BATTALION COMPLEX PH 3 720ACPH3
RTA SUBMITTAL
SECTION 05 12 00
STRUCTURAL STEEL
05/14
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)
AISC 303 (2016) Code of Standard Practice for Steel Buildings and Bridges
AISC 325 (2011) Steel Construction Manual
AISC 326 (2009) Detailing for Steel Construction
AISC 341 (2016) Seismic Provisions for Structural Steel Buildings
AISC 360 (2016) Specification for Structural Steel Buildings
AISC DESIGN GUIDE 10 (1997) Erection Bracing of Low-Rise Structural Steel Buildings
AMERICAN WELDING SOCIETY (AWS)
AWS A2.4 (2012) Standard Symbols for Welding, Brazing and Nondestructive Examination
AWS D1.1/D1.1M (2015; Errata 1 2015; Errata 2 2016) Structural Welding Code - Steel
ASME INTERNATIONAL (ASME)
ASME B46.1 (2009) Surface Texture, Surface Roughness, Waviness and Lay
ASTM INTERNATIONAL (ASTM)
ASTM A29/A29M (2016) Standard Specification for General Requirements for Steel Bars, Carbon and Alloy, Hot-Wrought
ASTM A307 (2014; E 2017) Standard Specification for Carbon Steel Bolts, Studs, and Threaded Rod 60 000 PSI Tensile Strength
ASTM A325 (2014) Standard Specification for Structural Bolts, Steel, Heat Treated, 120/105 ksi Minimum Tensile Strength
SECTION 05 12 00 Page 1
ASTM A36/A36M (2014) Standard Specification for Carbon Structural Steel
ASTM A490 (2014a) Standard Specification for Structural Bolts, Alloy Steel, Heat Treated, 150 ksi Minimum Tensile Strength
ASTM A500/A500M (2013) Standard Specification for Cold-Formed Welded and Seamless Carbon Steel Structural Tubing in Rounds and Shapes
ASTM A53/A53M (2012) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
ASTM A563 (2015) Standard Specification for Carbon and Alloy Steel Nuts
ASTM A563M (2007; R 2013) Standard Specification for Carbon and Alloy Steel Nuts (Metric)
ASTM A6/A6M (2017) Standard Specification for General Requirements for Rolled Structural Steel Bars, Plates, Shapes, and Sheet Piling
ASTM A992/A992M (2011) Standard Specification for Structural Steel Shapes
ASTM F1554 (2015; E 2016; E 2017) Standard Specification for Anchor Bolts, Steel, 36, 55, and 105-ksi Yield Strength
ASTM F436 (2011) Hardened Steel Washers
ASTM F844 (2007a; R 2013) Washers, Steel, Plain (Flat), Unhardened for General Use
SOCIETY FOR PROTECTIVE COATINGS (SSPC)
SSPC PA 1 (2016) Shop, Field, and Maintenance Coating of Metals
SSPC Paint 20 (2002; E 2004) Zinc-Rich Primers (Type I, Inorganic, and Type II, Organic)
SSPC Paint 29 (2002; E 2004) Zinc Dust Sacrificial Primer, Performance-Based
SSPC SP 3 (1982; E 2004) Power Tool Cleaning
SSPC SP 6/NACE No.3 (2007) Commercial Blast Cleaning
U.S. DEPARTMENT OF DEFENSE (DOD)
UFC 3-301-01 (2013; with Change 1) Structural Engineering
UFC 3-310-04 (2013) Seismic Design for Buildings
SECTION 05 12 00 Page 2
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Erection Drawings; G, DO
SD-02 Shop Drawings
Fabrication Drawings Including Description of Connections; G, DO
SD-03 Product Data
Shop Primer
Welding Electrodes and Rods
SD-06 Test Reports
Bolts, Nuts, and Washers
Weld Inspection Reports
Bolt Testing Reports
SD-07 Certificates
Steel
Bolts, Nuts, and Washers
AISC Fabrication Plant Quality Certification
AISC Erector Quality Certification
Welding Procedures and Qualifications
Welding Electrodes and Rods
1.3 AISC QUALITY CERTIFICATION
Work must be fabricated in an AISC Certified Fabrication Plant, Category BU.
