W9123822R0003 Amendment 003.pdf

PDF 215 KB Posted

Attached to
North Apron Repairs Federal contract opportunity
Solicitation number
W9123822R0003
Issued by
Department of the Army Corps of Engineers Engineering District Sacramento

About this file

This document provides an amendment to a solicitation for repairs to the North Apron at Hill Air Force Base in Utah. The contractor shall perform improvements including replacement of existing Portland cement concrete slabs and full rework of structural base materials in accordance with UFC standards. Additional work includes providing grounding points, pavement markings, replacement of an adjacent concrete swale and asphalt pavement. Demolition includes removal of existing concrete slabs, drainage swale and asphalt. The projected value is between $5 million and $10 million. This will be a total small business set-aside conducted using PSC Code Z2LA and NAICS 238110. The pre-proposal site visit will take place on January 26, 2022 and proposals are due by the date specified in the solicitation.

View the file

Other files for this federal contract opportunity

Other files attached to North Apron Repairs, newest first.
File Type Posted
Amendment 0005 Sheet 180-25-0984C-121-C-121.pdf PDF
Amendment 0005 Updated 32 13 14.13 Concrete Paving.pdf PDF
Amendment 0005 Sheet 180-25-0984C-122-C-122.pdf PDF
Amendment 0005 Survey.pdf PDF
Amendment 0005 Sheet 180-25-0984G-101-G-101.pdf PDF
W912822R0003 Amendment 0005.pdf PDF
SF30 W9123822R0003 0004 North Apron Extend.pdf PDF
Attachment 9 PPQ.pdf PDF
W9123822R0003 Site Visit Sign_In_Sheet.pdf PDF
Attachment 6 North Apron Site Walk.pdf PDF
Attachment 3 Supplemental Contract Requirements.pdf PDF
Attachment 4 DBW Rates.pdf PDF
Attachment 1 Specifications.pdf PDF
Attachment 2 Drawings.pdf PDF
Attachment 7_Utah Resident Office Map.pdf PDF
Attachment 8 Project Information Form.pdf PDF
Attachment 5 Pre Award Survey.pdf PDF
W9123822R0003 North Apron Repairs Amendment 002.pdf PDF
Atch 7_Utah Resident Office Map.pdf PDF
North Apron Site Walk.pdf PDF
W9123822R0003 Amendment 001.pdf PDF
Blank - Site Visit Roster_ (002).xlsx XLSX spreadsheet
Attachment 2 Drawings.pdf PDF
Attachment 4 Pre Award Survey.pdf PDF
Attachment 3 Davis Bacon Wage Determination.pdf PDF
Attachment 1 Specifications.pdf PDF
W9123822R0003.pdf PDF
Show all 27

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04 EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of amendment three is to number the attachments, update section 00 22 00, update Table of Contents, update KO contact information and remove "Flight Test" verbiage not related to the solicitation.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 18-Jan-2022

16B. UNITED STATES OF AMERICA 15C. DATE SIGNED 15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer) (Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9123822R0003

X 9B. DATED (SEE ITEM 11)

20-Dec-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

18-Jan-2022

CODE

USACE SACRAMENTO DISTRICT

ATTN: CONTRACTING DIVISION

1325 J STREET

SACRAMENTO CA 95814-2922

W91238 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODE CODE

EMAIL: TEL:

1 x

W9123822R0003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 01 10 - TABLE OF CONTENTS

The following have been modified:

TABLE OF CONTENTS

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION DATE # of Pages

Attachment 01 Specifications June 2021 633

Attachment 02 Drawings June 2021 26

Attachment 03 Supplemental Contract Instructions 13 Jan 2022 1

Attachment 04 Davis Bacon Wage Determination 7 Jan 2022 4

Attachment 05 Pre-award Survey 20 Dec 2021 4

Attachment 06 North Apron Site Walk 05 Jan 2022 1

Attachment 07 Utah Residence Office Map 05 Jan 2022 1

Attachment 08 Project Information Form 13 Jan 2022 1

SECTION 00 10 00 - SOLICITATION

Changed to: Work will be performed at Hill Air Force Base to Repair North Apron near Building 1, Facility 5000, and adjacent shoulder (Facility 5129). Replace existing Portland cement concrete (PCC) slabs in the east half of section A17B with 20’ x 20’ maximum panel sizes, along with full rework of structural base materials to include addition of an aggregate base course with stabilized drainage layer and geotextile filter fabric, as required for seasonal frost conditions, all in accordance with current UFC standards. Replace existing shoulder asphalt pavement, along with rework of the shoulder base. Demolition includes removal of existing apron PCC slabs and asphalt shoulder.In accordance w ith FAR 36.204(g) the projected magnitude of this project is between $5,000,000 and $10,000,000.The proposed contract action will be conducted using PSC Code Z2LA - Repair or Alteration of Airport Service Roads and

