FY19 Repair by Replacement Various Facilities, Blocks A &B, Pohakuloa Training Area, Island of Hawaii, Hawaii
Solicitation number
W9128A-19-B-0001
Issued by

About this file

Amendment 0003 - Specifications

View the file

Other files

File Type Posted
W9128A-19-B-0001_Abstract_of_Bids.pdf PDF
W9128A-19-B-0001_Am-0008_Drawings.pdf PDF
W9128A-19-B-0001_Am-0008_Specifications.pdf PDF
W9128A-19-B-0001_Am-0008.pdf PDF
W9128A-19-B-0001_Am_0007_Specifications.pdf PDF
W9128A-19-B-0001_Am_0007.pdf PDF
W9128A-19-B-0001_Am_0007_Drawings.pdf PDF
W9128A-19-B-0001_Am-0006_Specifications.pdf PDF
W9128A-19-B-0001_Am-0006_Drawings.pdf PDF
W9128A-19-B-0001_Am-0006.pdf PDF
W9128A-19-B-0001_Am-0005_Drawings.pdf PDF
W9128A-19-B-0001_Am-0005.pdf PDF
W9128A-19-B-0001_Am-0004_-_Drawings_(Part_2_of_2).pdf PDF
W9128A-19-B-0001_Am-0004.pdf PDF
W9128A-19-B-0001_Am-0004_-_Specifications.pdf PDF
W9128A-19-B-0001_Am-0004_-_Drawings_(Part_1_of_2).pdf PDF
W9128A-19-B-0001_Am-0003.pdf PDF
W9128A-19-B-0001_Am-0003_-_Drawings.pdf PDF
W9128A-19-B-0001_Am-0002.pdf PDF
W9128A-19-B-0001_Am-0001.pdf PDF
W9128A-19-B-0001_Drawings_(Part_9b_of_9).pdf PDF
W9128A-19-B-0001_Drawings_(Part_8_of_9).pdf PDF
W9128A-19-B-0001_Drawings_(Part_7_of_9).pdf PDF
W9128A-19-B-0001_Drawings_(Part_5_of_9).pdf PDF
W9128A-19-B-0001_Drawings_(Part_9_of_9).pdf PDF
W9128A-19-B-0001_Drawings_(Part_3_of_9).pdf PDF
W9128A-19-B-0001_Drawings_(Part_6_of_9).pdf PDF
W9128A-19-B-0001_IFB.pdf PDF
W9128A-19-B-0001_Specifications.pdf PDF
W9128A-19-B-0001_Drawings_(Part_4_of_9).pdf PDF
W9128A-19-B-0001_Drawings_(Part_2_of_9).pdf PDF
W9128A-19-B-0001_Drawings_(Part_1_of_9).pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section 01 90 00 – Page 7 (Am-0003)

S-2 ASBESTOS ABATEMENT (AUG 1996)

Asbestos abatement is part of the scope of work for the proposed contract. Refer to paragraphs entitled, "ASBESTOS --- (OCCUPATIONAL HEALTH AND ENVIRONMENTAL)" in Section 00800 and applicable sections of the technical specifications and drawings. The Contractor shall inform responsible representatives of their insurer(s)/surety(ies) that asbestos abatement is required for the proposed contract.

[End of Statement]

S-19A U.S. ARMY CORPS OF ENGINEERS SAFETY AND HEALTH REQUIREMENTS MANUAL,

EM 385-1-1 (Nov 2014)

This paragraph applies to contracts and purchase orders that require the contractor to comply with EM 385- 1-1 (e.g., contracts that include the Accident Prevention clause at FAR 52.236-13 and/or other safety provisions.) EM 385-1-1 and its changes are available at the following web site:

http://www.usace.army.mil/SafetyandOccupationalHealth/EM38511,2008BeingRevised.aspx

The Contractor shall be responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation.

Per EM 385-1-1 (latest version) Contractors shall ensure timely accident reporting is strictly adhered to.

PODR 265 will be completed within 24 hours of all accidents (excluding first aid injuries). ENG 3394 forms will be completed within 5 days of lost time accident and forwarded to the Contracting Officer or Contracting Officer Representative. All accidents will be reported through the Honolulu Engineer District Safety Office, (808) 835-4009 within 24 hours of the incident.

S-19.2 PERFORMANCE OF WORK BY THE CONTRACTOR - ITEMIZATION

In connection with the Contract Clause in Section 00700, entitled, "LIMITATIONS ON SUBCONTRACTING," the successful bidder must furnish the Contracting Officer within 30 calendar days after award the items of work which it will perform with its own forces and the estimated cost of those items. [FAR 36.501 and FAR 19.508(e)]

S-28.1 EXECUTION OF BID BOND (AUG 1994)

If the bidder's name and address on the bid form (Standard Form 1442) and those on the bid bond form (Standard Form 24) are different from each other, the bid may be rejected as nonresponsive. Accordingly, for its own protection, each bidder shall see to it that the name and address on both forms are identical.

S-28.2 PENAL SUM AND FORM OF BID BOND

Each bidder shall submit with its bid a separate Bid Bond (Standard Form 24) with good and sufficient surety or sureties acceptable to the Government, or other security as provided in contract clause entitled "BID GUARANTEE", in the CONTRACT CLAUSES section of the solicitation. The bid bond penalty may be expressed in terms of a percentage of the bid price or may be expressed in dollars and cents.

