FY09 Soo Utility LIne Replacement & Compresses Air System SOULAMD1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 10
MEASUREMENT AND PAYMENT
04/06
PART 1 GENERAL
1.1 SUBMITTALS
1.2 LUMP SUM PAYMENT ITEMS
1.2.1 Mobilization and Demobilization (Item 0001)
1.2.1.1 Payment
1.2.1.2 Unit of Measure
1.2.2 Asbestos Survey for Steam Line (Item 0002)
1.2.2.1 Payment
1.2.2.2 Unit of Measure
1.2.3 Design Distribution System For Steam and Underground Connecting
Gallery 1. (Item 0003)
1.2.3.1 Payment
1.2.3.2 Unit of Measure
1.2.4 Construct Steam Distribution System MacArthur Lock (Item 0004)
1.2.4.1 Payment
1.2.4.2 Unit of Measure
1.2.5 Construct Steam Distribution System Poe Lock, Davis Building, Administration Building and Underground Connecting Gallery 1 (Item 0005).
1.2.5.1 Payment
1.2.5.2 Unit of Measure
1.2.6 OPTION 1: Design New Building, Underground Connecting Gallery
2, Compressed Air Generation and Distribution Systems (Item 0006).
1.2.6.1 Payment
1.2.6.2 Unit of Measure
1.2.7 OPTION 2: Construct New Building, Underground Connecting
Gallery 2, Compressed Air Generation and Distribution System (Item 0007)
1.2.7.1 Payment
1.2.7.2 Unit of Measure
1.2.8 OPTION 3: Asbestos Survey for the Remaining Facility (Item 0008)
1.2.8.1 Payment
1.2.8.2 Unit of Measure
1.2.9 OPTION 4: Design Potable Water Distribution System (Item 0009)
1.2.9.1 Payment
1.2.9.2 Unit of Measure
1.2.10 OPTION 5: Construct Potable Water Distribution System (Item
0010)
1.2.10.1 Payment
1.2.10.2 Unit of Measure
1.2.11 OPTION 6: Design Four New Stair Structures (Item 0011)
1.2.11.1 Payment
1.2.11.2 Unit of Measure
1.2.12 OPTION 7: Construct Four New Stair Structures (Item 0012)
1.2.12.1 Payment
SECTION 01 22 00.00 10 Page 1
1.2.12.2 Unit of Measure
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section Table of Contents --
SECTION 01 22 00.00 10 Page 2
SECTION 01 22 00.00 10
MEASUREMENT AND PAYMENT
04/06
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES FOR
DESIGN/BUILD:
1.2 LUMP SUM PAYMENT ITEMS
Payment items for the work of this contract for which contract lump sum payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.2.1 Mobilization and Demobilization (Item 0001)
1.2.1.1 Payment
Payment will be made for costs associated with mobilization and demobilization, as defined in Special Clause PAYMENT FOR MOBILIZATION AND
DEMOBILIZATION.
1.2.1.2 Unit of Measure
Unit of measure: lump sum.
1.2.2 Asbestos Survey for Steam Line (Item 0002)
Asbestos Survey for Steam Line include, but not limited to all cost necessary to determine the amount and type of asbestos used on the steam lines.
1.2.2.1 Payment
Payment will be made for costs associated with surveys, testing and other operations necessary for asbestos abetment determination for the steam line.
SECTION 01 22 00.00 10 Page 3
1.2.2.2 Unit of Measure
Unit of measure: lump sum.
1.2.3 Design Distribution System For Steam and Underground Connecting Gallery 1. (Item 0003)
1.2.3.1 Payment
Payment will be made for costs associated with design of new distribution system for the steam as well as the new gallery located between the Poe and MacArthur Locks. This cost will includes, but not limited to, method for asbestos removal, design of steam lines with condensate return system, construction phasing of steam lines, design of new gallery 1, and electrical lighting and ventilation for the new gallery.
1.2.3.2 Unit of Measure
Unit of measure: lump sum.
