This specification section addresses construction and demolition waste management requirements for a firm fixed price contract to repair and stabilize cracks in two concrete river wall monoliths at Pike Island Locks and Dam in Wheeling, West Virginia. The contract requires installation of steel bar anchors and pressure grouting of cracks in the lock wall monoliths. Additional work includes demolition and replacement of concrete sections, reinforcement dowels, and recess frames. Waste from concrete demolition must be disposed of at a permitted solid waste facility, while ferrous and other recyclable materials will be recycled. The contractor must submit a waste management plan within 30 days of notice to proceed and maintain disposal records. The contract value is estimated between $500,000 and $1,000,000 with a 365-day period of performance. The solicitation will be issued on or around July 31, 2020 via SAM.gov.

View the file

Other files

File Type Posted
Bid Opening Attendance Register .pdf PDF
Bid Results.pdf PDF
Amendment 4 - W911WN20B8008-0013 Pike Island River Wall Crack Stabilization.pdf PDF
Plans W911WN20B8008 Amendment 0004.pdf PDF
Plans W911WN20B8008 Amendment 0003.pdf PDF
Amendment 3 - W911WN20B8008-0009 Pike Island River Wall Crack Stabilization.pdf PDF
01 35 00.00 08.pdf PDF
Attachment 5 - Repair Gate Schedule Additional.pdf PDF
Amendment 2 - W911WN20B8008-0008 Pike Island River Wall Crack Stabilization.pdf PDF
01 22 00.00 08.pdf PDF
Conformed CLINs 0001 through 0013 - W911WN20B8008.pdf PDF
13 51 00.10 08.pdf PDF
02 41 00.pdf PDF
Plans W911WN20B8008- Amendment 0002.pdf PDF
Site Visit Sign In Sheet - W911WN20C8008 Pike Island Crack Stabilization.pdf PDF
Amendment 0007 W911WN20B8008.pdf PDF
Amendment 0007 Spec Section 01 35 00.00 08.pdf PDF
Amendment 0007 Spec Section 01 35 26.00 08.pdf PDF
Amendment 0007 Spec Section 01 32 33.pdf PDF
Amendment 0007 Spec Section 03 30 53.00 08.pdf PDF
Amendment 0007 Wage Determination WV20200073 1-24-2020.pdf PDF
Amendment 0007 Spec Section 13 51 00.10 08.pdf PDF
A.03 W911WN20B8008 - Contract and Reference Drawings, Attachment 2.pdf PDF
A.03 Pike Island L&D River Wall Crack Stabilization 2020 Tech Specs Certified Final Documents, Attachment 1.pdf PDF
B.08 W911WN20B8008 (Pike Island Monolith Repairs -Crack Stabilization).pdf PDF
B.04 Wage Determination PA20200002 (July 24, 2020), Attachment 3.pdf PDF
A.02 Pike Island L&D Monolith R33 and R34 River Wall Crack Stabilization Virtual Site Visit, Attachment 4.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pike Island LD, River Wall Crack Stabilization

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 74 19.00 08

CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

PART 1 GENERAL

1.1 REFERENCES

1.2 GOVERNMENT POLICY

1.3 MANAGEMENT

1.4 SUBMITTALS

1.5 MEETINGS

1.6 ENVIRONMENTAL PROTECTION REQUIREMENTS

1.7 FEDERAL ENVIRONMENTAL COMPLIANCE REQUIREMENTS FOR

CONTRACTOR-PROPOSED DISPOSAL SITE

1.7.1 Background

1.7.2 Permitted Solid Waste Disposal Facility

1.8 WASTE MANAGEMENT PLAN

1.9 RECORDS

1.10 COLLECTION

1.10.1 Source Separated Method

1.10.2 Other Methods.

1.11 DISPOSAL

1.11.1 Reuse

1.11.2 Recycle

1.11.3 Return

1.11.4 Waste

1.11.4.1 Disposal of Solid Wastes

1.11.4.2 Disposal of Demolition Debris

1.11.4.3 Disposal of Waste Water

1.11.4.4 Disposal of Contractor Generated Hazardous Wastes

1.11.4.5 Disposal of Materials with Lead Coatings

1.11.4.6 Burning

1.11.4.7 Hauling Materials to Disposal Facilities

1.12 SPECIAL REQUIREMENTS FOR EXCAVATED MATERIAL HANDLING

1.12.1 General

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 DISPOSAL OF EXCAVATED MATERIAL