Submit AISC fabrication plant quality certification.
Work must be erected by an AISC Certified Erector, Category CSE. Submit AISC erector quality certification.
SECTION 05 12 00 Page 3
1.4 QUALITY ASSURANCE
1.4.1 Preconstruction Submittals
1.4.1.1 Erection Drawings
Submit for record purposes. Indicate the sequence of erection, temporary shoring and bracing. The erection drawings must conform to AISC 303 .
Erection drawings must be reviewed, stamped and sealed by a registered professional engineer.
1.4.2 Fabrication Drawing Requirements
Submit fabrication drawings for approval prior to fabrication. Prepare in accordance with AISC 326 and AISC 325 . Fabrication drawings must not be reproductions of contract drawings. Include complete information for the fabrication and erection of the structure's components, including the location, type, and size of bolts, welds, member sizes and lengths, connection details, blocks, copes, and cuts. Use AWS A2.4 standard welding symbols. Shoring and temporary bracing must be designed and sealed by a registered professional engineer and submitted for record purposes, with calculations, as part of the drawings. Any deviations from the details shown on the contract drawings must be clearly highlighted on the fabrication drawings. Explain the reasons for any deviations from the contract drawings.
1.4.3 Certifications
1.4.3.1 Welding Procedures and Qualifications
Prior to welding, submit certification for each welder stating the type of welding and positions qualified for, the code and procedure qualified under, date qualified, and the firm and individual certifying the qualification tests. If the qualification date of the welding operator is more than one-year old, the welding operator's qualification certificate must be accompanied by a current certificate by the welder attesting to the fact that he has been engaged in welding since the date of certification, with no break in welding service greater than 6 months.
Conform to all requirements specified in AWS D1.1/D1.1M .
PART 2 PRODUCTS
2.1 SYSTEM DESCRIPTION
Provide the structural steel system, including shop primer, complete and ready for use. Structural steel systems including design, materials, installation, workmanship, fabrication, assembly, erection, inspection, quality control, and testing must be provided in accordance with AISC 360 , AISC 341 , UFC 3-301-01 and UFC 3-310-04 except as modified in this contract.
2.2 STEEL
2.2.1 Structural Steel
Wide flange and WT shapes, ASTM A992/A992M . Angles, Channels and Plates, ASTM A36/A36M.
SECTION 05 12 00 Page 4
2.2.2 Structural Steel Tubing
ASTM A500/A500M , Grade B.
2.2.3 Steel Pipe
ASTM A53/A53M, Type E or S, Grade B, weight class STD (Standard) unless otherwise noted.
2.3 BOLTS, NUTS, AND WASHERS
Submit the certified manufacturer's mill reports which clearly show the applicable ASTM mechanical and chemical requirements together with the actual test results for the supplied fasteners.
2.3.1 Common Grade Bolts
2.3.1.1 Bolts
ASTM A307, Grade A. The bolt heads and the nuts of the supplied fasteners must be marked with the manufacturer's identification mark, the strength grade and type specified by ASTM specifications.
2.3.1.2 Nuts
ASTM A563M, Grade A, heavy hex style.
2.3.1.3 Washers
ASTM F844.
2.3.2 High-Strength Bolts
2.3.2.1 Bolts
ASTM A325, Type 1 .
2.3.2.2 Nuts
ASTM A563, Grade and Style as specified in the applicable ASTM bolt standard.
2.3.2.3 Washers
ASTM F436, plain carbon steel.
2.3.3 Foundation Anchorage
2.3.3.1 Anchor Rods
ASTM F1554 Gr 36, Class 1A.
2.3.3.2 Anchor Nuts
ASTM A563, Grade A, hex style.
2.3.3.3 Anchor Washers
ASTM F844.
SECTION 05 12 00 Page 5
2.3.3.4 Anchor Plate Washers
ASTM A36/A36M
2.4 STRUCTURAL STEEL ACCESSORIES
2.4.1 Welding Electrodes and Rods
AWS D1.1/D1.1M . Use minimum E70XX rod.
2.4.2 Non-Shrink Grout
Provide grout in accordance with section 03 30 00.00 10 CAST-IN-PLACE
CONCRETE.
