A.2.11.4 W9128A22R0004 Am-0005 Kahului Harbor - Specifications.pdf

PDF 585 KB Posted

Attached to
Kaunakakai Harbor Maintenance Dredging, Molokai, Hawaii and Kahului Harbor Maintenance Dredging, Maui, Hawaii
Solicitation number
W9128A22R0004
Issued by

About this file

This announcement constitutes a solicitation notice for the Kaunakakai Harbor Maintenance Dredging project on Molokai, Hawaii and the Kahului Harbor Maintenance Dredging project on Maui, Hawaii. The U.S. Army Corps of Engineers, Honolulu District intends to issue a solicitation to conduct maintenance dredging by mechanical clamshell dredge to remove accumulated sediments of approximately 35,000 cubic yards from Kaunakakai Harbor and 158,000 cubic yards from Kahului Harbor. Offerors must be registered in the System for Award Management and will be evaluated on experience, past performance, and technical approach using the lowest priced technically acceptable source selection procedure. The estimated period of performance is 18 months and the project magnitude is between $5 million to $10 million. As a small business set-aside under NAICS 237990, small businesses must perform at least 40% of the dredging volume using their own or other small business equipment.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MAINTENANCE DREDGING KAHULUIHARBOR

that are sometimes not identified by OSHA or USACE EM 385-1-1 .

Incorporate such additional safety precautions or requirements into the AHAs.

3.7.4 Base Mounted Drum Hoists

a. Operation of base mounted drum hoists must be in accordance with EM 385-1-1 and ASSP A10.22 .

b. Rigging gear must be in accordance with applicable ASME/OSHA standards.

c. When used on telecommunication towers, base mounted drum hoists must be in accordance with TIA-1019 , TIA-222 , ASME B30.7 , 29 CFR 1926.552 , and 29 CFR 1926.553 .

d. When used to hoist personnel, the AHA must include a written standard operating procedure. Operators must have a physical examination in accordance with EM 385-1-1 Section 16.B.05 and trained, at a minimum, in accordance with EM 385-1-1 Section 16.U and 16.T. The base mounted drum hoist must also comply with OSHA Instruction CPL 02-01-056 and

ASME B30.23 .

e. Material and personnel must not be hoisted simultaneously.

f. Personnel cage must be marked with the capacity (in number of persons) and load limit in pounds.

g. Construction equipment must not be used for hoisting material or personnel or with trolley/tag lines. Construction equipment may be used for towing and assisting with anchoring guy lines.

3.7.5 Use of Explosives

Explosives must not be used or brought to the project site without prior written approval from the Contracting Officer. Such approval does not relieve the Contractor of responsibility for injury to persons or for damage to property due to blasting operations.

Storage of explosives, when permitted on Government property, must be only where directed and in approved storage facilities. These facilities must be kept locked at all times except for inspection, delivery, and withdrawal of explosives.

3.8 EXCAVATIONS

Soil classification must be performed by a competent person in accordance with 29 CFR 1926 and EM 385-1-1 .

3.8.1 Utility Locations (DELETED)

Provide a third party, independent, private utility locating company to positively identify underground utilities in the work area in addition to any station locating service and coordinated with the station utility department.

SECTION 01 35 26 Page 33 Am-0005

2.1.7 Anchors

Barge and dredge anchor systems (e.g. anchors, chains, moorings, etc.)

shall be properly installed to avoid damaging corals. Only place anchors in areas where there are no corals present. Ensure anchor lines are continuously taut and do not drag on the seafloor or otherwise cause damage to corals from scour. Anchor systems should be inspected daily and monitored over time to assess integrity and potential damages to coral.

Contractor shall provide GPS coordinates of anchor location and verification that mid-line floats are operational to USACE on a weekly basis.

Upon the completion of construction, the Contractor shall submit to the Contracting Officer a signed certification that coral avoidance areas were not directly impacted by dredging operations.

In the event that coral has been damaged during dredge operations, the contractor shall immediately stop work and notify USACE and Hawaii Department of Land and Natural Resources - Department of Aquatic Resources (DLNR-DAR) to determine the appropriate corrective action.

Turbidity barrier/curtain anchors shall have a sufficient mass and spaced to secure the barrier as recommended by the manufacturer depending on the current velocities.

The contractor shall develop a contingency plan in the event of inadvertent damage to coral. The minimum following requirements shall be included in the contingency plan.

a. The contractor shall immediately stop work and notify USACE that unintended damage to corals may have occurred.

b. The contractor shall conduct an underwater survey to quantify damage to coral within 10 business days of determining that damage to coral may have occurred.

c. The contractor shall concurrently investigate and correct the cause of the damage to coral.

d. If no damage is detected, dredging will resume. If damage is detected, then contractor shall directly coordinate with DLNR Hawaii Department of Land and Natural Resources - Department of Aquatic Resources to determine the appropriate corrective action.

2.1.8 Mooring Buoys

Mooring buoys shall have provisions for the mooring line to be securely attached and be sufficiently buoyant to remain afloat under normal load conditions. Mooring placement will account for vessel draft to ensure they remain afloat at the lowest tide. Mooring lines shall remain taut throughout construction to avoid risk of entanglement or seafloor scour.

2.1.9 Lighted Buoys

Lighted buoys shall be manufactured self-contained buoys with automatic flashing lights (on at dusk, off at dawn) installed at 100 feet on center along the outer perimeter of the containment area.

