About this file

Tech Specs 1 of 6

View the file

Other files

File Type Posted
10r3-am6.pdf PDF
10r3-am5.pdf PDF
10r3-am4.pdf PDF
10r3-am3.pdf PDF
10r3-am2.pdf PDF
10r3-am1.pdf PDF
SOW PDF - 2010-06-18.pdf PDF
RFP 6.pdf PDF
Appendix A 100 Geotech Rpt SB 8-2-09.pdf PDF
RFP 5.pdf PDF
Final SCR PN 69308 - SR GTF Infrastructure.pdf PDF
Final SCR PN 68822 - SR EOD Unit.pdf PDF
RFP 4.pdf PDF
Final SR Field Characterization Rpt.pdf PDF
10r3-23jun10.pdf PDF
RFP 3.pdf PDF
APPENDIX J Dwgs-Sol File-6-23-10.pdf PDF
Final SCR PN 68786 - SR EG Unit.pdf PDF
RFP 2.pdf PDF
Final SCR PN 68821 - SR MP Unit.pdf PDF
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Design-Build Request For Proposal

FY09 Grow the Army Projects, PN 69308 Infrastructure Expansion, PN 68786 Brigade Complex, PN 68821 HHD MP Unit Operations and Maintenance & PN 68822 Explosive Ordnance Disposal Unit

RTA Submittal: 23 June 2010

South Range, Schofield Barracks, Oahu, Hawaii

Contract #W9128A-10-R-0003

SECTION 00 01 10

TABLE OF CONTENTS – PHASE I

REQUEST FOR PROPOSAL

FY09 Grow the Army Projects, PN 69308 Infrastructure Expansion, PN 68786 Brigade

Complex, PN 68821 HHD MP Unit Operations and Maintenance & PN 68822 Explosive

Ordnance Facility

South Range, Schofield Barracks, Oahu, Hawaii

DIVISION 01 - General Requirements

01 10 00 Statement of Work

01 32 01.00 10 Project Schedule

01 33 00 Submittal Procedures

01 33 16 Design After Award

01 35 29 Safety and Occupational Health Requirements

01 45 01.10 Quality Control System (QCS)

01 45 04.00 10 Contractor Quality Control

01 50 02 Temporary Construction Facilities

01 57 20 Environmental Protection

01 57 23 Storm Water Pollution Prevention Measures

01 62 35 Recycled/Recovered Materials

01 74 19 Construction and Demolition Debris Recycling

01 78 02.00 10 Closeout Submittals

01 90 00 Miscellaneous Provisions

DIVISION 31 - EARTHWORK

31 05 19 Geotextile

31 05 21 Geogrid

32 11 16 Subbase Course

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 11 23 Graded-Crushed Aggregate Base Course

32 12 10 Bituminous Tack And Prime Coats

32 12 16 Hot-Mix Asphalt (HMA) For Roads

32 13 11 Concrete Pavement For Roads And Hardstands

32 13 73 Compression Joint Seals For Concrete Pavements

32 31 13 Chain Link Fences And Gates

APPENDICES

Appendix A Geotechnical Information

Appendix B Not Used

Appendix C Not Used

Appendix D Not Used

Appendix E Environmental Information

Appendix F Conceptual Aesthetic Considerations

Appendix G GIS Data

Appendix H Exterior Signage

Appendix I Acceptable Plants List

Appendix J Drawings

Appendix K Life Cycle Cost Analysis Fuel Cost Information

Appendix L LEED Project Credit Guidance

Appendix M LEED Owner’s Project Requirements

Appendix N LEED Requirements for Multiple Contractor Combined Projects (Not Used)

Appendix O LEED Strategy Tables (Not Used)

Appendix P USGBC Registration of Army Projects

Appendix Q AREA COMPUTATIONS

Appendix AA DPW Conditional Release Form

Appendix BB DPW EXCAVATION PERMIT

Appendix CC Landscaping and Trash Dumpster Guidance

Appendix DD US ARMY GARRISON HAWAII NPDES PERMIT

Appendix EE Aqua Engineers Sewer Requirements

Appendix FF Exterior Materials Chart

Appendix GG South Range Land Acquisition

Appendix HH Minimum Pavement Sections

Appendix II GTA Infrastructure Water System Distribution Analysis

Appendix JJ GTA Infrastructure Traffic Study Information

Appendix KK TEMF Organizational Vehicle Listing

Appendix LL Culturally Sensitive Area Plan

Appendix MM Existing Range Road Plan

Appendix NN Telecommunications Labeling Requirements

Appendix OO South Range IED Training Area

Appendix PP Parking Lot Design Requirements

Appendix QQ (Not Used)

Appendix RR Hawaiian Electric Company (HECO) Notes

Appendix SS GTA Project Right of Entry Requirements

Appendix TT 100 Year Flood Inundation Existing Condition

Appendix UU Infrastructure Preliminary/Concept (10% to 35% Design) Drawings

Appendix VV DOT 4-222

SECTION 01 10 00

STATEMENT OF WORK

1.0 PROJECT OBJECTIVES

1.1 SECTION ORGANIZATION

2.0 SCOPE

2.1 PN 69308 Infrastructure Expansion Project

2.2 PN 68786 Engineer Unit Operations and Maintenance Project

2.3 PN 68821 HHD MP Unit Operations and Maintenance Project

2.4 PN 68822 Explosive Ordnance Facility Project

2.5 SITE DESIGN

2.5.1 PN 69308 Infrastructure Expansion Site Design

2.5.2 PN 68786 Engineer Unit Operations and Maintenance Site Design

2.5.3 PN 68821 HHD MP Unit Operations and Maintenance Site Design

2.5.4 PN 68822 Explosive Ordnance Facility Site Design

2.6 GOVERNMENT-FURNISHED GOVERNMENT-INSTALLED EQUIPMENT

(GFGI)