2.4.3 Welded Shear Stud Connectors
ASTM A29/A29M, Type B. AWS D1.1/D1.1M .
2.5 FABRICATION
Fabrication must be in accordance with the applicable provisions of AISC 325 . Fabrication and assembly must be done in the shop to the greatest extent possible. Punch, subpunch and ream, or drill bolt holes perpendicular to the surface of the member.
Compression joints depending on contact bearing must have a surface roughness not in excess of 500 micro inch as determined by ASME B46.1 , and ends must be square within the tolerances for milled ends specified in
ASTM A6/A6M.
Shop splices of members between field splices will be permitted only where indicated on the Contract Drawings. Splices not indicated require the approval of the Contracting Officer.
Do not splice truss top and bottom chords except as approved by the Contracting Officer. Chord splices must occur at panel joints at approximately the third point of the span. The center of gravity lines of truss members must intersect at panel points unless otherwise approved by the Contracting Officer. When the center of gravity lines do not intersect at a panel point, provisions must be made for the stresses due to eccentricity. Camber of trusses must be 1/8 inch in 10 feet unless otherwise indicated.
2.5.1 Markings
Prior to erection, members must be identified by a painted erection mark.
Connecting parts assembled in the shop for reaming holes in field connections must be match marked with scratch and notch marks. Do not locate erection markings on areas to be welded. Do not locate match markings in areas that will decrease member strength or cause stress concentrations.
2.5.2 Shop Primer
SSPC Paint 20 or SSPC Paint 29 , (zinc rich primer). Shop prime structural steel, except as modified herein, in accordance with SSPC PA 1 . Do not prime steel surfaces embedded in concrete, galvanized surfaces, or
SECTION 05 12 00 Page 6 surfaces within 0.5 inch of the toe of the welds prior to welding (except surfaces on which metal decking is to be welded). If flash rusting occurs, re-clean the surface prior to application of primer. Apply primer to a minimum dry film thickness of 2.0 mil.
Prior to assembly, prime surfaces which will be concealed or inaccessible after assembly. Do not apply primer in foggy or rainy weather; when the ambient temperature is below 45 degrees F or over 95 degrees F; or when the primer may be exposed to temperatures below 40 degrees F within 48 hours after application, unless approved otherwise by the Contracting Officer. Repair damaged primed surfaces with an additional coat of primer.
2.5.2.1 Cleaning
SSPC SP 6/NACE No.3 , except steel exposed in spaces above ceilings, attic spaces, furred spaces, chases that will be hidden to view in finished construction, and site/field weld locations may be cleaned to SSPC SP 3 when recommended by the shop primer manufacturer. Maintain steel surfaces free from rust, dirt, oil, grease, and other contaminants through final assembly.
2.5.2.2 SHOP PAINTING
Shop prime steel, except as modified herein, in accordance with SSPC PA 1 .
Clean steel before priming. If flash rusting occurs, re-clean the surface prior to application of primer. For steel which requires finish painting under Section 09 90 00 PAINTS AND COATINGS, the primer paint must be compatible with the finish paint.
2.5.3 Fireproofing and Epoxy Coated Surfaces
Surfaces to receive sprayed-on fireproofing or epoxy coatings must be cleaned and prepared in accordance with the manufacturer's recommendations, and as specified in Section 07 81 00 SPRAY-APPLIED
FIREPROOFING.
2.6 DRAINAGE HOLES
Adequate drainage holes must be drilled to eliminate water traps. Hole diameter must be 1/2 inch and location must be indicated on the detail drawings. Hole size and location must not affect the structural integrity.
PART 3 EXECUTION
3.1 ERECTION
a. Erection of structural steel, except as indicated in item b. below, must be in accordance with the applicable provisions of AISC 325 .
b. For low-rise structural steel buildings ( 60 feet tall or less and a maximum of 2 stories), the structure must be erected in accordance with AISC DESIGN GUIDE 10 .
After final positioning of steel members, provide full bearing under base plates and bearing plates using nonshrink grout. Place nonshrink grout in accordance with the manufacturer's instructions.
SECTION 05 12 00 Page 7 wildem1 Polygon
3.1.1 STORAGE
Material must be stored out of contact with the ground in such manner and location as will minimize deterioration.