Section 01 90 00 – Page 8

Failure to submit a bid guarantee by the time set for opening of bids may be cause for rejection of a bid, except as provided in "LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS" of this solicitation. [FAR 28.101-2]

S-28.3 PENAL SUM AND FORM OF BID GUARANTEE

Each offeror shall submit with its offer a separate bid guarantee using Standard Form 24, Bid Bond, with good and sufficient surety or sureties acceptable to the Government, or other security as provided in the clause entitled BID GUARANTEE in the CONTRACT CLAUSES section. This security shall be in the form of twenty percent (20%) of the offered price or three million dollars ($3,000,000), whichever is less.

The penal sum of the bond may be expressed in terms of a percentage of the offered price or may be expressed in dollars and cents.

Failure to submit a bid guarantee by the time and date set for receipt of proposals may be cause for rejection of a proposal, except as provided in provision 52.215-1, Instructions to Offerors--Competitive Acquisition.

S-36.2 MAGNITUDE OF THE PROPOSED PROJECT [FAR 36.204]

(a) Physical Characteristics:

Provide new facilities at Blocks A&B at Pohakuloa Training Area (PTA). The existing structures are to be complete demolished, and the existing slabs-on-grade are to remain. The contractor shall construct new buildings in accordance with the plans and specifications, and within the constraints of the existing building footprints. The work shall include grade and utility improvement.

(b) Estimated Price Range: The estimated price range of this work is:

$10,000,000 to $25,000,000.

S-36.18 ACCIDENT PREVENTION PLAN (DEC 1998)

Within 15 days after receipt of Notice of Award of the contract, and at least 7 days prior to the preconstruction conference, four copies of the Accident Prevention Program shall be submitted to the Contracting Officer for review and acceptance. The program shall consist of the following forms and documents:

(a) An executed POD Form 248-R Rev (1 Jun 98), Accident Prevention Program, Administrative Plan.

(b) An executed POD Form 184-R Rev (16 Oct 98), Activity Hazard Analysis. (At the Contracting Officer's discretion, the Contractor may submit its Activity Hazard Analysis only for the first phase of construction provided that it is accompanied by an outline of the remaining phases of construction. All remaining phases shall be submitted and accepted prior to the beginning of work in each phase.)

(c) A copy of company policy statement of accident prevention and any other guidance statements normally provided new employees.

Section 01 90 00 – Page 9

Contractor shall not commence physical work at the site until the program has been accepted by the Contracting Officer, or his authorized representative. In developing and implementing its Accident Prevention Program, the Contractor is also responsible for reviewing Section 1 of the most current edition of US Army Corps of Engineers Safety and Health Requirements Manual, Engineer Manual 385-1-1. [See paragraph entitled, SAFETY STANDARDS, in Section 00800]

S-36.33 NOTIFICATION TO OFFERORS – ACCESS TO MILITARY INSTALLATIONS (JULY 2004)

All vehicle operators must be prepared to provide a valid driver’s license, vehicle registration, certificate of insurance and current safety inspection to the security guard prior to entry to the Installation. Offerors should anticipate a delay in entering the Installation and allow sufficient time when attending a site visit or pre-proposal conference or hand delivering an offer.

S-102 CONTRACTOR SUPPLY and USE OF ELECTRONIC SOFTWARE FOR PROCESSING DAVIS-BACON ACT CERTIFIED LABOR PAYROLLS (April 2011)

The contractor is encouraged to use a commercially-available electronic system to process and submit certified payrolls electronically to the Government. The requirements for preparing, processing and providing certified labor payrolls are established by the Davis-Bacon Act as stated in FAR 52.222-8, PAYROLLS AND BASIC RECORDS and FAR 52.222-13, COMPLIANCE WITH DAVIS-BACON

AND RELATED ACT REGULATIONS.

If the contractor elects to use an electronic Davis-Bacon payroll processing system, then the contractor shall be responsible for obtaining and providing for all access, licenses, and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the contractor to comply with Davis-Bacon and related Act regulations. When the contractor uses an electronic Davis-Bacon payroll system, the electronic payroll service shall be used by the contractor to prepare, process, and maintain the relevant payrolls and basic records during all work under this construction contract and the electronic payroll service shall be capable of preserving these payrolls and related basic records for the required 3 years after contract completion. If the contractor chooses to use an electronic Davis-Bacon payroll system, then the contractor shall obtain and provide electronic system access to the Government, as required to comply with the Davis-Bacon and related Act regulations over the duration of this construction contract. The access shall include electronic review access by the Government contract administration office to the electronic payroll processing system used by the contractor.

The contractor's provision and use of an electronic payroll processing system shall meet the following basic functional criteria: commercially available; compliant with appropriate Davis Bacon Act payroll provisions in the FAR; able to accommodate the required numbers of employees and subcontractors planned to be employed under the contract; capable of producing an Excel spreadsheet-compatible electronic output of weekly payroll records (format at http://www.rmssupport.com/guides.aspx) for export in an Excel spreadsheet to be imported into the contractor's Quality Control System (QCS) version of Resident Management System (RMS), that in turn shall export payroll data to the Government's Resident Management System (RMS); demonstrated security of data and data entry rights; ability to produce contractor-certified electronic versions of weekly payroll data; ability to identify erroneous entries and track the data/time of all versions of the certified Davis Bacon payrolls submitted to the government over the life of the contract; capable of generating a durable record copy, that is, a CD or DVD and PDF file record of data from the system database at end of the contract closeout. This durable record copy of data from the electronic Davis-Bacon payroll processing system shall be provided to the Government during contract closeout.

