Amendment 0007 Spec Section 01 35 00.00 08.pdf

PDF 83 KB Posted

Attached to
Pike Island Monolith R33 and RR34 River Wall Crack Stabilization 2020
Solicitation number
W911WN20B8008
Issued by

About this file

This federal contract solicitation is for the Pike Island Monolith R33 and RR34 River Wall Crack Stabilization project. The U.S. Army Corps of Engineers, Pittsburgh District is seeking a firm-fixed price contract for installation of steel bar anchors, pressure grouting, concrete demolition and placement to repair and stabilize cracks in two concrete river wall monoliths at Pike Island Locks and Dam on the Ohio River in Wheeling, West Virginia. The period of performance is 365 days from notice to proceed with an estimated cost between $500,000 and $1,000,000. Work will involve temporary instrumentation, drilling and installing horizontal steel bar anchors, demolishing and pressure grouting concrete, replacing recess frames and covers, drilling dowels, placing reinforcement, and new concrete placement. Intermittent short-term lock shutdowns are permitted for critical operations, but most work must occur while the lock remains operational. River access may be required utilizing contractor-supplied barge or crane. The NAICS code is 237990 and bids are due through beta.SAM by July 2020.

View the file

Other files

File Type Posted
Bid Opening Attendance Register .pdf PDF
Bid Results.pdf PDF
Amendment 4 - W911WN20B8008-0013 Pike Island River Wall Crack Stabilization.pdf PDF
Plans W911WN20B8008 Amendment 0004.pdf PDF
Plans W911WN20B8008 Amendment 0003.pdf PDF
Amendment 3 - W911WN20B8008-0009 Pike Island River Wall Crack Stabilization.pdf PDF
01 35 00.00 08.pdf PDF
Attachment 5 - Repair Gate Schedule Additional.pdf PDF
Amendment 2 - W911WN20B8008-0008 Pike Island River Wall Crack Stabilization.pdf PDF
01 22 00.00 08.pdf PDF
Conformed CLINs 0001 through 0013 - W911WN20B8008.pdf PDF
13 51 00.10 08.pdf PDF
02 41 00.pdf PDF
Plans W911WN20B8008- Amendment 0002.pdf PDF
Site Visit Sign In Sheet - W911WN20C8008 Pike Island Crack Stabilization.pdf PDF
Amendment 0007 W911WN20B8008.pdf PDF
Amendment 0007 Spec Section 01 35 26.00 08.pdf PDF
Amendment 0007 Spec Section 01 32 33.pdf PDF
Amendment 0007 Spec Section 03 30 53.00 08.pdf PDF
Amendment 0007 Spec Section 01 74 19.00 08.pdf PDF
Amendment 0007 Wage Determination WV20200073 1-24-2020.pdf PDF
Amendment 0007 Spec Section 13 51 00.10 08.pdf PDF
A.03 W911WN20B8008 - Contract and Reference Drawings, Attachment 2.pdf PDF
A.03 Pike Island L&D River Wall Crack Stabilization 2020 Tech Specs Certified Final Documents, Attachment 1.pdf PDF
B.08 W911WN20B8008 (Pike Island Monolith Repairs -Crack Stabilization).pdf PDF
B.04 Wage Determination PA20200002 (July 24, 2020), Attachment 3.pdf PDF
A.02 Pike Island L&D Monolith R33 and R34 River Wall Crack Stabilization Virtual Site Visit, Attachment 4.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pike Island LD, River Wall Crack Stabilization

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 35 00.00 08

SPECIAL PROCEDURES

PART 1 GENERAL

1.1 SUMMARY

1.2 REFERENCES

1.3 SUBMITTALS

1.4 CONTRACTOR RESPONSIBILITIES

1.4.1 General

1.4.2 Licenses and Permits

1.5 DRAWINGS

1.5.1 Contract Drawings

1.5.2 Reference Drawings

1.5.3 Reference Datum

1.6 WORK AREAS AND RESTRICTIONS

1.6.1 Work Areas

1.6.2 Hauling Materials and Equipment

1.6.2.1 General

1.6.2.2 Hauling Permits

1.6.3 Laydown, Storage and Parking Areas

1.6.4 Access to Project Site

1.6.5 Utilities

1.6.6 Other Contractors

1.7 FEDERAL HOLIDAYS

1.8 EXISTING SURVEY CONTROLS

1.8.1 Project Alignment

1.9 CONTRACTOR'S FLOATING PLANT

1.9.1 General

1.9.2 Equipment Requirements

1.9.3 Signal Lights and Markers

1.9.4 Maintenance of Floating Plant

1.9.5 Mooring of Floating Plant

1.9.6 Suspension of River Traffic and Construction

1.9.6.1 Withdrawal of Equipment and Floating Plant

1.9.6.2 Plan of Action, Withdrawal of Equipment and Floating Plant

1.9.6.3 Compensation and Extension of Contract Period, Suspension of Work

1.9.7 Operation of Small Water Craft

1.10 RESTRICTIONS TO RIVER TRAFFIC FOR CONSTRUCTION

1.10.1 General

1.10.2 Closure of Main Lock Chamber

1.10.2.1 Temporary Lock Closures

1.10.3 Requests for Lockage Through Lock Chambers

1.11 DAMAGE TO WORK

1.12 PROTECTION OF UTILITIES

1.13 INSPECTIONS AND ACCEPTANCE OF WORK

1.14 OPERATION OF GOVERNMENT FACILITY

1.14.1 Pike Island Lock and Dam, Hours of Operation

SECTION 01 35 00.00 08 Page 1 CERTIFIED FINAL DOCUMENTS - W911WN20B8008 - Amendment 0001