SECTION 01 57 19 Page 18 (Am-0005)

2.2 Environmental Clamshell Bucket

An environmental bucket is required only when mid-depth silt curtains are deployed or if a visible plume emanates from the active dredge area. A non-environmental clamshell bucket may be used when full-depth curtains are deployed.

An environmental bucket has smooth cutting edge and utilizes hydraulic pressure or other mechanism to open and stay shut. The environmental bucket features a venting system that is open on the descent to reduce downward pressure, remains open during the scoop to reduce water content of dredged material and seals in dredge spoils prior to ascent. An environmental bucket must be operated as specified by the manufacturer to ensure proper operation to prevent leakage of dredged spoils. The size of the bucket to be used will not be determined until the construction phase, by the construction contractor.

PART 3 EXECUTION

3.1 PROTECTION OF NATURAL RESOURCES

Minimize interference with, disturbance to, and damage to fish, wildlife, their habitats, coral, live rock, and plants. Prior to the commencement of activities, consult with the Corps' Civil Works Environmental Compliance Coordinator, regarding rare species or sensitive habitats that need to be protected. The protection of rare, threatened, and endangered animal and plant species identified, including their habitats, is the Contractor's responsibility.

Preserve the natural resources within the project boundaries and outside the limits of permanent work. Restore to an equivalent or improved condition upon completion of work. Confine construction activities to within the limits of the work indicated or specified.

3.1.1 Endangered Species Act (ESA)

The protection of rare, threatened, and endangered animal and plant species identified, including their habitats, is the Contractor's responsibility. The following federally protected species are known and could be affected within the construction area:

Green sea turtle (Chelonia mydas), Central North Pacific DPS, threatened

Hawksbill sea turtle (Eretmochelys imbricata), endangered

Hawaiian Insular false killer whale (Pseudora crassidens), endangered

Giant manta ray (Manta birostris), threatened

Hawaiian monk seal (Monachus schauinslandi), endangered, including designated critical habitat

'Ua'u (Hawai'i) or Hawaiian petrel (Pterodroma sandwichensis)

'A'o (Hawai'i) or Newell's shearwater (Puffinus auricularis newelli)

'Ake'ake (Hawai'i) or Hawai'i distinct population segment (DPS) of band-rumped storm-petrel (Oceanodroma castro)

SECTION 01 57 19 Page 19

The Contractor must implement the best management practices listed in the following subsections to minimize potential impacts to threatened and endangered species and their designated critical habitat.

3.1.1.1 General Conditions for ESA Compliance

a. The Contractor must document and report to the Civil Works Environmental Compliance Coordinator immediately, all adverse interactions with listed species, including the disposition of any listed species that are injured or killed. Should an ESA-listed species be adversely affected, all work adversely affecting the species must stop and the Civil Works Environmental Compliance Coordinator immediately contacted.

b. Constant vigilance shall be kept for the presence of ESA-listed marine species throughout the performance period

(1) The Contractor shall designate a competent observer to search/monitor work sites and the areas adjacent to the authorized work area for ESA-listed marine species.

(2) Searches and monitoring shall be made prior to the start of work each day, including prior to resumption of work following any break of more than one-half hour. Additional period searches and monitoring throughout the work day are strongly recommended.

(3) Project-related personnel shall not attempt to disturb, touch, ride, feed or otherwise intentionally interact with any protected species;

(4) All in-water work will be postponed or halted when ESA-listed marine species are within 50 yards of the proposed work, and will only begin/resume after the animals have voluntarily departed the area, with the following exception: if ESA-listed marine species are noticed within 50 yards after work has already begun, that work may continue only if, in the best judgment of a biologist, the activity is unlikely to disturb or harm the animal(s), for example, divers performing surveys or underwater work (excluding the use of toxic chemicals) is likely safe, the use of heavy machinery is not.

c. Project footprints must be limited to the minimum area necessary to complete the project.

d. Project operations must be planned to accommodate weather and ocean forecasts. Operations must cease under unusual conditions, such as large tidal events and high surf conditions, except for efforts to avoid or minimize resource damage.

e. A pollution and erosion control plan for upland work and adjacent areas must be prepared and carried out. As a minimum, this plan shall include:

(1) Proper installation and maintenance of silt fences/curtains, sausages, equipment diapers, or drip pans.

(2) A contingency plan to control and clean spilled petroleum products and other toxic materials.

SECTION 01 57 19 Page 20

(3) Appropriate materials to contain and clean potential spills will be stored at the work site, and be readily available.

(4) All project-related materials and equipment placed in the water will be free of pollutants.

(5) Daily pre-work inspections of heavy equipment for cleanliness and leaks, with all heavy equipment operations postponed or halted until leaks are repaired and equipment is cleaned.

(6) Fueling of project-related vehicles and equipment will take place at least 560 feet away from the water and within a containment area, preferably over an impervious surface.

(7) A plan will be developed to prevent trash and debris from entering the marine environment.

f. Erosion controls must be properly installed before any alteration of the project area may take place.

g. Temporary access roads and drilling pads must avoid steep slopes, where grade, soil types, or other features suggest a likelihood of excessive erosion or failure; existing access routes must be utilized or improved whenever possible, in lieu of construction of new access routes.

h. Native species suitable for the impacted habitat must be considered for re-vegetation for the purposes of restoring upland areas temporarily disturbed by the authorized work to their pre-disturbance condition.

