This document package includes a solicitation and technical specifications for a federal construction contract. The U.S. Army Corps of Engineers, Pittsburgh District, is seeking to repair and stabilize cracks in two concrete river wall monoliths at Pike Island Locks and Dam in Wheeling, West Virginia. Services required include installing steel bar anchors and pressure grouting the cracks, demolishing and replacing concrete sections, regrouting recess frames, and placing reinforcement and new concrete. The contract is for one year with a period of performance of 365 days after notice to proceed. The estimated cost is between $500,000 and $1,000,000. The specifications detail equipment, photography, and submittal requirements to document progress. Bids must be submitted through beta.SAM.gov by July 31, 2020. The NAICS code is 237990 and the small business size standard is $39.5 million.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pike Island LD, River Wall Crack Stabilization
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 33
DIGITAL PROGRESS IMAGES
PART 1 GENERAL
1.1 SCOPE
1.2 SUBMITTALS
1.3 GENERAL REQUIREMENTS
1.3.1 Description
1.3.2 Digital Photographs
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 EQUIPMENT
3.2 PHOTOGRAPHY
-- End of Section Table of Contents --
SECTION 01 32 33 Page 1 CERTIFIED FINAL DOCUMENTS - W911WN20B8008 - Amendment 0001
SECTION 01 32 33
DIGITAL PROGRESS IMAGES
PART 1 GENERAL
1.1 SCOPE
The work under this section includes furnishing digital photographs showing the progress of the fabrication and/or construction operations throughout the contract period.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having an "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-11 Closeout Submittals
Thumbnail Hard Copy Prints of Progress Images; G, RO Glossy Prints of Selected Official Progress Images; G, RO Electronic Copy of Selected Official Progress Images; G, RO Electronic Copy of All Other Progress Images; G, RO
Copies of digital progress images in electronic form and hard copy form shall be submitted monthly for approval in accordance with paragraph PHOTOGRAPHY. Progress images shall be submitted in a timely manner as coordinated with the Contracting Officer or designated representative.
1.3 GENERAL REQUIREMENTS
1.3.1 Description
The Contractor shall, during the progress of the project (including progress of fabrication), furnish the Contracting Officer or designated representative progress photographs to depict progress of construction throughout the life of the contract. The photographs shall be taken using digital photography equipment furnished by the Contractor. Electronic copies of approved photographs shall be furnished on DVD or other storage media as approved by the Contracting Officer or designated representative.
1.3.2 Digital Photographs
Digital photographs shall comply with the requirements of paragraph PHOTOGRAPHY. The Contractor shall furnish, using Microsoft Word 2013 or later version, a file with each set of photographs which lists the following identifying information for each photographic image:
Name and location of project Contract number Date taken Contractor (and subcontractor, if applicable)
SECTION 01 32 33 Page 2
Orientation of view and brief description of work depicted
The filename of each photograph shall include the date the photograph was taken in the year-month-day format and each photograph shall be sequentially numbered. An example filename would be "2018-10-25-photo0001.jpg". The identifying data shall be placed in the document accompanying the photographs. The image of the photograph shall include the date stamp when the photograph was taken as part of the image. No identifying data, except the date stamp, shall appear on the photographs.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 EQUIPMENT
The Contractor shall be responsible for furnishing all photographic equipment to perform the work specified by this section. The camera shall have a CCD resolution no less than 14.0 million pixels per image which will provide enough detail to print an 8" by 10" high-resolution photograph. The camera shall produce images to be saved in one of the following graphic formats: JPG (Joint Photographic Experts Group), TIFF (Tagged Image File Format) or BMP (Windows Bitmap). Cell phone camera photographs shall not be accepted for digital progress photographs under this section.
3.2 PHOTOGRAPHY
The Contractor shall, during the progress of the work, furnish the Contracting Officer or designated representative digitally produced progress photographs to depict the progress of the work both on-site and off-site at fabrication facilities and/or construction sites. In coordination with the Contracting Officer or designated representative, one set of progress photographs per month shall be taken over the full duration of this contract, except photographs will not be required for periods when no work is in progress. Thumbnail Hard Copy Prints of Progress Images shall be submitted to the Contracting Officer or designated representative for approval between the first and fifth day of each month. The Contracting Officer's Representative Contracting Officer or their designated representative will select from the thumbnail views, unless directed otherwise, at least 10 views to become official progress images. The selected official progress images shall be printed in color in 8" by 10" format, shall be identified on the back in accordance with paragraph Digital Photographs, and shall be submitted for approval.
Glossy Prints of Selected Official Progress Images and Electronic Copy of Selected Official Progress Images shall be furnished within 10 calendar days of approval of the thumbnail images. Electronic copies shall be furnished on DVD with file of required photographic information.
Electronic Copy of All Other Progress Images (including those not selected) shall be furnished on separate DVD with file of required photographic information with the selected official progress images.
Digital photographs shall be taken continuously throughout each month in which work is in progress. Unless otherwise directed by the Contracting Officer or designated representative, photographs will not be required for periods of time in which work is not being performed. Additional sets of photographs shall be taken as directed by the Contracting Officer or designated representative. Enough digital photographs shall be taken to adequately depict each phase of the work and shall show progress made
SECTION 01 32 33 Page 3 during those phases and at the completion of the project. Digital photographs shall show work accomplished since the previous photographs.
Progress photographs shall be submitted as specified herein and in paragraph SUBMITTALS.
-- End of Section --
SECTION 01 32 33 Page 4
| 01 32 33 - DIGITAL PROGRESS IMAGES |
| 01 32 33 - DIGITAL PROGRESS IMAGES |
| PART 1 GENERAL |
| 1.1 SCOPE |
| 1.2 SUBMITTALS |
| 1.3 GENERAL REQUIREMENTS |
| 1.3.1 Description |
| 1.3.2 Digital Photographs |
| PART 2 PRODUCTS NOT APPLICABLE |
| PART 3 EXECUTION |
| 3.1 EQUIPMENT |
| 3.2 PHOTOGRAPHY |