1.14.2 Contractor's Work Hours

1.14.3 Coordination with Project Operations

1.15 SAFETY AND HEALTH REQUIREMENTS

1.16 POOL LEVELS

1.16.1 Hydrographs

1.17 SCAFFOLDING

PART 2 PRODUCTS

2.1 PRODUCTS AND PARTS OF STANDARD MANUFACTURE

PART 3 EXECUTION

3.1 SEQUENCE OF WORK

3.2 SEQUENCE OF OPERATIONS

3.3 PROTECTION OF EXISTING FACILITIES

3.3.1 Inspection of Protective Measures

3.3.2 Removal of Protective Measures and Clean up

3.4 ANTITERRORISM (AT) AND PROJECT SPECIFIC SECURITY REQUIREMENTS

3.4.1 Access and General Protection/Security Policy and Procedures

3.4.1.1 For Contractors Who Do Not Require Cac, But Require Access

To A Dod Facility Or Installation

3.4.2 Pre- screen candidates using E-Verify Program

3.4.3 Contract for Work on Federal Contracts

3.4.4 Changes in Security Requirements

3.4.5 Identification Of Employees

-- End of Section Table of Contents --

SECTION 01 35 00.00 08 Page 2

SECTION 01 35 00.00 08

SPECIAL PROCEDURES

PART 1 GENERAL

1.1 SUMMARY

This section addresses the general requirements applicable to the performance of the work under this contract. These requirements are in addition to those specified in other sections of the contract.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

U.S. DEPARTMENT OF HOMELAND SECURITY (DHS)

HSPD-12 (2004) Homeland Security Presidential Directive 12: Policy for a Common Identification Standard for Federal Employees and Contractors

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

33 CFR 81 72 COLREGS: Implementing Rules

33 CFR 84 Annex I: Positioning and Technical Details of Lights and Shapes

33 CFR 89 Inland Navigation Rules: Implementing Rules

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

EM 1110-2-1902 (2003) Slope Stability

EM 1110-2-2104 (1992; R 2003) Strength Design for Reinforced - Concrete Hydraulic Structures

EM 1110-2-2105 (1993) Design of Hydraulic Steel Structures

EM 1110-2-2502 (1989) Retaining and Flood Walls

EM 1110-2-2503 (1989) Design of Sheet Pile Cellular Structures Cofferdams & Retaining Structures

EM 1110-2-2504 (1994) Design of Sheet Pile Walls

SECTION 01 35 00.00 08 Page 3

U.S. COAST GUARD (USCG)

COMDTINST M16672.2D (1998) Navigation Rules, International - Inland

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having an "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Propelling Unit Agreement; G, RO

The written agreement between the Contractor and the lessor documenting the requirement for required towboat or propelling unit to be on site within the specified time limit shall be provided to the Contracting Officer or designated representative prior to mobilization of any floating plant to the work site.

Temporary Mooring Facilities; G, RO

The Contractor shall submit any proposed plans for development of temporary moorings to the Contracting Officer or designated representative. Moorings shall be designed in accordance with the requirements herein.

Plan of Action, Withdrawal of Equipment and Floating Plant; G, RO

The Contractor shall prepare and submit a Plan of Action for withdrawal of equipment and floating plant in accordance with paragraph "Plan of Action, Withdrawal of Equipment and Floating Plant."

Small Water Craft Operations Plan; G, RO

The Contractor shall develop and submit a plan for operation of small water craft within the area of the dam.

Traffic Control Plan

The Contractor shall develop and submit a plan for traffic control at the work site.

Local Road Condition Assessment Video; G, RO

Access Plan; G, RO

SD-07 Certificates

Threat Awareness Reporting Program Suspicious Activity Reporting Training

SECTION 01 35 00.00 08 Page 4

1.4 CONTRACTOR RESPONSIBILITIES

1.4.1 General

Responsibilities of the Contractor include, but shall not be limited to, all planning, programming, administration, coordination, and management to ensure that all work is performed in accordance with all laws, regulations, codes or directives. The Contractor shall be responsible for ensuring that the work performed meets or exceeds the requirements of the contract. The Contractor shall perform all related Contractor administrative services necessary to perform the work, such as quality control, contractor financial control, and maintenance of accurate and complete records and files. The Contractor shall also be responsible for establishing and executing programs required to ensure that all work is performed in strict accordance with all health, safety and environmental laws, regulations, codes and directives, to protect the general public, as well as Contractor and Government employees.

1.4.2 Licenses and Permits

The Contractor shall be responsible for complying with all state or local contractor licensing or registration laws and permit requirements. The Contractor shall be responsible for furnishing qualified personnel for work which requires specialized registration or training.

1.5 DRAWINGS

1.5.1 Contract Drawings

The contract drawings provided reflect the work to be performed under this contract. In accordance with Section 00 70 00 CONDITIONS OF THE CONTRACT, DFARS 252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS, the Contractor shall check all drawings immediately upon receipt, and verify the figures, dimensions, and representation of the work. The Contractor shall compare all drawings and verify the figures before laying out the work. Dimensions marked on drawings shall, in general, be followed. Use of scaled measurements shall not be allowed. The Contractor shall promptly notify the Contracting Officer or designated representative of any discrepancies, and shall be responsible for any errors which might have been avoided by complying with this paragraph. Any omissions from the contract drawings, specifications, or incorrect description of details of the work which are manifestly necessary to carry out the intent of the contract drawings and specifications, or which are customarily performed, shall not relieve the Contractor from performing such omitted or incorrectly described details of work, but shall be performed as if fully and correctly set forth and described in the contract drawings and specifications. Unless otherwise noted, dimensions and elevations, and other features shown on contract drawings are generally based on site surveys and measurements, and As-Built drawings. The Government cannot guarantee the accuracy of the dimensions, elevations, and features shown on the contract drawings which are based on the reference drawings, and it shall be the responsibility of the Contractor to verify all elevations and the dimensions shown by measurements in the field, at no additional cost to the Government.

