RFI 01 QA 20210822 - W9127Q-21-B-0001 Small Arms Range .pdf

PDF 86 KB Posted

Attached to
Small Arms Range #LRXQ159097
Solicitation number
W9127Q-21-B-0001
Issued by

About this file

This document contains a request for information and federal contract opportunity for the construction of a Small Arms Range facility. The project includes construction of an indoor small arms range building, site development, foundations, structural framing, interior and exterior finishes, and all related HVAC, electrical, plumbing and fire protection systems. The pre-bid conference will be held on August 12, 2021 with the bid due date of September 9, 2021. The period of performance is 365 calendar days from notice to proceed. The contract is set aside for small businesses with a NAICS code of 236220 and size standard of $39.5 million. The magnitude of the project is estimated between $5-10 million. The solicitation and plans are available through the System for Award Management website.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W9127Q-21-B-0001 Small Arms Range, #LRXQ159097

REQUEST FOR INFORMATION (RFI) #1

13 August 2021

1. Question regarding E-sheets and division 26 of the specifications.. See Amendment #01 to replace E.6 with E0.6-R1:

Question A: What size kVA cable is needed?

Answer: (3) 2 AWG AL, 15KV, 133% EPR, Type MV-105. Refer to details on revised sheet E0.6.

Question B: There is not a detail showing the pole hardware at the new dip pole. Please advise.

Answer: Refer to details on revised sheet E0.6.

Question C: Will 6” be needed on the bore for the primary, or will 4” be sufficient?

Answer: 4” is sufficient. Refer to details on revised sheet E0.6.

Question D: Do you want a spare conduit bored out to the pole?

Answer D: NO

2. Question: The small arms range equipment is specified in Section 11 67 23 of the specifications. Most suppliers advised that delivery in 90 to 120 calendar days with significant time required for installation and system testing. A period of performance of 365 calendar days is insufficient. We request the period of performance be increased to a minimum of 15 months or 450 days.

Answer 2: We are aware of the volatility of the construction market and related lead times.

We believe even with a 90-day delivery, the period of performance of 365 calendar days shall remain during the bid process.

REMINDER:

1. Proposal Due Date – Thursday, September 09, 2021 @ 1:00 PM (CST)