Section 01 90 00 – Page 10

All contractor-incurred costs related to the contractor's provision and use of an electronic payroll processing service shall be included in the contractor's price for the overall work under the contract. The costs for Davis-Bacon Act compliance using electronic payroll processing services shall not be a separately bid/proposed or reimbursed item under this contract.

S-8 UTILITY OUTAGES

Utility outages shall be as hereinafter specified, unless otherwise indicated or specified. Interruptions to existing utilities shall be held to a minimum. Outages to facilitate connections to existing systems shall be scheduled to take place during periods of minimum demand. The Contractor shall submit a planned schedule of outages to the Contracting Officer for proper coordination with existing facilities, and shall notify the Contracting Officer in writing. For water outages, the contractor shall coordinate with the Government and Pural Water Specialty Co., Mr. Harold Hart (email: harold.hart@pluralwater.com, phone:

808-960-1648) not less than 14 days in advance of the intended interruptions. For electrical outages, see the Electrical Outage SOP attached to this section for notification of electrical interruptions. Planned schedule of outages shall include specific dates, times, and anticipated duration of proposed outages. In the event the proposed outages interfere with station operations, the Contracting Officer will consider or offer alternate dates and/or times. Outages may be permitted during off-peak hours, hours of darkness, weekends, and holidays, at no additional cost to the Government. Work shall be planned to minimize outages. No utility outage will be permitted until the Contractor receives written approval from the Contracting Officer.

S-18 ASBESTOS --- (OCCUPATIONAL HEALTH AND ENVIRONMENTAL)

(a) THE CONTRACTOR IS WARNED THAT EXPOSURE TO AIRBORNE ASBESTOS HAS BEEN

ASSOCIATED WITH FOUR DISEASES: LUNG CANCER, CERTAIN GASTROINTESTINAL

CANCERS, PLEURAL OR PERITONEAL MESOTHELIOMA AND ASBESTOSIS. Studies indicate there are significantly increased health dangers to persons exposed to asbestos who smoke and further, to family members and other persons who become indirectly exposed as a result of the exposed worker bringing asbestos-laden work clothing home to be laundered.

(b) The Contractor is advised that friable and/or nonfriable asbestos containing material has been identified in area(s) where contract work is to be performed. Friable asbestos containing material means any material that contains more than 1 percent asbestos by weight that hand pressure can crumble, pulverize or reduce to powder when dry. Nonfriable asbestos containing materials do not release asbestos fiber during routine handling and end-use. However, excessive fiber concentrations may be produced during uncontrolled abrading, sanding, drilling, cutting, machining, removal, demolition or other similar activities.

(c) Care must be taken to avoid releasing, or causing to be released, asbestos fibers into the atmosphere where they may be inhaled or ingested. The Occupational Safety and Health Administration (OSHA) has set standards at 29 CFR 1910.1001, for exposure to airborne concentrations of asbestos, fibers, methods of compliance, medical surveillance, housekeeping procedures and other measures that must be taken when working with or around asbestos containing materials which release airborne asbestos fibers at concentrations in excess of those established 29 CFR 1910.1001. 29 CFR 1910.1001 has been identified as applicable to construction (29 CFR 1926.55 gases, vapors, fumes, dusts and mists). The Environmental Protection Agency (EPA) has established standards at 40 CFR 61.140-156 for the control of asbestos emissions to the environment and the handling and disposal of asbestos wastes.

(d) When contract work activities are carried out in locations where the potential exists for exposure to airborne asbestos fibers as described in paragraph (b), or where asbestos waste will be generated, the Contractor shall assure that all measures necessary to provide effective protection to persons from exposure

Section 01 90 00 – Page 11 to asbestos fibers (and prevention of contamination to property, materials, supplies, equipment and the internal and external environment) are effectively instituted.

(e) As a minimum, the Contractor shall comply with the provisions of 29 CFR 1910.1001 and 1926.55; 49 CFR 72.101, 172.200-204, 172.316, 173.1090; 40 CFR 61.140-156; and any state implementing hazardous waste under the Resources Conservation and Recovery Act (RCRA) requirements and any other applicable federal, state or local requirements.

(f) In addition to the information required in Contract Clause, ACCIDENT PREVENTION, of this contract, the Contractor's Accident Prevention Plan must also fully address the following topics, and at the Contractor's option may include additional information as applicable.

(1) Medical Surveillance: (29 CFR 1910.1001(J)).

(2) Employee training: Prior to beginning work in asbestos containing material area(s) (29 CFR

1910.1001 and 29 CFR 1910.134).

(3) Respiratory protection: (29 CFR 1910.1001 and 29 CFR 1910.134)

(4) Personal protective clothing and equipment: (29 CFR 1910.1001(d)). The use of compressed air to remove asbestos from workers' clothing is prohibited. The Contractor shall specify the type of change room, wash facilities and laundering facilities as applicable.

(5) Airborne asbestos monitoring: 29 CFR 1910.1001(f)). Specify the monitoring and analytical procedures to be used before, during, and after completion of contract work in areas where asbestos containing materials are located. All asbestos monitoring shall be conducted under the guidance of an industrial hygienist certified by the American Board of Industrial Hygiene. Samples shall be analyzed by an American Industrial Hygiene Association (AIHA) accredited laboratory proficient in the analysis of asbestos and asbestos containing materials. Turn around time from end of sampling period to review of results of analyses by Contractor shall be no longer than 72 hours.