1.5.2 Reference Drawings

The reference drawings included in the folio of contract drawings show original construction conditions of the original construction and the existing facilities and structures shown on the drawings. To the best

SECTION 01 35 00.00 08 Page 5 knowledge of the Government, the reference drawings reflect the original work incorporated into this project, and do not reflect changes or new work since the date of the drawing. Unless otherwise noted, dimensions and elevations, and other features shown on reference drawings are generally based on As-Built conditions. Where known variations in actual construction occur between that shown on the reference drawings and that existing, it will be noted on the drawings or within the specifications, as practical. The Government cannot guarantee the accuracy of the dimensions, elevations, and features shown on the reference drawings, and it shall be the responsibility of the Contractor to verify all elevations and the dimensions shown by measurements in the field, at no additional cost to the Government. The Contracting Officer or designated representative shall be notified of any discrepancies prior to commencing work. It is noted that some of the As-Built conditions reflected by the reference drawings have since been modified. Such modifications to the As-Built conditions are described within the sections of these specifications where applicable.

1.5.3 Reference Datum

Note that the reference drawings are based on Legacy vertical datum, and that the contract drawings are based on NAVD88 vertical datum which is approximately 0.42 feet less than that shown on the reference drawings.

1.6 WORK AREAS AND RESTRICTIONS

1.6.1 Work Areas

The work areas under this contract shall be on and adjacnet to the river lock wall. As required by Section 00 70 00 CONDITIONS OF THECONTRACT , FAR 52.236-10 OPERATIONS AND STORAGE AREAS, all operations of the Contractor shall be confined to areas shown on the drawings required to accomplish the work under this contract and as authorized and approved by the Contracting Officer or designated representative. All work areas shall be coordinated with the Contracting Officer or designated representative prior to commencement of work. The Contractor shall submit an Access Plan for Government operating personnel to the Contracting Officer or designated representative.

1.6.2 Hauling Materials and Equipment

1.6.2.1 General

The Contractor's traffic on roads selected for hauling material to and from the site shall interfere as little as possible with public traffic.

The Contractor shall investigate the adequacy of existing roads and the allowable load limit on these roads. The Contractor shall be responsible for all damage to existing roads and property occasioned by any of his operations. When intending to transport any heavy loads on roadways, the Contractor shall investigate all weight limits for the roads he intends to use and shall secure any required bond(s) from the respective owner(s).

The Contractor shall document the existing condition of the roadways that he will be using, with the owners thereof. In the past, local road condition assessment video recordings of the original roadway conditions have provided satisfactory documentation. Prior to beginning any construction, the Contractor shall videorecord on a format acceptable to the Contracting Officer or designated representative all existing structures including, but not limited to, local roads, public and private property, and any other areas as directed by the Contracting Officer. The owners of such roadways and other property should be present at the time

SECTION 01 35 00.00 08 Page 6 of the documentation. An unedited copy of all video recordings shall be given to the owners and the Contracting Officer or designated representative within 5 calendar days after documentation. All damage to transportation facilities, public or private property, or utilities caused by the Contractor's operations shall be repaired to the satisfaction of the Contracting Officer or designated representative at no additional cost to the Government. Any damage to the roadways, caused by the Contractor's operations, shall be repaired in kind by the Contractor and at his own expense. Roads shall be kept clear of all debris generated by the Contractor's operations. Roads shall be cleaned of any spillage. Upon completion of all work requiring use of the local roads, the roadways shall be restored to their preconstruction condition by cleaning and or reconstruction of damaged drainage facilities, base courses, and pavements as necessary. Repairs shall be made in the same manner as the original construction. No separate payment will be made for maintaining and restoring the condition of the roads, and all costs in connection therewith shall be considered as incidental to performance of the work.

1.6.2.2 Hauling Permits

The Contractor shall be responsible for acquiring all necessary oversized hauling permits and general hauling permits for any equipment or debris transported via roadways, as required. No heavy hauling on public roads will be permitted until all permits and bonds have been obtained as required. All costs associated with securing these permits shall be borne by the Contractor.

1.6.3 Laydown, Storage and Parking Areas

An area at the site, as shown, will be reserved for Contractor parking, field offices, laydown, and storage. Storage areas at the site will be limited to areas identified in the contract and as required for performance of the work under this contract. No other areas will be made available at the project for storage of equipment and materials. Unless otherwise specified, storage will not be permitted on service bridges, bulkheads, decks and similar structures. All such work and storage areas and adjacent facilities shall be protected from damage by the Contractor's operations. Any damage caused by the Contractor's operations shall be repaired to the satisfaction of the Contracting Officer or designated representative at the Contractor's expense. The Contractor's use of such storage areas shall not interfere with operation of the facilities.

Access onto floating plant may be made from the lock walls, but must be closely coordinated with the Contracting Officer. The most direct access to the lock walls may be from the river. The Contractor shall investigate and arrange for all personnel access to the floating plant.

1.6.4 Access to Project Site

The Contractor will be permitted to cross the miter gates to access the Middle Wall and River Wall. Construction loads on the miter gate walkways and grating/planking on the Land, Middle, and River Walls must not exceed 100 pounds per square foot. Larger loads may be acceptable pending the Government's review and approval.

1.6.5 Utilities

Unless otherwise specified, the Government will not make any utilities or services available to the Contractor; and the Contractor shall be

SECTION 01 35 00.00 08 Page 7 responsible for furnishing all utilities and services required for performance of the work under this contract.

