain and execute required permits, manifests, etc. Tank cleaning shall be done in accordance with UFGS 33 01 50.55.

4.1.3. The tank Inspection shall be in conformance with applicable industry standards API 653, API RP 575, NFPA 30, NFPA 326, UFGS 33 01 50.65, and in compliance with 40 CFR 112, UFC 3-460-01, UFC 3-460-03 and any other applicable federal, state, local and service requirements. Scan 100 percent of the tank bottom, as interior appurtenances allow, for indications such as metal loss, pits, cracks, gouges, and general corrosion. Distinguish between product and backside indications. Measure metal thickness with an ultrasonic method. Procedures must be compliant with ASME BPVC SEC V.

Record measurements, exclusive of coating, for all tank bottom plates.

Provide UT thickness measurement on no less than five locations per bottom plate and at indications from the screening technologies determined to be relevant. Mark relevant indications on tank surfaces in a neat and professional manner adjacent to the indication. Collect data to be used in the assessment of corrosion growth, structural integrity, brittle fracture, and hydraulic integrity. Complete the API Std 653 checklist and provide them with the DRAFT and FINAL reports. Utilize UFC 3-460-01 Table 8-1 and indicate appurtenances that are not present. The attached Inspection Report template should be utilized in submitting both the DRAFT and FINAL inspection reports. Contractor shall leave a clean and orderly site upon the completion of the inspection.

4.1.4. The contractor must complete a Coating Condition Survey (CCS) on all the interior and exterior tank coating systems. The CCS should be accomplished by personnel from a business that routinely performs coating evaluations, and the individual investigator should be Certified NACE Level II or higher. The CCS should be sufficiently detailed to provide all technical information about the coatings. At a minimum, the CCS should provide a detailed report of:

1. Existing coating conditions, including condition of coating film, and the existence of potentially hazardous substances that may impact coating management (i.e. lead, cadmium, chromium); 2. Analysis of remaining coating life, suitability of overcoating, and technical requirements for overcoating; 3. Technical recommendations for the most cost effective management of existing coating systems, including any hazardous materials present in paint film; and 4. Any other information of interest to the coating system management that should be identifiable by an individual trained and experienced in the field of coating analysis, coating failure analysis, and coating design. A total of three coating samples must be taken: one from the exterior shell, one on the interior shell within three feet of the bottom, and one on the interior shell above the IFR. Repair sample locations in accordance with UFGS 09 97 13.27 and UFGS 09 97 13.17. The findings from the CCS must be included on the DRAFT and FINAL inspection reports.

4.1.5. The contractor shall visually inspect the secondary containment area for the ability to contain the entire contents of the tank in the event of catastrophic failure, assessing for cracks, settlement, and deterioration. Record dimensions of cracks and provide photographic evidence of each deficiency.

Visually assess the liner integrity and impermeability where applicable.

Provide calculations demonstrating the containment area has sufficient capacity in accordance with 40 CFR 112. Containment drain system shall be tested as follows.

4.1.5.1. Drain Line and Release Valve. The Contractor shall perform a hydrostatic test to ensure the drainpipe and release valve do not leak. Test in accordance with applicable requirements of AWWA C600 for hydrostatic testing. Ensure the release valve is closed and pressurize the end of the pipe within the containment basin sump. Test for leakage by filling the pipe with water and pressurizing to 10 psi using a suitable pump connected to the pipeline. The test pressure shall not vary by more than ±1 psi for the duration of the test. Hold this pressure for not less than 2 hours. If the system does not hold pressure, check the outfall point to see if water is bypassing the valve. Test pressure shall be maintained during the test by adding makeup water through the pressure test pump into the pipeline. Accurately note the amount of makeup water required to maintain pressure during the test.

4.1.5.2. Containment Drain Inlet. The Contractor shall perform a hydrostatic test to ensure the integrity of the inlet sump. Test for leakage by filling the inlet with water to a level at least 1-2 inches above the top of the inlet structure.