2.7 FURNITURE REQUIREMENTS:

3-0 FACILITY REQUIREMENTS

3-1 COMPANY OPERATIONS FACILITY (COF)

3-1.1 COF GENERAL REQUIREMENTS

3-1.2 COF FUNCTIONAL AND OPERATIONAL REQUIREMENTS

3-1.3 COF TECHNICAL REQUIREMENTS

3-2 BRIGADE AND BATTALION HEADQUARTERS FACILITY

Section 01 10 00 W9128A-10-R-0003

3-2.1 BRIGADE AND BATTALION HEADQUARTERS GENERAL

REQUIREMENTS

3-2.2 BRIGADE AND BATTALION HEADQUARTERS FUNCTIONAL AND

OPERATIONAL REQUIREMENTS

3-2.3 BRIGADE AND BATTALION HEADQUARTERS TECHNICAL

REQUIREMENTS

3-2.4 BRIGADE AND BATTALION HEADQUARTERS FURNITURE

REQUIREMENTS

3-2.5 BRIGADE AND BATTALION HEADQUARTERS REFERENCES

3-3 TACTICAL EQUIPMENT MAINTENANCE FACILITY (TEMF)

3-3.1 TEMF GENERAL REQUIREMENTS

3-3.2 TEMF FUNCTIONAL AND OPERATIONAL REQUIREMENTS

3-3.3 TEMF REFERENCES

3-4 CRIMINAL INVESTIGATION DIVISION COMMAND BATTALION

HEADQUARTERS

3-4.1 CIDC BN HQ GENERAL REQUIREMENTS

3-4.2 CIDC BN HQ FUNCTIONAL AND OPERATIONAL REQUIREMENTS

3-4.3 CIDC BN HQ TECHNICAL REQUIREMENTS

3-4.4 CIDC BN HQ – FURNITURE REQUIREMENTS

3-5 Administrative Facilities

3-6 Central Plants (CP)

3-7 Remote Switching Center

Section 01 10 00

4.0 APPLICABLE CRITERIA

5.0 SITE PLANNING AND DESIGN

6.0 Roads and Parking

7.0 Grading and Drainage

8.0 Water System

9.0 Sewer System

10.0 Site Security

11.0 Landscaping

12.0 ARCHITECTURAL

13.0 STRUCTURAL DESIGN

14.0 PLUMBING

15.0 HEATING, VENTILATING AND AIR CONDITIONING

16.0 THERMAL PERFORMANCE

17.0 ENERGY CONSERVATION

18.0 Fire Protection

19.0 Sustainable Design

20.0 ELECTRICAL

21.0 TELECOMMUNICATIONS

Section 01 10 00

1.0 OBJECTIVES

The objective of this contract is to design and construct facilities for the military that are consistent with the design and construction practices used for civilian sector projects that perform similar functions to the military projects. For example, a Company Operations Facility (COF) has the similar function as an office warehouse in the civilian sector; therefore the design and construction practices for a Company Operations Facility should be consistent with the design and construction of an office warehouse building.

Comparison of Military Facilities to Civilian Facilities

Military Facility Civilian Facility

Company Operations Facility (COF) Office Warehouse

Battalion/Brigade Headquarters (BN HQ/BDE HQ) Office

Tactical Equipment Maintenance Facility (TEMF) Heavy Equipment/Vehicle Maintenance Garage

Criminal Investigation Division Command Battalion Headquarters (CIDC BN HQ)

Office

It is the Army's objective that these buildings will have a 25-year useful design life before a possible re-use/re-purpose or renovation requirement, to include normal sustainment, restoration, modernization activities, and a 50-year building replacement life. Therefore, the design and construction should provide an appropriate level of quality to ensure the continued use of the facility over that time period with the application of reasonable preventive maintenance and repairs that would be industry-acceptable to a major civilian sector project OWNER. The site infrastructure will have at least a 50-year life expectancy with industry-accepted maintenance and repair cycles.

The project sites should be developed for efficiency and to convey a sense of unity or connectivity with the adjacent buildings and with the Installation as a whole.

Requirements stated in this contract are minimums. Innovative, creative, and life cycle cost effective solutions, which meet or exceed these requirements are encouraged. Further, the Contractor is encouraged to seek solutions that will expedite construction (panelization, pre-engineered, etc.) and shorten the schedule. The intent of the Government is to emphasize the placement of funds into functional/operational requirements. Materials and methods should reflect this by choosing the lowest Type of Construction allowed by code for this occupancy/contract allowing the funding to be reflected in the quality of interior/exterior finishes and systems selected.

Section 01 10 00

2.0. SCOPE: Design and construction of four (4) MILCON projects, as follows:

• PN 69308 Infrastructure Expansion

- Referred to as “Infrastructure project”

• PN 68786 Engineer Unit Operations and Maintenance Project,

• PN 68821 HHD MP Unit Operations and Maintenance Project, and

• PN 68822 Explosive Ordnance Disposal Unit Project

- Collectively referred to as “Campus projects”

2.1. Infrastructure Project: PN 69308 Infrastructure Expansion Project (CLIN 0001 & 0002)

The purpose of this project is to provide the site improvements and utilities necessary to access and support the Campus projects and future development of South Range. See Appendix UU, drawing C-2 and E-1 for approximate layout of the major features. Major features include:

• Road connecting South Range to Schofield Barracks – Mellichamp Extension Road (paragraph 6.2.2) and signalized intersection improvements at Lyman Road (paragraph 6.2.2.3)

• Road providing access and circulation to campus projects - Road B (paragraph 6.2.3)

• Road providing access to SPS and future South Range Development site – Road A Extension (paragraph 6.2.3.3)

• Replacement for range roads impacted by construction (paragraph 6.2.6)

• Stormwater collection, detention, treatment and disposal systems (paragraph 7.0)

• Water supply system connecting the existing water system on Schofield Barracks to a new 1 MG storage tank and distribution system to the Campus projects (paragraph 8.0)

• Sewage collection system from Campus project sites to the existing wastewater treatment plant (WWTP) at Wheeler Army Airfield (paragraph 9.0)

• New South Range Substation and electrical distribution system connecting the new South Range Substation to the Campus projects. Street light system for Mellichamp Extension, Road B (paragraph 20.4.1.6).

• Telecommunications distribution system connecting the existing system on Schofield Barracks to the Campus projects, including new Remote Switching Center (RSC) (paragraph 21.0)

• Security measures providing a barrier between the installation and surrounding land owners and a separation of functions within the installation (paragraph 10.0)

2.2. Campus Projects: PN 68786 Engineer Unit Operations and Maintenance (CLIN 0003 & 0004) PN 68821 HHD MP Unit Operations and Maintenance (CLIN 0005 & 0006) PN 68822 Explosive Ordnance Facility (CLIN 0007 & 0008)

The purpose of these projects is to provide the operation and administration facilities for the assigned units. Major features are tabulated in Table 2.2-1. See Appendix J, drawing C-1 for approximate location of the projects.

Section 01 10 00

Table 2.2-1 Campus Projects Features

2.2.1 Support Facilities

The Campus projects include the site improvements required to support the facilities noted in Table 2.2-1, including but not limited to:

• Road system providing access and circulation to the Campus projects – Roads A, C, D, and C Extension (paragraph 6.2.3)

• Utility services, within the campus and Roads A, C, D, and C Extension – water, sewer, electricity, telecommunications, fire protection, mass notification (paragraphs 8.0, 9.0, 20.0, 21.0).

Street light system for Roads A, C, D, and C Extension (paragraph 20.4.1.6).

• Stormwater collection, detention, and treatment (paragraph 7.0)

• Security – exterior lighting, fencing, antiterrorism/force protection (ATFP) measures (paragraph 10.0)

• Landscaping (paragraph 11.0)

2.3. GOVERNMENT-FURNISHED GOVERNMENT-INSTALLED EQUIPMENT (GFGI)

Coordinate with Government on GFGI item requirements and provide suitable structural support, brackets for projectors/VCRs/TVs, all utility connections and space with required clearances for all GFGI items.

Computers related hardware, copiers, faxes, printers, video projectors, VCRs and TVs are GFGI.

2.4. FURNITURE REQUIREMENTS:

Provide furniture design for all spaces, including existing furniture and equipment to be re-used.

Coordinate with the user to define requirements for furniture systems, movable furniture, equipment, existing items to be reused, storage systems, etc. Early coordination of furniture schedule is required so the facility is complete and usable at turnover.

Furniture procurement is not included in this contract.

3-0 FACILITY REQUIREMENTS

3-1 COMPANY OPERATIONS FACILITY (COF)

The specifications in paragraph 3-1 apply to three (3) COFs that are required under this contract:

PN68786: One (1) Standard-design 2-150 PN company COF for the Engineer Unit Operations and Maintenance Project PN68821: One (1) Standard-design 1-200 PN company COF for the HHD MP Unit Operations and Maintenance Project PN68822: One (1) Standard-design 1-100 PN company COF for the Explosive Ordnance Facility Project

3-1.1 COF GENERAL REQUIREMENTS:

COFs provide administrative and supply facilities for unit personnel functions and storage of their equipment.

These facilities serve as the primary staging, training, and deployment center for personnel and their individualized gear.

3-1.1.1. Facility Relationships

COFs are typically located within an operations complex along with Tactical Equipment Maintenance Facilities (motor pools) and Battalion/Brigade HQ. The facilities within this complex shall be oriented to support deployment and daily operations.

3-1.1.2 Gross Building Area

Gross areas of facilities shall be computed according to subparagraphs below. Maximum gross area limits indicated in Paragraph 2.0, SCOPE, may not be exceeded. A smaller overall gross area is permissible if all established net area program requirements are met.

(1) Enclosed Spaces. The gross area includes the total area of all floors, including basements, mezzanines, penthouses, usable attic or sloping spaces used to accommodate mechanical equipment or for storage with an average height of 6’-11” measured from the underside of the structural system and with the perimeter walls measuring a minimum of 4’-11” in height, and other enclosed spaces as determined by the effective outside dimensions of the building. (NOTE: Exterior Covered Hardstand area associated with Company Operations Facilities shall be calculated as enclosed space, i.e. full scope).

(2) One-Half Spaces. One-half of the area will be included in the gross area for balconies and porches; exterior covered loading platforms or facilities, either depressed, ground level, or raised; covered but not enclosed passageways or walks; covered and uncovered but open stairs; and covered ramps.

(3) Excluded Spaces. Crawl spaces; exterior uncovered loading platforms or facilities, either depressed, ground level, or raised; exterior insulation applied to existing buildings; open courtyards; open paved terraces; roof overhangs and soffits for weather protection; uncovered ramps; uncovered stoops; and utility tunnels and raceways will be excluded from the gross area.

3-1.1.3. Functional Spaces

Net area requirements for functional spaces are included in the Space Criteria table (Table 3-1.2). If net area requirements are not specified in the Statement of Work, the space shall be sized to accommodate the required function, comply with code requirements, comply with overall gross area limitations and other r equirements of the Contractor (for example, area requirements for corridors, stairs, and mechanical rooms will typically be left to the discretion of the Contractor).

3-1.1.4. Handicapped Access

COFs are intended for use by able-bodied military personnel only , therefore, are not requi red to meet handicapped accessible requirements.

3-1.1.5. Site Design and Functional Area

Site features include service yard and service yard drives, utilities, and site improvements.