1.6.6 Other Contractors

The Contractor is alerted to the fact that other contractors may be employed by the Government or local interests at, or in the vicinity of the site. See also Section 00 73 00 SUPPLEMENTARY CONDITIONS, clause WORK

UNDER OTHER CONTRACTS.

1.7 FEDERAL HOLIDAYS

The ten Federal holidays observed are:

New Year's Day (January 1st) Martin Luther King Day (3rd Monday in January) President's Day (3rd Monday in February) Memorial Day (Last Monday in May) Independence Day (July 4th) Labor Day (1st Monday in September) Columbus Day (2nd Monday in October) Veterans Day (November 11th) Thanksgiving Day (4th Thursday in November) Christmas Day (December 25th)

When one of the above designated holidays falls on a Sunday, the following Monday is observed as a legal holiday. When a legal holiday falls on a Saturday, the preceding Friday is observed as a holiday. Work shall be scheduled around the above listed Federal holidays except as specified herein or as approved by the Contracting Officer or designated representative.

1.8 EXISTING SURVEY CONTROLS

1.8.1 Project Alignment

All new work to be constructed under this contract shall be constructed level, plumb, and accurately from survey control points established by the Contractor as necessary to construct all work within the proper alignment.

The Contractor shall verify the elevations and positions of the Corps of Engineers survey controls before using them to layout the work under this contract, and shall notify the Contracting Officer or designated representative of any discrepancies prior to commencing work.

1.9 CONTRACTOR'S FLOATING PLANT

1.9.1 General

Floating plant, and the operation of such plant, shall comply with the requirements of EM 385-1-1 , Section 19. Floating plant which is not being used in the performance of the work shall be secured in a manner that does not interfere with navigation on the river. Emergency plans for removing or securing floating plant and evacuating personnel in the event of severe weather shall be prepared in accordance with EM 385-1-1 , Section 19.A.03.

The Contractor shall provide personnel as necessary to adjust moorings to provide for fluctuations of pool level. A propelling unit capable of moving the floating plant must be available at all times. If the Contractor chooses to have a leased towboat or propelling unit off-site, the plant must be capable of being on-site within 4-hours notice. The

SECTION 01 35 00.00 08 Page 8 written propelling unit agreement between the Contractor and the lessor documenting this requirement shall be provided to the Contracting Officer or designated representative prior to mobilization of any floating plant.

The agreement shall also include documentation that the propelling unit operator currently possesses a U.S. Coast Guard "Operator of Uninspected Towing Vessels" license. The Contractor shall be fully responsible for selection of floating plant which is suitable for the performance of the work under this contract. Contractor's floating plant shall operate only within the areas of work shown on the drawings, unless such areas are modified with the approval of the Contracting Officer or designated representative.

1.9.2 Equipment Requirements

The Contractor shall select floating plant and towboats and propelling units of a size and capacity suitable for performance of the work under this contract. Towboats and propelling units shall have sufficient horsepower capacity to control the floating plant used, considering the size and draft of the plant, for the expected river velocities and wind conditions. The Contractor shall submit a plan of all floating plant, floating plant based equipment (i.e. cranes, derricks), temporary operating systems (i.e. generators, compressors, welding machines, etc.), and other appurtenant features which he will have present during the contract period. The Contractor shall use sketches, diagrams, and narratives to indicate location of all floating plant-equipment. The Contractor shall use manufacture catalog information or other suitable data to describe the specific equipment to be used. The Contractor shall also indicate the methods and procedures that will be used to deliver materials, supplies and equipment via floating plant.

All floating plants regulated by the United States Coast Guard (USCG) shall have required USCG documentation that is current before being placed in service. A copy shall be posted in a public area aboard the vessel.

All dredges and quarter boats not subject to USCG inspection and certification, or not having a current ABS classification shall be inspected in the working mode annually by a marine surveyor accredited by the National Association of Marine Surveyors (NAMS) or the Society of Accredited Marine Surveyors (SAMS) having at least five years experience in commercial marine plant and equipment.

All other floating plants shall be inspected before being placed in use, and at least annually, by a qualified person in accordance with EM 385-1-1 Section 19, Paragraph A.01

All officers and crew aboard a floating plant shall be in possession of a current, valid USCG license.

1.9.3 Signal Lights and Markers

The Contractor shall display signal lights and conduct his operations in accordance with the General Regulations of the Coast Guard, as set forth in COMDTINST M16672.2D or 33 CFR 81 Appendix A (International) and 33 CFR 84 through 33 CFR 89 (inland) as applicable. The Contractor shall be required to furnish and install all buoys, lights, signs, and other safety devices as required by Coast Guard rules and regulations. All equipment and devices shall be Coast Guard approved.

SECTION 01 35 00.00 08 Page 9

1.9.4 Maintenance of Floating Plant

The Contractor shall maintain all floating plant equipment in good working condition throughout the contract period.

1.9.5 Mooring of Floating Plant

The Contractor shall be responsible for all mooring of floating plant.

When not in use, the Contractor's floating plant shall be securely moored.

The Contractor shall also be solely responsible for providing personnel in order to adjust mooring lines as required by the prevailing river conditions.

In addition to the use of spuds for securing floating plant, the Contractor may construct temporary mooring facilities such as dolphins, pile clusters and dead man anchorages within the main channel for mooring. Any such temporary mooring structures shall be placed no closer than 1,000 feet from the upstream face of the dam, unless otherwise shown on the drawings or approved by the Contracting Officer or designated representative, and shall not adversely obstruct flow. If temporary mooring facilities are located within 1,000 feet of the upstream face of the dam, mooring of the floating plant shall be coordinated with the Lockmaster and approved by the Contracting Officer or designated representative. Temporary mooring within this area shall not be permitted during high water to prevent the floating plant from being swept through the dam.