The inlet shall hold this water for not less than 2 hours with no measurable change in the water level.

4.1.6. The existing wiper seal (foam log, double wiper etc.) shall be removed and completely replaced with a new double wiper seal in accordance with UFGS 33 56 21.17 and the IFR manufacturer's recommendations; penetration seals in the floating pan will also need replaced.

4.1.7. Coverage of the UT scan shall include 5 points per shell plate on the first shell course. Spot UT scans shall be made once every foot along the circumference of the tank shell within the critical zone and along the tank chime as accessible. 5 points per shell plate shall also be taken along the spiral staircase for each shell course as accessible. Provide UT scans of tank shell nozzles on the first shell course and their respective reinforcement plates as applicable. Include all findings in the inspection report.

4.1.8. Upon completion of the Internal inspection the contractor shall provide a legible tank stencil or decal, consisting of black letters at least 1” in height, stating the date cleaned and inspected, the contractor’s name and the name of the contractor’s personnel supervising the work. Remove any existing stencils displaying previous inspection information. New information shall be provided in the following format:

Date Cleaned and Inspected: Day-Month-Year ABC Contracting Supervisor: John Doe

4.1.9. Provide Tel-con out briefing prior to closing up the tank.

4.1.10. When the tank is ready to be closed and RTO, the Contractor is responsible to provide new stainless-steel bolts and all manway gaskets on the first shell course and ensure there are no leaks at the manways by filling the tank to at least the first shell course.

4.1.11. Provide photographic documentation of the following: PLC make and model, Input/Output Alarm Modules including directories, Level Alarm Panel, Annunciator Panel, and any As-Builts that are in the alarm panel. Coordinate with the installation as needed to obtain this information.

4.1.12. Provide DRAFT and FINAL inspection reports per the attached templates.

The report(s) must include a record of non-destructive examination (NDE) findings with drawings depicting plate layout and thickness measurement locations. Incorporate engineering analysis, suitability for service analysis, corrosion rate determinations, and remaining service life calculations. Provide separate report for each tank inspected. Specify the due date for the next inspection. Include the API Std 653 inspector of record certificate number and signature.

PART 5

APPLICABLE PUBLICATIONS

5. APPLICABLE PUBLICATIONS (CURRENT EDITIONS)

5.1. The Contractor must abide by all applicable regulations, publications, manuals, and local policies and procedures.

American Petroleum Institute (API) 653 Standard for the Tank Inspection, Repair, Alteration, and

Reconstruction 650 Welded Tanks for Oil Storage

RP 575 Inspection Practices for Atmospheric and Low-pressure Storage Tanks

Std 2015 Requirements for Safe Entry and Cleaning of Petroleum Storage Tanks

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 30 Flammable and Combustible Liquids Code NFPA 70 National Electrical Code (NEC) NFPA 326 Standard for Safeguarding of Tanks and Containers for Entry, Cleaning, or Repairs NFPA 704 Standard System for the Identification of the Hazards of Materials for Emergency Response

UNIFIED FACILITIES CRITERIA (UFC)

UFC 3-460-01 Design: Petroleum Fuel Facilities UFC 3-460-03 Petroleum Fuel Systems Maintenance

UNIFIED FACILITIES GUIDE SPECIFICATIONS (UFGS)

UFGS 09 97 13.17 Three Coat Epoxy Interior Coating of Welded Steel Petroleum

Fuel Tanks UFGS 09 97 13.27 High Performance Coating for Steel Structures UFGS 33 01 50.55 Cleaning of Petroleum Storage Tanks UFGS 33 01 50.65 Inspection of Field Fabricated Fuel Storage Tanks UFGS 33 56 21.17 Single Wall Aboveground Fixed Roof Steel POL Storage Tank