3-1.1.6. ADAPT-BUILD MODEL An Adapt-Build Model for a Brigade and Battalion (HQ) Facilities, which contains a fully developed design, including a Building Information Model (BIM), 2-D CADD files, and specifications, can be downloaded from the following FTP site ftp://ftp.usace.army.mil/pub/sas/COF/ . This design is provided as a guide that exemplifies a technically suitable product and incorporates mandatory functional/operational requirements for a similar (although perhaps not an exact) facility to be constructed under this contract. It will be left to the contractor’s discretion if, and how, they will use the sample design provided to satisfy the requirements of this contract. This model is not intended to modify or override specific requirements of this contract and, under all circumstances, it will be incumbent upon the contractor to adhere to the site specific scope and functional/operational requirements specified within the contract.

Neither this statement of work, nor the adapt-build model, are intended to diminish the contractor’s responsibilities under the clauses titled “Responsibility of the Contractor for Design,” “Warranty of Design,” and “Construction Role During Design.” The contractor shall be the designer-of-record and shall be responsible for the final design and construction product, including but not limited to, adherence to the installation architectural theme, building code compliance and suitability of the engineering systems provided. The government assumes no liability for the model design provided and, to the extent it is used by the contractor, the contractor will be responsible for all aspects of the design as designer-of-record.

3-1.2. COF FUNCTIONAL AND OPERATIONAL REQUIREMENTS

3-1.2.1. General

COF functional layout and adjacency requirements are as indicated on the COF concept drawings. The extent to which the COF concept drawings represent required layouts and the allowable latitude for changes to them is as noted on the COF concept drawings. COFs should be easily adaptable to accommodate variations in size and number of companies in the Army’s future force. The design objective of the basic battalion level COF complex is to provide a flexible facility suitable to a mix of battalions of varying composition while utilizing a modular approach.

3-1.2.2 Functional Areas

The COF is comprised of three vertical construction components consisting of an Administrative Module, Readiness Module, and exterior covered hardstand. In conjunction with this, each site-specific project shall include necessary site amenities, such as vehicle service yards, access drives, equipment wash stations, and exterior utilities. These components are more fully described below.

(1) Administration Module. Space shall be provided for the following administration and support functions:

(a) Private offices for the Commander, First Sergeant, Executive Officer and Training Room

(b) Space for printer and fax machines, waste and paper recycling receptacles, and supply closet for storage

(c) Shared office space for platoon leaders and platoon sergeants

(d) Conference space for meetings and/or training

(e) Showers, locker room, and latrines to serve both the administrative personnel assigned to the company and for off post personnel - a place for commuters to shower and change after PT

(f) Consolidated utility spaces to serve the entire facility including a mechanical room, electrical room, telecommunication rooms (including SIPRNet), janitor’s closet, vending area to also accommodate recycling receptacles and recycling storage closet. Accommodation for Secure Internet Protocol Routing Network (SIPRNet)

Section 01 10 00 shall be constructed in accordance with AR 380-5, Chapter 7.

(2) Readiness Module. Space will be provided for the following operational and supply functions:

(a) Readiness Bays to provide accommodation for individual combat equipment (TA-50) lockers (CFCI) for all unit personnel, plus co-located area for equipment maintenance, training, and pre-deployment preparations. Interior equipment maintenance area will be nominally sized so that up to 50 percent of the unit personnel can layout TA-50 gear simultaneously, based on providing 40 square feet (5-foot by 8-foot plus a circulation factor) for each layout space. Each company area shall accommodate forklift access from the readiness bay to the exterior loading areas. The bay floor shall be capable of supporting forklift movement throughout the area. Slab shall be designed for forklift truck maximum axle load of 5 kips and maximum load capacity of 2 kips. Interior mud wash utility sinks shall be provided in the Readiness Areas. Sinks shall be allocated on the basis of one utility sink for every 50 soldiers in the company.

(b) Supply Bays to provide storage space for company supplies and equipment - Tables of Equipment (TOE) and Common Tables of Allowance (CTA), weapons, and consumable supplies (including items awaiting issue, turn-in, or repair). Also, it provides accommodation for the supply sergeant, supply clerk(s) and the armorer in performing shipping and receiving functions. Specific storage areas included in the supply bay include:

Weapons vault for storage of arms, ammunition, and explosives (AA&E)

Secure storage roo m for non-sensitive items (high value items, other than AA&E, for which accountability is a concern) Nuclear, biological, and chemical (NBC) equipment storage

Communications equipment storage

Consumable unit storage

(c) Accommodation for overflow/expansion from either admin or storage spaces. This provision shall be accomplished by the utilization of a mezzanine over the entire open area of the Readiness Module, within the area limitations of IBC and NFPA 101. The COF concept drawings indicate overflow/expansion arrangements that meet user operability requirements. The expansion space indicated on the COF concept drawings shall be provided at the time of initial project construction.

(3) Exterior Covered Hardstand. Outside sheltered space for equipment maintenance, weapons cleaning, and pre-deployment preparation. This area shall be sized in accordance with Paragraph 2.0 SCOPE. Provide a column free interior to the greatest extent possible to allow for the greatest flexibility in use. The minimum canopy height shall be 14'-0" or such height as required to allow for operational truck access. The minimum clear depth shall be 30'-0".

3-1.2.3. COF Army Standards

The following items are the Army mandatory features for the COFs.

Section 01 10 00

(1) Battalion Centric Design. Design that consolidates COFs for an entire battalion in a single building. The design standard is intended to crea te a facility that consolidates between three and eight companies of a battalion in a single building. This single building can be reconfigured internally without changing the footprint of the building if the battalion structure changes.

(2) Open Design for Admin and Readiness Modules. Open design for both admin and readiness modules, easy to reconfigure in response to changes in force structure, equipment, and doctrine. Consistent with the battalion centric focus, both the admin and the readiness (supply) modules will employ design features that are durable but reconfigurable without altering the structural design of the building. The goal is to allow ready adaptability in response to changes in force structure, equipment, and doctrine. The addition of internal load bearing structures that limit design flexibility will not be permitted.