3.1.1.2 Project-Specific Best Management Practices for ESA Compliance

a. Vessel operators shall alter course to remain at least 100 yards from whales, and at least 50 yards from other marine mammals and sea turtles.

b. Vessel operators shall reduce vessel speed to 10 knots or less when piloting vessels in the proximity of marine mammals, and to 5 knots or less when piloting vessels in areas of known or suspected turtle activity.

c. If approached by a marine mammal or turtle, the vessel operator shall put the engine in neutral and allow the animal to pass.

d. Vessel operators shall not encircle or trap marine mammals or sea turtles between multiple vessels or between vessels and the shore.

e. Before any equipment, anchor(s), or material enters the water, a responsible party, i.e., permittee/site manager/project supervisor, shall verify that no ESA-listed species are in the area where the equipment, anchor(s), or materials are expected to contact the substrate. If practicable, the use of divers to visually confirm that the area is clear is preferred.

f. Equipment operators shall employ "soft starts" when initiating work each day and after each break of 30 minutes or more that directly impacts the bottom. Buckets and other equipment shall be sent to the

SECTION 01 57 19 Page 21 bottom in a slow and controlled manner for the first several cycles before achieving full operational impact strength or tempo.

g. All objects lowered to the bottom shall be lowered in a controlled manner. This can be achieved using buoyancy controls such as lift bags, or the use of cranes, winches, or other equipment that affect positive control over the rate of descent.

h. Mooring systems shall employ the minimum line length necessary to account for expected fluctuations in water depth due to tides and waves.

i. Mooring systems shall be designed to keep the line as tight as possible, with the intent to eliminate the potential for loops to form.

j. Mooring lines shall consist of a single line. No additional lines or material capable of entangling marine life may be attached to the mooring line or to any other part of the deployed system.

k. Mooring systems shall be designed to keep the gear off the bottom, by use of a mid-line float when appropriate, with the intent to eliminate scouring of corals or entanglement of the line on the substrate.

l. Any permanent or long-term deployment shall include an inspection and maintenance program to reduce the likelihood of failures that may result in loose mooring lines lying on the substrate or hanging below a drifting buoy.

m. Mooring systems, including those used for temporary markers, scientific sensor buoys, or vessel moorings, shall be completely removed from the marine environment immediately at the completion of the authorized work or the end of the mooring's service life. The only exceptions to this rule shall be mooring anchors such as eyebolts that area epoxied into the substrate and which pose little or no risk to marine life.

n. Maintenance dredging shall not be undertaken if any ESA-listed species is within 50 yards of the authorized work, and those operations shall immediately shut-down if an ESA-listed species enters within 50 yards of the authorized work.

o. Anchoring locations and moorings must be designed to avoid, to the greatest extent practicable, impacts to live corals, sea grass, and other benthic organisms.

p. With the exception of the actual dredging apparatus (e.g. clamshell buckets, or the scoop and articulated arm of a backhoe, hydraulic head, etc.), heavy equipment will be operated from above and out of the water.

q. The portions of the equipment that enter the water will be clean and free of pollutants.

r. Appropriate silt containment devices must be used and properly installed to avoid degradation of adjacent coral reefs, and aquatic vegetation.

s. Fully shield all outdoor lights so the bulb can only be seen from below bulb height and only use when necessary.

SECTION 01 57 19 Page 22

t. Install automatic motion sensor switches and timer controls on all outdoor lights or turn off lights when human activity is not occurring in the lighted area.

u. Nighttime dredging (between 1800 and 0600 hrs) shall not occur at the entrance channel and near Pier 1 at Kahului Harbor during seabird fledgling season (September 15-December 15). Disposal operations to the ODMDS will be allowed at night during this period.

3.1.2 Essential Fish Habitat

The Contractor must comply with the following measures to avoid and minimize adverse effects to Essential Fish Habitat (EFH).

3.1.2.1 Measures for EFH Compliance

a. Upon completion of all activities, all project materials shall be removed and all areas temporarily impacted by construction activities shall be fully restored to their pre-construction conditions.

b. Vessels, barges or other in-water structures must first attempt to tie-off to existing harbor structures. If anchoring on the seafloor is necessary, then anchors must be placed exclusively in soft sediments. Anchors and anchor components must cause no direct physical impact to corals beyond the federal limits. Anchor and anchorline footprints of all in-water equipment must be designed to occupy the smallest footprint necessary to achieve safe and effective anchorage. Reference Attachment 1 for coral cover map.

c. During peak coral spawning (one week before and after the full moon in July and August)

(1) dredging at night will be prohibited; and

(2) any in-water sediment containment devices must not be left overnight.

d. While entering or exiting the harbor, all vessels, barges and scows must remain in the marked USCG ingresss/egress channel until it passes the outer buoy.

e. Weather conditions must be considered to ensure the safety of equipment and personnel during in-water operations. Work must cease during unfavorable weather conditions such as storm surge, etc. that could compound impacts to surrounding resources. The Contractor shall use the PacIOOS data at http://pacioos.hawaii.edu/ and other readily available tide and climate data to inform and adaptively manage dredge and water quality monitoring operations daily.

f. As documented in the EPP, each vessel must have written spill prevention plan on board that identifies the appropriate response and safety protocols and the contact information for appropriate authorities to be notified in the unlikely event of a spill.

g. As documented in the EPP, the Contractor must designate on-site personnel responsible for ensuring no inadvertent discharges of debris, petroleum, or other harmful materials into the water.

