ATTACHMENT 18 - Contractors Price Schedule Worksheet.xlsx
XLSX spreadsheet 20 KB Posted
- Attached to
- Fort Leonard Wood MATOC IDIQ
- Solicitation number
- W911S7-23-R-0001
About this file
This document contains a contractor's price schedule worksheet template for a multiple award task order contract (MATOC) opportunity with the Department of the Army Materiel Command Mission and Installation Contracting Command Fort Eustis. The price schedule worksheet template includes line items for general requirements, existing conditions, concrete, masonry, metals, wood and composites, thermal and moisture protection, openings, finishes, specialties, equipment, furnishings, special construction, conveying equipment, fire suppression, plumbing, HVAC, integration and automation, electrical, communications, electronic safety and security, earthwork, exterior improvements, utilities, transportation, waterway and marine construction, process interconnections, material processing and handling equipment, process heating cooling and drying equipment, process gas and liquid handling purification and storage equipment, pollution control equipment, water and wastewater equipment, and electric power generation. Pricing includes labor, equipment, material, labor burden, overhead, profit, and performance and payment bonds.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Contractor's Price Schedule Worksheet | Contractor: | Date Prepared: | ||||
| Name and Title of Person Authorized to Sign for Offeror: | Sheet #: | |||||
| Project: | ||||||
| Location: | Fort Leonard Wood | No. of Sheets: | ||||
| RFTOP #: | Signature: | |||||
| Division Summary | Labor | Equipment | Material | Total | ||
| Man Hours | Cost | |||||
| 01 - General Requirements | ||||||
| 02 - Existing Conditions | ||||||
| 03 - Concrete | ||||||
| 04 - Masonry | ||||||
| 05 - Metals | ||||||
| 06 - Wood, Plastics, and Composites | ||||||
| 07 - Thermal and Moisture Protection | ||||||
| 08 - Openings | ||||||
| 09 - Finishes | ||||||
| 10 - Specialties | ||||||
| 11 - Equipment | ||||||
| 12 - Furnishings | ||||||
| 13 - Special Construction | ||||||
| 14 - Conveying Equipment | ||||||
| 21 - Fire Suppression | ||||||
| 22 - Plumbing | ||||||
| 23 - Heating, Ventilating, and Air-Conditioning (HVAC) | ||||||
| 25 - Integration Automation | ||||||
| 26 - Electrical | ||||||
| 27 - Communications | ||||||
| 28 - Electronic Safety and Security | ||||||
| 31 - Earthwork | ||||||
| 32 - Exterior Improvements | ||||||
| 33 - Utilities | ||||||
| 34 - Transportation | ||||||
| 35 - Waterway and Marine Construction | ||||||
| 40 - Process Interconnections | ||||||
| 41 - Material Processing and Handling Equipment | ||||||
| 42 - Process Heating, Cooling, and Drying Equipment | ||||||
| 43 - Process Gas and Liquid Handlings, Purification and Storage Equipment | ||||||
| 44 - Pollution Control Equipment | ||||||
| 46 - Water and Wastewater Equipment | ||||||
| 48 - Electric Power Generation |
| Subtotal: |
| Labor Burden: |
| Subtotal: |
| Overhead: |
| Profit: |
| Subtotal: |
| Performance and Payment Bonds: |
Total Price: