L1_RFP_Question_Comment_Form_OneSAF_Amendment0003.pdf

PDF 194 KB Posted

Attached to
One Semi-Automated Forces - Award Notice Federal contract opportunity
Solicitation number
W900KK-18-R-0010
Issued by
Department of the Army Materiel Command Contracting Command Orlando Contracting Center

About this file

Responses to questions asked by Contractors

View the file

Other files for this federal contract opportunity

Other files attached to One Semi-Automated Forces - Award Notice, newest first.
File Type Posted
W900KK-18-R-0010.amendment0004.conformed.pdf PDF
1_RFP_Question_Comment_Form_OneSAF_Amendment0004.pdf PDF
Attachment_L3_-_Cost_Price_Workbook(v3).xlsx XLSX spreadsheet
W900KK-18-R-0010.amendment0004.mod.pdf PDF
W900KK-18-R-0010.modification_amend.0003.pdf PDF
W900KK-18-R-0010.conformed_amend.0003.docx.pdf PDF
L1_RFP_Question_Comment_Form_OneSAF_Amendment_0002.pdf PDF
Attachment_L3_-_Cost_Price_Workbook(update).xlsx XLSX spreadsheet
W900KK-18-R-0010.modification(amend2).pdf PDF
W900KK-18-R-0010.conform(amend2).pdf PDF
L1_RFP_Question_Answer_OneSAF.pdf PDF
L1_Amendment.01_Question_Answer_OneSAF.pdf PDF
W900KK-18-R-0010_Amendment.01_Modification.pdf PDF
W900KK-18-R-0010_Amendment.01_Conformed.pdf PDF
2_OneSAF_PWS_4Dec2017_TO_0001.pdf PDF
Amendment_01_Letter.pdf PDF
Attachment_L3_-_Cost_Price_Workbook.xlsx XLSX spreadsheet
Exhibit_A_CDRLs-Corrected.pdf PDF
3_OneSAF_PWS_TO_0002.pdf PDF
L5_OneSAF_WBS_Recompete.xlsx XLSX spreadsheet
8_OneSAF_GFE_Listing.xlsx XLSX spreadsheet
L1_RFP_Question_Comment_Form.xlsx XLSX spreadsheet
4_OneSAF_QASP.pdf PDF
7_OneSAF_V9.0_UseCases.pdf PDF
L2_OneSAF_DISTRIBUTION_AGREEMENT_for_USG_and_DOD_Cntr_only_-_20170927.pdf PDF
Exhibit_B_DSL.pdf PDF
L3_OneSAF_Contract_Price_Workbook.xlsx XLSX spreadsheet
6_OneSAF_9__Memo.pdf PDF
W900KK-18-R-0010.Final.pdf PDF
L8_Proposal_Receipt_Form.pdf PDF
L6_PastPerformance_Questionnaire.pdf PDF
L4_Pre_award_Survey_of_Prospective_Offeror_Accounting_System.pdf PDF
L7_Past_Performance_POC_List.xlsx XLSX spreadsheet
2_OneSAF_PWS_TO_0001.pdf PDF
1_OneSAF_PWS_IDIQ.pdf PDF
Exhibit_A_CDRLs_.pdf PDF
9_Key_Personnel.pdf PDF
5_W900KK-18-R-0010_OneSAF_DD254.pdf PDF
Draft_OneSAF_WBS_Recompete_25Sep2017.pdf PDF
Draft_OneSAF_V9.0_UseCases.pdf PDF
OneSAF_Access_Request.pdf PDF
OneSAF_DISTRIBUTION_AGREEMENT_for_USG_and_DOD_Cntr_only_-_20170927.pdf PDF
Draft_OneSAF_PWS_21June2017_IDIQ.pdf PDF
Draft_OneSAF_9__Memo.pdf PDF
Draft_OneSAF_PWS_21June2017_TO_0001.pdf PDF
Draft_OneSAF_PWS_21June2017_TO_0002.pdf PDF
Show all 46

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question and Answer Form

W900KK-18-R-0010 - One Semi-Automated Forces Amendment 0003

Relates to:

(RFP or Att

#/Sect#/Page #)

Question/Comment Government Response

Amendment 1 RFP/Section

F/45

Amendment 1 RFP/Section

L.1.17/Figure 1/110

Section F (p 45) of the amended solicitation provides a Period of

Performance (PoP) for CLIN 1304 (Integration, Test and Release) of 16 months (15 OCT 19 to 14 FEB 21). Considering Figure 1 in Section L.1.17

(p 110) indicates that the corresponding base year CLIN should have a

PoP of 4 months, we understand that this may be an error and that CLIN

1304's PoP should be 15 OCT 19 to 14 FEB 20. Will the Government please confirm this understanding?

Figure 1 in Section L.1.17 (p 110) indicates the correct PoP for CLIN 1304. The PoP in Section F

(p 45) will be updated to reflect 15 OCT 19 to 14

FEB 20

Amendment 1 RFP/Section

F/48

Amendment 1 RFP/Section

L.1.17/Figure 1/110

The Section F PoPs for CLINs 5801-5804 do not conform to the dates in

Section L.1.17's Figure 1. Currently, Section F indicates that the

Government intends for Offerors to develop, integrate, test and release the features in Task Order 8 (OY5) within a compressed 12-month timeframe, while Figure 1 indicates that the Offeror should start developing those features in the middle of the development cycle for

Task Order 7 (OY4). We understand that to begin developing the next iteration of features before the current features in development have been tested, integrated and released to be contrary to industry best practice. Therefore we understand the Government's intent is to develop a more limited scope of features within the compressed 12-month development cycle for Task Order 8 (OY5). Will the Government please confirm this understanding?

