This document is a Cantonment Grounds Maintenance Labor Matrix template designed to track and allocate labor hours across various grounds maintenance tasks throughout a 12-month contract period. The matrix provides a monthly breakdown (January through December) for categorizing labor expenditures by task and labor category.

The template is structured in two primary sections: Indirect Work and Direct Work. Indirect Work includes Project Manager and Quality Control Chief positions, plus two additional undefined labor categories. Direct Work encompasses nine distinct maintenance tasks: One-Time Fence Line Clearing, Improved Grounds A/B/C, Semi-Improved Grounds, Unimproved Grounds, Pruning Shrubs, Pruning Crape Myrtles, and Herbicide Application to Railroad Rights-of-Way. Each direct work task includes three labor category line items to be populated. The matrix includes columns for each calendar month and a total hours column, with rows for calculating total hours per month and cumulative total hours for the 12-month period. The document serves as a planning and tracking tool for contractors to identify resource requirements, labor category assignments, and monthly hour distributions for grounds maintenance operations at a military cantonment.

View the file

Other files

File Type Posted
UPDATED 2.6 - Attachment 1 - Instruction to Offerors and Evaluation Criteria O ISRAEL 2-4-26 1.pdf PDF
UPDATED 2.6 - 8.13 Technical Exhibit (TE-13) Parker School Year Feb-26 V1 (1).pdf PDF
ANSWERED 2.6 Questions.pdf PDF
UPDATED 2.6 - Attachment 3 - PWS MODIFICATION 1 Feb-26 omi.pdf PDF
Attachment 3 - PWS same as Word Version.pdf PDF
TE 8.10 WORK CAPABILITY LEVELS August 2025.pdf PDF
TE 8.11 Gen loc of internal fencing and cable barriers Auugust 2025.pdf PDF
TE 8.3 TE - Area B REVISION 1 - 30September2025 1 (1).pdf PDF
Site Visit - OZARK_GATE_TO_BLDG_5700 1-14-26.jpg JPG image
TE 8.12 EXAMPLE PAYMENT CALCULATIONS WHEN RESD IS USED August 2025.pdf PDF
W9124G-25-R-A009 -Updated on 1.15.26 to close date only 2.11.26 (1).pdf PDF
SITE VISIT RegistrationForm.docx DOCX document
Attachment - 1 Instruction to Offerors and Evaluation Criteria UPDATE 1.14.26.docx DOCX document
Attachment 4 - SITE VISIT INFORMATION CANTONMENT ITINERARY - UPDATE 1.14.26.docx DOCX document
Attachment 3 - PWS.docx DOCX document
Technical Exhibit 8.8.pdf PDF
W9124G-25-R-A009.pdf PDF
Attachment 2 - Bid Schedule.xlsx XLSX spreadsheet
Attachment 4 - SITE VISIT INFORMATION CANTONMENT ITINERARY.docx DOCX document
Technical Exhibit 8.2.pdf PDF
TE 8.4 TE - Area C August 2025.pdf PDF
TE 8.1 PRS Table August 2025.pdf PDF
Technical Exhibit 8.3.pdf PDF
Attachment 1 - Instruction to Offerors and Evaluation Criteria.docx DOCX document
SCA Wage Determination 2015-4631.txt TXT text file
Technical Exhibit 8.9.pdf PDF
Technical Exhibit 8.7.pdf PDF
Technical Exhibit 8.6.pdf PDF
Attachment 5- Site Visit - Gate Map.jpg JPG image
Technical Exhibit 8.5.pdf PDF
Attachment 6- Past Performance Questionnaire.docx DOCX document
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CANTONMENT GROUNDS MAINTENANCE LABOR MATRIX

JAN

FEB

MAR

APR

MAY

JUN

JUL

AUG

SEP

OCT

NOV

DEC

Total Hours

Indirect Work (LC=Labor Category)

Project Manager

Quality Control Chief

LC:

Direct Work

1 ONE TIME FENCE LINE

CLEARING

LC:

1 IMPROVED

GROUNDS “A”

LC:

2 IMPROVED

GROUNDS “B”

LC:

3 IMPROVED

GROUNDS “C”

LC:

4 SEMI-IMPROVED

GROUNDS

LC:

5 UNIMPROVED

GROUNDS

LC:

7 PRUNING SHRUBS

8 PRUNING CRAPE

MYRTLES

LC:

9 HERBICIDE

APPLICATION TO

RR’s

LC:

Total Hours Per Month

Total Hours In 12-Months