(6) Housekeeping: (29 CFR 1910.1001(h)). Dry sweeping of contract work areas contaminated with asbestos containing material is prohibited. The Contractor shall specify methods and materials used to package asbestos containing waste and plan to control any incidental airborne release or spill of asbestos containing material.

(7) Methods of compliance: (29 CFR 1910.1001(c)). Contractor shall include procedures relating to engineering controls, local exhaust ventilation, particular tools to be used and work practices (1910.1001(c)). Specify methods, materials and equipment to be used to prevent asbestos contamination to property, materials, supplies, equipment and the internal and external environment during maintenance, renovation or other contract activities. Local Exhaust ventilation equipment including power operated tools equipped with local exhaust ventilation shall conform with the Standard Fundamentals Governing the Design and Operation of Local Exhaust Systems ANSI Z9.2 latest revised edition. Describe the type of high-efficiency filtered (HEPA) vacuum cleaners that shall be used to vacuum asbestos containing materials. Describe methods and materials to be used to assure all asbestos containing material will be thoroughly wetted by use of a wetting agent and water before removal and that airborne asbestos dust will be kept to a minimum.

(8) Methods and materials to be used to decontaminate any property, materials, supplies, equipment and the environment if asbestos contamination results. (29 CFR 1910.1001(c)).

(9) Recordkeeping procedures. (29 CFR 1910.1001(i) and 1910.20).

(10) Specific description of packaging, marking and shipping conveyances to be used to transport asbestos containing waste from the generation point to a storage or disposal facility in compliance with Department of Transportation requirements. (49 CFR 172.101, 172.200-204, 176,316, 173.1090).

Section 01 90 00 – Page 12

(11) Emergency procedures that would be taken if an accident of spill of asbestos containing material occurs during the transport of asbestos containing waste. (40 CFR 61.20-25).

(12) Methods and equipment used to off load and bury asbestos containing waste control airborne emissions at the burial site. (40 CFR 61.20-25).

(g) The Contractor shall complete and return to the Contracting Officer within 15 working days after the completion of all airborne asbestos monitoring conducted under this contract, a 'Summarization of Airborne Asbestos Sampling Results' form (ENG Form 4921-R, Jan 86) provided by the Government. NOTE: This completed summarization form is to be used by the US Army Corps of Engineers for statistical information purposes and does not relieve the Contractor from his recordkeeping requirements as described in 29 CFR 1910.1001(i) and 1910.20.

(h) An industrial hygiene asbestos survey was conducted in the contract work area(s) to identify the presence of asbestos containing materials as described in paragraph (b) above. The data collected is contained in the ASBESTOS SURVEY REPORT found at the end of this section.

(i) The industrial hygiene asbestos survey described in paragraph (h) may not have identified all asbestos containing materials in the contract work area(s). When contract work area(s) appear to have asbestos containing material not identified in the ASBESTOS SURVEY REPORT, the Contractor shall conduct an asbestos survey to identify such material(s) in a manner similar to that described in the ASBESTOS

SURVEY REPORT.

S-19 SAFETY STANDARDS (NOV 2003)

a. The successful offeror will be required to comply with Chapter 396 of the Hawaii Occupational Safety and Health Act (OSHA) standards and Title 12 Department of Labor and Industrial Relations, Subtitle 8 Division of Occupational Safety and Health, Part 2 General Industry Standards as well as with the Corps of Engineers Manual 385-1-1, Safety and Health Requirements Manual. [Title 29, CFR, Chap 18, Part 1910

(OSHA)]

b. The successful offeror shall attend the Honolulu District’s Effective Planning in Accident Prevention Training Course held quarterly or view the course video within 60 days after award of the contract.

Confirmation of having taken the course shall be forwarded to the Contracting Officer Representative by a letter signed by the President of the Company.

S-23.1 EMERGENCY PLANNING COMMUNITY RIGHT TO KNOW ACT (EPCRA)

EXTREMELY HAZARDOUS SUBSTANCES (EHS), CERCLA HAZARDOUS SUBSTANCES,

AND OTHER OSHA HAZARDOUS CHEMICALS (MAY 2000

This applies to any contractor utilizing EPCRA EHS, CERCLA hazardous substances, and other OSHA hazardous chemicals in performance of any work while on any US Army Garrison, Hawaii (USAG-HI) installations. The EPCRA EHS are defined in EPA document EPA 550-B-98-017, Title III List of List, Consolidated List of Chemicals Subject to the Emergency Planning and Community Right to Know Act and Section 112(r) of the Clean Air Act Amended. Contractors are responsible for knowing which chemicals they may use or transport are contained on the list. For convenience, contractors may review a copy of the EPA document at the Directorate of Public Works (DPW) Environmental Department. To obtain a copy of the list, the document is also available at the U.S. Environmental Protection Agency (EPA) Web address http://www.epa.gov/ceppo/p-gen.htm. For contractors’ information, the locations of these chemicals stored on USAG-HI installations are available upon request. To obtain the list of locations, Section 01 90 00 – Page 13 forward request to the following E-mail address: takenakc@schofield-emh1.army.mil. Indicate name, company, contract awarded and description of contract. A data base of locations of chemicals will then be forwarded upon review and approval of request. Contractors working on USAG-HI installations are encouraged to review this database which will provide information where potentially hazardous chemicals are stored.

(1) Reporting. All spills of substances containing EPCRA EHS and CERCLA hazardous substances, and OSHA hazardous chemicals will be immediately reported to the Directorate of Public Works (DPW) Spill Response line at 656-1111 during normal working hours. After normal working hours or weekends/holidays, all spills will be reported to the DPW Work Order Desk at 656-1275. The Contracting Officer must be notified during the first business hour immediately after. All waste developed resulting from EPCRA EHS, CERCLA hazardous substances, and other OSHA hazardous chemicals being utilized will be immediately reported to the DPW Environmental Office, phone: 656- 2878 x 1022 (Mr. Akasaki).

(2) All Contractors Utilizing Substances Containing EPCRA EHS, CERCLA hazardous substances, and other OSHA hazardous chemicals will perform the following prior to contract start.

(a) Review the Installation Spill Contingency Plan, the Installation Hazardous Waste Management Plan and the 40-hour Environmental Compliance Officer Course manual available at the DPW Environmental Department or at the Directorate of Contracting. Upon review, the contractor or designated responsible employee shall sign a certification statement that they have reviewed and understand the contents of these documents.

(b) Provide a list of all EPCRA EHS, CERCLA hazardous substances, and other OSHA hazardous chemicals projected to be utilized, the estimated quantities of each and the Material Safety Data Sheets to the DPW Environmental Department and also to building 6040 East Range for material bar-codes.

(c) Provide the name, phone number, and pager number of a company spill response point of contact. The point of contact must be trained in spill response.

(d) Provide a copy of an agreement with a hazardous materials spill response company in the event of a spill.

(e) Provide copies of training certificates on environmental training and spill response training.

(f) Appoint a primary and alternate Environmental Compliance Officer in writing.

(g) Develop a notification procedure in the event of a spill to include phone numbers of response personnel, support agencies, National Response Center, State Hazard Evaluation Emergency Response Office and Civil Defense.

(3) Annual Update. On an annual basis, but not later than 1 February of each year, provide DPW Environmental Department an updated list as referenced in (2)(b) above.

(4) Contractor Caused Spills or Waste Generated of Substances Containing EPCRA EHS, CERCLA Hazardous Substances, and OSHA Hazardous Chemicals.

(a) All spills caused by the contractor will be cleaned up under supervision of the contractor and a qualified hazardous materials spill response company, at no cost to the government, in accordance with all applicable laws and regulations and to the satisfaction of the DPW Environmental Department.

(b) Accomplish all spill notifications as required by the U.S. Environmental Protection Agency and State of Hawaii to the Hazard Evaluation Emergency Response Office, Local Emergency Response Commission and National Response Center.

Section 01 90 00 – Page 14

(c) Pay for disposal cost of all contaminated materials to include but not limited to soil, sorbent materials, disposable equipment and other materials contaminated by the spill. Ensure all disposal is in accordance with all applicable laws and regulations at authorized disposal sites.

S-23.2 ASBESTOS PROHIBITION & CERTIFICATION (SEP 2000)

a. Materials or products containing more than one percent asbestos shall not be used in this project. The Contracting Officer, at any time prior to acceptance of the work, or during the period designated for warranty of the work, if any, may reject materials and products that contain asbestos in excess of one percent, and direct the removal of such materials and products from the jobsite, at the sole expense of the contractor, and without additional time granted for performance of the work. After completion of this contract, if asbestos (exceeding 1%) is discovered in the products or materials (excluding items permitted by the exception) installed by the contractor, the Government reserves the right to direct the Contractor to perform asbestos abatement and restoration work, as required, at the Contractors' sole cost. Asbestos abatement work (removal and disposal of asbestos-containing materials and products) shall be accomplished in accordance with currently applicable United States Government and State of Hawaii standards for such work.

"Exception: Where suitable asbestos-free (equal to or less than 1% asbestos) substitutes do not exist for a material or product, the contractor may use a material or product containing asbestos in excess of 1%, with the prior written approval of the Contracting Officer. The Contractor shall submit a written request for such substitution, accompanied by a certification from the manufacturer of the material or product that shall set forth, in specific detail, the amount of asbestos present in the material or product. When available, laboratory analysis of the material or product for asbestos content shall be included with the submittal."

b. The Government may conduct asbestos testing on suspected asbestos-containing materials and products excluding items permitted by the "Exception", and such testing will be conducted at the expense of the Government. However, wherever destructive testing is required, or a material or product must be utilized by the Government for testing, the Contractor, shall, at its own expense, repair or replace the material or product, or the item of work that has been disturbed by testing, if the test results confirm presence of asbestos exceeding 1%. In the event test results indicate 1% or less asbestos content or complete absence of asbestos, the Contractor shall restore the test site to its original condition and the cost of restoration work, as approved by the Contracting Officer, shall be borne by the Government.

c. As a minimum, the Contractor shall furnish manufacturer's certification for the items listed below, excluding items permitted by the "Exception", certifying that they are asbestos free or do not contain asbestos in excess of 1%, as applicable. However, when presence of asbestos is suspected in other products and materials used in this project, the Contractor shall be required to provide such certification for those additional items when so directed by the Contracting Officer. Asbestos certification shall be required for the items applicable to this project only.

