R0023 Non-ARRA Task Order Supplemental Contract Requirements.pdf

PDF 13 KB Posted

Attached to
Multiple Award IDIQ Contract to Repair Military Family Housing at Beale AFB, CA
Solicitation number
W91238-10-R-0023
Issued by

About this file

Non-ARRA Task Order Supplemental Contract Requirements

View the file

Other files

Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W91238-10-R-0023 1 of 1 Non-ARRA Supplemental Contract Requirements July 9, 2010

NON-ARRA SUPPLEMENTAL CONTRACT REQUIREMENTS

1. Performance Period. Refer to contract section 00700, FAR 52.211-10. The performance period for the work stated is 730 days or less.

2. Liquidated Damages. Refer to contract section 00700, FAR 52.211-12, Liquidated Damages-Construction. Liquidated damages for this work is $1,555.00 for each day of delay.

3. Authorities. No person other than the Government Contracting Officer/Administrative Contracting Officer has the authority to make any changes to this contract action that impact cost or schedule. Authority from the Contracting Officer/Administrative Contracting Officer to the contractor to make changes that impact cost or schedule will be in the form of an official, signed modification.

4. Wage Determination. General Decision No. CA100009 dated 07/09/2010, or its most current modification at the time of award is hereby applicable to work performed under this task order. The most current decision or its modification can be found at http://www.wdol.gov/dba http://www.wdol.gov/dba�

NON-ARRA SUPPLEMENTAL CONTRACT REQUIREMENTS

File details come from the government source that posted it. Updated .