W91238-10-R-0023 Amd 0001 ARRA Task Order Pricing Schedule
CONTRACTOR SHALL FURNISH ALL LABOR, MATERIAL, EQUIPMENT, ETC. NECESSARY TO
PERFORM ALL WORK IN STRICT ACCORDANCE WITH THE TERMS AND CONDITIONS SET FORTH
IN THE CONTRACT TO INCLUDE ALL ATTACHMENTS THERETO.
LINE ITEM UNIT OF UNIT TOTAL
NO. DESCRIPTION QUANTITY MEASURE PRICE PRICE
0001 64 Military Family Homes 1 LUMP SUM $_________
See below Pricing Schedule Breakout for specific work items to be included in the price, Items 0000-0140. All work to be performed according to the attached Plans and Specifications.
(ARRA Funded)
Pricing Schedule Breakout:
0000 – Mobilization & Demobilization 1 Lump Sum $__________
This line item includes all mobilization and demobilization costs. The Contractor will be required to complete 10 housing units prior to starting additional units. This line item will also include any and all costs associated with this phasing.
0100 – Asbestos and Lead Testing 1 Lump Sum $__________
This line item includes all testing for the presence of asbestos and lead for all 64 houses. The testing shall be performed in accordance with all local, state and federal laws and regulations.
0101 – Mold Removal _____ per House for 64 Houses = __________Total
This line item is for treatment and removal of all areas that have been identified and/or are suspected of having mold and/or mold growth in the listed houses. The costs include the demolition and replacement of sheetrock/gypsum up to 330 sf per house.
0102 – Additional Mold Removal ______ per sf up to 32,000 square feet = __________Total
This line item is for treatment and removal of all areas that have been identified and/or are suspected of having mold and/or mold growth in the listed houses. The costs include the demolition and replacement of sheetrock/gypsum in these houses for quantities greater than 330 sf per house.
0103 – Window Replacement Housing Unit Type A ______ per house for 32 Houses
This line item is for the replacement of all 12 existing vinyl framed windows with new vinyl framed windows in the houses listed. The costs include the demolition and replacement of sheetrock/gypsum on the interior and stucco on the exterior in a 1 foot perimeter around each window.
0104 – Window Replacement Housing Unit Type B ______ per house for 23 22 Houses
This line item is for the replacement of all 14 existing vinyl framed windows with new vinyl sheetrock/gypsum on the interior and stucco on the exterior in a 1 foot perimeter around each window.
0105 – Window Replacement Housing Unit Type C ______ per house for 4 Houses
This line item is for the replacement of all 12 existing vinyl framed windows with new vinyl sheetrock/gypsum on the interior and stucco on the exterior in a 1 foot perimeter around each window.
0106 – Window Replacement Housing Unit Type D ______ per house for 5 6 Houses
This line item is for the replacement of all 13 existing vinyl framed windows with new vinyl sheetrock/gypsum on the interior and stucco on the exterior in a 1 foot perimeter around each window.
0107 – Window Replacement Housing Unit Type E ______ per house for 0 Houses
This line item is for the replacement of all 13 existing vinyl framed windows with new vinyl sheetrock/gypsum on the interior and stucco on the exterior in a 1 foot perimeter around each window.
0108 – Flooring Replacement Housing Unit Type A ______ per house for 32 Houses
This line item is for the demolition of all existing VCT flooring in the houses listed. The cost includes furnish and install of new ceramic tile flooring in the kitchen and laundry room; and new laminated flooring in the entry, hallways, bedrooms, dining area, and living room.
This line item also includes the demolition of all existing baseboards, and installation of new baseboards in all of the rooms, excluding bathrooms.
0109– Flooring Replacement Housing Unit Type B ______ per house for 23 22 Houses
This line item is for the demolition of all existing VCT flooring in the houses listed. The cost includes furnish and install of new ceramic tile flooring in the kitchen and laundry room; and new laminated flooring in the entry, hallways, bedrooms, dining area, and living room.
0110– Flooring Replacement Housing Unit Type C ______ per house for 4 Houses
This line item is for the demolition of all existing VCT flooring in the houses listed. The cost includes furnish and install of new ceramic tile flooring in the kitchen and laundry room; and new laminated flooring in the entry, hallways, bedrooms, dining area, and living room.
0111– Flooring Replacement Housing Unit Type D ______ per house for 5 6 Houses
This line item is for the demolition of all existing VCT flooring in the houses listed. The cost includes furnish and install of new ceramic tile flooring in the kitchen and laundry room; and new laminated flooring in the entry, hallways, bedrooms, dining area, and living room.