Design loads, "hydraulic" design factors, criteria and standards used for development of temporary mooring structures, as a minimum, shall be in accordance with the following Corps of Engineers hydraulic structure design standards:

EM 1110-2-1902 Slope Stability, 31 Oct 03

EM 1110-2-2104 Strength Design for Reinforced - Concrete Hydraulic Structures, 20 Aug 03

EM 1110-2-2105 Design of Hydraulic Steel Structures, Change 1, 31 May 94

EM 1110-2-2502 Retaining and Flood Walls, 29 Sep 89

EM 1110-2-2503 Design of Sheet Pile Cellular Structures Cofferdams & Retaining Structures, 29 Sep 89

EM 1110-2-2504 Design of Sheet Pile Walls, 31 Mar 94

A copy of these "Engineering Manuals" may be obtained at the following website: http://www.usace.army.mil/inet/usace-docs/ .

Additional Corps of Engineers design standards may be applicable dependent on the nature of the mooring structure proposed.

Any proposed temporary mooring facilities developed below Ordinary High Water (OHW) shall comply with the conditions of the Corps of Engineers Nationwide Permit (NWP) No. 33, "Temporary Construction, Access & Dewatering," which is found in Public Notice No. 07-17 dated March 20, 2017 (

SECTION 01 35 00.00 08 Page 10 https://www.lrp.usace.army.mil/Portals/72/docs/regulatory/2017%20Public%20 Notices/PA%20-%20NWP%20March%202017%20PN.pdf?ver=2017-03-22-095215-887 ).

Typical temporary mooring cells, dolphins, or H-piles placed below OHW are within the scope of NWP No. 33. The Contractor is responsible to design temporary mooring facilities that comply with the conditions of the NWP.

Development of plans for any proposed mooring shall be prepared under the direction of, or directly by, a Registered Professional Engineer(s) licensed within the United States. Any required investigations (i.e. soil and rock mechanics, rock depth) shall be the responsibility of the Contractor, and all costs for such investigation shall be borne by the Contractor.

Any temporary moorings constructed by the Contractor shall be completely removed at the completion of the project.

1.9.6 Suspension of River Traffic and Construction

1.9.6.1 Withdrawal of Equipment and Floating Plant

Navigational restrictions require that all river traffic through Pike Island Lock(s) and Dam be suspended when the river level reaches El.

648.3 NAVD88 (lower gauge = 38 feet) El. 650.52 NAVD88 (Upper gauge = 19 feet). Therefore, all work performed from floating plant at the project site shall be suspended when the river level is at this stage. Work from areas not affected by this river stage may continue. The Contractor's floating plant shall be moored away from the dam by the time the river level reaches El. 648.3 / 650.52 NAVD88, and work is suspended. It shall also be the Contractor's responsibility to withdraw any land-based equipment that would be subject to damage by rising river stages at this level from such affected areas, before they are subject to damage. The Contractor shall monitor the prevailing river conditions at the project site, referring to the upstream project river gauge, river forecasts issued by the National Weather Services, and the Corps of Engineers River Forecast System, and shall determine when to withdraw equipment and floating plant. The withdrawal of equipment and floating plant shall ultimately be the Contractor's decision and will not be directed by the Government. It shall be the Contractor's responsibility to determine the time necessary to make a complete and safe withdrawal of equipment and floating plant with due consideration given to the location of mooring area; amount of equipment; size of the floating plant, and capacity of towboats and propelling units to operate safely and efficiently at the expected river velocities. All floating plant and equipment shall remain securely moored during the period when river levels are at or above El.

648.3 / 650.52 NAVD88, and river traffic and work is suspended. The Contractor shall also be responsible for providing personnel during the suspension to adjust mooring lines as required by the prevailing river conditions. The Contractor shall resume all work, and remobilize equipment and floating plant from its moored location when the river level reaches El. 648.3 / 650.52 NAVD88 with a falling condition forecasted.

1.9.6.2 Plan of Action, Withdrawal of Equipment and Floating Plant

The Contractor shall prepare and submit a Plan of Action for withdrawal of equipment and floating plant. The plan shall detail the procedures for withdrawal of equipment and floating plant in the event that suspension of river traffic and work is imminent. The Plan of Action shall include but is not limited to the following information:

SECTION 01 35 00.00 08 Page 11

- Procedure(s) For Monitoring River Conditions Including River Levels, Discharges, And Velocities

- Mooring Location(s)

- Monument River Condition Which Affect Notification Actions

- Monument River Conditions Which Affect Withdraw

- Sequence and Duration of Withdraw

- Procedures for Care of Moored Floating Plant and Equipment

- Monument River Conditions Affecting Remobilization

- Sequence and Duration of Remobilization

The Plan of Action shall include a listing of key Contractor's Points of Contact and telephone numbers. The Plan of Action shall include the withdrawal of any subcontractor's equipment and floating plant. The Contractor's Plan of Action shall be consistent with the applicable requirements for Emergency Planning as described in EM 385-1-1 . All key Contractor personnel including superintendents, foremen, safety officers, and QC personnel shall be given a copy of the Plan of Action and shall be thoroughly familiar with their duties under this plan. Subcontractors shall also be thoroughly familiar with their responsibilities and duties under the plan.