Figure 1 in Section L.1.17 (p 110) indicates the correct PoP for Task Order 8 (16 months). The intent of the Government is to award Task Order

8 and have an overlap with Task Order 7.

With respect to the limited scope, reference

Section M.3.5.2 (Amendment 2 of RFP, p 145) -

"TO 02 shares similar scope with TOs: 03, 04, 06, 07 and 08 and shall be priced accordingly". Based on this, the Offeror cannot assume that Task

Order 8 will have a more limited scope of features.

Amendment 1 RFP/Section

F/48

Amendment 1 RFP/Section

L.1.17/Figure 1/110

Section F (p 48) of the amended solicitation provides a PoP for CLIN 5804

(Integration, Test and Release) of 12 months (15 OCT 23 to 14 OCT 24).

Considering not only that Figure 1 in Section L.1.17 (p 110) indicates that the corresponding base year CLIN should have a PoP of 4 months but also that the PoP for CLIN 5804 would run concurrently with its preceding

CLIN (4704 - 15 OCT 23 to 14 FEB 24), we understand that this may be an error and that the PoP for CLIN 5804 should be 15 JUN 24 to 14 OCT 24 to account for the compressed development cycle in OY5. Will the

Government please confirm this understanding?

The PoP in Section F for CLIN 5804 (p 48) has been corrected and posted in amendment 2 of the solicitation. (Posted on 14 Dec 2017)

Relates to:

(RFP or Att

#/Sect#/Page #)

Question/Comment Government Response

Amendment 1 RFP/Section

F/45

Section F (p 45) of the amended solicitation provides a PoP for CLIN 2104

(1 Week Training Sessions) of 24 months (15 OCT 20 to 14 OCT 22).

Considering that this CLIN would run concurrently with its successor CLIN

(3504 - 15 OCT 21 to 14 OCT 22), we understand that this may be an error and that the PoP for CLIN 2104 should be 15 OCT 20 to 14 OCT 21. Will the Government please confirm this understanding?

The PoP in Section F (p 45) of the amended solicitation for CLIN 2104 (1 week Training

Session) of 24 months is a typographical error.

The RFP will be updated with the correct PoP of

15-OCT 2020 TO 14-OCT-2021

5 Previous questions

The questions posed in this document prevent Offerors from finalizing

Work Breakdown Structure, labor skill mixes, and pricing details without making critical assumptions. These details must, in turn, be shared with an Offeror's partners. Considering not only the delays that these clarifications have caused but also the extended holiday, we respectfully submit that maintaining the current due date poses an undue burden to

Offerors and their partners. We also believe that this time burden will increase the probability that all proposals will contain errors that may require ENs, thereby delaying evaluation. Will the Government please consider providing a 2-week extension to the proposal due date?

The POP has been extended to 12 January 2018.

The Integrated Product Team believes that this extension reflects the proper amount of time required to present an accurate proposal.

Relates to:

(RFP or Att

#/Sect#/Page #)

Question/Comment Government Response

Based on the most recent Q&A received for the subject solicitation, there is still some ambiguity on the requirements for subcontractors with a proposal valued at less than the $5M threshold. We have a clear understanding that all subcontractors are required to provided the completed Attachment L3- Cost Price Workbook, however there's still a misunderstanding regarding section L.9.9 (c- Indirect Rates) of the solicitation. Company X submitted a question regarding both section L.9.9

(c) & (d), however the Government's response only addressed section

L.9.9 (d). Based on the Government's response to section L.9.9 (d), we feel that it's the Government's intent that the indirect rate information in section L.9.9 (c) is also not applicable to subcontractor's with a proposed value of less than $5M. Is it possible for the Government to confirm this position within the next 24hrs so that we can provide this guidance to our subcontractors?

L.9.9.c states;

"Offerors will identify the start and end of their fiscal year and the allocation/application base for each indirect rate. Offerors will provide historical actuals for the most recent three years, 2015, 2016 and YTD 2017 (base, pool and calculated rate). Offerors will state whether or not the prior years' actuals have been audited by DCAA. Offeror will submit forecasted rates for each fiscal year covered in the solicitation (base, pool and calculated rate). If the Offeror does not have a budget or detailed forecast for all fiscal years covered in the solicitation, only the calculated rate information will be required for those fiscal years. Offeror will submit actual sales for each of the last three years, 2015, 2016 and YTD

2017. Offeror will submit forecasted sales (for the current fiscal year-end and each fiscal year covered by this solicitation). Offerors shall consider the effect of winning this award when forecasting rates and sales. The identified indirect rate information will be submitted for both the Offeror and all subcontractors."

This means that all subcontractors will have to provide the supporting documentation for their indirect rates and labor rates as requested in section L.9.9.c. This subcontractor proprietary data should be submitted separately from the primes proposal.

Section L.9.8, second paragraph states;

"For subcontractors that exceed $5 million, subcontractor proposals shall be submitted in the same level of detail as the prime proposal, to include labor build- up, indirect rate information and material/other direct costs compositions, when required. If the subcontractor's proposal contains company proprietary data, the subcontractor can elect to provide a "redacted" proposal copy to the Offeror and submit their FAR 15.404 compliant proposal directly to the POCs identified in L.1.4 and L.1.5 of this solicitation."

This means that if the subcontractor's contribution to the work is under $5M they are not required to submit a complete proposal with the same level of detail as the prime proposal, just the requested information as requested in section L.9.9.c.

File details come from the government source that posted it.