0112– Flooring Replacement Housing Unit Type E ______ per house for 0 Houses
This line item is for the demolition of all existing VCT flooring in the houses listed. The cost includes furnish and install of new ceramic tile flooring in the kitchen and laundry room; and new laminated flooring in the entry, hallways, bedrooms, dining area, and living room.
0113 – Seal Existing Concrete Housing Unit Type A ______ per house for 32 Houses
This line item is for sealing of all interior concrete surfaces which are to receive flooring. The cost includes the sealant and its application.
0114 – Seal Existing Concrete Housing Unit Type B ______ per house for 23 22 Houses
0115– Seal Existing Concrete Housing Unit Type C ______ per house for 4 Houses
0116– Seal Existing Concrete Housing Unit Type D ______ per house for 5 6 Houses
0117– Seal Existing Concrete Housing Unit Type E ______ per house for 0 Houses
0118– Bathroom Remodel Housing Unit Type A ______ per house for 32 Houses
This line item is for the complete demolition of all existing bathroom infrastructure, including up to 50 square feet of dry rot, and replacement with new items, including ceramic tile flooring and baseboards. This includes all full and partial bathrooms in the house.
0119– Bathroom Remodel Housing Unit Type B ______ per house for 23 22 Houses
This line item is for the complete demolition of all existing bathroom infrastructure, including up
0120 – Bathroom Remodel Housing Unit Type C ______ per house for 4 Houses
This line item is for the complete demolition of all existing bathroom infrastructure, including up
0121 – Bathroom Remodel Housing Unit Type D ______ per house for 5 6 Houses
This line item is for the complete demolition of all existing bathroom infrastructure, including up
0122– Bathroom Remodel Housing Unit Type E ______ per house for 0 Houses
This line item is for the complete demolition of all existing bathroom infrastructure, including up
0123 – Additional Dry Rot ______ per sf up to 640 square feet = __________Total
This line item includes the removal of additional dry rot identified in any house, and installation of new wood as required. (Not to be used for the first 50 sf of dry rot encountered in bathrooms.)
0124 – Interior Painting Housing Unit Type A ______ per house for 32 Houses = __________Total
This line item includes the preparation and painting of all interior sheetrock/gypsum walls and ceiling surfaces and all doors.
0125 – Interior Painting Housing Unit Type B ______ per house for 23 22 Houses ceiling surfaces and all doors.
0126 – Interior Painting Housing Unit Type C ______ per house for 4 Houses = __________Total ceiling surfaces, and all doors.
0127 – Interior Painting Housing Unit Type D ______ per house for 5 6 Houses = __________Total
0128 – Interior Painting Housing Unit Type E ______ per house for 0 Houses = __________Total
0129– Exterior Painting Housing Unit Type A ______ per house for 32 Houses = __________Total
This line item includes the preparation and painting of all exterior stucco, wood trim and doors.
0130– Exterior Painting Housing Unit Type B ______ per house for 23 22 Houses
0131– Exterior Painting Housing Unit Type C ______ per house for 4 Houses
0132– Exterior Painting Housing Unit Type D ______ per house for 5 6 Houses
0133– Exterior Painting Housing Unit Type E ______ per house for 0 Houses
0134– Exterior Doors Housing Units Type A, B & C ______ per house for 59 58 Houses
This line item is for the removal and replacement of 5 exterior doors and frames per house for the hot water heater closet, furnace room, exterior bulk storage rooms, and exterior garage personnel door.
0135– Exterior Doors Housing Units Type D & E ______ per house for 5 6 Houses
This line item is for the removal and replacement of 6 exterior doors and frames per house for the hot water heater closet, furnace room, exterior bulk storage rooms, and exterior garage personnel door.
0136 – Splash Blocks ______ per splash block for 536 Splash Blocks = __________Total
This line item is for new concrete splash blocks to be placed at the bottom of each and every downspout.
0137 – French Drain ______ per lf for 1,920 2,350 Lineal feet = __________Total
This line item is for the complete installation of French Drains to be installed around the houses per drawings 1 & 2.
0138 – Remove Sod, Add Rock Housing Units Type A, B & C ______ per house for 59 58 Houses
This line item is for removal of sod for a distance of 4 feet from each house. Also includes the installation of the weed block fabric and decorative rock.
0139 – Remove Sod, Add Rock Housing Units Type D & E ______ per house for 5 6 Houses
This line item is for removal of sod for a distance of 4 feet from each house. Also includes the installation of the weed block fabric and decorative rock.
0140 – HVAC ______ per house for 64 Houses = __________Total
This line item includes clean the existing plenum, apply sealant, and replace the drip pan.