SECTION 01 57 19 Page 23

h. As documented in the EPP, dredge operators must submit a contingency plan detailing progressive, action-specific, risk-based responses to potential malfunctions of dredge equipment, barges, scows and in-water BMPs such as sediment containment devices.

i. All dredge vessels, barges and scows must be equipped with Dredging Quality Management (DQM) instrumentation systems, or similar, to allow near real-time monitoring of the scow's status (e.g. GPS positioning, hull status (open or closed), heading (course and speed), volume (draft), displacement and bin ullage sounding at all times to ensure performance, accuracy and accountability. Such records will be made available to the Government upon request.

j. Subject to approval by the Government, dredge operators must submit to the Government maintenance and inspection records, current to within six months or since its last use for whatever purpose, for any containment scow to be used to complete the proposed work, and a plan for the continued maintenance and inspection through the construction period.

k. In-water sediment containment devices must be used to contain project generated turbidity and prevent spread beyond the active work area.

(1) Dredging shall not begin/resume until sediment control devices are properly deployed and fully encircling the active dredge area.

(2) These devices must be clean of chemical, biological, or physical pollutants prior to placement in state waters and not become a source of water pollution during use.

(3) The reach of the equipment is positioned inside the sediment containment device while the containment scow is positioned outside the sediment containment device, to minimize ingress/egress frequency.

(4) Sediment containment devices must be appropriately sized. The dredging impact area shall be no larger than is required to operate the necessary equipment, and the size and position of the area must be strategically planned to reduce the number of times it must be repositioned. Prior to repositioning, sediment containment devices must remain in place until turbidity levels within the enclosure have returned to ambient levels.

(5) In the limits of this project, a full-depth silt curtain shall be employed to encircle the active dredging area where water conditions permit use of a full-depth silt curtain (See Section

2.1 above).

(6) If conditions require mid-depth silt curtains, which shall be confirmed by the Government, Contractor shall be required to employ an environmental bucket to minimize turbidity and comply with State Water Quality Standards (See Section 2.1 above).

(7) Sediment containment devices should be inspected on a regular basis, with daily inspections during and after the presence of other marine traffic using the harbor and during and after experiencing severe weather conditions (i.e., strong currents, high winds and/or waves). Contractor should be prepared to remove these devices in advance of severe storms to avoid risk of damage

SECTION 01 57 19 Page 24 or loss.

l. Inspection and maintenance protocols for all in-water equipment and BMPs shall be described in the EPP.

m. Contractor shall deploy position the sediment containment device no closer than 10 feet from the base of the hardbottom ledge to ensure the sediment containment device causes no physical damage, abrasion or other physical contact with corals beyond the dredge footprint along the western portion of the project area and 10 feet from fronting the entire pier. Contractor shall monitor the positioning of the sediment containment device throughout the dredge action and must stop work and reposition the device if its ballast migrates closer than 10 feet of the base of the ledge or the pier face causes or has the potential to cause physical damage to corals beyond the dredge footprint .

n. Containment scows must be adequately sized to prevent overflow/over-topping and must be equipped with functional seals to prevent leakage of dredged material.

o. The Contractor shall monitor for heightened sea states or other conditions that may cause the silt curtain ballast to shift position and/or the silt curtain to move about excessively, and thereby increase the risk of abrasion or other damage to coral.

p. The Contract shall avoid dredging areas located in proximity to known high coral cover areas during such conditions. The Contractor will be provided with maps of hard substrate and coral abundance created by the USFWS coral cover map (Attachment 1).

q. Contractor shall:

(1) Prioritize areas located in close proximity to or up-current of known high coral cover area during calm sea state.

(2) Minimize the area encircled by the silt curtain to the greatest extent practicable when dredging areas located in close proximity to or up-current of known high coral cover areas.

r. As submitted in the EPP, the Contractor must develop a site-specific BMP plan to be reviewed by the Government prior to start of work. The Site-Specific BMP Plan must contain turbidity to the active dredge area to the greatest extent practicable. The plan must include a visual turbidity monitoring plan throughout the duration of construction to ensure the efficacy of the sediment containment BMP in comparison to ambient levels. When reviewing the contractor's proposed BMP plan, the Corps will only approve a plan that, at a minimum, includes the following or comparable alternative components:

(1) The contractor shall prepare a housekeeping policy for land-based staging areas and project vessels that controls trash, debris, and project chemicals and fluids (gasoline, oil) from entering state waters. There shall be no discharge of any type of wash water and/or effluent into State waters without first obtaining a DOH National Pollutant Discharge Eliminations System (NPDES) permit authorizing such discharge into State waters.

(2) At least once per day, the contractor shall look for turbid water escaping the active dredge area into the harbor, and note the

SECTION 01 57 19 Page 25 size, direction and duration of the turbidity plume. The contractor shall document and report any violation of State water quality standards to the appropriate Corps representative, and as needed, enact contingency measures to address this violation.