1. Vinyl sheet/vinyl tile flooring, including accessories and adhesives

2. Insulation materials including facing

3. Gaskets for piping and duct work

4. Acoustical Tiles

5. Firestopping materials

Section 01 90 00 – Page 15

6. Fireproofing materials

7. Special Coating, including factory applied coatings, on sheetmetal roofing and siding

8. Wallboard for all interior and exterior applications including joint compounds

9. Adhesives (other than Item 1) used in the project

10. Tape materials used in the project

11. Roofing and Siding, nonmetallic

12. Felt materials and cushion materials

13. Pre-mixed mortars, grouts, leveling compounds, fillers, and other cementitious materials

14. Caulking and sealing materials

d. All submittals shall be accompanied by a certification from the manufacturer of the material or product that the material or product is asbestos-free; or shall set forth, in specific detail, the amount of asbestos present in the material or product. Documentary evidence of laboratory analysis of the material or product for asbestos content, conducted by an independent testing laboratory accredited for asbestos analysis by either the American Industrial Hygiene Association (AIHA) or the National Voluntary Laboratory Accreditation Program (NVLAP) administered by the National Institute of Standards and Technology

(NIST).

e. The Contractor shall implement asbestos awareness and require all subcontractors, vendors, and suppliers to furnish materials and products free of asbestos except where and exception is warranted. The Contractor shall require all subcontractors, vendors, and suppliers to provide manufacturers certifications and data to support the exception. The request for exception shall be provided in writing to the Contracting Officer 30 days prior to commencement of any field work related to that product for which the exception is sought for the project.

f. The Contractor shall monitor all subcontractors, vendors, and suppliers to ensure asbestos containing building materials are not used in the project except those permitted by the Exception.

g. Recording

(1) The Contractor shall annotate on the as-built drawings the location where asbestos containing building materials and products have been used. The annotation shall contain the material and quantity.

(2) Where projects are completed using no asbestos, the Contractor shall prepare and sign a Certification of Asbestos Free Facility. The certification shall contain the project name, contract number, date of certification, and Contractor’s name. The certificate shall state that, to the best of Contractor’s knowledge, the facility has been completed without the use of asbestos containing building materials and products. The certification shall be signed by the company president or principal or by an individual authorized to sign for the president or principal.

S-28.8 PERFORMANCE AND PAYMENT BONDS (OCT 1995)

Within fourteen (14) calendar days after the date of contract award, the bidder to whom award is made shall furnish the Government with two bonds, each with good and sufficient surety or sureties acceptable to the

Section 01 90 00 – Page 16

Government; namely, a Performance Bond (Standard Form 25) and a Payment Bond (Standard Form 25- A).

Any bonds furnished will be furnished by the Contractor to the Government prior to issuance of a Notice to Proceed by the Government. [FAR 28.102-3]

S-36.5 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

1. This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the contract clause entitled DEFAULT (FIXED-PRICE CONSTRUCTION). In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

2. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

WORK DAYS BASED ON 5-DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

3 2 3 2 2 1 1 2 2 2 2 5

3. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph 2, above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the contract clause entitled DEFAULT (FIXED-PRICE CONSTRUCTION). [ER 415-1-15, 31 Oct 89]

S-36.7 IDENTIFICATION OF EMPLOYEES

The Contractor shall be responsible for furnishing to each employee and for requiring each employee engaged on the work to display such identification as may be approved and directed by the Contracting Officer. All prescribed identification shall immediately be delivered to the Contracting Officer for cancellation upon the release of any employee. When required by the Contracting Officer, the Contractor shall obtain and submit fingerprints of all persons employed or to be employed on the project.

Section 01 90 00 – Page 17

S-36.8 GROUND-FAULT CIRCUIT INTERRUPTERS

Ground-fault circuit interrupters for all 125-volt single phase 15- and 20-ampere receptacle outlets which are not part of the permanent wiring of the building or structure shall be provided by the Contractor in accordance with Section 305-6 of the 2008 or latest edition National Electrical Code.

S-37.10 - Pursuant to Department of Defense Instruction Number 2000, “DoD Antiterrorism (AT) Standards,” dated October 2, 2006 iWATCH iWatch Training. iWATCH within the Army is a nation-wide modern version of a neighborhood watch program focused on the threat of terrorist activity. It is an antiterrorism awareness program that the contractor’s workforce, while on Army installations, must all be familiar with to promote and enhance reporting suspicious activity or behavior. The program has two elements: “passive” and “active.” The passive element is an individual’s situational awareness of his or her surroundings. The active element of iWATCH involves individuals taking action to report suspicious behavior or activities to law enforcement for more investigation.

Contractor personnel, to include subcontractors, performing on or within an Army controlled facility, area or on an Army installation are required to brief and train their personnel on the iWatch program for that area, facility or installation. Training standards will be provided by the COR with 5 calendar days of contract award. Contractor personnel are train all personnel within 30 days of award or within 30 days of a hiring action. Contractors are to report training to the COR within 45 days of contract award or a hiring action.

