- Solicitation number
- W9128A-19-B-0001
About this file
Amendment 0005
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
FY18 MCA PN91742 Operational Readiness Training Complex (Barracks), Phase 1, Pohakuloa Training Area, Island of Haw aii, Haw aii
See Continuation Page
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9128A19B0001
X 9B. DATED (SEE ITEM 11)
28-May-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
Am-0005
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
12-Jul-2019
CODE
CECT - CONTRACTING DIVISION
USACE, HONOLULU DISTRICT
BLDG 252 (CECT-POH)
FT. SHAFTER HI 96858-5440
W9128A 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9128A19B0001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
1. CHANGES TO SPECIFICATIONS. Attached hereto are revised pages/paragraphs to the specifications. The revision mark “(Am-0005)” is shown on each revised page.
a. REVISED SECTIONS. The following are revised pages to the solicitation. Changes are marked in “*” asterisks.
Standard Form 1442 – Page 1 Section 01 90 00 – Page 21
b. NEW SECTIONS. The following are new pages to the solicitation.
Section 00 60 00, Appendix A – Requests for Information (#47 through 63)
2. CHANGES TO DRAWINGS.
a. REVISED DRAWINGS. The following revised drawings replace like-numbered drawings and are issued
Sheet ID Mark Revision Date
GI001 5 07/09/19
GI003 5 07/09/19
CD101 5 07/09/19
CD102 5 07/09/19
C-002 5 07/09/19 C-501 5 07/09/19 A-106 5 07/03/19 A-304 5 07/03/19
S-001 5 07/05/19 S-101 5 07/05/19 S-103 5 07/05/19 S-104 5 07/05/19 S-105 5 07/05/19
S-106 5 07/05/19 S-301 5 07/05/19 S-302 5 07/05/19 S-303 5 07/05/19 S-304 5 07/05/19 S-305 5 07/05/19
S-502 5 07/05/19 S-503 5 07/05/19
PS101 5 07/09/19
E-603 5 07/05/19
3. The bid opening date is EXTENDED (see SF1442, Page 1, Block 13A).
FY18 MCA PN91742 Operational Readiness Training Complex (Barracks), Phase 1, Pohakuloa Training Area, Island of Hawaii, Hawaii
X
DAYNA MATSUMURA 808-835-4379
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
07-Jun-2019
(RFP)
(IFB)
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance within _______7 calendar days and complete it within ________ 720 calendar days after receiving award, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the work required are due at the place specified in Item 8 by ___________ local time ______________ 23 Jul 2019 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______ 90 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
CONTRACTING DIVISION
USAED, HONOLULU
BLDG 230, ROOM 103
FT. SHAFTER HI 96858-5440
W9128A
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX: TEL: TEL: FAX:
W9128A19B0001 2
(Am-0005)
FY18 MCA PN91742 Operational Readiness Training Complex (Barracks) Phase 1 Pohakuloa Training Area, Island of Hawaii, Hawaii
RFI # References Question Government Response 47 Section 07 61 14.00 20, Paragraph 1.7 Warranty Requested Deviation: Replace Section 07 61 14.00 20 Part 1.7 Warranty with a manufacturers "Component Warranty" on the metal roofing system.
Reason for Deviation: HPM Building Supply, manufacturing metal roofing since 1963, does not offer a "no-dollar-limit materials and workmanship warranty"
See Section 07 61 14.00 20, Paragraph 1.7 Warranty, per the original solicitation.
48 Sheet S-001, Foundation Note 3
Please confirm if probing for voids is required for this project and if yes please confirm that probes are required for each footing on every building.
See Revised Sheet S-001, per Am-0005.
49 Sheet S-001, Foundation Note 3
If voids are found, how is that paid under this contract? Is this to be included in our lump sum price with the burden on the contractor to assume a quantity or will the unit rate discussed in the note be established at award?
See Revised Sheet S-001, per Am-0005.
50 Sheet S-502, Detail A1 Does this footing require one probe or two probes? See Revised Sheet S-001, per Am-0005.
51 Sheet C-501 The concrete sidewalk and bootwash detail on Sheet C-501 does not depict how thick the No. 67 gravel should be under the concrete. Will the USACE please clarify how thick they want the No. 67 gravel under the concrete? If 4” thick No. 67 gravel is installed under the bootwash concrete, the bottom of the No. 67 Gravel would not extend below the 12” toe of the bootwash. Please advise.
See Revised Sheet C-501, Details C1 and D2, per Am-0005.
52 Roofing manufacturer cannot not provide no-dollar cap warranty. Please clarify acceptable warranty parameters.
See Section 07 61 14.00 20, Paragraph 1.7 Warranty, per the original solicitation.
53 Sheet A-106 (and others) : Laundry equipment is shown but is not specified in the RFP. Is this contractor furnished or GFE?
See Revised Sheets A-106 and A-304, per Am-0005.
