This document provides details on heating and cooling equipment across multiple facilities as well as information on an upcoming federal contract opportunity for installation support services. The equipment list specifies steam boilers and chilled water chillers by building number, including capacity in pounds per hour. Installation types are denoted as heating, cooling, or both. The federal contract opportunity is a pre-solicitation for non-personal services to provide maintenance, operations, supply, transportation, and administrative support to tenants located on Redstone Arsenal, Alabama. The requirement includes maintenance of equipment and facilities, operations and maintenance of utility systems, supply operations, and transportation. The contractor shall perform to standards in an attached performance work statement. Questions will only be accepted via email to the listed point of contact by the specified date.

View the file

Other files

File Type Posted
Tech Ex 15 - Builder Program Data 10 Sep 19_Reduced Size.pdf PDF
Tech Ex 47 - Installation Restoration Sites 10 Sep 19.pdf PDF
Tech Ex 55 - Hydrdants 11 Sep 19.pdf PDF
Tech Ex 03 - Real Property Assets 10 Sep 19.pdf PDF
Tech Ex 16 - Pavement-Drainage MaintenanceZoneMap 10 Sep 19.pdf PDF
Tech Ex 46 - Bridges-Culverts 10 Sep 19.pdf PDF
Tech Ex 07 - Phase-in Phase-Out Plan 10 Sep 19.pdf PDF
Tech Ex 04 - Wage Rate Requirements Shop 4 Oct 19.pdf PDF
Tech Ex 21 - Cranes and Hoists 10 Sep 19.pdf PDF
Tech Ex 14 - MDA-FBI Bldgs at CL1 10 Sep 19.pdf PDF
Tech Ex 28 - Giant Voice Location Map-Bldg Notification Systems List 10 Sep 19.pdf PDF
Tech Ex 49 - RSA SWEEPING SCHEDULE 4 Oct 19.pdf PDF
Tech Ex 23 - Fire Alarms Sprinklers Hood Suppression Systems 10 Sep 19.pdf PDF
Tech Ex 01 - Redstone Arsenal Area Map 10 Sep 19.pdf PDF
Tech Ex 51 - Winterizing List 10 Sep 19.pdf PDF
Tech Ex 05 - Form DD 254 10 Sep 19.pdf PDF
ISS Questions and Response_Rev 1_6 Apr 20.xlsx XLSX spreadsheet
Tech Ex 33 - Backflow Preventers 10 Sep 19.pdf PDF
Tech Ex 20 - Generator Testing Refusal Memo 10 Sep 19.pdf PDF
Tech Ex 27 - Air Compressors 10 Sep 19.pdf PDF
Tech Ex 53 - Playground Equipment 10 Sep 19.pdf PDF
Tech Ex 09 - RSA Historic Property List 10 Sep 19.pdf PDF
Tech Ex 06 - Gov Facilities Assigned to Contractor 10 Sep 19.pdf PDF
Tech Ex 43 - Boiler 10 Sep 19.pdf PDF
Tech Ex 26 - IMRE-PW (EIP Ref Recvry) Form 1 10 Sep 19.pdf PDF
Tech Ex 48 - General Notes-Individual Site Maps 10 Sep 19.pdf PDF
Tech Ex 30 - Points of Demarcation 10 Sep 19.pdf PDF
Tech Ex 19 - Generator List 10 Sep 19.pdf PDF
Tech Ex 45 - RSA Road Map with Boundaries 10 Sep 19.pdf PDF
Tech Ex 22 - Elevators 10 Sep 19.pdf PDF
Tech Ex 13 - Preventative Maintenance Task Sheet 10 Sep 19.pdf PDF
Tech Ex 29 - Utility Meter Count 10 Sep 19.pdf PDF
PWS November 13 2019 r4 6Apr20.docx DOCX document
Tech Ex 17 - Bldg Component Checklist 10 Sep 19.pdf PDF
Tech Ex 12 - PM Frequency Tables 10 Sep 19.pdf PDF
Tech Ex 35 - Sump Pumps 10 Sep 19.pdf PDF
Tech Ex 52 - Ice-Snow Plan 10 Sep 19.pdf PDF
Tech Ex 10 - Facilities with Niagra or JACE Controls 10 Sep 19.pdf PDF
Tech Ex 18 - Cooking Exhaust Systems List 10 Sep 19.pdf PDF
Tech Ex 54 - Retention Ponds 10 Sep 19.pdf PDF
Tech Ex 39 - RSA SCADA 3 Sept 19.pdf PDF
Tech Ex 50 - Gov Furnished Equipment List 10 Sep 19.pdf PDF
Tech Ex 08 - Supported Organizations 10 Sep 19.pdf PDF
Tech Ex 02 - Historical Workload Data 10 Sep 19.pdf PDF
Tech Ex 36 - Grease Pits-Oil-Water Separators 10 Sep 19.pdf PDF
Tech Ex 37 - Septic Tanks_Lift Stations 10 Sep 19.pdf PDF
Attachment 1 400 Engineering Services NS FY21 10Oct19 r3 25Mar20.docx DOCX document
PWS November 13 2019 r3 25Mar20.docx DOCX document
Attachment 3 411 Facility Maintenence Vertical NS FY21 10Oct19 r3 26Mar2....docx DOCX document
Attachment 6 505 Environmental Compliance Services NS FY21 10Oct19 r3 26....docx DOCX document
Show 40 more