1.9.6.3 Compensation and Extension of Contract Period, Suspension of Work

The withdrawal of floating plant and equipment is considered an incidental condition of work dictated by the nature of the work site. The Contractor's withdrawal of equipment and floating plant shall not be construed as a direction on the part of the Government or Contracting Officer or designated representative, under the provisions of Section

00 70 00 CONDITIONS OF THE CONTRACT, FAR 52.242-14 SUSPENSION OF WORK,

which shall not apply to this work condition. No compensation will be made to the Contractor for withdrawal of this equipment nor will any delay costs be made for the period during which work cannot be accomplished. In accordance with Section 00 70 00 CONDITIONS OF THE CONTRACT, FAR 52.249-10 DEFAULT (FIXED PRICE CONSTRUCTION), the contract period will be extended equitably for the withdrawal of floating plant and equipment.

1.9.7 Operation of Small Water Craft

Operators of small water craft must have a Boating Safety Education Certificate issued for a course approved by the National Association of State Boating Law Administrators (NASBLA). The Contractor shall develop, prepare and submit a small water craft operations plan addressing the operation of small water craft within the "Restricted Area" of the Pike Island Lock(s) and Dam. The plan shall address safe operations of small water craft and shall include; maximum river stages, maximum river flows, horsepower requirements, training, and any other items necessary to address all the hazards associated with navigating in the "Restricted Area" of the dams.

1.10 RESTRICTIONS TO RIVER TRAFFIC FOR CONSTRUCTION

Unless specifically authorized or directed, no interruption of traffic through the lock chambers or their approaches will be permitted. The Contractor will not be given any privileges for priority lockage under the conditions of this contract, unless specifically authorized by the Contracting Officer or designated representative.

SECTION 01 35 00.00 08 Page 12

1.10.1 General

The Contractor's attention is directed to the fact that the lock and dam facility has two lock chambers at Pike Island Lock and Dam. The Land Chamber will not be allowed to be taken out of operation and no interruption of commercial traffic through the chamber or its approaches will be permitted during the performance of this contract, except as specified in paragraph Closure of Main Lock Chamber.

1.10.2 Closure of Main Lock Chamber

1.10.2.1 Temporary Lock Closures

The Government will permit short term closure of the River/Main Chamber for up to 8 hours per day, Monday through Friday, except Federal holidays with the goal being to have the least amount of interruption to the River/Main Chamber. Short term closures will be provided for all work associated with the eight chamber side anchors leading up to concrete placement, anchor installation and stressing, and any work post placement. Short term closures will only be provided during stressing and grouting activities for the twenty eight river side anchors. Up to three short term closures per week can be provided. One long term closures for up to 48 hours will be permitted for placement of concrete for the new concrete cap. Only one 48 hour closure will be permitted to be scheduled in one calendar week, with neither a short term or long term closure occurring during the same week. During these temporary lock closures, the Contractor will be permitted to perform work which requires closure of the River/Main Chamber. At the end of each Temporary Lock Closure, the Contractor shall ensure that the River/Main Chamber is fully operational.

Temporary closures will not be permitted on Federal holidays or the following holiday weekends:

Memorial Day Weekend Fourth of July Labor Day Weekend

The Contractor shall notify the Contracting Officer or designated representative at least 35 calendar days prior to anticipated requirement for temporary lock closures. The Government will review the Contractor's request for the temporary lock closures and will either approve or deny the Contractor's request depending on previously scheduled priority lockages and may provide alternative temporary closure dates.

1.10.3 Requests for Lockage Through Lock Chambers

The Government recognizes that the Contractor may need to lock through the the facility outside of the temporary lock closures, however, these lockages must be fully coordinated with the Lockmaster and kept to an absolute minimum to ensure there are no delays to commercial river traffic. All lockages must be subject to the following:

a. The Government retains the right to determine the order and priority of lockages at the sole discretion of the Lockmaster. The Government reserves the right to supercede and delay any requested lockage for any reason (such as increased commercial river traffic, maintenance, equipment failure, emergencies etc.) at the sole discretion of the Government. The Contractor is advised that these delays will not be subject to Section 00 70 00 CONDITIONS OF THE CONTRACT, FAR 52.233-1 DISPUTES, and shall not be considered as

SECTION 01 35 00.00 08 Page 13 direction from the Contracting Officer or designated representative.

These delays will not result in any additional time extensions or payment of any delay costs, nor shall they be the basis of any claim against the Government.

b. The Contractor is not permitted to use the Land Chamber for staging of equipment. The River Chamber maybe used to stage equipment during the temporary lock closures only.

c. All requests for lockages must be coordinated with the Lockmaster in accordance with the following provisions:

1) Upon approval of an estimated date and estimated time for a proposed lockage, the Contractor must be ready to perform the requested lockage. The Contractor is advised that the Government will not be liable in the event the Chamber is not available at the requested date and time, and that any resulting delay will not be subject to Section 00 70 00 CONDITIONS OF THE CONTRACT, FAR 52.233-1 DISPUTES, and will not result in any additional time extensions or payment of any delay costs, nor shall they be the basis of any claim against the Government.

2) The Contractor must configure his floating plant, work operations and all equipment to allow safe, uninterrupted lockage through the Chamber in such a manner that no delays to the normal lockage time period will be incurred.

3) The Contractor is advised that the request for lockage may be delayed or postponed indefinitely due to unexpected conditions such as high water, lock breakdowns, or unanticipated maintenance demands, etc.

4) Requests for lockages that do not meet these criteria will not be approved. Requests for unscheduled lockages due to anticipated flooding or other emergency will considered on a case by case basis. Lockages or other interference with river traffic due to any situation which endangers human life will be permitted as the circumstances warrant. Movement of floating plant in the approaches to the locks must at all times be fully coordinated with the Lockmaster and Contracting Officer or designated representative, but shall not delay river traffic through the active chamber.