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

40 CFR 112 EPA: Oil Pollution Prevention

PART 6

ATTACHMENT

7. Attachment/Technical Exhibit List:

7.1. Attachment A – General Installation Security Requirements

7.2. Attachment B – Fuel Storage Tank List

7.3. Attachment C – Fuel Storage Tank Data Sheet

7.4. Attachment D – Monthly Contractors Progress, Management and Status Report

7.5. Attachment E – Inspection Telecon Briefing Template

7.6. Attachment F – API Internal Inspection Report Template

7.7. Attachment G – Return to Service Letter

7.8. Attachment H – Not Applicable

7.9. Attachment I – API External Template

7.10. Attachment J.1 – Fac 738 Internal Inspection Report 2010

7.11. Attachment J.2 – Fac 738 External Inspection Report 2014

7.12. Attachment J.3 – Fac 738 External Inspection Report 2019

TECHNICAL EXHIBIT 1

Performance Requirements Summary

The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.

Performance Objective

Standard Performance Threshold

Method of Surveillance

PRS # 1.

Kick-Off Meeting with USACE and Stakeholders

Para. 1.4.7.

State, local, and federal requirements regulating fuel storage tanks

100% The contractor will schedule this Meeting either on-site prior to commencement of work or via teleconference prior to being onsite. Submit agenda and meeting minutes to stakeholders.

PRS # 2.

Provide API 653 Internal Inspection and visual inspection of the containment area

Para. 4.1.2 & 4.1.3.

State, local, and federal requirements regulating fuel storage tanks

100% Random Inspection

PRS # 3.

Provide API 653 Internal Inspection reports

Para 4.1.12

State, local, and federal requirements regulating fuel storage tanks

100% Random Inspection.

The contractor is to provide a DRAFT and FINAL report for MCX review and comment

PRS # 4.

Provide a CCS Report.

Para. 4.1.4.

NACE Level II 100% Random Inspection.

PRS # 5.

Provide a UT Inspection.

Para. 4.1.7.

State, local, and federal requirements regulating fuel storage tanks

100% Random Inspection.

PRS #6.

Wiper Seal Replacement Para. 4.1.6.

State, local, and federal requirements regulating fuel storage tanks

100% Random Inspection

PRS #7.

Out-Brief Meeting with USACE and Stakeholders

Para 4.1.9.

State, local, and federal requirements regulating fuel storage tanks

100% Contractor will coordinate a Tel-con and distribute the report of findings 24 hrs prior to the scheduled conference

DELIVERABLES SCHEDULE

DELIVERABLE SCOPE OF

WORK

PARAGRAPH

DUE DATE

Project Inspection Management Plan/Work Plan, Accident Prevention Plan & Health and Safety Plan (Draft)

3.3 & 3.4 15 days after award

Project Inspection Management Plan/Work Plan, Accident Prevention Plan & Health and Safety Plan (Final)

3.3 & 3.4 5 days after receipt of comments

Inspection and Evaluation Report – (Draft) 4.1.12

28 days after Field Inspection

Coating Conditions Survey (CCS) Report 4.1.4 28 Days after Field Inspection

Inspection and Evaluation Report – to include populated Attachment C Excel Sheet for each base (Final)

4.1.12

7 days after receipt of comments

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Facility 738

FFP

API Internal Tank Inspection Service –Facility 738 - All work to conduct Kick-Off meeting, complete API internal tank inspection, complete containment testing, UT scan, and complete DRAFT and FINAL reports FOB: Destination

PSC CD: H391

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0002 1 Tank Wiper Seal Replacement Facility - 738

FFP

Wiper Seal Replacement Facility - 738 - All work to replace wiper seal and pan penetration seals accordance with the PWS.