Latest 50 of 59 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

This is a representative list of equipment as of date of publication and is subject to update as required

Bldg. Type (heating-H; cooling-C) Nomenclature/Capacity (LBS/HR) Comments

3775 H-Steam Boiler #1 / 3451

5494 H-Steam Boiler#1 / 2070

5540 H-Steam Boiler #1 / 5175

5661 H-Steam Boiler #1 / 1380 (layed up) Bldg. closed

7105 H-Steam Boiler #1 / 8625

H-Steam Boiler #2 / 8625

7153 H-Steam Boiler #1 / 6000

H-Steam Boiler #2 / 6000

7291 H-Steam Boiler #1 / 8625

H-Steam Boiler #2 / 2760

7668 H-Steam Boiler #1 / 20700

H-Steam Boiler #2 / 8625

H-Steam Boiler #3 / 8625

H-Steam Boiler #4 / 13800

7855 H-Steam Boiler #1 / 5175

H-Steam Boiler #2 / 5175

8028 H-Steam Boiler #1 / 2760

H-Steam Boiler #2 / 2760

8874 H-Steam Boiler #1 /2070

H-Steam Boiler #2 / 2020

8977 H-Steam Boiler #1 / 5175

H-Steam Boiler #2 / 3450

7549 H-Steam Boiler #1 / 2760

Technical Exhibit #42 Central Heating/Boiler Plants 10 Sep 19

H-Steam Boiler #2 / 1600

3316 C-Chilled Water Chiller#1 / 300 ton Centrifugal

C-Chilled Water Chiller #2 / 700 ton Centrifugal

C-Chilled Water Chiller #3 / 500 ton Centrifugal

Cont. Central Heating/Cooling Plants:

Bldg. Type (heating-H; cooling-C) Nomenclature/Capacity (LBS/HR) Comments

5306 H-Steam to Hot Water; C-chilled Water Chiller #1 /1400 Ton Centrifugal

Chiller #2 / 380 Ton Absorption

Chiller #3 / 380 Ton Absorption

Chiller #4 /800 Ton Absorption

Chiller #5 / 1050 Ton Absorption

5221 H-steam to Hot water; Gas to Hot

Water; C-Chilled Water Chiller #1 / 1050 Ton Centrifugal

Chiller #2 / 550 Ton Centrifugal

Chiller #3 / 550 Ton Centrifugal

Technical Exhibit #42 Central Heating/Boiler Plants 10 Sep 19