1.11 DAMAGE TO WORK

The responsibility for damage to any part of the permanent work shall be as set forth in Section 00 70 00 CONDITIONS OF THE CONTRACT, FAR 52.236-7 PERMITS AND RESPONSIBILITIES. However, if, in the judgment of the Contracting Officer or designated representative, any part of the permanent work performed by the Contractor is damaged by flood or earthquake, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor shall make the repairs as ordered by the Contracting Officer or designated representative and full compensation for such repairs will be made at the applicable contract unit or lump sum prices as fixed and established in the contract. If, in the opinion of the Contracting Officer or designated representative, there are no contract unit or lump sum prices applicable to any part of such work, an equitable adjustment pursuant to the Section

SECTION 01 35 00.00 08 Page 14

00 70 00 CONDITIONS OF THE CONTRACT, FAR 52.243-4 CHANGES, will be made as full compensation for the repairs of that part of the permanent work for which there are no applicable contract unit or lump sum prices. Except as herein provided, damage to all work (including temporary construction), utilities, materials, equipment and plant shall be repaired to the satisfaction of the Contracting Officer or designated representative at the Contractor's expense, regardless of the cause of such damage.

1.12 PROTECTION OF UTILITIES

Notwithstanding the Section 00 73 00 SUPPLEMENTARY CONDITIONS, paragraph "PROTECTION OF UTILITIES", and Section 00 70 00 CONDITIONS OF THE

CONTRACT, FAR 52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES,

EQUIPMENT, UTILITIES, AND IMPROVEMENTS, the Contractor shall locate and clearly identify all underground and above ground utility lines, wires, cables, pipes, poles, support lines, and culverts, within the Contractor's work area. The Contractor shall contact the West Virginia Miss Utility at telephone (800) 245-4848 at least three days prior to beginning any Construction activity. The Contractor shall be responsible for any costs for the Miss Utility System. The Contractor shall conduct his operations such that the utilities are not damaged or disturbed. Any damage to utilities caused by the Contractor's actions shall be repaired by him at no additional expense to the Government. The Contractor shall store materials and equipment in a manner that does not interfere with utility company services or utility company access to the facilities. The Contractor shall relocate any equipment or stockpiles, at no additional cost to the Government, that interfere with utility company operations, emergency repairs, or standard maintenance services.

1.13 INSPECTIONS AND ACCEPTANCE OF WORK

Not withstanding other provisions of this contract, all materials and work to be performed under this contract shall be inspected and accepted by the Contracting Officer or designated representative . Inspections and acceptance will be performed on phases of the work, before the next definable sequential phase of work commences, OR may be performed at the completion of all of the work, as determined appropriate by the Contracting Officer or designated representative. The Contracting Officer or designated representative shall be the individual(s) solely authorized to reject materials, disapprove or approve any work in progress, or order or direct any revision or change to the plans and specifications as presently shown and stated.

1.14 OPERATION OF GOVERNMENT FACILITY

The Pike Island Lock and Dam facility shall remain in operation at all times. The Contractor shall perform his work in a manner which will not interfere with the operation of the facilities and the duties of Government personnel. Particular care shall be taken during all operations under this contract to prevent damage to any operating equipment or facilities at the project. The Contractor shall take all necessary precautions to ensure the safety of the workers in accordance with the applicable provisions of EM 385-1-1 . Contractor operations shall be performed in such a manner to ensure that project personnel, navigation industry personnel and the public are protected at all times.

1.14.1 Pike Island Lock and Dam, Hours of Operation

Pike Island Lock and Dam operates 24 hours per day.

SECTION 01 35 00.00 08 Page 15

1.14.2 Contractor's Work Hours

Contractor's work hours shall be restricted to 8:00 AM to 4:30 PM, Monday through Friday, or as otherwise approved by the Contracting Officer or designated representative. The contractor shall coordinate with the Contracting Officer or designated representative to make sure Government personnel are present during major features of work.

1.14.3 Coordination with Project Operations

The Contractor shall perform all work in a manner that will not interfere with the duties of the Government operations personnel. Particular care shall be taken during all operations under this contract to prevent damage to any operating equipment or facilities at the project. The Contractor shall continuously maintain safe access to all areas of the project for operating personnel, during every phase of the work, unless otherwise directed by the Contracting Officer or designated representative.

1.15 SAFETY AND HEALTH REQUIREMENTS

Safety and Health Requirements shall conform to Section 01 35 26.00 08 GOVERNMENTAL SAFETY REQUIREMENTS, EM 385-1-1 , and the requirements of the Occupational Safety and Health Administration. Where provisions of EM 385-1-1 vary with OSHA requirements, the more stringent requirements shall be applied.

1.16 POOL LEVELS

The target pool level of upstream of the Dam is El. 643.3 NAVD88 (gage reading = 11.8 feet). The target pool level downstream of the dams is El.

622.3 NAVD88 (gage reading = 11.7 feet). The Contractor shall refer to the DISCHARGE-DURATION and STAGE-DISCHARGE curves presented in the drawings for determining the percentage of time for which this river level is equaled or exceeded.

1.16.1 Hydrographs

The river hydrograpsh and stage duration curves are given on the drawings for the upper and lower pool conditions. The duration for particular pool stages can be determined by obtaining the relevant pool stage for that pool.

1.17 SCAFFOLDING

The Contractor shall furnish, erect, maintain, and finally remove all necessary scaffolding required for the performance of the work under this contract. Scaffolding shall be erected and maintained in accordance with the scaffolding requirements of EM 385-1-1 . Necessary safety equipment and apparatus shall be provided to adequately protect all personnel employed by the Contractor against the hazards of falling and drowning and any other hazards encountered during the prosecution of the work. The scaffolding shall be adequate to permit proper performance of the work and permit inspection by Government inspectors. Scaffolding shall not be removed, except as directed, until the work has been inspected by the Contracting Officer or designated representative.