3.2 CONNECTIONS
Except as modified in this section, connections not detailed must be designed in accordance with AISC 360 . Build connections into existing work. Do not tighten anchor bolts set in concrete with impact torque wrenches. Holes must not be cut or enlarged by burning. Bolts, nuts, and washers must be clean of dirt and rust, and lubricated immediately prior to installation.
3.2.1 Common Grade Bolts
ASTM A307 bolts must be tightened to a "snug tight" fit. "Snug tight" is the tightness that exists when plies in a joint are in firm contact. If firm contact of joint plies cannot be obtained with a few impacts of an impact wrench, or the full effort of a man using a spud wrench, contact the Contracting Officer for further instructions.
3.2.2 High-Strength Bolts
Pretension all ASTM A325 and ASTM A490 bolted connections. Bolts must be installed in connection holes and initially brought to a snug tight fit. After the initial tightening procedure, bolts must then be fully tensioned, progressing from the most rigid part of a connection to the free edges.
Pretensioning of high strength bolts shall be accomplished using the Turn of Nut Pretensioning method included in the AISC Specification for Structural Joints using ASTM A325 or A490 Bolts. Once all bolts in each connection have been brought to a snug tight condition, match mark each nut and bolt with a high visibility paint before pretensioning all nut and bolt assemblies in the joint. The Contractor and the Government shall use the match marks as an additional method of verification that pretensioning has been completed for all bolts in accordance with paragraph 8.2.1 and Table 8-2 of the AISC Specification.
3.3 GAS CUTTING
Use of gas-cutting torch in the field for correcting fabrication errors will not be permitted on any major member in the structural framing. Use of a gas cutting torch will be permitted on minor members not under stress only after approval has been obtained from the Contracting Officer.
3.4 WELDING
Welding must be in accordance with AWS D1.1/D1.1M . Provide AWS D1.1/D1.1M qualified welders, welding operators, and tackers.
Develop and submit the Welding Procedure Specifications (WPS) for all welding, including welding done using prequalified procedures.
Prequalified procedures may be submitted for information only; however, procedures that are not prequalified must be submitted for approval.
SECTION 05 12 00 Page 8
3.4.1 Removal of Temporary Welds, Run-Off Plates, and Backing Strips
Remove only from finished areas.
3.5 SHOP PRIMER REPAIR
Repair shop primer in accordance with the paint manufacturer's recommendation for surfaces damaged by handling, transporting, cutting, welding, or bolting.
3.5.1 Field Priming
Steel exposed to the weather, or located in building areas without HVAC for control of relative humidity must be field primed. After erection, the field bolt heads and nuts, field welds, and any abrasions in the shop coat must be cleaned and primed with paint of the same quality as that used for the shop coat.
3.6 FIELD QUALITY CONTROL
Perform field tests, and provide labor, equipment, and incidentals required for testing. The Contracting Officer must be notified in writing of defective welds, bolts, nuts, and washers within 7 working days of the date of the inspection.
3.6.1 Welds
3.6.1.1 Visual Inspection
AWS D1.1/D1.1M . Furnish the services of AWS-certified welding inspectors for fabrication and erection inspection and testing and verification inspections.
Inspect proper preparation, size, gaging location, and acceptability of welds; identification marking; operation and current characteristics of welding sets in use.
3.6.1.2 Nondestructive Testing
Nondestructive testing must be in accordance with AWS D1.1/D1.1M . Test locations must be selected by the Contracting Officer. If more than 20 percent of welds made by a welder contain defects identified by testing, then all welds made by that welder must be tested by ultrasonic testing, as approved by the Contracting Officer. When all welds made by an individual welder are required to be tested, magnetic particle testing must be used only in areas inaccessible to ultrasonic testing. Retest defective areas after repair. Submit weld inspection reports.
3.6.2 High-Strength Bolts
3.6.2.1 Testing Bolt, Nut, and Washer Assemblies
Test a minimum of 3 bolt, nut, and washer assemblies from each mill certificate batch in a tension measuring device at the job site prior to the beginning of bolting start-up. Demonstrate that the bolts and nuts, when used together, can develop tension not less than the provisions specified in AISC 360 , depending on bolt size and grade. The bolt tension must be developed by tightening the nut. A representative of the
SECTION 05 12 00 Page 9 manufacturer or supplier must be present to ensure that the fasteners are properly used, and to demonstrate that the fastener assemblies supplied satisfy the specified requirements. Submit bolt testing reports.