1.2.4 Construct Steam Distribution System MacArthur Lock (Item 0004)
1.2.4.1 Payment
Payment will be made for costs associated with construction of steam distribution system starting along the north wall of the MacArther Lock.
This cost includes, but not limited to, pipe removal, asbestos abatement, new hangers, condensate return system, new pipe lines, pipe insulation, temporary measures necessary to connect the new steam lines in the MacArthur Lock to the existing steam lines in the Poe Lock, and any temporary capping of the condensate return system.
1.2.4.2 Unit of Measure
Unit of measure: lump sum.
1.2.5 Construct Steam Distribution System Poe Lock, Davis Building, Administration Building and Underground Connecting Gallery 1 (Item 0005).
1.2.5.1 Payment
Payment will be made for costs associated with construction of entire steam distribution system starting from the Emergency Steam Plant to the north wall of the MacArther Lock, excluding the steam distribution system in the MacArther Lock. This cost shall include, but not limited to, pipe removal, new hangers, condensate return system, new steam lines, pipe insulation, and construction of underground connecting gallery 1 with lighting, hatches and access ports.
1.2.5.2 Unit of Measure
Unit of measure: lump sum.
SECTION 01 22 00.00 10 Page 4
1.2.6 OPTION 1: Design New Building, Underground Connecting Gallery 2, Compressed Air Generation and Distribution Systems (Item 0006).
1.2.6.1 Payment
Payment will be made for costs associated with design of new distribution system for air, the air compressor building, the new underground connecting gallery 2(located north of the Poe Lock), the electrical system required for the compressed air system, new compressor building and gallery 2.
1.2.6.2 Unit of Measure
Unit of measure: lump sum.
1.2.7 OPTION 2: Construct New Building, Underground Connecting Gallery 2, Compressed Air Generation and Distribution System (Item 0007)
1.2.7.1 Payment
Payment will be made for costs associated with construction of air distribution system including new piping, air compressor equipment, electric system and all items necessary to monitor and control the new air distribution system construction of the air compressor building and construction of the underground connecting gallery 2 with lighting, hatches and access ports.
1.2.7.2 Unit of Measure
Unit of measure: lump sum.
1.2.8 OPTION 3: Asbestos Survey for the Remaining Facility (Item 0008)
Asbestos Survey for the remaining facility include, but not limited to, all costs associated with the surveying, testing and determination of removal method for the water lines and other fixtures.
1.2.8.1 Payment
Payment will be made for costs associated with surveys, testing and other operations necessary for asbestos abatement.
1.2.8.2 Unit of Measure
Unit of measure: lump sum.
1.2.9 OPTION 4: Design Potable Water Distribution System (Item 0009)
1.2.9.1 Payment
Payment will be made for costs associated with design of new distribution system for potable water. This cost includes, but not limited to, method for asbestos removal, design of water, and construction phasing.
1.2.9.2 Unit of Measure
Unit of measure: lump sum.
SECTION 01 22 00.00 10 Page 5
1.2.10 OPTION 5: Construct Potable Water Distribution System (Item 0010)
1.2.10.1 Payment
Payment will be made for costs associated with construction of water distribution system. This cost includes, but not limited to, pipe removal, asbestos abatement, new hangers, and new pipe lines.
1.2.10.2 Unit of Measure
Unit of measure: lump sum.
1.2.11 OPTION 6: Design Four New Stair Structures (Item 0011)
1.2.11.1 Payment
Payment will be made for all costs associated with the design of the stairwell located at four locations in the galleries of the Poe Lock.
1.2.11.2 Unit of Measure
Unit of measure: lump sum.
1.2.12 OPTION 7: Construct Four New Stair Structures (Item 0012)
1.2.12.1 Payment
Payment will be made for costs associated with construction of the four stairs, including but not limited to, removing the exist stairs, placing new stairs, anchoring the structures re-anchor the existing medium voltage cables in the vertical stairwell.
1.2.12.2 Unit of Measure
Unit of measure: lump sum.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section --