SOO Utility Line Replacement and Air Compressor Building RFI 080409 Posted.pdf
PDF 17 KB Posted
- Solicitation number
- W911XK-09-R-0028
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Site Visit 2.pdf | ||
| W911XK-09-R-0028 Amendment 0004.pdf | ||
| Amendment 0003.pdf | ||
| SAOAsbestos_InventoryReport.pdf | ||
| SOO Utility Line Replacement and Air Compressor Building RFI 080709.pdf | ||
| SOO Utility Line Replacement and Air Compressor Building RFI 080609 Posted.pdf | ||
| Amendment 0002.pdf | ||
| Conformed with Amendment 0001.pdf | ||
| 01 22 00.00 10.pdf | ||
| Amendment 0001.pdf | ||
| 01 04 00.pdf | ||
| NSITE4.pdf | ||
| Sign in Sheet.pdf | ||
| SOO Utility Line Replacement Preproposal Present Final.pdf | ||
| SPECIAL NOTICE Site Visit change.doc | DOC document | |
| SPECIAL NOTICE Site Visit change.doc | DOC document | |
| Plans Drawings .zip | ZIP file | |
| Appendix.pdf | ||
| Solicitation SpecificationW911XK-09-R-0028.zip | ZIP file | |
| Exhibits A B C and D.zip | ZIP file | |
| SPECIAL NOTICE Site Visit.doc | DOC document |
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W911XK-09-R-0028 Updated 4 August 2009 SOO Utility Line Replacement and Air Compressor Building
Questions and Answers as of 04 August 2009
This document will be continually updated with questions and answers. Please be sure to check www.fbo.gov for the latest Q&A document.
1. QUESTION: The specification calls for “oil-free air”. Can you please clarify this definition?
ANSWER: Oil must be absent from compressed air before it enters the air dryer system.
2. QUESTION: Can the compressor be oil-flooded units with high levels of filtration?
ANSWER: See answer for question 1
3. QUESTION: Can the compressors be oil-flooded compressors with food grade lubricant instead of oil?
ANSWER: No
4. QUESTION: Can you please point to an ISO 8753.1 Air Quality specification and the definition?
ANSWER: Air quality must be such that it will not cause problems with air dryer or cause environmental issues.
5. QUESTION: I have read through the electrical requirements section of this specification.
I have not found any designation in regards to the type of motor on the air compressors.
Industry standards and practices lean towards TEFC (Totally Enclosed Fan Cooled) motors vs. ODP (open drip proof) in regards to reliability and quality. Do you have a position in regards to this?
ANSWER: No position
6. QUESTION: When can another site visit and tour of the tunnels be scheduled??
ANSWER: Under Review
7. QUESTION: Can the proposal due date be extended two weeks to 9/1/09?
8. QUESTION: Can the last day for questions be extended to 8/21/09??
http://www.fbo.gov/
W911XK-09-R-0028 Updated 4 August 2009 SOO Utility Line Replacement and Air Compressor Building
9. QUESTION: When can another site visit for our design partner and prospective subcontractors be scheduled??
ANSWER: See Question 6.
10. QUESTION: Would there be a possibility for the USACE to issue a separate contract for the Asbestos Abatement with the prime contractor still managing the abatement contractor?
ANSWER: Under Review