PSC CD: H391

NET AMT

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 Destination Government Destination Government 0002 Destination Government Destination Government

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 182 dys. ADC 1 COE PROGRAMS MANAGEMENT

BRANCH

LAURA STEPHENS

USA, OMAHA CENWO-PM-P

1616 CAPITOL AVE

OMAHA NE 68102-4901

402-995-2802

966752

0002 182 dys. ADC 1 (SAME AS PREVIOUS LOCATION)

966752

CLAUSES INCORPORATED BY REFERENCE

52.203-11 Certification and Disclosure Regarding Payments to Influence

Certain Federal Transactions

SEP 2024

52.203-12 Limitation On Payments To Influence Certain Federal Transactions

JUN 2020

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements

JAN 2017

52.204-7 System for Award Management OCT 2018 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-13 System for Award Management Maintenance OCT 2018 52.204-18 Commercial and Government Entity Code Maintenance AUG 2020 52.204-23 Prohibition on Contracting for Hardware, Software, and

Services Developed or Provided by Kaspersky Lab Covered Entities

DEC 2023

52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment

NOV 2021

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment

NOV 2021

52.209-10 Prohibition on Contracting With Inverted Domestic Corporations

NOV 2015

52.209-11 Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law

FEB 2016

52.232-40 Providing Accelerated Payments to Small Business Subcontractors

MAR 2023

52.242-15 Stop-Work Order AUG 1989 252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7000 Requirements Relating to Compensation of Former DoD

Officials

SEP 2011

252.203-7002 Requirement to Inform Employees of Whistleblower Rights DEC 2022 252.203-7005 Representation Relating to Compensation of Former DoD

Officials

SEP 2022

252.204-7002 Payment For Contract Line or Subline Items Not Separately Priced

APR 2020

252.204-7008 Compliance With Safeguarding Covered Defense Information Controls

OCT 2016

252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting

MAY 2024

252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support

JAN 2023

252.204-7016 Covered Defense Telecommunications Equipment or Services -- Representation

DEC 2019

252.204-7017 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services -- Representation

MAY 2021

252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services

JAN 2023

252.204-7019 Notice of NIST SP 800-171 DoD Assessment Requirements NOV 2023 252.204-7020 NIST SP 800-171 DoD Assessment Requirements NOV 2023 252.204-7021 Contractor Compliance with the Cybersecurity Maturity

Model Certification Level Requirement

JAN 2023

252.223-7008 Prohibition of Hexavalent Chromium JAN 2023 252.225-7031 Secondary Arab Boycott Of Israel JUN 2005 252.225-7048 Export-Controlled Items JUN 2013

252.225-7050 Disclosure of Ownership or Control by the Government of a Country that is a State Sponsor of Terrorism

DEC 2022

252.225-7973 (Dev) Prohibition on the Procurement of Foreign-Made Unmanned Aircraft Systems - Representation (DEVIATION 2024- O0014)

AUG 2024

252.232-7003 Electronic Submission of Payment Requests and Receiving Reports

DEC 2018

252.232-7015 Performance-Based Payments--Representation DEC 2022 252.232-7016 Notice of Progress Payments or Performance-Based Payments APR 2020 252.237-7010 Prohibition on Interrogation of Detainees by Contractor

Personnel

JAN 2023

252.244-7000 Subcontracts for Commercial Products or Commercial Services

NOV 2023

252.244-7000 Subcontracts for Commercial Products or Commercial Services

NOV 2023

252.246-7004 Safety of Facilities, Infrastructure, and Equipment for Military Operations

OCT 2010

252.247-7023 Transportation of Supplies by Sea OCT 2024

CLAUSES INCORPORATED BY FULL TEXT

52.212-1 INSTRUCTIONS TO OFFERORS--COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES

(SEP 2023)

(a) North American Industry Classification System (NAICS) code and small business size standard. The NAICS code(s) and small business size standard(s) for this acquisition appear elsewhere in the solicitation. However, the small business size standard for a concern that submits an offer, other than on a construction or service acquisition, but proposes to furnish an end item that it did not itself manufacture, process, or produce is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition--

(1) Is set aside for small business and has a value above the simplified acquisition threshold;

(2) Uses the HUBZone price evaluation preference regardless of dollar value, unless the offeror waives the price evaluation preference; or

(3) Is an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.