54 Detail A1 on sheet C-002 shows three stabilized construction entrances and concrete wash-out areas specifically placed on site as indicated. However, based on the site visit observations around these areas, all three locations do not appear to allow adequate space (if any) to construct these temporary construction entrances and concrete wash-out areas due to the presence of existing transformers, panelboards, power poles, guy-wires, vehicle barrier control panels/boxes, and other similar obstructions (some, but not all, of which are referenced on electrical sheets ED101 through ED105). Please advise where the stabilized construction entrances and concrete wash-out areas should be located to avoid conflicts with current as-built conditions.
See note on Revised Sheet C-002, per Am-0005.
55 What is the traffic rating on the existing gravel road fire lanes and grated drains (reference sheet GI003)?
See note on Revised Sheet GI003, per Am-0005.
56 Is the contractor allowed to utilize the existing gravel road fire lanes between/around the buildings on this project for ingress/egress of equipment and materials?
See note on Revised Sheet GI003, per Am-0005.
Section 00 60 00, Appendix A (Am‐0005)
FY18 MCA PN91742 Operational Readiness Training Complex (Barracks) Phase 1 Pohakuloa Training Area, Island of Hawaii, Hawaii
57 Sheet CD101 indicates demolition of the existing septic tank and leaching wells #3 and #4 adjacent to building 133. However, at the site visit, this area appeared to be recently disturbed and backfilled with gravel. Were these items previous demolished and if so, will they therefore no longer be included in this project?
Items to be demolished per contract requirements.
58 Notes 2, 3, and 4 on sheet CS102 refer to previous projects where infrastructure work was previous performed. Please provide all available as-built drawings from previous site projects in the vicinity of this new proposed project.
No as-builts will be provided.
59 Notes 4 and 9 on sheets CD101 and CD102 indicate that satisfactory soil material is to be placed on top of the 3B Fine Gravel fill and compacted to 95 percent (backfills for abandoned cesspools/wells and septic tanks). However, due to the nature of the 3B Fine Gravel fill compared to the finer particles of the soil fill, the soil to be placed may not be possible to compact and/or may settle into the 3B Fine during these operations as well as over time. Please clarify how these potential issues are to be avoided for the backfill materials and procedures specified (i.e. will additional geotextile type fabric be required between the different backfill types, etc?).
See Revised Sheets CD101 and CD102, per Am-0005.
60 Details B1, C1, and C3 on sheet E-603 are labeled for buildings 122/122A and 113/113A. However, these building numbers to not appear to be included in this project. Please clarify the buildings that will utilize these details.
See Revised Sheet E-603, per Am-0005.
61 Under the “Concrete Crack Repair Bid Quantities” notes on sheets S-101, S-103, S-104, S-105, and S-106 indicate that “crack repair shall be presented as a separate line item with the bid schedule”. However, the bid schedule for this project does not include any such bid options. Please clarify how these details/notes are to be included in the pricing of this project.
See notes on Revised Sheets S-101, S-103, S-104, S-105, and S-106, per Am- 0005.
62 Foundation note 3 on sheet S-001 indicates that the “Contractor shall provide unit price per cubic yard if voids are found and grouting is required”. However, the bid schedule for this project does not include any such bid options. Please clarify how these costs are to be included in this bid or if any such work per said note will constitute a change order during construction.
See Revised Sheet S-001, per Am-0005.
63 Detail B1 on sheet S-106 refers to section details labeled C1/S-512 and C3/S-512.
However, no such section details are included on sheet S-512. Section cuts on sheet S-511 appear to be the intent, however, please clarify where the section cuts are to be found.
See Revised Sheet S-106, per Am-0004.
Section 00 60 00, Appendix A (Am‐0005)
Section 01 90 00 – Page 21 (Am-0005)
6. In the event the Provost Marshal issues extended passes for vehicles, lost passes shall be reported immediately, in writing, to the appropriate Provost Marshal Office, in order to obtain new passes.
Notification shall include all circumstances surrounding the loss of the original passes. All vehicle passes issued shall be returned to the Provost Marshal upon completion of the contract, termination of an employee or discontinued use of the registered vehicles.
7. Failure to follow the procedures outlined above may result in delays in entering Army Installations.
The Government is not responsible for any adverse impact on the contractor or its operation as a result of delays due to the failure to register vehicles.
[End of Statement]
UAI 5152.236-9009 PARTNERING (FEB 2000)
In order to most effectively accomplish this contract, the Government proposes to form a partnership with the Contractor to develop a cohesive building team. It is anticipated that this partnership would involve the U.S. Army Garrison Hawaii Directorate of Public Works, the U.S. Army Garrison Hawaii – Pohakuloa, the Contractor, primary subcontractors and designers, and the U.S. Army Corps of Engineers. This partnership would strive to develop a cooperative management team drawing on the strengths of each team member in an effort to achieve a quality project within budget and on schedule. This partnership would be bilateral in membership and participation will be completely voluntary. Any cost associated with effectuating this partnership, excluding travel and lodging cost of Government personnel, will be borne by the Contractor.
The partnering meetings shall be held within 60 calendar days after Notice to Proceed is issued by the Government. Location: Island of Hawaii, Total of 25 Government personnel to attend.
(End of clause)