This document contains a question and answer session and draft solicitation for healthcare housekeeping services at Brooke Army Medical Center. The solicitation seeks proposals for indefinite delivery, indefinite quantity contracts to provide housekeeping, waste management, linen services, and exterior building services at the medical center facilities totaling 2.4 million square feet. Services will be required starting December 1, 2019 through November 30, 2024. An amendment to incorporate a new collective bargaining agreement will be issued during discussions, but the response deadline of February 21, 2020 will remain unchanged. Comments on the draft performance work statement are due by November 30, 2018 and should be directed to the contracting officer or contract specialist.

View the file

Other files

File Type Posted
Questions and Answer Document - 7 February 2020.pdf PDF
Attachment 3 (BAMC Healthcare Houskeeping Services)- Price Matrix Revision 1 Dated 6 Feb 2020.xlsx XLSX spreadsheet
W81K04-19-R-0003 0006 (Conformed Copy - 7 February 2020).pdf PDF
W81K04-19-R-0003 0006 (7 February 2020).pdf PDF
W81K04-19-R-0003 (Conformed Copy-8 January 2020).pdf PDF
W81K04-19-R-0003 0005 (8 January 2020).pdf PDF
W81K04-19-R-0003 0004 (8 January 2020).pdf PDF
REVISION_1-Exhibit_C-Summary_of_Cleanablable_SF-5_Jun_19.xls XLS spreadsheet
Attachment_5-Question_and_Answer_Document-14_Jun_19.xlsx XLSX spreadsheet
W81K04-19-R-0003_Amendment_0003-14_Jun_19.pdf PDF
REDCACTED_BAMC_protest_with_Exhibits_(fin)_-_REDCATED.pdf PDF
Pre-Proposal_Conference_Slides-BAMC-10_May_19.pdf PDF
Government_Sign-in_Sheet_10_May_2019.pdf PDF
Pre-Proposal_Conference_Questions_and_Answers_-_10_-_11_May_2019.pdf PDF
Pre-proposal_Site_Visit_Minutes_10_-_11_May_2019.pdf PDF
Government_Sign-In_Sheet_11_May_2019.pdf PDF
Pre-Proposal_Site_Visit_Facility_Tour-10_11_May_19.pdf PDF
Pre-Proposal_Conference_and_Site_Visit_Ctr_Sign-In_List-10_May_19.pdf PDF
Pre-Proposal_Conference_and_Site_Visit_Ctr_Sign-In_List-11_May_19.pdf PDF
W81K04-19-R-0003__Amendment_0002-17_May_19.pdf PDF
Exhibit_D_-_Total_SQ_FT_by_Type,_Revision_2_dated_16_May_2019.xls XLS spreadsheet
Exhibit_D_-_Total_SQ_FT_by_Type,_Revision_1_dated_9_May_2019.xls XLS spreadsheet
W81K04-19-R-0003-Amendment_0001-_9_May_19.pdf PDF
Exhibit_L_Control_Access_Room_Area_Identification.xlsx XLSX spreadsheet
Exhibit_D_Total_SQ_Ft_by_Types__19_Feb_19.xls XLS spreadsheet
Exhibit_C_Summary_of_Cleanable_SQ_FT_01_Feb_19.xls XLS spreadsheet
W81K04-19-R-0003_(Official_Released-8_May_19).pdf PDF
Attachment_7-Mission_Essential.pdf PDF
Exhibit_F_Linen_Distribution_Pickup_Locations_(New-Revised)_17_April_19.docx DOCX document
Exhibit_K_Asbestos_Locations.pdf PDF
Exhibit_J_CBA_01_Feb_2019.pdf PDF
Attachment_3-Price_Matrix-24_Apr_19.xlsx XLSX spreadsheet
Attachment_8-Checklist_for_Reviewing_Subk_Plans.doc DOC document
DRAFT_Attachment_7_-_Mission_Essential.pdf PDF
DRAFT_Attachment_3_-_Price_Matrix_-_.xls XLS spreadsheet
DRAFT_Exhibit_F_-_Linen_Distribution.docx DOCX document
DRAFT_Exhibit_C_and_D_-_Summary_of_Buiding_and_Detail_of_Buildings.xls XLS spreadsheet
DRAFT__Attachment_4_-_Staffing_Chart_(1).docx DOCX document
DRAFT_Exhibit_K_Asbestos_Locations_14_Dec_17.pdf PDF
DRAFT_-_W81K04-19-R-0003_SAMMC_Solicitation.docx DOCX document
DRAFT_Exhibit_J_-_Collective_Bargaining_Agreement.pdf PDF
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page and Paragraph

Offeror’s Questions
Governments Response
Section B, 0027 Phase-In
With the awarding of an incumbent extension that currently overlaps with the Phase-In date shown in Section B, is it the intention of the Government to issue an updated Section B?
Depending on the actual date of award, the Phase-In dates may change. Accordingly, the extension would be adjusted accordingly.
A new CBA agreement went into effect on 1 February 2020, but is not included in the re-compete, solicitation, W81K04-19-R-0003. Do you plan to incorporate with Amendment 007, or should we base pricing on Addendum A with rates effective 1 October 2018. Also do you foresee any changes with the current due date of 21 February 2020?
An amendment will be issued during discussions to incorporate the new CBA; therefore, the current due date of 21 February 2020 will not change.