3.6.2.2 Inspection
Inspection procedures must be in accordance with AISC 360 . Confirm and report to the Contracting Officer that the materials meet the project specification and that they are properly stored. Confirm that the faying surfaces have been properly prepared before the connections are assembled. Observe the specified job site testing and calibration, and confirm that the procedure to be used provides the required tension.
Monitor the work to ensure the testing procedures are routinely followed on joints that are specified to be fully tensioned.
Inspection by both the Contractor and the Government will include turn of nut pretensioning for high-strength bolts.
3.6.2.3 Testing
The Government has the option to perform nondestructive tests on 5 percent of the installed bolts to verify compliance with pre-load bolt tension requirements. Provide the required access for the Government to perform the tests. The nondestructive testing will be done in-place using an ultrasonic measuring device or any other device capable of determining in-place pre-load bolt tension. The test locations must be selected by the Contracting Officer. If more than 10 percent of the bolts tested contain defects identified by testing, then all bolts used from the batch from which the tested bolts were taken, must be tested at the Contractor's expense. Retest new bolts after installation at the Contractor's expense.
-- End of Section --
SECTION 05 12 00 Page 10
| DIVISION 05 - METALS |
| 05 12 00 - STRUCTURAL STEEL |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 SUBMITTALS |
| 1.3 AISC QUALITY CERTIFICATION |
| 1.4 QUALITY ASSURANCE |
| 1.4.1 Preconstruction Submittals |
| 1.4.1.1 Erection Drawings |
| 1.4.2 Fabrication Drawing Requirements |
| 1.4.3 Certifications |
| 1.4.3.1 Welding Procedures and Qualifications |
| PART 2 PRODUCTS |
| 2.1 SYSTEM DESCRIPTION |
| 2.2 STEEL |
| 2.2.1 Structural Steel |
| 2.2.2 Structural Steel Tubing |
| 2.2.3 Steel Pipe |
| 2.3 BOLTS, NUTS, AND WASHERS |
| 2.3.1 Common Grade Bolts |
| 2.3.1.1 Bolts |
| 2.3.1.2 Nuts |
| 2.3.1.3 Washers |
| 2.3.2 High-Strength Bolts |
| 2.3.2.1 Bolts |
| 2.3.2.2 Nuts |
| 2.3.2.3 Washers |
| 2.3.3 Foundation Anchorage |
| 2.3.3.1 Anchor Rods |
| 2.3.3.2 Anchor Nuts |
| 2.3.3.3 Anchor Washers |
| 2.3.3.4 Anchor Plate Washers |
| 2.4 STRUCTURAL STEEL ACCESSORIES |
| 2.4.1 Welding Electrodes and Rods |
| 2.4.2 Non-Shrink Grout |
| 2.4.3 Welded Shear Stud Connectors |
| 2.5 FABRICATION |
| 2.5.1 Markings |
| 2.5.2 Shop Primer |
| 2.5.2.1 Cleaning |
| 2.5.2.2 SHOP PAINTING |
2.5.3 Fireproofing and Epoxy Coated Surfaces
2.6 DRAINAGE HOLES
| PART 3 EXECUTION |
| 3.1 ERECTION |
| 3.1.1 STORAGE |
| 3.2 CONNECTIONS |
| 3.2.1 Common Grade Bolts |
| 3.2.2 High-Strength Bolts |
| 3.3 GAS CUTTING |
| 3.4 WELDING |
| 3.4.1 Removal of Temporary Welds, Run-Off Plates, and Backing Strips |
| 3.5 SHOP PRIMER REPAIR |
| 3.5.1 Field Priming |
| 3.6 FIELD QUALITY CONTROL |
| 3.6.1 Welds |
| 3.6.1.1 Visual Inspection |
| 3.6.1.2 Nondestructive Testing |
| 3.6.2 High-Strength Bolts |
| 3.6.2.1 Testing Bolt, Nut, and Washer Assemblies |
| 3.6.2.2 Inspection |