3.1.1 General

3.1.2 Permitted Solid Waste Disposal Facilities

3.2 INSPECTION

3.3 DISPOSAL REQUIREMENTS

-- End of Section Table of Contents --

SECTION 01 74 19.00 08 Page 1 CERTIFIED FINAL DOCUMENTS - W911WN20B8008 - Amendment 0001

SECTION 01 74 19.00 08

CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1926 Safety and Health Regulations for Construction

40 CFR 263 Standards Applicable to Transporters of Hazardous Waste

1.2 GOVERNMENT POLICY

Government policy is to apply sound environmental principles in the design, construction and use of facilities. As part of the implementation of that policy: (1) practice efficient waste management when sizing, cutting, and installing products and materials and (2) use all reasonable means to divert construction and demolition waste from landfills and incinerators and to facilitate their recycling or reuse.

1.3 MANAGEMENT

Develop and implement a waste management program. Take a pro-active, responsible role in the management of construction and demolition waste and require all subcontractors, vendors, and suppliers to participate in the effort. Construction and demolition waste includes products of demolition or removal, excess or unsuitable excavated material, excess or unusable construction materials, packaging materials for construction products, and other materials generated during the construction process but not incorporated into the work. In the management of waste, consider the availability of viable markets, the condition of the material, the ability to provide the material in suitable condition and in a quantity acceptable to available markets, and time constraints imposed by internal project completion mandates. Implement any special programs involving rebates or similar incentives related to recycling of waste. Revenues or other savings obtained for salvage, or recycling accrue to the Contractor. Appropriately permit firms and facilities used for recycling, reuse, and disposal for the intended use to the extent required by federal, state, and local regulations. Also, provide on-site instruction of appropriate separation, handling, recycling, salvage, reuse, and return methods to be used by all parties at the appropriate stages of the project.

SECTION 01 74 19.00 08 Page 2

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Waste Management Plan; G, RO

Disposal sites; G, RO

SD-11 Closeout Submittals

Records

1.5 MEETINGS

Conduct Construction Waste Management meetings. After award of the Contract and prior to commencement of work, schedule and conduct a meeting with the Contracting Officer or designated representative to discuss the proposed Waste Management Plan and to develop a mutual understanding relative to the details of waste management. The requirements for this meeting may be fulfilled during the coordination and mutual understanding meeting outlined in Section 01 45 00.00 08 QUALITY CONTROL. At a minimum, discuss environmental and waste management goals and issues at the following additional meetings:

a. Pre-bid meeting, if applicable.

b. Preconstruction meeting.

c. Regular QC meetings.

d. Work safety meetings.

1.6 ENVIRONMENTAL PROTECTION REQUIREMENTS

The Contractor shall comply with all applicable Federal, State, and local statues, laws and regulations. The Contractor shall provide environmental protective measures and procedures to prevent and control pollution, limit habitat disruption, and correct environmental damage that occurs during construction as specified in Section 01 57 19.00 08 0 TEMPORARY

ENVIRONMENTAL CONTROLS.

1.7 FEDERAL ENVIRONMENTAL COMPLIANCE REQUIREMENTS FOR CONTRACTOR-PROPOSED

DISPOSAL SITE

These requirements apply only to that material which is identified as acceptable for disposal at an area other than a permitted solid waste disposal facility. Material which is specified to be disposed at a permitted solid waste disposal facility or hazardous waste facility must be disposed as specified for those materials.

SECTION 01 74 19.00 08 Page 3

1.7.1 Background

As an agency of the Federal government, the Pittsburgh District, US Army Corps of Engineers (District), is responsible for insuring compliance of its activities (including those undertaken by its contractors) with all applicable Federal environmental and cultural protection statutes, and regulations.