(3) Visual inspection of sediment containment devices of sufficient frequency to minimize potential failure and ensure proper use and installation. Contractor shall include inspection protocols in the BMP Plan, and consider the following items:

i. Confirmation that the design freeboard is being maintained. If freeboard is reduced, inspect the curtain skirt for marine growth, sediment or debris that might cause reduced freeboard. Check floats for damage.

ii. Confirmation that the curtain is maintaining its anchored profile. If the curtain or a portion thereof appears out of place, inspect the anchoring system and placement of the anchors. Adjust and/or repair the anchoring system as required.

iii. Ensure the turbidity curtain has not moved into shallower water whereby the bottom of the curtain is resting on bottom.

iv. The weight of the ballast chain can slowly work itself into the bottom soil over time and become lodged. When removing or repositioning the turbidity curtain, ensure that the ballast chain is not held so securely by the sediment that the skirt will tear away from the ballast chain pocket.

v. At 1-2 month intervals, inspect the curtain for UV radiation damage, chemical damage and marine growth. As needed, remove excessive marine growth in a manner that does not violate state water quality standards. This may require removal/replacement with land-based cleaning that does not allow wash water to enter State waters.

iv. Documentation of non-compliance of any Blanket 401 WQC conditions (e.g.,visual plume outside of enclosed active dredge area) and action taken to address non-compliance; and,

v. Maintain monitoring and inspection records, including actions taken to correct violations, at the project site or nearby field office that demonstrate compliance with all Blanket 401 WQC conditions.

vi. Establishment of a turbidity threshold (e.g. 10% above ambient) that complies with Blanket Water Quality Certification WQC0901 and corresponding progressive responses to exceedances including inspecting the BMPs, replacing the BMPs, adjusting/ doubling up combining BMPs, and stopping work.

vii. Contractor shall prepare and submit to USACE , as a stand-alone document an anchoring plan detailing measures to control and monitor the positions of all anchors and anchor cables, sufficient to avoid damage to corals outside the dredge footprint. See paragraph 2.1.7 Anchors. and other marine growth.

Anchors may not be placed within coral buffer zone or areas outside the federal channel. Contractor shall provide GPS coordinates of bucket location if requested by government.

SECTION 01 57 19 Page 26

3.1.3 Clean Water Act

The Contractor must employ necessary procedures, measures and monitoring to ensure the maintenance dredging complies with State of Hawaii Water Quality Standards.

3.1.3.1 Water Quality Monitoring

The Contractor shall develop a water quality monitoring plan that complies with the terms and conditions of the Blanket Water Quality Certification (Attachment 6). The purpose of the water quality monitoring plan is to ensure appropriate installation, maintenance and efficacy of in-water sediment containment devices e.g. silt curtains, and to ensure the maintenance dredging complies with state Water Quality Standards.

The Water Quality Monitoring Requirements from the State of Hawaii are provided in Attachment 6. The Contractor shall comply with the general conditions of the State of Hawaii 401 Blanket Water Quality Certification, including monitoring and reporting. See Attachment 6 for specific requirements and the general conditions.

Attachment 2 is a draft Water Quality Monitoring Plan that may be further developed for use by the contractor, with contractor-specific information added, or the Contractor may elect to develop its own water quality monitoring plan, as specified above.

3.1.4 Flow Ways

Do not alter water flows or otherwise significantly disturb the native habitat adjacent to the project and critical to the survival of fish and wildlife, except as specified and permitted.

3.1.5 Vegetation

Disclose a removal and planting plan, if proposed, in the EPP. Except in areas specified in the EPP, do not remove, cut, deface, injure, or destroy trees or shrubs without the Contracting Officer's permission. Do not fasten or attach ropes, cables, or guys to existing nearby trees for anchorages unless authorized by the Contracting Officer. Where such use of attached ropes, cables, or guys is authorized, the Contractor is responsible for any resultant damage.

Protect existing trees that are to remain to ensure they are not injured, bruised, defaced, or otherwise damaged by construction operations. Remove displaced rocks from uncleared areas. Coordinate with the Contracting Officer and Corps' Civil Works Environmental Compliance Coordinator to determine appropriate action for trees and other landscape features scarred or damaged by equipment operations.

3.1.6 Streams

Stream crossings are not permitted.

3.2 STORMWATER

Do not discharge stormwater from construction sites to the sanitary sewer. If the water is noted or suspected of being contaminated, it may only be released to the storm drain system if the discharge is

SECTION 01 57 19 Page 27 specifically permitted. Obtain authorization in advance from the Contracting Officer and Corps' Civil Works Environmental Compliance Coordinator for any release of contaminated water.

3.2.1 Erosion and Sediment Control Measures

Provide erosion and sediment control measures in accordance with state and local laws and regulations. Preserve vegetation to the maximum extent practicable.

Erosion control inspection reports may be compiled as part of a stormwater pollution prevention plan inspection reports.

3.2.1.1 Erosion Control

Prevent erosion by mulching, Compost Blankets, Geotextiles, temporary slope drains. Stabilize slopes by sodding, seeding, or such combination of these methods necessary for effective erosion control. Use of hay bales is prohibited.

3.2.1.2 Sediment Control Practices

Implement sediment control practices to limit runoff and the discharge of pollutants from exposed areas of the site. Implement sediment control practices prior to soil disturbance and prior to creating areas with concentrated flow, during the construction process to minimize erosion and sediment laden runoff. Include the following devices: silt fence, temporary diversion dikes, and storm drain inlet protection.

3.2.2 Work Area Limits

Mark the areas that need not be disturbed under this Contract prior to commencing construction activities. Mark or fence isolated areas within the general work area that are not to be disturbed. Protect monuments and markers before construction operations commence. Where construction operations are to be conducted during darkness, any markers must be visible in the dark. Personnel must be knowledgeable of the purpose for marking and protecting particular objects.

3.2.3 Contractor Facilities and Work Areas

Place field offices, staging areas, stockpile storage, and temporary buildings in areas designated on the drawings or as directed by the Contracting Officer. Move or relocate the Contractor facilities only when approved by the Government. Provide erosion and sediment controls for onsite borrow and spoil areas to prevent sediment from entering nearby waters. Control temporary excavation and embankments for plant or work areas to protect adjacent areas.

