INDUSTRY QUESTIONS 03NOV20.pdf
PDF 128 KB Posted
- Attached to
- REQUEST FOR PROPOSAL (RFP) A-KITS
- Solicitation number
- W58RGZ-20-R-0063
About this file
This document contains questions and responses related to a solicitation for the manufacture of airframe modification kits. The solicitation seeks proposals from small businesses located in the Huntsville-Decatur-Albertville Combined Statistical Area to manufacture wiring harnesses, mechanical brackets, and procure and kit components according to technical data packages. Proposals are due by November 16, 2020 for an indefinite-quantity contract over five years. Manufacturers must employ a quality system certified to ANSI/ASQ/ISO 9001 and ISO 17025 and be capable of fabricating electrical and electronic assemblies per J-STD-001 Class 3 and IPC-A-610 Class 3. Tin whisker mitigation is required per GEIA-STD-0005-2 at control level 2B. The Army Contracting Command - Redstone Arsenal intends to award to sources that can provide the kits in support of Air Soldier System installations on rotary aircraft.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question: 1 AR (as required) is used throughout the drawing package. Is awardee providing these items or is it expected that the installation team will have? If required by awardee, quantities are needed. Cannot price or provide appropriately if not known.
USG Response:
Items marked AR are typically compounds, sealants, thread, webbing etc. where no quantities can be definitized.
Awardee should provide and should assess how much of the said part should be needed to apply where needed, as required.
Question: 2
CLIN 1001, 1051840-10
1051840 drawing tree shows 1052122 sub to drawing 1052117 However, 1052117 BOM does not include 1052122. Is this part required? If so, we recommend adding to the BOM.
USG Response:
In the Revision section of drawing 1052117 Rev 14, it states “REPLACED WASHERS (1052122-01) WITH
GROMMET (3MPU4).”
Question: 3 Drawing 1502122 is missing part numbers in the BOM. Is this part available from known source or does it have to be manufactured? If manufactured, need part numbers for individual parts.
USG Response:
Since 1052122-01 is replaced with grommet (3MPU4) is this part and drawing is no longer needed.
Question: 4
CLIN 1003, 1051783-10.
Drawing 1052000; fn3 on 1051772. Is awardee providing anything? Is this just the instructions for the installation team?
This is for the installation team, offeror is not responsible for providing 1052000-10 and 1052000-20.
Question: 5 CLIN 1005, 1051772-10. Same as 1003
This is for the installation team, offeror is not responsible for providing 1052000-10 and 1052000-20.
Question: 6 CLIN 1007, 1051772-30. Same as 1003
This is for the installation team, offeror is not responsible for providing 1052000-10 and 1052000-20.
Question: 7
CLIN 1009, 1051779-10
Item number 1 on this BOM, part number 1051773 contains a harness, part number 1051913.
The component list for 1051913 contains a completed harness, part number 1051898-10. If this harness is needed it should be moved up to the next level (should be on the BOM for 1051773).
The 1051898-10 is a subcomponent of the 1051913 harness assembly. 1051898-10 should NOT be called out as a separate item in the parts list for 1051773 because once it is built into the 1051913 it is no longer a standalone harness.
Question: 8 CLIN 1009 - Request drawing for ABC60692.
USG Response:
ABC60692 is proprietary and cannot be provided.
Question: 9
CLIN 1011, WTG00151-001
WTG00091-099, Ceiling Panel Mod, Is awardee providing anything. Are these just instructions for the installation team?
USG Response:
The awardee is to provide the WTG00091-099 which is a kit containing all of the parts from WTG00091-001 (except for the Ceiling Panel which per Note 6 is a GFE aircraft component). Please note that Delta Note 16 requires a special marking to be applied to the -007 which is a subcomponent of the -099 kit.
Question: 10
CLIN 1021, 1052502-10
1052414, confirm no parts needed; Are these just the instructions for the installation team?
No parts are needed, this is instructions for the installation team only.
Question: 11 CLIN 1001, DWG 1051896, NOTE 2 lists that this drawing is to be used in conjunction with 1051891, 1051810, 1051734, OR 1051710. 1051734 and 1051710 are not included in the TDP. Please provide.
USG Response:
Wiring diagrams for installing the harnesses into the aircraft. These will be provided and sent to the awardee. (SEE ATTACHMENTS: : 1051734 & 1051710) both dated 110320.
Question: 12 In Attachment 5 on WTG00091-007, there is no BOM for WTG00091-009 which is called for in WTG00091-007
WTG00091-009 is a manufactured part and does not require a separate BOM. The material is called out in the parts list material/specification column at FN 5 and the dimensions are called out on sheet 7.
Question: 13 Is the government or the contractor responsible for the warehousing?
USG Response:
The contractor is responsible for warehousing all material until the A-kit is shipped to the USG.
Question: 14 What is the ship to location?
USG Response:
The ship to location will be provided at award of order but ship to location is anticipated to be local Huntsville area.
All hardware CLINs are inspection and acceptance at Origin.
Question: 15
Are subcontractors or vendors are also required to have quality systems in place that meets Section C of the solicitation (ANSI/ASQ/ISO 9001 and ISO 17025 certification)?
USG Response:
Per Solicitation Section C-DESCRIPTION/SPECIFICATIONS/WORK STATEMENT Paragraph 5.4 (U) Subcontractor/Supplier Quality Assurance. The contractor shall ensure that all applicable quality requirements, associated specifications, and any other contractual agreements are flowed down to their lower tier subcontractors/suppliers and that compliance is verified.
Question: 16 If that documentation for each team member is required to be submitted in proposal?
USG Response:
No, only the prime contractor is required to submit certification with the proposal response. Note that sub-contractors qualifications may be reviewed during pre-award survey or at start of work meetings.
Question: 17 Can the certification documentation be exempted from page count?
Per Solicitation Section L-2 b) The detailed list and explanation for an equivalent system shall not be included in the page count for the Technical Volume