(3) TA-50 Lockers. Individual combat equipment (TA-50) lockers in sufficient quantity to meet the capacity of the facility (100 percent of maximum personnel in each company). Provide permanently installed, individual steel lockable lockers sized 42” (w) x 24” (d) x 78” (h) to allow each soldier to securely store current TA-50 as well as future Soldier Systems equipment.

(4) Interior Operations and Maintenance Area. The interior space of the readiness module is intended to provide space for equipment maintenance and pre/post-deployment checks, as well as other unit preparatory and training requirements.

The space includes the provision for individual TA-50 and other equipment storage, and future fielding of Soldier Systems equipment. The space is to be nominally sized to provide 40 SF layout areas for 50 percent of the upper limit of the design capacity of the facility (50 percent of the maximum personnel). Variations to the locker arrangement shown in the COF concept drawings are permitted, but may result in a reduced number of layout spaces. Revised configurations that reduce the available layout area to less than 25 percent of the design capacity of the readiness module will not be permitted. The readiness module will be designed to accommodate the use of fork lifts. In addition to the above, wire mesh cage storage shall be provided for unit supply, NBC, and communications equipment located at the supply bay area .

(5) Exterior Covered Hardstand. Exterior covered hardstand adjacent to the Readiness Module will be provided for each company to accommodate outside equipment maintenance, weapons cleaning, pre/post-deployment preparation, vehicle loading, close formation, etc. This space is to be nominally sized to provide 40 SF layout areas for 25 percent of the upper limit of the design capacity of the facility (25 percent of the maximum personnel). Water, lighting, and electrical connections shall be provided.

(6) Arms Vaults. Arms vaults to accommodate storage of arms, ammunition and explosives (AA&E) shall be provided for each company. These vaults shall be designed in accordance with physical security requirements contained in AR 190-11, Appendix G. Ceiling height shall be minimum 12 feet t o accommodate stacked gun racks and lockers. An option exists for use of prefabricated, modular vaults conforming to Fed. Spec. AA-V-2 737 requirements. Provide a GSA approved Class 5 Armory vault door with lock in accordance with Fed. Spec. AA-D-600D and a Dutch style day gate with issue port.

(7) Non-Sensitive Secure Storage (other than AA&E). Provide secure storage of items with a high dollar value or

Section 01 10 00 items for which command accountability is required. The room shall be constructed of material to prevent forcible entry.

The minimum acceptable construction is expanded steel fabric behind impact resistant gypsum board at both walls and ceiling. The door shall provide a degree of security, and as a minimum, shall be constructed of sheet metal material not less than 16 gauge in thickness and be equipped with a hasp to accommodate a high security padlock Provide provision for ICIDS (Internal Commercial Intrusion Detection System).

(8) Consolidated Showers and Latrines. A single set of shower/latrine facilities shall be provided for each combined COF (UNICOF). Sufficient shower stalls shall be provided to accommodate 25 percent of the design capacity of the complex within a 1 hour duration and shall be not less than those indicated on the COF concept drawings. The design layout shall allow adjustment for the ratio of males and females in any unit by repositioning the dividing wall between their facilities at the time of initial construction. The facilities will have INTERIOR access to these facilities. Lockers with benches shall be provided on a 3:1 ratio of lockers/shower. Minimum locker size shall be 12”(w)x18”(d)x36”(h).

(9) Economy of Construction t o Suit Function. Designers shall consider economy of construction to suit the function, i.e. warehouse or light industrial type facilities.

(10) Operational Site Orientation. Operational facility relationships require locating COFs within a complex with direct access to the unit motor pool or other corresponding work areas. The intent is to provide a single battalion centric complex containing facilities to support company operations and vehicle maintenance in a single fenced compound.

When site conditions do not permit this configuration, COFs should be placed adjacent to the vehicle maintenance complex to facilitate the movement of personnel and equipment between the two facilities.

3-1.3. COF TECHNICAL REQUIREMENTS

3-1.3.1. Site Design

The following site design requirements are applicable to the design of COFs:

(1) Exterior Covered Hardstand

Provide an exterior covered hardstand adjacent to the readiness module. The concrete pavement under the covered hardstand shall be sloped between 1 and 2 percent to drain away from the Readiness Module. Provide weatherproof lighting and weatherproof general purposes receptacles with ground fault protection. Lighting control shall be provided with local switches with photocell override. Provide one duplex receptacle for every two columns.

(2) Service Yard

Provide a rigid concrete pavement for the service yard adjacent to the Readiness Module/Exterior Covered Hardstand.

The service yard shall be of sufficient depth to accommodate up to a 35-foot long vehicle with a 45-foot turning radius along the entire length of the Readiness Module/Exterior Covered Hardstand. The service yard shall be sloped between 1 and 2 percent to drain away from the Readiness Module/Exterior Covered Hardstand area. Provide accommodation for boot/TA-50 gear equipment washing, drainage, and grit removal. Wastewater from the boot/TA-50 gear equipment washing shall be routed to a sediment trap prior to discharge to sanitary sewer systems. The sediment trap shall be sized

Section 01 10 00 to remove particles larger than No. 4 sieve (0.187 inch). Provide one boot/TA-50 gear washing station per company.

Each wash station shall include four hose bibb and drying rack (handrail).

(3) Entrance Drive into Service Yard

Provide two 28-foot wide rigid concrete pavement entrance drives from the Service Yard to an adjacent roadway.

Service drives shall be located on opposite sides of the service yard.

(4) Bollards

Provide 6-inch diameter by 5-foot high, concrete-filled, schedule 80 galvanized steel pipe bollards, 5-foot O.C.

spacing, 5 feet from edge of electrical and mechanical equipment, painted safety yellow for each column of the exterior covered hardstand located adjacent to the service yard where frequent vehicle movement increases the risk of damage by vehicle impact. Bollard footings shall be designed to withstand vehicular impact.