3.2.4 Municipal Separate Storm Sewer System (MS4) Management

Comply with any MS4 permit requirements within the project site.

3.3 SURFACE AND GROUNDWATER

3.3.1 Cofferdams, Diversions, and Dewatering

Construction operations for dewatering, removal of cofferdams, tailrace excavation, and tunnel closure must be constantly controlled to maintain

SECTION 01 57 19 Page 28 compliance with existing state water quality standards and designated uses of the surface water body. Comply with State of Hawaii water quality standards and anti-degradation provisions. Do not discharge excavation ground water to the sanitary sewer, storm drains, or to surface waters without prior specific authorization in writing from the Contracting Officer and Corps' Civil Works Environmental Compliance Coordinator.

Discharge of hazardous substances will not be permitted under any circumstances. Use sediment control BMPs to prevent construction site runoff from directly entering any storm drain or surface waters.

3.3.2 Waters of the United States

Do not enter, disturb, destroy, or allow discharge of contaminants into waters of the United States. The protection of waters of the United States shown on the drawings in accordance with paragraph LICENSES AND PERMITS is the Contractor's responsibility. Authorization to enter specific waters of the United States identified does not relieve the Contractor from any obligation to protect other waters of the United States within, adjacent to, or in the vicinity of the construction site and associated boundaries.

3.4 PROTECTION OF CULTURAL RESOURCES

3.4.1 Archaeological Resources

If, during excavation or other construction activities, any previously unidentified or unanticipated historical, archaeological, and cultural resources are discovered or found, activities that may damage or alter such resources will be suspended. Resources covered by this paragraph include, but are not limited to: any human skeletal remains or burials;

artifacts; shell, midden, bone, charcoal, or other deposits; rock or coral alignments, pavings, wall, or other constructed features; and any indication of agricultural or other human activities. Upon such discovery or find, immediately notify the Contracting Officer and Corps' Civil Works Environmental Compliance Coordinator so that the appropriate authorities may be notified and a determination made as to their significance and what, if any, special disposition of the finds should be made. Cease all activities that may result in impact to or the destruction of these resources. Secure the area and prevent employees or other persons from trespassing on, removing, or otherwise disturbing such resources.

3.5 AIR RESOURCES

Equipment operation, activities, or processes will be in accordance with 40 CFR 64 and state air emission and performance laws and standards.

3.5.1 Oil or Dual-fuel Boilers and Furnaces

Provide product data and details for new, replacement, or relocated fuel fired boilers, heaters, or furnaces to the Contracting Officer. Data to be reported include: equipment purpose (water heater, building heat, process), manufacturer, model number, serial number, fuel type (oil type, gas type) size (MMBTU heat input). Provide in accordance with paragraph

PRECONSTRUCTION AIR PERMITS.

3.5.2 Accidental Venting of Refrigerant

Accidental venting of a refrigerant is a release and must be reported immediately to the Contracting Officer.

SECTION 01 57 19 Page 29

3.5.3 EPA Certification Requirements

Heating and air conditioning technicians must be certified through an EPA-approved program. Maintain copies of certifications at the employees' places of business; technicians must carry certification wallet cards, as provided by environmental law.

3.5.4 Dust Control

Keep dust down at all times, including during nonworking periods. Dry power brooming will not be permitted. Instead, use vacuuming, wet mopping, wet sweeping, or wet power brooming. Air blowing will be permitted only for cleaning nonparticulate debris such as steel reinforcing bars. Only wet cutting will be permitted for cutting concrete blocks, concrete, and bituminous concrete. Do not unnecessarily shake bags of cement, concrete mortar, or plaster. Employ other BMPs as necessary to ensure that dust-generated activities comply with the "Basic Water Quality Criteria Applicable to All Waters" as specified in HAR § 11-54-4.

3.5.4.1 Particulates

Dust particles, aerosols and gaseous by-products from construction activities, and processing and preparation of materials (such as from asphaltic batch plants) must be controlled at all times, including weekends, holidays, and hours when work is not in progress. Maintain excavations, stockpiles, haul roads, permanent and temporary access roads, plant sites, spoil areas, borrow areas, and other work areas within or outside the project boundaries free from particulates that would exceed 40 CFR 50 , state, and local air pollution standards or that would cause a hazard or a nuisance. Sprinkling, chemical treatment of an approved type, baghouse, scrubbers, electrostatic precipitators, or other methods will be permitted to control particulates in the work area. Sprinkling, to be efficient, must be repeated to keep the disturbed area damp. Provide sufficient, competent equipment available to accomplish these tasks.

Perform particulate control as the work proceeds and whenever a particulate nuisance or hazard occurs. Comply with state and local visibility regulations.

3.5.4.2 Abrasive Blasting

Blasting operations cannot be performed without prior approval of the Contracting Officer and Corps' Civil Works Environmental Compliance Coordinator. The use of silica sand is prohibited in sandblasting.

Provide tarpaulin drop cloths and windscreens to enclose abrasive blasting operations to confine and collect dust, abrasive agent, paint chips, and other debris.

3.5.5 Odors

Control odors from construction activities. The odors must be in compliance with state regulations and local ordinances and may not constitute a health hazard.

3.6 WASTE MINIMIZATION

Minimize the use of hazardous materials and the generation of waste.

SECTION 01 57 19 Page 30

Include procedures for pollution prevention/ hazardous waste minimization in the Hazardous Waste Management Section of the EPP. If no written plan exists, obtain information by contacting the Contracting Officer.

