This document contains a contractor's price schedule worksheet template for construction projects at Fort Leonard Wood. The template includes line items for labor, equipment, materials, and pricing by division for general requirements, concrete, masonry, metals, wood and composites, thermal and moisture protection, openings, finishes, specialties, equipment, furnishings, special construction, conveying equipment, fire suppression, plumbing, HVAC, electrical, communications, electronic safety and security, earthwork, exterior improvements, utilities, transportation, waterway and marine construction, process interconnections, material processing and handling equipment, process heating and cooling, and pollution control equipment. Contractors would populate this template with their pricing details when responding to the related federal contract opportunity.

The related federal contract opportunity is a solicitation from the Department of the Army Materiel Command Mission and Installation Contracting Command Fort Eustis for an indefinite-delivery/indefinite-quantity multiple-award task order contract for construction projects at Fort Leonard Wood. The solicitation number is W911S7-23-R-0001 and responses are due by the date specified in the solicitation. Awards will be made to multiple contractors to perform work on task orders issued against the contract over the subsequent years.

View the file

Other files

File Type Posted
W911S723R0001 Amendment 0004.pdf PDF
ATTACHMENT 18 - Contractors Price Schedule Worksheet.xlsx XLSX spreadsheet
W911S723R0001 Amendment 0003.pdf PDF
ATTACHMENT 3 - Davis-Bacon Act WD MO20230019 13 October 2023.pdf PDF
ATTACHMENT 4 - RFTOP Letter.pdf PDF
ATTACHMENT 20 Q and A - W911S7-23-R-0001.pdf PDF
ATTACHMENT 2 - Davis-Bacon Act WD MO20230005 13 October 2023.pdf PDF
W911S7-22-R-0001 Amendment 0002.pdf PDF
ATTACHMENT 19 - Davis-Bacon Act WD MO20230001 13 October 2023.pdf PDF
W911S7-23-R-0001 Amendment 00001.pdf PDF
ATTACHMENT 4 - RFTOP Letter.docx DOCX document
ATTACHMENT 10 - 8457_a4-DETAILS.pdf PDF
ATTACHMENT 15 - 8457_E3.pdf PDF
ATTACHMENT 16 - 8457_m-M1.pdf PDF
ATTACHMENT 8 - 8457_a2-FLOOR PLAN.pdf PDF
ATTACHMENT 7 - DEMOLITION PLAN.pdf PDF
ATTACHMENT 1 - FLW MATOC SOW.pdf PDF
ATTACHMENT 3 - MO20230005 14 July 2023.pdf PDF
ATTACHMENT 5 - Combined Specifications Kitchen 580.pdf PDF
ATTACHMENT 2 - Davis-Bacon Act WD MO20230005 8 September 2023.pdf PDF
ATTACHMENT 13 - 8457_E1.pdf PDF
W911S7-23-R-0001 MATOC Solicitation - 13 Aug 2023.pdf PDF
ATTACHMENT 11 - 8457_a5-ELEVATIONS.pdf PDF
ATTACHMENT 6 - 8457_a0-TEMPORARY KITCHEN.pdf PDF
ATTACHMENT 14 - 8457_E2.pdf PDF
ATTACHMENT 12 - 8457_a6-ELEVATIONS (2).pdf PDF
ATTACHMENT 17 - 8457_m-M2.pdf PDF
ATTACHMENT 9 - 8457_a3-REFLECTED CEILING PLAN.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Contractor's Price Schedule WorksheetContractor:Date Prepared:
Name and Title of Person Authorized to Sign for Offeror:Sheet #:
Project:
Location:Fort Leonard WoodNo. of Sheets:
RFTOP #:Signature:
Division SummaryLaborEquipmentMaterialTotal
Man HoursCost
01 - General Requirements (Do not use, calculate below)
02 - Existing Conditions (Do not use, calculate below)
03 - Concrete
04 - Masonry
05 - Metals
06 - Wood, Plastics, and Composites
07 - Thermal and Moisture Protection
08 - Openings
09 - Finishes
10 - Specialties
11 - Equipment
12 - Furnishings
13 - Special Construction
14 - Conveying Equipment
21 - Fire Suppression
22 - Plumbing
23 - Heating, Ventilating, and Air-Conditioning (HVAC)
25 - Integration Automation
26 - Electrical
27 - Communications
28 - Electronic Safety and Security
31 - Earthwork
32 - Exterior Improvements
33 - Utilities
34 - Transportation
35 - Waterway and Marine Construction
40 - Process Interconnections
41 - Material Processing and Handling Equipment
42 - Process Heating, Cooling, and Drying Equipment
43 - Process Gas and Liquid Handlings, Purification and Storage Equipment
44 - Pollution Control Equipment
46 - Water and Wastewater Equipment
48 - Electric Power Generation
Subtotal:
Labor Burden:
Subtotal:
Overhead:
Profit:
Subtotal:
Performance and Payment Bonds:

Total Price: