Amendment AM-0006

View the file

Other files

File Type Posted
10r3-am5.pdf PDF
10r3-am4.pdf PDF
10r3-am3.pdf PDF
10r3-am2.pdf PDF
10r3-am1.pdf PDF
SOW PDF - 2010-06-18.pdf PDF
RFP 6.pdf PDF
Appendix A 100 Geotech Rpt SB 8-2-09.pdf PDF
RFP 5.pdf PDF
Final SCR PN 69308 - SR GTF Infrastructure.pdf PDF
Final SCR PN 68822 - SR EOD Unit.pdf PDF
RFP 4.pdf PDF
RFP 1.pdf PDF
Final SR Field Characterization Rpt.pdf PDF
10r3-23jun10.pdf PDF
RFP 3.pdf PDF
APPENDIX J Dwgs-Sol File-6-23-10.pdf PDF
Final SCR PN 68786 - SR EG Unit.pdf PDF
RFP 2.pdf PDF
Final SCR PN 68821 - SR MP Unit.pdf PDF
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. CONTRACT ID CODE PAGE OF PAGES

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1 2

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

AM-0006 30 Jul 10

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

Contracting Division USAED, Honolulu, Bldg 230 Ft Shafter, HI 96858-5440

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and Zip Code) (x) 9A. AMENDMENT OF SOLICITATION NO.

W9128A-10-R-0003 X

9B. DATED (SEE ITEM 11)

6/23/10

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

[ X ]The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers [ ] is extended, [ X ] is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning __1__ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor [ ] is not, [ ] is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

FY09 Grow The Army Projects: PN 69308, PN 68786, PN 68821, PN 68822, South Range, Schofield Barracks, Oahu, Hawaii

See Page 2 of 2 Pages

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY

(Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITION UNUSABLE

30-105 STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

RFP No. W9128A-10-R-0003 Standard Form 30 Amendment No. AM-0006 Page 2 of 2 Pages Item No. 14 (Continued)

CHANGES TO THE SOLICITATION. Attached hereto are new pages to the solicitation. The revision marked “(AM-0006)” is shown on each page.

1. DELETED PAGES: None

2. REVISED PAGES: None

3. NEW PAGE: Following is the new page to the solicitation:

Section 00900 – page 00900-7

4. The proposal due date of August 5, 2010, 2:00 P.M., Hawaiian Standard Time, remains unchanged.

RFP No. W9128A-10-R-0003

SECTION 00900

Questions and Answers Grow The Army Projects

Q # Question Answer

Please verify the past performance evaluations do NOT count toward the 5 page limit for Factor 1, Experience. See AM-0005, Section 00 22 10, para 4.1.2.

Section 00 22 10-5 (AM-0003), para. 4.2.2, Relevant Contract Definition table, Size column states, “Construction or Design-build contract approximately $100 million or larger”. Will a DB Single Award Task Order Contract (SATOC) with three phased TOs equaling $133.5 M be evaluated as “$100M or larger”?

Task Order Contracts, Delivery Order Contracts, Multiple Award Task Order Contracts (MATOCs), Job Order Contracts, Indefinite Delivery – Indefinite Quantity Contracts, and Multi-Trade Contracts will not be considered a relevant contract. However, a single task or delivery order under any of these types of contracts will be considered equivalent to a relevant contract provided that task or delivery order meets the requirements for a relevant contract as set forth in paragraph 4.2.2.

Are topographic and LIDAR surveys available for the Offeror to take a look at? If so, when will it be available to download?

Topographic surveys will be available during Phase 2. There are no LIDAR surveys.

AM-0006

00900-7