FY09 Soo Utility LIne Replacement & Compresses Air System SOULAMD1

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 04 00

THE DESIGN/BUILD PROCESS

PART 1 GENERAL

1.1 DESIGN/BUILD PROCESS:

1.2 PROPOSAL PHASE:

1.3 DESIGN PHASE:

1.4 CONSTRUCTION PHASE:

1.5 SCHEDULE:

PART 2 NOT USED

PART 3 NOT USED

-- End of Section Table of Contents --

SECTION 01 04 00 Page 1

SECTION 01 04 00

THE DESIGN/BUILD PROCESS

PART 1 GENERAL

1.1 DESIGN/BUILD PROCESS:

The facility shall be designed and built by a single firm or team of firms (referred to as the Contractor or Design-Build Contractor) that has registered Architects and Engineers employed by or subcontracted to their organization.

1.2 PROPOSAL PHASE:

The Proposal Phase includes the period from the time of issuance of the Request for Proposal (RFP) through the selection process and the final award of the contract to the successful Offeror.

1.3 DESIGN PHASE:

The Design Phase for this project will be broken into two parts:

Part I (Base Bid)- Design of Distribution System for the Steam Lines and Underground Connecting Gallery 1 and the Asbestos Survey of the Steam Lines.

Part II (Options) - Design of the New Building, Underground Connecting Gallery 2, Compressed Air Generation and Distribution System;

Asbestos Survey for the Remaining Facility, Design of the Potable Water Distribution System; and Design Four New Stair Structures.

During the Design Phase for each part, the Contractor shall develop and submit for review and comment by the Government Quality Control Plan, 50% Design Analysis, Asbestos Assessment Plan, 100% Design Analysis, the 50% Design Submittal; Plans and Specifications, the 95% Design Submittal; Plans and Specifications and the 100% Design Submittal; Plans and Specifications.

The 100% Design Analysis shall be submitted for review with the 50% Design Submittal; Plans and Specifications.

The 100% Design Submittal shall be submitted by the Design Build firm for review by the Government to insure all comments have been resolved and incorporated. Once the Government determines all comments have been resolved it will notify the Design Build firm that the design plans and specifications are ready to be Released for Construction of each part.

1.4 CONSTRUCTION PHASE:

The Construction Phase for this project is divided into two parts:

Part I -

a. Construct Steam Lines at the MacArthur Lock

b. Construct Steam Lines (north of the north wall of the

SECTION 01 04 00 Page 2

MacArther Lock) and the Underground Connecting Gallery 1.

Part II - Construct Options: Construct New Building, Underground Connecting Gallery 2, Compressed Air Generation and Distribution Systems; Construct Water Distribution System; and Construct Four Stair Structures.

A Released for Construction letter for each part will be provided to the Design Build contractor. Each letter will initiate the Construction Phase for its part. The issue of the letter normally occurs within two weeks of the Design Phase approval.

Part I Construction

The construction of the Steam Lines at the MacArther Lock (Part I a.) must be completed by February 26, 2010. The lines must be fully operational by February 26, 2010.

The existing steamlines at the Poe Lock must remain operational until April 15, 2010.

The construction of the steam lines along with the underground connecting gallery 1 (Part I b.) must be completed by November 1, 2010.

PART II Construction

The existing air distribution system cannot be disrupted between November 1 and April 15. Air flow to the locks must be available during that time frame.

Water service to the facility must not be interrupted for more than a twelve hour period during non-peak work hours. A 72 hour notice to the COR will be required prior to shut-down. It must be completed in accordance with Section 01 32 01, Project Schedule. If more than a twelve hour period is required, temporary facilities and potable water must be provided at the Administration Building, the Davis Building and the Shelters.

1.5 SCHEDULE:

The schedule and sequence of work shown below is prepared by the government for the contractor's use in schedule preparation. This schedule is not intended to be the actual awarded design-build schedule. Upon receipt of the Notice to Proceed for Design, the selected contractor will be required to submit two proposed design and construction schedules. Schedule 1 will be required for Part I - the Design and Construction of the Steam Lines and Underground Connecting Gallery 1 (Base Bid). Schedule 2 will be for the design and construction of both Part I and Part II consisting of the Base Bid with all options. The schedules will be completed in accordance with Section 01 32 01, Project Schedule, based on their resources and approach for this project. Government performance and review periods can not be altered in the contractor's proposed schedule.

PART I (ONLY) - PROJECT SCHEDULE FOR BASE BID(Calendar Days) Design and Construct the Distribution System for the Steam Lines, the Underground Connecting Gallery 1 and the Asbestos Survey of the Steam Lines.

Minimum Number Of Days

SECTION 01 04 00 Page 3

Activity Between Activities Date

Issue RFP 16 Jul 09

Pre-Evaluation Site Visit 30 Jul 09

Proposal Submitted 17 Aug 09

Proposal Evaluation 9 Sep 09

Award Design Build Contract 7 Oct 09

Notice to Proceed to Design 21 Oct 09

Site Visit 10 Days from NTP

50% Design Analysis 20 Days from NTP

100% Design Analysis, Asbestos Assessment, & 35 Days from NTP 50% Design Submittal;Plans and Specs

Corps Review of 50% Design Submittal; 5 40 Days from NTP Plans and Specs and 100% Design Analysis

50% Design BCOE Review Conference 41 Days from NTP for 50% Plans and Specs and 100% Design Analysis

D/B Contractor makes corrections 5 47 Days from NTP from 50% Design Review Conference and DrChecks comments closed