NAICS code 238110 - Poured Concrete Foundation and Structure Contractors.This proposed contract action will proceed as a total Small Business set-aside. This solicitation corresponds with Sources Sought W9123822S0001 and Pre-Solicitation notice W9123822R0003..

SECTION 00 21 00 - INSTRUCTIONS

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government

Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from

U.S. Army Corps of Engineers, Sacrament District

ATTN: Construction Contracting Officer, John Wysocki, Room 878

1325 J Street

Sacramento, CA 95814

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of provision)

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for--

When: Wednesday, 26 Jan 2022

Time: 0900 – 1200 MDT

Where: Hill AFB, Utah

(Show up at South Gate at least 30 minutes prior to ensure ability to get on base)

(c) Participants will meet at--

SEE ATTACHMENTS 7 & 8 FOR INSTRUCTIONS TO ATTEND ON BASE.

Please provide the information per the site visit instructions via email

Mr. Dan Ross, daniel.j.ross@usace.army.mil

Cc:

Ms. Deanna Zemovich, deanna.c.zemovich@usace.army.mil

Mr. John Wysocki, john.wysocki@usace.army.mil

Mr. Harold Teague, harold.e.teague@usace.army.mil

(End of provision)

SECTION 00 22 00 - SUPPLEMENTARY INSTRUCTIONS

mailto:daniel.j.ross@usace.army.mil mailto:john.wysocki@usace.army.mil mailto:harold.e.teague@usace.army.mil

5.2.1 FACTOR ONE – EXPERIENCE AND CAPABILITY

Offerors shall submit at least two (2) example projects, but no more than four (4) for the proposed “relevant” projects demonstrating that the prime and subcontractor(s) demonstrate recent and relevant experience and capability to successfully perform work similar in size, scope, and complexity to the project described in this solicitation.

For this factor, projects considered “relevant” must meet all of the following criteria:

(a) Experience as a prime contractor on a project of similar size and scope.

(b) Example project includes airfield paving on or near an active flight line.

(c) Experience designing a project of similar size and scope -Removed

(d) Experience Valued at $5M or greater

(e) Completed within the last 5 years

Projects considered “recent” must have been completed and turned over within the 5 years preceding the date of this solicitation to the time that proposals are due. Do not submit construction projects that are not either complete or substantially complete. For this purpose, “substantially complete” means that only punch list items remain for project acceptance or that the 95% of the elements of the project have been turned over to the customer for beneficial occupancy.

If an Offeror presents a project that is less than 95% complete, the proposal must include an explanation why that project should be considered substantially complete.

Complete the Attachment – Contractor’s Project Experience Form for example projects in Factor 1.

If the offeror represents the combining of two or more companies, state if the example project represents a joint venture of the listed parties.

Please number your project submissions and include a matrix similar to the one below for purposes of matching your submissions to their applicable experience areas:

Evaluation Areas Project #1 Project #2

Prime Contractor /

Sub-Contractor

Airfield Paving on or near an active flight line

Designed Project requiring

Airfield Paving on or near an active flight line

Project valued at $5M or greater

Completed within the last 5 years

Offerors shall provide all of the information requested herein and complete the form Attachment-

Contractor’s Project Experience for each project submitted for Relevant Experience Subcontractor(s).

A Letter of Commitment and Authorization from the appropriate subcontractor(s) shall be provided in the proposal. This letter states the business concern’s intent to work on this project in the proposed specified capacity if the offeror is awarded the contract.

Where performance of a base contract and one or more options is relied upon by an offeror to meet any criterion under this Factor, the same base contract and contract option(s) will be evaluated for purposes of the remaining criteria for Relevant Experience (and Past Performance).

The narrative is limited to ten (10) 8-1/2” x 11” pages.

EVALUATION CRITERIA:

If any of the above requirements are not met in Factor 1 above, Factor 1 will be given a rating of ‘Unacceptable’.

See Table 1- Technical Acceptable/Unacceptable Ratings in Section 2.5.

(End of Summary of Changes)