This document provides details for a federal solicitation seeking dredging services. The U.S. Army Corps of Engineers, Honolulu District is soliciting proposals to conduct maintenance dredging of accumulated sediments at Kaunakakai Harbor, Molokai, Hawaii and Kahului Harbor, Maui, Hawaii. The solicitation is set aside for small businesses and seeks to award a fixed price contract. For Kaunakakai Harbor, the scope includes dredging an estimated 35,000 cubic yards of material for disposal at the Kahului Offshore Dredged Material Disposal Site. For Kahului Harbor, dredging will remove approximately 158,000 cubic yards, with disposal at the same location. The total estimated dredging amount for both projects is 193,000 cubic yards. The period of performance is 18 months. Evaluation will be based on experience, past performance, and technical approach using the lowest priced technically acceptable process. The project magnitude is between $5-10 million.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section 01 90 00
John.A.Alden@usace.army.mil
(g) Failure to comply and purchase Defense Base Act (DBA) Insurance in accordance with FAR Clauses
52.228-3 Workers' Compensation Insurance (Defense Base Act), from the U.S. Army Corps of Engineers mandatory Insurance Carrier/Broker (CNA Insurance/Rutherfoord International) for the Prime and all of the
Subcontractors at every tier, shall be considered a material breech and could cause your contract to be terminated for default/cause.
[End of Statement]
S-36.5 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
1. This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the contract clause entitled DEFAULT (FIXED-PRICE CONSTRUCTION). In order for the
Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
2. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and
Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY
WORK DAYS BASED ON 5 DAY WORK WEEK
LOCATION JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Island of Maui to include sites at Haleakala 6 5 8 6 4 3 5 4 5 6 7 7
3. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the
Contractor's scheduled work day. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph 2, above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the contract clause entitled DEFAULT (FIXED-PRICE CONSTRUCTION). [ER 415-1-15, 31 Oct
89]
[End of Statement]
S-36.7 IDENTIFICATION OF EMPLOYEES
The Contractor shall be responsible for furnishing to each employee and for requiring each employee engaged on the work to display such identification as may be approved and directed by the Contracting Officer. All prescribed identification shall immediately be delivered to the Contracting Officer for cancellation upon the release of any
(DELETED)
(Am-0007)