Disposal sites proposed by the Contractor must be permitted sites which comply with all pertinent Federal and State environmental protection statutes and are commercially available. The Contractor shall submit documentation verifying that the Contractor's proposed disposal site meets all Federal environmental statutes and is commercially available.

District approval of a Contractor-proposed disposal site is predicated upon the Contractor's demonstration that the site is in compliance with Federal statutes and is commercially available.

1.7.2 Permitted Solid Waste Disposal Facility

A permitted solid waste disposal facility is a landfill or other facility which is properly permitted by the state in which the work is located for the disposal of municipal, residual, or construction/demolition waste.

The facility shall be permitted to accept the particular material being disposed.

1.8 WASTE MANAGEMENT PLAN

Submit a waste management plan within 30 calendar days after notice to proceed and not less than 10 calendar days before the preconstruction meeting. The plan demonstrates how to meet the the project waste diversion goal. Also, include the following in the plan:

a. Name of individuals on the Contractor's staff responsible for waste prevention and management.

b. Actions that will be taken to reduce solid waste generation, including coordination with subcontractors to ensure awareness and participation.

c. Description of the regular meetings to be held to address waste management.

d. Description of the specific approaches to be used in recycling/reuse of the various materials generated, including the areas on site and equipment to be used for processing, sorting, and temporary storage of wastes.

e. Characterization, including estimated types and quantities, of the waste to be generated.

f. Name of landfill and/or incinerator to be used and the estimated costs for use, assuming that there would be no salvage or recycling on the project.

g. Identification of local and regional reuse programs, including non-profit organizations such as schools, local housing agencies, and organizations that accept used materials such as materials exchange networks and Habitat for Humanity. Include the name, location, and phone number for each reuse facility to be used, and provide a copy of the permit or license for each facility.

SECTION 01 74 19.00 08 Page 4

h. List of specific waste materials that will be salvaged for resale, salvaged and reused on the current project, salvaged and stored for reuse on a future project, or recycled. Identify the recycling facilities by name, location, and phone number, including a copy of the permit or license for each facility.

i. Identification of materials that cannot be recycled/reused with an explanation or justification, to be approved by the Contracting Officer or designated representative.

j. Description of the means by which any waste materials identified in item (h) above will be protected from contamination.

k. Description of the means of transportation of the recyclable materials (whether materials will be site-separated and self-hauled to designated centers, or whether mixed materials will be collected by a waste hauler and removed from the site).

l. Anticipated net cost savings determined by subtracting Contractor program management costs and the cost of disposal from the revenue generated by sale of the materials and the incineration and/or landfill cost avoidance.

Revise and resubmit Plan as required by the Contracting Officer or designated representative. Approval of Contractor's Plan will not relieve the Contractor of responsibility for compliance with applicable environmental regulations or meeting project cumulative waste diversion requirement. Distribute copies of the Waste Management Plan to each subcontractor, the Quality Control Manager, and the Contracting Officer or designated representative.

1.9 RECORDS

Maintain records to document the quantity of waste generated; the quantity of waste diverted through sale, reuse, or recycling; and the quantity of waste disposed by landfill or incineration. Make the records available to the Contracting Officer or designated representative during construction, and deliver to the Contracting Officer or designated representative upon completion of the construction a copy of the records.

1.10 COLLECTION

Separate, store, protect, and handle at the site identified recyclable and salvageable waste products in a manner that maximizes recyclability and salvagability of identified materials. Provide the necessary containers, bins and storage areas to facilitate effective waste management and clearly and appropriately identify them. Provide materials for barriers and enclosures around recyclable material storage areas which are nonhazardous and recyclable or reusable. Locate out of the way of construction traffic. Provide adequate space for pick-up and delivery and convenience to subcontractors. Recycling and waste bin areas are to be kept neat and clean, and handle recyclable materials to prevent contamination of materials from incompatible products and materials.

Clean contaminated materials prior to placing in collection containers.

Use cleaning materials that are nonhazardous and biodegradable. Handle hazardous waste and hazardous materials in accordance with applicable regulations. Separate materials by one of the following methods:

SECTION 01 74 19.00 08 Page 5

1.10.1 Source Separated Method

Separate waste products and materials that are recyclable from trash and sorted as described below into appropriately marked separate containers and then transported to the respective recycling facility for further processing. Deliver materials in accordance with recycling or reuse facility requirements (e.g., free of dirt, adhesives, solvents, petroleum contamination, and other substances deleterious to the recycling process). Separate materials into the following category types as appropriate to the project waste and to the available recycling and reuse programs in the project area. Comingling of materials is acceptable where local recycling facilities have the capability to handle such materials.:

a. Land clearing debris.

b. Asphalt.

c. Concrete and masonry.

d. Metal (e.g. banding, stud trim, ductwork, piping, rebar, roofing, other trim, steel, iron, galvanized, stainless steel, aluminum, copper, zinc, lead brass, bronze).

(1) Ferrous.

(2) Non-ferrous.

e. Wood (nails and staples allowed).

f. Debris.

g. Glass (colored glass allowed).

h. Paper.

(1) Bond.

(2) Newsprint.

(3) Cardboard and paper packaging materials.

i. Plastic.

Type

1 Polyethylene Terephthalate (PET, PETE)

2 High Density Polyethylene (HDPE)

3 Vinyl (Polyvinyl Chloride or PVC)

4 Low Density Polyethylene (LDPE)

5 Polypropylene (PP)

SECTION 01 74 19.00 08 Page 6

Type

6 Polystyrene (PS)

7 Other. Use of this code indicates that the package in question is made with a resin other than the six listed above, or is made of more than one resin listed above, and used in a multi-layer combination.

j. Gypsum.

k. Non-hazardous paint and paint cans.

l. Carpet.

m. Ceiling tiles.

n. Insulation.

o. Beverage containers.

1.10.2 Other Methods.

Other proposed methods may be used when approved by the Contracting Officer or designated representative.

1.11 DISPOSAL

Control accumulation of waste materials and trash. Recycle or dispose of collected materials off-site at intervals approved by the Contracting Officer or designated representative and in compliance with waste management procedures. Except as otherwise specified in other sections of the specifications, dispose of in accordance with the following:

1.11.1 Reuse

Give first consideration to salvage for reuse since little or no re-processing is necessary for this method, and less pollution is created when items are reused in their original form. Consider sale or donation of waste suitable for reuse.

1.11.2 Recycle

Recycle waste materials not suitable for reuse, but having value as being recyclable. Recycle all fluorescent lamps, HID lamps, and mercury-containing thermostats removed from the site. Arrange for timely pickups from the site or deliveries to recycling facilities in order to prevent contamination of recyclable materials.

1.11.3 Return

Set aside and protect misdelivered and substandard products and materials and return to supplier for credit.

SECTION 01 74 19.00 08 Page 7

1.11.4 Waste

Dispose of materials with no practical use or economic benefit to waste-to-energy plants where available. As the last choice, dispose of materials at a landfill or incinerator.

1.11.4.1 Disposal of Solid Wastes

Solid waste shall be placed in containers and disposed on a regular schedule. All handling and disposal shall be conducted in such a way as to prevent spillage and contamination. The Contractor shall transport all solid waste off Government property and dispose at a commercially available and properly permitted solid waste disposal facility in compliance with Federal, State, and local requirements.

1.11.4.2 Disposal of Demolition Debris

Demolition products, except that which is to be recycled or salvaged, shall be transported from Government property for proper disposal at a commercially available and properly permitted solid waste disposal facility in compliance with Federal, State, and local requirements.

Metals which are removed may be recycled as scrap. Materials which are coated with lead based paints shall be disposed in accordance with paragraph "Disposal of Materials with Lead Coatings".

1.11.4.3 Disposal of Waste Water

Waste water directly derived from construction activities, including but not limited to water used in drilling, concrete cutting, joint preparation, and dewatering of work areas, shall not be discharged before being treated to remove pollutants. Waste water shall be collected and placed in holding tanks so the suspended materials can settle prior to discharge to the stream or watercourse.

1.11.4.4 Disposal of Contractor Generated Hazardous Wastes

Hazardous waste generated by construction activities shall be removed from the work area and be disposed at a properly permitted commercially available disposal facility in compliance with Federal, State, and local requirements. The Contractor shall maintain separation and/or segregate hazardous waste from other materials and wastes, and shall protect it from the weather by placing it in a safe covered location; precautionary measures against accidental spillage such as berming or other appropriate measures shall be taken. Hazardous waste shall be removed from Government property within 60 calendar days. Hazardous waste shall be transported in accordance with 40 CFR 263 . The Contractor shall be responsible for preparing all waste manifests (EPA Form No. 8700-22 "Uniform Hazardous Waste Manifest Form"). A copy of each waste manifest and a copy of the disposal certificate from the Resource Conservation and Recovery Act (RCRA) facility shall be furnished to the Contracting Officer or designated representative. Hazardous waste shall not be dumped onto the ground, into storm sewers or open water courses, or into the sanitary sewer system.

1.11.4.5 Disposal of Materials with Lead Coatings

All miscellaneous metals and other items which are coated with a lead primer shall become the property of the Contractor, and shall be completely removed from the project site. These items may be sold as

SECTION 01 74 19.00 08 Page 8 scrap (for basic steel processing) with the lead primer adhered, or may be disposed of in accordance with the applicable Federal, State, County and local laws. Items with lead coatings, if not salvaged by the Contractor as scrap metal for reprocessing, shall be disposed of at an EPA approved disposal facility authorized to receive and process materials coated with lead product. The Contractor shall inform all workers involved with the removal of this material of the fact that the material is undercoated with lead primer. Safety and health measures shall conform to EM 385-1-1 and 29 CFR 1926 , Part 62. If materials containing lead are disposed of, the Contractor shall perform all required testing of the coating system and submit a certified copy of the test results along with a certified Uniform Hazardous Waste Manifest to the Contracting Officer or designated representative. The manifest shall document the testing, transport and disposal of the material, and shall attest that the materials were disposed at a facility approved by the Pennsylvania Department of Environmental Resources for processing or disposal of such materials.

1.11.4.6 Burning

the use of burning at the project site for the disposal of refuse and debris will not be permitted. If burning is permitted, specific requirements will be included in the Task Order.

1.11.4.7 Hauling Materials to Disposal Facilities

Care shall be exercised in hauling the materials to the disposal facilities to preclude spillage and damage to public and private property and thoroughfares. Any materials spilled from the hauling equipment shall be removed by the Contractor at the Contractor's expense. The Contractor shall make all necessary arrangements and comply with all requirements associated with hauling the materials over streets and roads. (See also Section 01 35 00.00 08 SPECIAL PROCEDURES, paragraph WORK AREAS AND RESTRICTIONS, subparagraph Use of Local Roads and Streets.

1.12 SPECIAL REQUIREMENTS FOR EXCAVATED MATERIAL HANDLING

1.12.1 General

In general, excavated material which is not used for fill or backfill and associated debris shall be disposed of at a commercially available and properly permitted solid waste disposal facility as defined in paragraph Permitted Solid Waste Disposal Facility.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

3.1 DISPOSAL OF EXCAVATED MATERIAL

3.1.1 General

The material excavated which is not used for fill or backfill and associated debris shall be disposed of at a permitted solid waste disposal facility as defined in paragraph "Permitted Solid Waste Disposal Facility". Hauling and placement shall be in accordance with applicable Federal, State and local requirements. Hauling equipment shall be of a type to prevent spillage during hauling. Any material spilled on public

SECTION 01 74 19.00 08 Page 9 or private highways shall be promptly removed at no additional cost to the Government. Disposal of excavated material and debris which is classified as residual waste shall also comply with the requirements of paragraph SPECIAL REQUIREMENTS FOR EXCAVATED MATERIAL HANDLING. All expenses of transportation, material handling, and disposal of materials at the solid waste disposal facility or disposal area, including any disposal fees, shall be borne by the Contractor. The Contractor shall be responsible for complying with all requirements of the solid waste disposal facility or disposal site, including, but not limited to sampling and testing documentation. Disposal of excavated material and debris at the solid waste disposal facility or disposal site shall conform to the requirements of the facility operator, and all operations associated with such disposal shall be the Contractor's responsibility. Waste manifests shall be prepared and submitted in accordance with paragraph SUBMITTALS, Waste Classification, Handling, and Disposal Plan. Certificates of disposal shall be obtained from the permitted solid waste disposal facility and submitted to the Contracting Officer or designated representative.

3.1.2 Permitted Solid Waste Disposal Facilities

Material specified to be disposed at a commercially available and properly permitted solid waste disposal facility shall delivered to a facility as defined in paragraph Permitted Solid Waste Disposal Facility and in accordance with applicable Federal, state and local laws and regulations.

3.2 INSPECTION

If the Contracting Officer or designated representative notifies the Contractor in writing of any observed noncompliance with contract requirements or Federal, State, or local laws, regulations and concerning disposal of materials, the Contractor shall inform the Contracting Officer or designated representative of proposed corrective action and take such action to correct the noncompliance. If the Contractor fails to comply promptly, the Contracting Officer or designated representative may issue an order stopping all or part of the work related to the disposal until satisfactory corrective action is taken. No time extensions will be granted and no costs or damages allowed to the Contractor for any such suspension.

3.3 DISPOSAL REQUIREMENTS

The following general requirements apply to disposal of waste materials unless other or more specific requirements are specified in the other sections.

SECTION 01 74 19.00 08 Page 10

Tabl e 1 Di sposal Requi r ement s

Material Disposal Requirements Testing Requirements

Solid Waste Commercially Available and As required by Properly Permitted Municipal facility Waste Facility

Demolition Debris Commercially Available and Heavy metals and other than concrete Properly Permitted Municipal as required by rubble (including or Construction/Demolition facility Bituminous Pavement) Waste Facility or burning of combustible materials where approved

Concrete Rubble Commercially Available and As required by Properly Permitted Municipal facility Waste or Construction/ Demolition Waste or Municipal Facility

Waste Water Discharge after removal of As required by suspended solids the facility Task Order

Contractor Generated Commercially Available and As required by Hazardous Waste Properly Permitted Hazardous facility Waste Facility

Sediment Commercially Available and As required by Properly Permitted Municipal, the facility Task

Residual, or Construction/ Order Demolition Waste Facility

-- End of Section --

SECTION 01 74 19.00 08 Page 11

01 74 19.00 08 - CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 74 19.00 08 - CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
PART 1 GENERAL
1.1 REFERENCES
1.2 GOVERNMENT POLICY
1.3 MANAGEMENT
1.4 SUBMITTALS
1.5 MEETINGS
1.6 ENVIRONMENTAL PROTECTION REQUIREMENTS
1.7 FEDERAL ENVIRONMENTAL COMPLIANCE REQUIREMENTS FOR CONTRACTOR-PROPOSED
1.7.1 Background
1.7.2 Permitted Solid Waste Disposal Facility
1.8 WASTE MANAGEMENT PLAN
1.9 RECORDS
1.10 COLLECTION
1.10.1 Source Separated Method
1.10.2 Other Methods.
1.11 DISPOSAL
1.11.1 Reuse
1.11.2 Recycle
1.11.3 Return
1.11.4 Waste
1.11.4.1 Disposal of Solid Wastes
1.11.4.2 Disposal of Demolition Debris
1.11.4.3 Disposal of Waste Water
1.11.4.4 Disposal of Contractor Generated Hazardous Wastes
1.11.4.5 Disposal of Materials with Lead Coatings
1.11.4.6 Burning
1.11.4.7 Hauling Materials to Disposal Facilities
1.12 SPECIAL REQUIREMENTS FOR EXCAVATED MATERIAL HANDLING
1.12.1 General
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 DISPOSAL OF EXCAVATED MATERIAL
3.1.1 General
3.1.2 Permitted Solid Waste Disposal Facilities
3.2 INSPECTION
3.3 DISPOSAL REQUIREMENTS