(5) Privately Owned Vehicles (POV) Parking

Company Operations Facility. Total POV parking shal l be provided at the ratio of one space for every two people for the maximum design capacity of all Company Operations Facilities.

3-1.3.2 Architectural Design

(1) Exterior architectural features of the building shall be designed based on the following and in accordance with the established Installation architectural theme.

(2) The Readiness Module shall be constructed to meet the requirements of a Risk Level II analysis in accordance with AR 190-51 and AR 190-13. In conjunction with this, it has been determined that a minimum exterior wall construction consisting of 26 gauge metal wall panels with insulation and an interior metal liner panel extended to a height 8’ above the finished floor will satisfy the minimum Risk Level II requirements of AR 190-51, Appendix B-2, paragraph c. The minimum interior wall construction for demising walls between company readiness areas shall consist of a stud wall with impact resistant gypsum wall board on each side.

(3) Natural Lighting. Provide windows for natural lighting and ventilation in all office areas wherever possible. All operable windows provided shall have locks and insect screens. Natural lighting shall be provided at Readiness Areas to the greatest extent possible.

(4) Sound Insulation. Provide sound insulation in all administration areas to meet a minimum rating of STC 42 at walls and floor/ceiling assemblies, and a rating of STC 33 for doors, which are to be solid core wood in a metal frame. In addition to the sound insulation required, conference areas shall meet a Noise Criteria (NC) 30 rating in accordance with ASHRAE Fundamentals Handbook.

(5) Office and Administrative Areas. Provide maximum flexibility for future change within office and administration areas. The command section offices shall be constructed to provide privacy and sound control in accordance with SOUND INSULATION paragraph above. Minimize load-bearing walls to the greatest extent possible to accommodate future reconfiguration of spaces. This same construction requirement is also applicable to walls between companies in

Section 01 10 00 the readiness areas.

(6) TA-50 St orage Lockers. TA-50 lockers shall be provided as indicated in Paragr aph 3-1.2. 3 (3) , with size and appearance similar to that shown below. TA-50 lockers shall be single tier, heavy duty, all welded ventilated type and meet the following minimum requirements:

(a) All tops, bottoms and shelves shall be constructed of minimum 16 gauge thick cold rolled sheet steel. All sides, intermediate partitions and backs shal l be constructed of minimum 14 gauge fl attened expanded metal or perforated metal with a minimum free area of 50%, welded to angle iron frames. Frames shall be constructed of minimum 1” X 1” X 1/8” ang le i ron st eel. Thickness of metal and details of assembly and supports shal l provide strength and stiffness.

(b) Double doors shall have a three-point three-sided cremone latch and shall be padlockable. Doors shall be hinged with minimum five knuckle heavy duty steel pin butt hinges welded to both door and locker frame - provide three hinges per single tier door.

(c) Each locker shall include: one aluminum number plate (numbered in sequential order), one full width shelf located 12” from the top with clothes hangar rod and three locker hooks mounted below.

(d) Lockers shall be galvanized and coated with a high quality durable finish with color to be manufacturer’s standard tan or gray.

(e) Locker shall be anchored to concrete floor in accordance with manufacturer’s recommendations.

3-1.3.3 Fire Protection

(1) Standards and Codes

All fi re protection and li ife safety features shal l be in accordance with UFC 3-600-01 and the criteria referenced therein.

COFs shall be classified as mission essential and shall be provided with sprinkler protection.

(2) Fire Protection and Life Safety Analysis

A fire protection and life safety design analysis shall be provided for all buildings in the project. The analysis shall be submitted with the interim design submittal. The analysis shall include classification of occupancy (both per the IBC and NFPA 101); type of construction; height and area limitations (include calculations for allowable area increases); life safety provisions (exit travel distances, common path distances, dead end distances, exit unit width required and provided); building separation or exposure protection; specific compliance with NFPA codes and the IBC; requirements for fire-rated walls, doors, fire dampers, etc.; analysis of automatic suppression systems and protected areas; water supplies; smoke control systems; fire alarm system, including connection to the base-wide system; fire detection system; standpipe systems; fire extinguishers; interior finish ratings; and other pertinent fire protection data. The submittal shall include a life safety floor plan for all buildings in the project showing occupant loading, occupancy classifications and construction type, egress travel distances, exit capacities, areas with sprinkler protection, fire extinguisher locations, ratings of fire-resistive assemblies, and other data necessary to exhibit compliance with life safety code requirements.

(3) Sprinkler System

Provide complete wet pipe sprinkler protection for Company Operations Facilities, including both Administrative Modules and Readiness Modules, designed in accordance with UFC 3-600-01 and NFPA 13. The Covered Hardstand, if not separated by adequate distance per the IBC, Table 602, shall be considered to be part of the COF facility and shall require sprinkler protection. The sprinkler system design shall be in accordance with UFC 3-600-01 and NFPA 13. The sprinkler hazard classifications shall be in accordance with UFC 3-600-01, NFPA 13, and other applicable criteria. Design densities, design areas and exterior hose streams shall be in accordance with UFC 3-600-01. The sprinkler systems shall be designed and all piping sized with computer generated hydraulic calculations. The exterior hose stream demand shall be included in the hydraulic calculations. A complete sprinkler system design, including sprinklers, branch lines, floor mains and risers, shall be shown on the drawings. The sprinkler system plans shall include node and pipe identification used in the hydraulic calculations. See paragraph 7.4 for discharge requirements for sprinkler system drains, including main drains, test drains, and auxiliary drains.

(a) Sprinkler Service Main and Riser

The sprinkler service main shall be a dedicated line from the distribution main. Sprinkler service and domestic service shall not be combined. The sprinkler service main shall be provided with an exterior post indicator valve with tamper switch reporting to the fire alarm control panel (FACP). The ground floor entry penetration shall be sleeved per NFPA 13 requirements for seismic protection. The sprinkler entry riser shall include a double check backflow preventer, a fire department connection, and a wall hydrant for testing of backflow preventer. The sprinkler system shall include an indicating control valve for each sprinkler system riser, a flow switch reporting to the FACP, and an exterior alarm bell.

All control valves shall be OS&Y gate type and shall be provided with tamper switches connected to the FACP.

Facilities with multiple floors shall be provided with floor control valves for each floor. The floor control valve assembly shall be in accordance with UFC 3-600-01, Figure 4-1.

(b) Exterior Hose Stream

Exterior hose stream demand shall be in accordance with UFC 3-600-0 1. Exterior hose stream demand shall be included in the sprinkler system hydraulic calculations.

(c) Backflow Preventer

A double check backflow preventer shall be provided on the fire water main serving each building. This shall be located within the building. An exterior wall hydrant with dual hose connections with OS&Y valve shall be provided to allow testing of backflow preventer at design flow as required by NFPA 13.

(d) Fire Department Connection

Section 01 10 00

A fire department connection shall be provided for each building with sprinkler protection. These shall be located to be directly accessible to the fire department.

(4) System Components and Hardware

Materials for the sprinkler system, fire pump system, and hose standpipe system shall be in accordance with NFPA 13 and NFPA 20.

(5) Protection of Piping Against Earthquake Damage

Sprinkler and fire pump piping systems shall be protected against damage from earthquakes. Seismic protection shall include flexible and rigid couplings, sway bracing, seismic separation assemblies where piping crosses building seismic separation joints, and other features as required by NFPA 13 for protection of piping against damage from earthquakes.

(6) Fire Detection and Alarm

Refer to Paragraph 3-1.3.7, Electrical and Communication Systems, for requirements.

(7) Building Construction

Construction shall comply with requirements of UFC 3-600-01, the International Building Code and NFPA 101.

(a) Fire Extinguisher Cabinets and Brackets

Fire Extinguisher cabinets and brackets shall be provided when fire extinguishers are req uired by UFC 3-600-01 and NFPA 101. Placement of cabinets and brackets shall be in accordance with NFPA 10. Semi-recessed cabinets shall be provided in finished areas and brackets shall be provided in non-finished areas (such as utility rooms, storage rooms, shops, and vehicle bays). Provide fire extinguisher cabinets and brackets as required however, fire extinguishers are Not in Contract (NIC)

(b) Interior Wall and Ceiling Finishes

Interior wall and ceiling finishes and movable partitions shall conform to the requirements of UFC 3-600-01 and NFPA 101.

3-1.3.4 Thermal Performance

See Paragraph 16.0

3-1.3.5 Plumbing

(1) Exterior Wall Hydrants In addition to wall hydrants provided around perimeter of building(s), one additional exterior wall hydrant or wall faucet per company shall be provided at the hardstand.

(2) Domestic Hot Water System

The main water heating equipment shall be located within a mechanical room, and also located on the ground floor level only. Instantaneous water heaters are not allowed to be used for hot water serving all COF areas except Readiness Area.

System storage and recovery shall be sized to deliver sufficient capacity at the showers to meet paragraph 3-1.2.3(8) requirements. Usage diversity factor for the showers shall be one. Minimum system total storage of water heater(s) shall be 400 gallons for 1- and 2-company COFs, and 600 gallons for 3-company and larger COFs.

3-1.3.6 Heating, Ventilating, and Air Conditioning

(1) Administrative Areas

The admin building’s HVAC system design should include flexibility in zoning to where it can address future changes in occupant densities (e.g., a platoon office suite converted to a conference room). Administrative areas shall be temperature-controlled by the DDC system. Temperature setpoint adjustment shall be accomplished via DDC System by authorized personnel.

(a) Communications and SIPRNet rooms will each be served by an independent and ded icated air-handling system.

Air handling unit system(s) shall not be floor-space mounted within the actual space served. Rooms shall be maintained at 72 degrees F and 50 percent relative hu midity year-round. Assum e 1 775 B TU per hour for the equipment heat dissipation. Contractor shall verify this load during the design stage.

(2) Readiness Areas

The readiness module shall be mechanically ventilated. The ventilation unit serving the readiness area shall be capable of providing outside air quantities, in accordance with ASHRAE 62.1, for the design people load of the readiness area.

Independent and dedicated packaged A/C units shall be provided for the Arms Vaults and Non-Sensitive Secure Storage Areas. Ventilation for Arms Vaults shall be provided in accordance with ASHRAE 62.1 requirements for storage rooms.

Communication rooms located in Readiness Building will be served by an independent and dedicated air-handling system and shall be conditioned in accordance with I3A.

(3) HVAC Controls

See paragraph 15 for HVAC Controls for minimum control system points schedules. These schedules identify as a minimum points to be monitored and controlled by the building automation system (BAS). The points schedule drawings convey a great deal of information critical to the design, installation, and subsequent performance of the control system. It includes hardware input/output information, device ranges and settings, ANSI 709.1 communication protocol data, and information about data that is to be used at the operator workstation by the Monitoring and Control software. These schedules are available as an excel spread sheet and as AutoCAD drawings on the Engineering Knowledge Online (EKO) website https://eko.usace.army.mil/fa/bas/. Point schedule of system types not addressed in the EKO shall be developed by the Contractor, and shall be sufficiently detailed to a level consistent to a similar listed system in EKO. It is recommended that all of the guidance and instruction documents be reviewed prior to using any of the info, as the documents provide necessary and critical information to the use of the website drawings and other information.

3-1.3.7 Electrical and Communications

Section 01 10 00

See Paragraphs 20 and 21 for clarifications and additional requirements for the electrical and communication systems.