(b) Submission of offers. Submit signed and dated offers to the office specified in this solicitation at or before the exact time specified in this solicitation. Offers may be submitted on the SF 1449, letterhead stationery, or as otherwise specified in the solicitation. As a minimum, offers must show--

(1) The solicitation number;

(2) The time specified in the solicitation for receipt of offers;

(3) The name, address, and telephone number of the offeror;

(4) A technical description of the items being offered in sufficient detail to evaluate compliance with the requirements in the solicitation. This may include product literature, or other documents, if necessary;

(5) Terms of any express warranty;

(6) Price and any discount terms;

(7) "Remit to" address, if different than mailing address;

(8) A completed copy of the representations and certifications at Federal Acquisition Regulation (FAR) 52.212-3 (see FAR 52.212-3(b) for those representations and certifications that the offeror shall complete electronically);

(9) Acknowledgment of Solicitation Amendments;

(10) Past performance information, when included as an evaluation factor, to include recent and relevant contracts for the same or similar items and other references (including contract numbers, points of contact with telephone numbers and other relevant information); and

(11) If the offer is not submitted on the SF 1449, include a statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation. Offers that fail to furnish required representations or information, or reject the terms and conditions of the solicitation may be excluded from consideration.

(c) Period for acceptance of offers. The offeror agrees to hold the prices in its offer firm for 30 calendar days from the date specified for receipt of offers, unless another time period is specified in an addendum to the solicitation.

(d) Product samples. When required by the solicitation, product samples shall be submitted at or prior to the time specified for receipt of offers. Unless otherwise specified in this solicitation, these samples shall be submitted at no expense to the Government, and returned at the sender's request and expense, unless they are destroyed during preaward testing.

(e) Multiple offers. Offerors are encouraged to submit multiple offers presenting alternative terms and conditions, including alternative line items (provided that the alternative line items are consistent with FAR subpart 4.10), or alternative commercial products or commercial services for satisfying the requirements of this solicitation. Each offer submitted will be evaluated separately.

(f) Late submissions, modifications, revisions, and withdrawals of offers:

(1) Offerors are responsible for submitting offers, and any modifications, revisions, or withdrawals, so as to reach the Government office designated in the solicitation by the time specified in the solicitation. If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that offers or revisions are due.

(2)(i) Any offer, modification, revision, or withdrawal of an offer received at the Government office designated in the solicitation after the exact time specified for receipt of offers is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition; and--

(A) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of offers; or

(B) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of offers and was under the Government's control prior to the time set for receipt of offers; or

(C) If this solicitation is a request for proposals, it was the only proposal received.

(ii) However, a late modification of an otherwise successful offer, that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.

(3) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the offer wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.

(4) If an emergency or unanticipated event interrupts normal Government processes so that offers cannot be received at the Government office designated for receipt of offers by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation or other notice of an extension of the closing date, the time specified for receipt of offers will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.

(5) Offers may be withdrawn by written notice received at any time before the exact time set for receipt of offers.

Oral offers in response to oral solicitations may be withdrawn orally. If the solicitation authorizes facsimile offers, offers may be withdrawn via facsimile received at any time before the exact time set for receipt of offers, subject to the conditions specified in the solicitation concerning facsimile offers. An offer may be withdrawn in person by an offeror or its authorized representative if, before the exact time set for receipt of offers, the identity of the person requesting withdrawal is established and the person signs a receipt for the offer.

(g) Contract award (not applicable to Invitation for Bids). The Government intends to evaluate offers and award a contract without discussions with offerors. Therefore, the offeror's initial offer should contain the offeror's best terms from a price and technical standpoint. However, the Government reserves the right to conduct discussions if later determined by the Contracting Officer to be necessary. The Government may reject any or all offers if such action is in the public interest; accept other than the lowest offer; and waive informalities and minor irregularities in offers received.