95% Design Submittal; Plans and Specs 55 Days from NTP Submittal Due

Corps Review of 95% Design Submittal; 5 60 Days from NTP Plans and Specs

95% Design BCOE Review Conference 61 Days from NTP for 95% Plans and Specs

A/E makes final corrections 5 66 Days from NTP to 95% Plans and Specifications All DrChecks comments closed

A/E submits 100% Design submittal; 5 71 Days from NTP Plans and Specification

Government Review of 100% Design 5 76 Days from NTP Submittal; Plans & Specifications for comment resolution and incorporation

Corps Contracting Division sends 5 81 Days from NTP Authorization Letter to Release Plans and Specifications for Construction

Construction Complete 26 Feb 2010 for the MacArthur Lock

SECTION 01 04 00 Page 4

Steam Lines

Construction Complete 30 Jul 2010 for the all other Steam Lines and Underground Connecting Gallery 1

PART I AND PART II - PROJECT SCHEDULE FOR BASE BID WITH ALL OPTIONS(Calendar Days) Design and Construct the Base Bid: Distribution System for the Steam Lines, the Underground Connecting Gallery 1 and the Asbestos Survey of the Steam Lines; New Building, Underground Connecting Gallery 2, Compressed Air Generation and Distribution Systems; Water Distribution System; and Four Stair Structures.

Minimum Number

Activity Between Activities Date

Issue RFP 16 Jul 09

Pre-Evaluation Site Visit 30 Jul 09

Proposal Submitted 17 Aug 09

Proposal Evaluation 9 Sep 09

Award Design Build Contract 7 Oct 09

Notice to Proceed to Design 21 Oct 09

Site Visit 10 Days from NTP

Part I - Design Phase Design of the Steam Lines, Underground Connecting Gallery 1 and Asbestos Survey of the Steam Lines

Minimum Number Of Days Activity Between Activities Date

50% Design Analysis 20 Days from NTP

100% Design Analysis, Asbestos Assessment, & 35 Days from NTP 50% Design Submittal;Plans and Specs

Corps Review of 50% Design Submittal; 5 40 Days from NTP Plans and Specs and 100% Design Analysis

50% Design BCOE Review Conference 41 Days from NTP for 50% Plans and Specs and 100% Design Analysis

D/B Contractor makes corrections 5 47 Days from NTP from 50% Design Review Conference and DrChecks comments closed

95% Design Submittal; Plans and Specs 55 Days from NTP Submittal Due

SECTION 01 04 00 Page 5

Corps Review of 95% Design Submittal; 5 60 Days from NTP Plans and Specs

95% Design BCOE Review Conference 61 Days from NTP for 95% Plans and Specs

A/E makes final corrections 5 66 Days from NTP to 95% Plans and Specifications All DrChecks comments closed

A/E submits 100% Design submittal; 5 71 Days from NTP Plans and Specification

Government Review of 100% Design 5 76 Days from NTP Submittal; Plans & Specifications for comment resolution and incorporation

Corps Contracting Division sends 5 81 Days from NTP Authorization Letter to Release Plans and Specifications for Construction

PART II Design Phase Design of: New Building, Underground Connecting Gallery 2, Compressed Air Generation and Distribution System; Asbestos Survey for the Remaining Facility, Potable Water Distribution System; and Four New Stair Structures.

Activity Between Activities Date

50% Design Analysis Submittal Due 30 Days from NTP for Government Review

Corps Review and Comment on 14 44 Days from NTP 50% Design Analysis

50% Design Submittal;Plans and Specs, 60 Days from NTP 100% Design Analysis and Asbestos Plan

Corps Review of 50% Design Submittal; 14 74 Days from NTP Plans and Specs with 100% Design Analysis

50% Design BCOE Review Conference 75 Days from NTP for 50% Plans and Specs and 100% Design Analysis

D/B Contractor makes corrections 10 85 Days from NTP from 50% Design Review Conference and DrChecks comments closed

95% Design Submittal; Plans and Specs 120 Days from NTP Submittal Due

SECTION 01 04 00 Page 6

Corps Review of 95% Design Submittal; 14 134 Days from NTP Plans and Specs

95% Design BCOE Review Conference 135 Days from NTP for 95% Plans and Specs

A/E makes final corrections 10 145 Days from NTP to 95% Plans and Specifications All DrChecks comments closed

A/E submits 100% Design submittal; 5 150 Days from NTP Plans and Specification

Government Review of 100% Design 5 155 Days from NTP Submittal; Plans & Specifications for comment resolution and incorporation

Corps Contracting Division sends 5 160 Days from NTP Authorization Letter to Release Plans and Specifications for Construction

Part I and Part II - Construction Phase Construct Steam Lines, Underground Connecting Gallery 1 and Asbestos Removal of the Steam Lines New Building, Underground Connecting Gallery 2, Compressed Air Generation and Distribution System; Asbestos Removal, Potable Water Distribution System, Four New Stair Structures.

Activity Between Activities Date

Construction Complete 26 Feb 2010 for the MacArthur Lock Steam Lines

Construction Complete 30 Jul 2010 for the all other Steam Lines and Underground Connecting Gallery 1

Construction Complete 1 Nov 10 for New Building, Underground Connecting Gallery 2, Compressed Air Generation and Distribution System; Asbestos Removal, Potable Water Distribution System, Four New Stair Structures.

SECTION 01 04 00 Page 7

PART 2 NOT USED

PART 3 NOT USED

-- End of Section --