(1) Interior Electrical and Communications

(a) Electrical

1. Characteristics. Select electrical characteristics of the power system to provide a safe, efficient, and economical distribution of power, based u pon the size and types of loads to be served. Use distribution and utilization voltages of the highest level that is practical for the load to be served.

2. Nonlinear Loads. The effect of nonlinear loads such as computers and other electronic devices shall be considered and accommodated as necessary. These loads generate harmonics, which can overload conventionally sized conductors or equipment and thereby cause safety hazards and premature failures. Circuits serving such devices shall be equipped with a separate neutral conductor not shared with other circuits. Panelboards and any dry type transformers shall be rated accordingly.

3. Lightning Protection System and Transient Voltage Surge Protection. Design shall be in accordance with NFPA 780 and other referenced criteria. Provide transient voltage surge protection.

4. Receptacles. Power receptacles shall be provided per NFPA 70 and in conjunction with the proposed equipment and furniture layouts. Provide power connectivity to each workstation. Power poles shall not be used. Provide duplex receptacles adjacent to each duplex (voice/data) outlet and CATV outlet.

(b) Lighting. Lighting and l ighting controls shall comply with the recommendations of the Illumination Engineering Society of North America (IESNA) and the requirements of ASHRAE 90.1.

1. Interior Lighting. Interior ambient illumination shall provide a generally glare free, high quality lighting environment and conform to IESNA RP-1-04.

2. Interior Lighting Controls. Local manual controls shall supplement automatic controls in offices and specialized areas such as conference rooms. Occupancy sensor controls shall be provided in restrooms, electrical rooms, telecommunications rooms and similar spaces. Interior ambient illumination shall provide a generally glare free, high quality lighting environment and conform to IESNA RP-1-04. Lighting fixtures with dimming ballasts capable of dimming to 5 percent shall be provided in conference rooms.

(c) Telecommunication

1. Telecommunications Rooms. Telecommunications Rooms shall be provided for voice and data. There shall be a minimum of one room on each floor, located as near t he center of the building as practicable, and s tacked between floors. The telecommunications rooms shall be designed in accordance with the I3A Guide and ANSI/EIA/TIA-569- B. Where copper cable runs exceed 295 feet, provide additional telecommunication rooms as required.

2. Telecommunications Outlets. Telecommunications outlets shall be provided per the I3A technical guide based on functional purpose of the various spaces with the facility as modified by user special operational requirements. All COF workstations shall have voice and data connection capability. All conference rooms shall have voice and data connection capability (minimum two outlets). A wall telephone outlet with a single jack shall be provided in each mechanical room, electrical room, arms vault and communications room. Provide a duplex (voice/data) outlet in each of the Storage Rooms in the Readiness Module. Treat the COF Readiness Module open area as I3A “other” space providing a minimum of one dual outlet per 500 SF of gross building space. Telecommunications infrastructure shall meet the Installation Information Infrastructure Architecture (I3A) Guide and ANSI/TIA/EIA requirements.

3. Cable Trays. Provide cable tray pathways through-out the facility (Admin and Readiness Modules) to support the systems required for the construction of the facility as well as user 's computer net works, video integration system, telecommunication systems and other specialized electronic systems.

4. For Detached Readiness Modules, provide a separate communication room where possible, if space is not available for a separate communication room then the incoming telephone services (fiber and copper) shall be terminated in accordance with I3A Figure B-5 in an appropriate secure area or a lockable cabinet.

(d) SIPRNET

1. The SIPRNET room and infrastructure shall be designed and constructed in accordance with the “Building SIPRNET Communication Room - New Construction Guidance”, paragraph of the Technical Guide for the Integration of SIPRNET (Secret Internet Protocol Router Network). The SIPRNET building infrastructure design and installation shall be coordinated with the local DOIM and Physical Security Office.

2. In t he NSTISSI 7003 and the Techni cal Guide for Integration of SIPR NET, paragraph “ Protective Distribution System”, the word "shall" shall be substituted for the word "should" or “will” in this paragraph.

3. Install one SIPRNET outlet with one drop in each Company Commander's office. Install one SIPRNET outlets with four drops in each unit conference room. The SIPRNET building infrastructure shall use Category 6 UTP copper cables with red cable jacket and red outlet modules. Cables shall be terminated in the SPIRNET room and at the outlet in accordance with the I3A Technical Guide for data cables. Where copper cable runs exceed 295 feet, see guidance in paragraph “Building SIPRNET Communication Room - New Construction Guidance”.

4. The surface mounted raceway shall be used instead of the surface mounted conduit unless otherwise indicated by the local Network Enterprise Center (NEC) or Physical Security Office.

(e) Cable Television. CATV shall be provided in all private offices, conference rooms (minimum two outlets), and one in each of the readiness areas. The cable television system shall consist of cabling, pathways, and outlets. All building CATV systems shall conform to APPLICABLE CRITERIA to include I3A Technical Guide and the UFC 3- 580-01 Telecommunications Bldg Cabling Systems Planning/Design. For Detached Readiness Modules, the incoming CATV service shall be terminated in a 24”x24”x12” wall mounted enclosure with a dedicated NEMA 5-20 receptacle.

Section 01 10 00

Interior building cable television (CATV) cables in raceways shall terminate in this enclosure.

(f) Audio/Visual Systems. Provisions (consisting of a power receptacle and conduit for signal wiring) for a Government furnished Government-installed projector shall be provided in each conference room.

(g) Intrusion Detection System. Contractor shall install the necessary conduit, electrical power, and wiring, to support installation of an ICIDS system in each of the Arms Room and SIPRNet Room. The Government shall install the signal devices and equipment necessary to activate the system.

(h) Mass Notification System. A mass notification system consisting of speakers, strobes, cabling, pathways, activator stations, and a main console/amplifier utilizing a telephone and wireless input for local facility wide instruction shall be provided to provide coverage throughout each facility and throughout the complex as req uired by UFC 4-010-01.