LEVEL I ANTITERRORISM (AT) STANDARDS

(a) Pursuant to Department of Defense Instruction Number 2000, “DoD Antiterrorism (AT) Standards,” dated October 2, 2006, each contractor employee requiring access to a Federally-controlled installation, facility and/or Federally-controlled information system(s) shall complete Level I AT Awareness Training on an annual basis and receive a certificate of completion. The training is accessible from any computer and is available at https://jkodirect.jten.mil (Course #JS-US007-14). The contractor is responsible for ensuring that all applicable employees have completed antiterrorism awareness training and shall certify that their workforce has completed the training through the submission of completion certificate (s) to the Contracting Officer and the Contracting Officer’s Representative (if appointed) within five working days after contract award or prior to access to a Federally-controlled installation or information system.

(b) In the event that the automated system at https://jkodirect.jten.mil (Course #JS-US007-14) is not available (e.g., server problems), Level I AT Awareness Training can be provided by a qualified instructor.

However, if the training is not completed online, the Level I AT Awareness Instructor qualification must be coordinated with the Installation Antiterrorism Officer (or Installation Security equivalent) and the resultant name(s) of approved instructors shall be provided the contracting officer or designee along with all associated cost or schedule impacts to the contract. Antiterrorism performance (Level 1 AT Awareness Training attendance and compliance) may be documented as a performance metric under the resultant contract, and be part of past performance information in support of future source selections.

Section 01 90 00 – Page 18

ACCESS TO ARMY INSTALLATIONS – PERSONNEL and VEHICLES

(a) Commercial businesses must possess and present a contractor IAP to gain entry at any access control point (ACP). Installation Access Passes are processed by the Installation Access Pass Office, Pohakuloa Training Area.

(b) In order to obtain a contractor IAP, the contracting office representative must submit a signed and approved IAP application along with a personnel information sheet to the Installation Access Office.

Printed proof of social security numbers will need to be presented with all substantiating documents to the IAP Office. After the office has processed the paperwork (typically 2-4 weeks), the contractor may pick up his or her pass at the office. The contractor must bring some form of identification with proof of his or her social security number.

(c) Vendors and contractors with commercial vehicles who do business on Army installations on a regular basis can receive extended passes for individual and fleet vehicles, for periods stipulated by the COR/sponsor, by registering their vehicles at the IAP Office. Company “Multiple Operator” memorandums will be presented to IAP personnel upon requesting a vehicle IAP.

(d) The Contractor shall provide to the Contracting Officer Representative the names and Social security Numbers of individuals requiring access in performance of the contract no later than 14 days prior to start of performance. The Army Organization or Directorate for whom the contractor is working is responsible for processing the paperwork to obtain passes.

(e) The Contractor is responsible for assuring personnel required to access any installation in performance of the contract obtain the required identification. Costs for employees to travel to the Government location will be borne by the contractor. Failure to obtain required identification will not relieve the contractor from contract performance. Contractor shall be responsible for the return of identification cards upon the expiration of the contract or when an employee is no longer performing work under the contract.

(f) The Contractor will provide a list of the names of all employees and subcontractor employees who will access any Army facility in the performance of this contract. Contractor will provide written document used to verify employees and subcontractor's employees compliance with FAR 52.222-54, Employment Eligibility Verification (clause that requires contractor to do background check.) The contractor will provide written proof from the Immigration and Naturalization Service that all employees listed are approved for employment within the US.

(g) At any time contractor employees are operating contractor-owned vehicles on an Army Installation, they shall have in their possession a letter signed by a corporate officer authorizing the individual to drive the vehicle.

(h) The Contracting Officer and the Provost Marshal office shall be notified of any changes in vehicles within three business days of the change.

(i) Lost vehicle passes shall be reported immediately in order to obtain new passes. All vehicle passes issued shall be returned to the Installation Access Office upon completion of the contract, termination of an employee or discontinued use of the registered vehicles.

(j) Failure to follow the procedures outlined above may result in delays in entering Army Installations. The Government is not responsible for any adverse impact on the contractor or its operation as a result of delays due to the failure to register vehicles.

(k) Contractors operating vehicles on an Army post will not use cell phones unless used with a hands-free device. This applies to ALL personnel driving privately-owned and government vehicles on Army installations and housing areas. Failure to comply will result in the loss of on-post driving privileges:

Section 01 90 00 – Page 19

First offense – 14 days Second offense – 30 days Third offense – 180 days

If caught driving while privileges are suspended, your privileges may be further suspended for a 5-year period.

(l) The Provost Marshall has the authority to change the above procedures without notice. Contractors shall adhere to any changes in security procedures.

S-36.11 POSTERS AND NOTICES

Wage Rate, Equal Employment Opportunity, and Nondiscrimination in Employment Posters and Notices will be provided to the Contractor by the Contracting Officer. The Contractor shall mount these posters and notices, together with the wage determination decision, under weatherproof, transparent, protective covering, in one or more conspicuous places, as approved, and readily available to employees.

S-36.12 PROJECT SIGN (March 2007)

Two (2) project signs shall be fabricated and erected at a location designated by the Contracting Officer.

The signs shall be constructed as shown in EP 310-1-6a, dated 01 Jun 06, pages 16-1 thru 16-4, copy of which is provided at the end of this section (Appendix A). The signs shall be erected as soon as possible and within 15 days after the date of notice to proceed. Upon completion of the project, the sign shall be removed and disposed of.