Describe the anticipated types of the hazardous materials to be used in the construction when requesting information.

3.6.1 Salvage, Reuse and Recycle

Identify anticipated materials and waste for salvage, reuse, and recycling. Describe actions to promote material reuse, resale or recycling. To the extent practicable, all scrap metal must be sent for reuse or recycling and will not be disposed of in a landfill.

Include the name, physical address, and telephone number of the hauler, if transported by a franchised solid waste hauler. Include the destination and, unless exempted, provide a copy of the state or local permit (cover) or license for recycling.

3.7 DREDGE MATERIAL MANAGEMENT AND DISPOSAL

3.7.1 Dredged Material Determination Documentation

Dredged material shall be managed, handled and transported in accordance with all applicable federal, state and local regulations. Dredged material shall be appropriately disposed of at an USEPA designated ocean disposal site. The final disposition of dredged material was determined based on the results of appropriate sampling, testing and analysis necessary to determine suitability at ocean disposal areas, per applicable federal, state and local regulations. The Government will provide the results of the dredged material suitability determination to the Contractor for disposal planning purposes. No in-water sampling is required. All dredged material suitable for ocean disposal has been vetted through the USEPA and is indicated on the plans. The dredged material management plan will be submitted to the Government with the EPP. Reference Attachment 3 for a summary of sediment characteristics.

The complete Sediment Characterization Report including sediment core logs and photos will be made available upon request.

3.7.1.1 Ocean Disposal for Dredged Material

Material dredged from the Kahului Harbor has been determined to be suitable for ocean disposal, and shall disposed at the USEPA-designated Kahului Ocean Dredged Material Disposal Site (ODMDS). Ocean disposal, including procedures, monitoring, reporting and notification must comply with the attached Kahului ODMDS site use conditions, reference Attachment

4. Constant vigilance for threatened and endangered marine species is required.

3.7.2 Control and Management of Hazardous Waste

Do not dispose of hazardous waste at the project site. Do not discharge any waste to a sanitary sewer, storm drain, or to surface waters or conduct waste treatment or disposal without written approval of the Contracting Officer.

3.7.2.1 Hazardous Waste/Debris Management

Identify construction activities that will generate hazardous waste or debris. Provide a documented waste determination for resultant waste

SECTION 01 57 19 Page 31 streams. Identify, label, handle, store, and dispose of hazardous waste or debris in accordance with federal, state, and local regulations, including 40 CFR 261 , 40 CFR 262 , 40 CFR 263 , 40 CFR 264 , 40 CFR 265 , 40 CFR 266 , and 40 CFR 268 .

Manage hazardous waste in accordance with the approved Hazardous Waste Management Section of the EPP. Store hazardous wastes in approved containers in accordance with 49 CFR 173 and 49 CFR 178 . Do not bring hazardous waste onto the project site. Provide the Contracting Officer with a copy of waste determination documentation for any solid waste streams that have any potential to be hazardous waste or contain any chemical constituents listed in 40 CFR 372-SUBPART D.

3.7.2.2 Waste Storage/Satellite Accumulation/90 Day Storage Areas

Accumulate hazardous waste at satellite accumulation points and in compliance with 40 CFR 262.34 and applicable state or local regulations.

Individual waste streams will be limited to 55 gallons of accumulation (or 1 quart for acutely hazardous wastes). If the Contractor expects to generate hazardous waste at a rate and quantity that makes satellite accumulation impractical, the Contractor may request a temporary 90 day accumulation point be established. Submit a request in writing to the Contracting Officer and provide the following information (Attach Site Plan to the Request):

Contract Number

Contractor

Haz/Waste or Regulated Waste POC

Phone Number

Type of Waste

Source of Waste

Emergency POC

Phone Number

Location of the Site

Attach a Waste Determination form for the expected waste streams. Allow 10 working days for processing this request. Additional compliance requirements (e.g. training and contingency planning) that may be required are the responsibility of the Contractor. Barricade the designated area where waste is being stored and post a sign identifying as follows:

"DANGER - UNAUTHORIZED PERSONNEL KEEP OUT"

3.7.2.3 Universal Waste Management

Manage the following categories of universal waste in accordance with federal, state, and local requirements and installation instructions:

a. Batteries as described in 40 CFR 273.2

SECTION 01 57 19 Page 32

b. Lamps as described in 40 CFR 273.5

c. Mercury-containing equipment as described in 40 CFR 273.4

3.7.2.4 Electronics End-of-Life Management

Recycle or dispose of electronics waste, including, but not limited to, used electronic devices such computers, monitors, hard-copy devices, televisions, mobile devices, in accordance with 40 CFR 260 -262, state, and local requirements, and installation instructions.

3.7.2.5 Disposal Documentation for Hazardous and Regulated Waste

Contact the Contracting Officer for the facility RCRA identification number that is to be used on each manifest.

3.7.3 Releases/Spills of Oil and Hazardous Substances

3.7.3.1 Response and Notifications

Exercise due diligence to prevent, contain, and respond to spills of hazardous material, hazardous substances, hazardous waste, sewage, regulated gas, petroleum, lubrication oil, and other substances regulated in accordance with 40 CFR 300 . Maintain spill cleanup equipment and materials at the work site. In the event of a spill, take prompt, effective action to stop, contain, curtail, or otherwise limit the amount, duration, and severity of the spill/release. In the event of any releases of oil and hazardous substances, chemicals, or gases; immediately (within 15 minutes) notify the Contracting Officer and the state or local authority.