(h) Multiple awards. The Government may accept any item or group of items of an offer, unless the offeror qualifies the offer by specific limitations. Unless otherwise provided in the Schedule, offers may not be submitted for quantities less than those specified. The Government reserves the right to make an award on any item for a quantity less than the quantity offered, at the unit prices offered, unless the offeror specifies otherwise in the offer.

(i) Availability of requirements documents cited in the solicitation.

(1)(i) The GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29, and copies of Federal specifications, standards, and product descriptions can be downloaded from the ASSIST website at https://assist.dla.mil.

(ii) If the General Services Administration, Department of Agriculture, or Department of Veterans Affairs issued this solicitation, a copy of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained from the address in paragraph (i)(1)(i) of this provision.

(2) Most unclassified Defense specifications and standards may be downloaded from the ASSIST website at https://assist.dla.mil.

(3) Defense documents not available from the ASSIST website may be requested from the Defense Standardization Program Office by--

(i) Using the ASSIST feedback module (https://assist.dla.mil/feedback); or

(ii) Contacting the Defense Standardization Program Office by telephone at 571-767-6688 or email at assisthelp@dla.mil.

(4) Nongovernment (voluntary) standards must be obtained from the organization responsible for their preparation, publication, or maintenance.

(j) Unique entity identifier. (Applies to all offers that exceed the micro-purchase threshold, and offers at or below the micro-purchase threshold if the solicitation requires the Contractor to be registered in the System for Award

Management (SAM).) The Offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation "Unique Entity Identifier" followed by the unique entity identifier that identifies the Offeror's name and address. The Offeror also shall enter its Electronic Funds Transfer (EFT) indicator, if applicable. The EFT indicator is a four-character suffix to the unique entity identifier. The suffix is assigned at the discretion of the Offeror to establish additional SAM records for identifying alternative EFT accounts (see FAR subpart 32.11) for the same entity. If the Offeror does not have a unique entity identifier, it should contact the entity designated at www.sam.gov for unique entity identifier establishment directly to obtain one. The Offeror should indicate that it is an offeror for a Government contract when contacting the entity designated at www.sam.gov for establishing the unique entity identifier.

(k) Reserved.

(l) Debriefing. If a post-award debriefing is given to requesting offerors, the Government shall disclose the following information, if applicable:

(1) The agency's evaluation of the significant weak or deficient factors in the debriefed offeror's offer.

(2) The overall evaluated cost or price and technical rating of the successful and the debriefed offeror and past performance information on the debriefed offeror.

(3) The overall ranking of all offerors, when any ranking was developed by the agency during source selection.

(4) A summary of the rationale for award;

(5) For acquisitions of commercial products, the make and model of the product to be delivered by the successful offeror.

(6) Reasonable responses to relevant questions posed by the debriefed offeror as to whether source-selection procedures set forth in the solicitation, applicable regulations, and other applicable authorities were followed by the agency.

(End of provision)

52.212-2 EVALUATION--COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2021)

(a) The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The following factors shall be used to evaluate offers:

(Contracting Officer shall insert the significant evaluation factors, such as (i) technical capability of the item offered to meet the Government requirement; (ii) price; (iii) past performance (see FAR 15.304); and include them in the relative order of importance of the evaluation factors, such as in descending order of importance.)

Technical and past performance, when combined, are . (Contracting Officer state, in accordance with FAR 15.304, the relative importance of all other evaluation factors, when combined, when compared to price.)

(b) Options. The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. The Government may determine that an offer is unacceptable if the option prices are significantly unbalanced. Evaluation of options shall not obligate the Government to exercise the option(s).

(c) A written notice of award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party. Before the offer's specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.

52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS--COMMERCIAL PRODUCTS AND

COMMERCIAL SERVICES (MAY 2024)

The Offeror shall complete only paragraph (b) of this provision if the Offeror has completed the annual representations and certification electronically in the System for Award Management (SAM) accessed through https://www.sam.gov. If the Offeror has not completed the annual representations and certifications electronically, the Offeror shall complete only paragraphs (c) through (v) of this provision.