S-36.17 EQUIPMENT EXPENSE RATES IN NEGOTIATED ACTIONS (AUG 2018)

Whenever a contract or modification of contract price is negotiated, the Contractor's cost proposals for equipment ownership and operating expenses shall be determined in accordance with the requirements of Special Contract Requirements statement, entitled "EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE," of this solicitation. EP 1110-1-8 "Construction Equipment Ownership and Operating Expense Schedule" is available at http://www.usace.army.mil/inet/usace-docs/eng-pamphlets/ep1110-1-8(vol10)/toc.htm for State of Hawaii (Region 10) and at http://www.usace.army.mil/inet/usace-docs/eng-pamphlets/ep1110-1-8(vol12)/toc.htm for Kwajalein Island, Roi-Namur Island, and Meck Island (Area 12), including Guam, American Samoa, and Johnston Island). [FAR 31.105(d)(2)(i) and UAI 31.105(d)(2)(i)(B)].

S-36.21 AVAILABILITY AND USE OF UTILITY SERVICES (JAN 2006)

(a) The Government will make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. Unless otherwise provided in the contract, the amount of each utility service consumed shall be charged to or paid for by the Contractor at prevailing rates charged to the Government or, where the utility is produced by the Government, at reasonable rates

Section 01 90 00 – Page 20 determined by the Contracting Officer. The Contractor shall carefully conserve any utilities furnished without charge.

(b) The Contractor, at its expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of each utility used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia.

(c) Schedule of utilities available from the Government without charge:

1. The Contractor will need to bring their own office trailer.

2. Contractor may tie into the PTA electrical system for their office needs only, but need to provide and install their own pad mounted transformer and meter. DPW has the right to charge the contractor for electricity usage. Coordination is required with the DPW at least 90 days prior to tying into the PTA electrical system, since high voltage support is needed from DPW USAG-HI. Please reference attached Electrical Outage form.

3. The Contractor shall provide its own water to PTA.

S-36.34 VEHICLE REGISTRATION

1. All vehicles operating on Army Installations must have a valid registration, valid certificate of insurance, current safety inspection and be operated by a licensed driver. Vehicle operators shall be prepared to present these documents when requested by the security guard.

2. Contractor vehicles utilized in performance of the contract shall be registered with the Installation

Provost Marshal for entry into any Army Installation. This includes contractor employees’ privately-owned vehicles (POVs) used to travel to and from the job site. Employees will be allowed to register only one vehicle. It shall be the sole responsibility of the contractor to register vehicles with the Provost Marshal.

3. Prior to contract performance, the contractor shall provide the Contracting Officer with a list of company-owned vehicles, employee POVs, and any subcontractor vehicles to be registered. The Contracting Officer will prepare a request for vehicle registration to the Provost Marshal. Upon receipt of the signed request the contractor shall report directly to the Provost Marshal for vehicle registration.

Contractor employees must report in person for registration of their POVs. The following documents will be required to be presented to the Provost Marshal for vehicle registration:

a. Contracting Officer’s request for vehicle registration.

b. Valid Vehicle registration

c. Valid Certificate of Insurance

d. Current Safety Inspection

e. Valid driver’s license

4. At any time contractor employees (or subcontractor employees) are operating contractor-owned vehicles on an Army Installation, they shall have in their possession a letter signed by a corporate officer authorizing the individual to drive the vehicle.

5. The Contracting Officer and the Provost Marshal office shall be notified of any changes in vehicles within three business days of the change.

Section 01 90 00 – Page 21

6. In the event the Provost Marshal issues extended passes for vehicles, lost passes shall be reported immediately, in writing, to the appropriate Provost Marshal Office, in order to obtain new passes.

Notification shall include all circumstances surrounding the loss of the original passes. All vehicle passes issued shall be returned to the Provost Marshal upon completion of the contract, termination of an employee or discontinued use of the registered vehicles.

7. Failure to follow the procedures outlined above may result in delays in entering Army Installations.

The Government is not responsible for any adverse impact on the contractor or its operation as a result of delays due to the failure to register vehicles.

Introduction: Construction Project Signs EP 310-1-6a 01 Jun 06

16-1

The use of signs to identify Corps managed or supervised design, construc-tion, and rehabilitation projects - both for military and civil works - is an important part of efforts to keep the public informed of Corps work. For this purpose, a construction project sign package has been adopted. This package consists of two signs: one for project identification and the other to show on-the-job safety performance of the contractor.

These two signs are to be displayed side by side and mounted for reading by passing viewers. Exact placement location will be designated by the contracting officer’s representative.

The panel sizes and graphic formats have been standardized for visual consistency throughout all Corps operations.

Panels are fabricated using HDO plywood or aluminum with dimensional lumber uprights and bracing. The sign faces are nonreflective vinyl.

All legends are to be die-cut or computer-cut in the sizes and typefaces specified and applied to the white panel back-ground following the graphic formats shown on pages 16-2 and 16-3. The Communication Red panel on the left side of the construction project sign with Corps Signature (reverse version) is screen-printed onto the white back-ground.

A display of these two signs is shown on the following two pages. Mounting and fabrication details are provided on page 16-4.

Special applications or situations not covered in these guidelines should be referred to the district Sign Program Manager.

W9128A-19-B-0001

Section 01 90 00, Appendix A, S-36.12, Project Signs - Page 1

Construction Project Identification Sign

16-2

EP 310-1-6a 01 Jun 06

Below are two samples of the Construc-tion Project Identification sign showing how this panel is adaptable for use to identify either military (top) or civil works projects (bottom). The graphic format for this 4’x 6' sign panel follows the legend guidelines and layout as specified below.