Submit verbal and written notifications as required by the federal ( 40 CFR 300.125 and 40 CFR 355 ), state, local regulations and instructions. Provide copies of the written notification and documentation that a verbal notification was made within 20 days. Spill response must be in accordance with 40 CFR 300 and applicable state and local regulations. Contain and clean up these spills without cost to the Government.

3.7.3.2 Clean Up

Clean up hazardous and non-hazardous waste spills. Reimburse the Government for costs incurred including sample analysis materials, clothing, equipment, and labor if the Government will initiate its own spill cleanup procedures, for Contractor- responsible spills, when: Spill cleanup procedures have not begun within one hour of spill discovery/occurrence; or, in the Government's judgment, spill cleanup is inadequate and the spill remains a threat to human health or the environment.

3.7.4 Mercury Materials

Immediately report to the Contracting Officer and Corps' Civil Works Environmental Compliance Coordinator instances of breakage or mercury spillage. Clean mercury spill area to the satisfaction of the Contracting Officer.

Do not recycle a mercury spill cleanup; manage it as a hazardous waste for disposal.

SECTION 01 57 19 Page 33

3.7.5 Wastewater

Disposal of wastewater must be as specified below.

3.7.5.1 Treatment

Do not allow wastewater from construction activities, such as onsite material processing, concrete curing, foundation and concrete clean-up, water used in concrete trucks, and forms to enter water ways or to be discharged prior to being treated to remove pollutants. Dispose of the construction- related waste water in accordance with 40 CFR 403 , state, regional, and local laws and regulations.

3.7.5.2 Surface Discharge

For discharge of ground water, obtain a state or federal permit specific for pumping and discharging ground water prior to surface discharging in accordance with federal, state, and local laws and regulations.

3.8 HAZARDOUS MATERIAL MANAGEMENT

Include hazardous material control procedures in the Safety Plan, in accordance with Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS.

Address procedures and proper handling of hazardous materials, including the appropriate transportation requirements. Do not bring hazardous material onto Government property that does not directly relate to requirements for the performance of this contract. Submit an SDS and estimated quantities to be used for each hazardous material to the Contracting Officer prior to use. Typical materials requiring SDS and quantity reporting include, but are not limited to, oil and latex based painting and caulking products, solvents, adhesives, aerosol, and petroleum products. Use hazardous materials in a manner that minimizes the amount of hazardous waste generated. Containers of hazardous materials must have National Fire Protection Association labels or their equivalent. Certify that hazardous materials removed from the site are hazardous materials and do not meet the definition of hazardous waste, in accordance with 40 CFR 261 .

3.9 PREVIOUSLY USED EQUIPMENT

Clean previously used construction equipment prior to bringing it onto the project site. Equipment must be free from soil residuals, egg deposits from plant pests, noxious weeds, and plant seeds. Consult with the U.S.

Department of Agriculture jurisdictional office for additional cleaning requirements.

3.10 CONTROL AND MANAGEMENT OF POLYCHLORINATED BIPHENYLS (PCBS)

Manage and dispose of PCB-contaminated waste in accordance with 40 CFR 761 and Section 02 84 33 REMOVAL AND DISPOSAL OF POLYCHLORINATED BIPHENYLS

(PCBS).

3.11 CONTROL AND MANAGEMENT OF LIGHTING BALLAST AND LAMPS CONTAINING PCBS

Manage and dispose of contaminated waste in accordance with 40 CFR 761 .

SECTION 01 57 19 Page 34

3.12 MILITARY MUNITIONS

In the event military munitions, as defined in 40 CFR 260, are discovered or uncovered, immediately stop work in that area and immediately inform the Contracting Officer.

3.13 PETROLEUM, OIL, LUBRICANT (POL) STORAGE AND FUELING

POL products include flammable or combustible liquids, such as gasoline, diesel, lubricating oil, used engine oil, hydraulic oil, mineral oil, and cooking oil. Store POL products and fuel equipment and motor vehicles in a manner that affords the maximum protection against spills into the environment. Manage and store POL products in accordance with EPA 40 CFR 112 , and other federal, state, regional, and local laws and regulations. Use secondary containments, dikes, curbs, and other barriers, to prevent POL products from spilling and entering the ground, storm or sewer drains, stormwater ditches or canals, or navigable waters of the United States. Describe in the EPP (see paragraph ENVIRONMENTAL PROTECTION PLAN) how POL tanks and containers must be stored, managed, and inspected and what protections must be provided. Storage of fuel on the project site must be in accordance with EPA, state, and local laws and regulations and paragraph OIL STORAGE INCLUDING FUEL TANKS.

3.13.1 Used Oil Management

Manage used oil generated on site in accordance with 40 CFR 279 .

Determine if any used oil generated while onsite exhibits a characteristic of hazardous waste. Used oil containing 1,000 parts per million of solvents is considered a hazardous waste and disposed of at the Contractor's expense. Used oil mixed with a hazardous waste is also considered a hazardous waste. Dispose in accordance with paragraph

HAZARDOUS WASTE DISPOSAL.

3.13.2 Oil Storage Including Fuel Tanks

Provide secondary containment and overfill protection for oil storage tanks. A berm used to provide secondary containment must be of sufficient size and strength to contain the contents of the tanks plus 5 inches freeboard for precipitation. Construct the berm to be impervious to oil for 72 hours that no discharge will permeate, drain, infiltrate, or otherwise escape before cleanup occurs.