(a) Definitions. As used in this provision --

"Covered telecommunications equipment or services" has the meaning provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.

"Economically disadvantaged women-owned small business (EDWOSB) concern" means a small business concern that is at least 51 percent directly and unconditionally owned by, and the management and daily business operations of which are controlled by, one or more women who are citizens of the United States and who are economically disadvantaged in accordance with 13 CFR part 127, and the concern is certified by SBA or an approved third-party certifier in accordance with 13 CFR 127.300. It automatically qualifies as a women-owned small business eligible under the WOSB Program.

"Forced or indentured child labor" means all work or service-

(1) Exacted from any person under the age of 18 under the menace of any penalty for its nonperformance and for which the worker does not offer himself voluntarily; or

(2) Performed by any person under the age of 18 pursuant to a contract the enforcement of which can be accomplished by process or penalties.

"Highest-level owner" means the entity that owns or controls an immediate owner of the offeror, or that owns or controls one or more entities that control an immediate owner of the offeror. No entity owns or exercises control of the highest level owner.

"Immediate owner" means an entity, other than the offeror, that has direct control of the offeror. Indicators of control include, but are not limited to, one or more of the following: Ownership or interlocking management, identity of interests among family members, shared facilities and equipment, and the common use of employees.

"Inverted domestic corporation" means a foreign incorporated entity that meets the definition of an inverted domestic corporation under 6 U.S.C. 395(b), applied in accordance with the rules and definitions of 6 U.S.C. 395(c).

"Manufactured end product" means any end product in product and service codes (PSCs) 1000-9999, except--

(1) PSC 5510, Lumber and Related Basic Wood Materials;

(2) Product or Service Group (PSG) 87, Agricultural Supplies;

(3) PSG 88, Live Animals;

(4) PSG 89, Subsistence;

(5) PSC 9410, Crude Grades of Plant Materials;

(6) PSC 9430, Miscellaneous Crude Animal Products, Inedible;

(7) PSC 9440, Miscellaneous Crude Agricultural and Forestry Products;

(8) PSC 9610, Ores;

(9) PSC 9620, Minerals, Natural and Synthetic; and

(10) PSC 9630, Additive Metal Materials.

"Place of manufacture" means the place where an end product is assembled out of components, or otherwise made or processed from raw materials into the finished product that is to be provided to the Government. If a product is disassembled and reassembled, the place of reassembly is not the place of manufacture.

"Predecessor" means an entity that is replaced by a successor and includes any predecessors of the predecessor.

"Reasonable inquiry" has the meaning provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.

"Restricted business operations" means business operations in Sudan that include power production activities, mineral extraction activities, oil-related activities, or the production of military equipment, as those terms are defined in the Sudan Accountability and Divestment Act of 2007 (Pub. L. 110-174). Restricted business operations do not include business operations that the person (as that term is defined in Section 2 of the Sudan Accountability and Divestment Act of 2007) conducting the business can demonstrate--

(1) Are conducted under contract directly and exclusively with the regional government of southern Sudan;

(2) Are conducted pursuant to specific authorization from the Office of Foreign Assets Control in the Department of the Treasury, or are expressly exempted under Federal law from the requirement to be conducted under such authorization;

(3) Consist of providing goods or services to marginalized populations of Sudan;

(4) Consist of providing goods or services to an internationally recognized peacekeeping force or humanitarian organization;

(5) Consist of providing goods or services that are used only to promote health or education; or

(6) Have been voluntarily suspended.

"Sensitive technology"--

(1) Means hardware, software, telecommunications equipment, or any other technology that is to be used specifically--

(i) To restrict the free flow of unbiased information in Iran; or

(ii) To disrupt, monitor, or otherwise restrict speech of the people of Iran; and

(2) Does not include information or informational materials the export of which the President does not have the authority to regulate or prohibit pursuant to section 203(b)(3) of the International…

This is the start of the file's text. The full file is on GovTribe.