SECTION 01 35 00.00 08 Page 16

PART 2 PRODUCTS

2.1 PRODUCTS AND PARTS OF STANDARD MANUFACTURE

All materials, supplies and articles furnished so as to be incorporated into the work under this contract shall, whenever so specified and otherwise practicable, be standard products of recognized reputable manufacturers. Standard products of manufacturers other than those specified will be accepted when it is proven to the satisfaction of the Contracting Officer or designated representative, in accordance with the Section 00 70 00 CONDITIONS OF THE CONTRACT CLAUSES, FAR 52.236-5 MATERIAL AND WORKMANSHIP, that they are equal in performance, strength, durability, usefulness and convenience for the purpose intended. Any changes required in the details and dimensions shown on the drawings as a result of the substitution of standard products, other than those provided for, shall be properly made as approved by the Contracting Officer or designated representative, and at the expense of the Contractor. All products specified by "similar or equal to" a particular brand name are for descriptive purposes only and are not to imply that the product is available from only that source.

PART 3 EXECUTION

3.1 SEQUENCE OF WORK

The work shall be prosecuted in such order of precedence as best suits the Contractor's construction schedule and the following restrictions. The Contractor shall perform the work in a diligent, effective manner, and shall schedule his operations in such a manner that the work is completed on time. In accordance with contained in Section 00 70 00 CONDITIONS OF THE CONTRACT, FAR 52.211-12 LIQUIDATED DAMAGES - CONSTRUCTION, the Contractor will be assessed the daily monetary damages for failure to complete the work in the allotted contract period.

3.2 SEQUENCE OF OPERATIONS

Subject to the provisions of paragraph entitled Work Under Other Contracts of this section, and to such limitations as may be imposed by other agencies during the removal, relocation, adjustment and reconstruction of their facilities on the banks and in the channel , the work shall be prosecuted in such order of precedence as best suits the Contractor's Construction Schedule. For the information of the Contractor in preparing his schedule of construction operations, tentative information furnished the Government by local agencies indicates that work schedules for the relocation, adjustment and reconstruction of utilities and removal of miscellaneous structures will be as described within the Technical Provisions of these specifications. The owning agencies have assured the Government that they will coordinate and complete the adjustment of their facilities to the end that interference with the contract work will be held to a minimum.

3.3 PROTECTION OF EXISTING FACILITIES

Prior to the start of construction operations, the Contractor shall provide protection for the existing structures, equipment and other facilities so that no dust, debris, or other contaminants shall come into contact with the these items. All such protection shall be capable of being quickly removed in the event emergency operation of the equipment or facility is required. This protection shall be as set forth below.

SECTION 01 35 00.00 08 Page 17

Polyethylene sheeting shall not be placed over floor openings or other vertical openings unless adequate protection is provided to prevent falls through the openings.

3.3.1 Inspection of Protective Measures

Prior to installation of protection measures, the Contractor and the Contracting Officer or designated representative shall inspect each item to determine existing conditions. Protective coverings on equipment will be inspected and must have the approval of the Contracting Officer or designated representative prior to start of the construction operations.

All protective coverings shall be inspected daily or more frequently when conditions require, and any damaged coverings shall be repaired or replaced. No construction operations will be permitted without the protection in place. The Contractor and the Contracting Officer or designated representative shall inspect each item being protected upon completion of all work on the affected gate and removal of the protection. Any damage caused by inadequate protection shall be repaired to the satisfaction of the Contracting Officer or designated representative at the Contractor's expense.

3.3.2 Removal of Protective Measures and Clean up

Upon completion of all work for which protection is provided, the Contractor shall remove the protection, inspect the items being protected, and clean up as required to return the items to their original condition prior to the construction operations.

3.4 ANTITERRORISM (AT) AND PROJECT SPECIFIC SECURITY REQUIREMENTS

This paragraph contains information for security requirements for work on Government Property. The purpose of these security requirements it to ensure that all Contractor or subcontractor employees working on this contract have received proper clearance for access to the Government property. Identification of Critical Infrastructure and submission of required employee information will be discussed at the Preconstruction Meeting. Required employee information shall be submitted to the Resident Engineer and Pittsburgh Office of Security and Law Enforcement, as applicable, at l east 15 cal endar days pr i or t o r equi r ed empl oyee access t o t he pr oj ect .

3.4.1 Access and General Protection/Security Policy and Procedures

The Contractor and all associated subcontractors' employees shall comply with applicable installation, facility, and area commander installation and facility access and local security policies and procedures (provided by the Government Representative). The Contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the installation the USACE Security Office. The Contractor workforce must comply with all personal identity verification requirements as directed by DoD, HQDA, and/or local policy.

In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes. The Contractor must submit the full name, Social Security Number (a valid state driver's license number with state of issue maybe used instead of a SSN), Date of Birth, Place of Birth, and Citizenship for all associated contractor or subcontractor employees to the USACE Security Office, Stephen Davidson, SECTION 01 35 00.00 08 Page 18

412-395-7504, stephen.davidson@usace.army.mil, or Fax at 412-395-7504, all background check requests must include the contract number, USACE Contracting Officer or designated representative and USACE project name or location. The District retains the right to deny any contractor and subcontractor employee from working on one of its contracts based on final background investigation results.

3.4.1.1 For Contractors Who Do Not Require Cac, But Require Access To A Dod Facility Or Installation

Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using…