Industry Question 6 NOV 20.pdf

PDF 97 KB Posted

Attached to
REQUEST FOR PROPOSAL (RFP) A-KITS
Solicitation number
W58RGZ-20-R-0063
Issued by

About this file

This document contains a request for proposal for the manufacture of airframe modification kits. The U.S. Army Contracting Command - Redstone Arsenal is seeking proposals from small businesses located in the Huntsville-Decatur-Albertville Combined Statistical Area to manufacture wiring harnesses, mechanical brackets, and procure and kit components for advanced sight and display computer collectors, encryptable aircraft wireless intercom system collectors, and aviation information system collectors over the next five years on an indefinite delivery basis. Proposals are due by November 16, 2020. Manufacturers must employ a quality system compliant with ISO 9001 and ISO 17025 and be capable of fabricating electrical and electronic assemblies per IPC standards as well as implementing tin whisker mitigation plans per GEIA-STD-0005-2 at control level 2B.

View the file

Other files

File Type Posted
Industry Question 19-NOV-2020.pdf PDF
Industry Question 17-NOV-2020.pdf PDF
W58RGZ-20-R-0063-0002.pdf PDF
INDUSTRY QUESTIONS 13-NOV-2020.pdf PDF
W58RGZ-20-R-0063-0001.pdf PDF
Industry Question 111020.pdf PDF
Extension 11-09-20.pdf PDF
Industry Question 110920.pdf PDF
Industry Questions (MOLEX PNs) USG RESPONSE 5 (11052020).pdf PDF
1051734X16 110320.pdf PDF
1051710_X00 WIRING DIAGRAM ASDC UH-60AL 110320.pdf PDF
INDUSTRY QUESTIONS 03NOV20.pdf PDF
INDUSTRY QUESTIONS (PERIOD of PERFORMANCE-SOW UPDATE)10212020.pdf PDF
INDUSTRY QUESTIONS 10222020.pdf PDF
W58RGZ-20-R-0063r2.pdf PDF
Attachment 1 W58RGZ-20-R-0063 A-kit TDP Index 21 Oct 2020 Update.xlsx XLSX spreadsheet
INDUSTRY QUESTIONS (TDP Drawings) USG RESPONSE (10192020).pdf PDF
1Attachment 1 W58RGZ-20-R-0063 A-kit TDP Index 27 Aug 2020.xlsx XLSX spreadsheet
1051893D_X10.pdf PDF
Attachment 0011 Price Input Workbook _ 27 Aug 2020.xlsx XLSX spreadsheet
Attachment 0012 GFP AKIT IDIQ.xlsx XLSX spreadsheet
W58RGZ-20-R-0063r1.pdf PDF
CONTRACTING FORMAL RESPONSE POSTING W58RGZ-20-R-0063 REV1.pdf PDF
Exhibit B W58RGZ-20-R-0063 A-Kit Document Summary List 3 Aug 2020.pdf PDF
Exhibit A CDRLs W58RGZ-20-R-0063 A-Kits 3 Aug 2020.pdf PDF
W58RGZ-20-R-0063 .pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Industry Question:

In attachment 10 on drawing 1052466 AIP Assembly, the switch is not identified. Please advise.

USG Response:

The switch is identified as P/N: NASM91528-1UB4.

Industry Question:

In Attachment 6, part numbers WTG00031-001 and WTG00032-001 contain an obsolete part according to the manufacturer of the part number listed. FN5 111028-0300 is obsolete, with no replacement. Please advise.

USG Response:

The answer to this question was provided on 5 Nov per Email Question on wiring harness components. The answer repeated below applies to AI question above:

Reference Section C 3.1.f &g. These cables have been accounted for and are not required to be provided by the contractor.

Section C.3.1.f

f. For HH-60M AWIS Kit part number (p/n) WTG00083-001, the contractor shall not purchase the Fill Cables WTG00032-001 & WTG00173-001.

g. For CH-47F AWIS kit p/n WTG00093-001, the contractor shall not provide Fill Cables WTG00031-001 and WTG00032-001.

Furthermore, Section C. 3.3.2 GFE/GFM/GFI Items provides information on GFE.

Section C.3.3.2 a.&b:

The US Government will provide the following items as GFE/GFI for A-kit manufacture:

a. For HH-60M AWIS kit p/n WTG00151-001, the US Government will provide Fill Cables p/n WTG00032- 001 and p/n WTG00173-001.

b. For CH-47F AWIS kit p/n WTG00093-001, no GFE cables will be provided. The kits will not include WTG00031-001 and WTG0032-001.

Industry Question:

Order density: with reference to storage and warehousing, what would be the amount of kits required to be stored at one time and average length of time on a monthly basis. We are seeking this information for proposal planning and pricing purposes. Suggest that the government provide a “plug number” to eliminate assumption/perceived risk.

USG Response:

The USG cannot provide an average storage quantity or length of time as the contractor may request DCMA inspection and acceptance as soon as kits are ready for delivery. Items are typically shipped within a week of acceptance by USG. PM AW has a local storage/staging warehouse that delivered kits will be stored in prior to fielding.

Industry Question:

Can the government provided drawing trees for WTG000156, WTG00040-001 and WTG00091?

USG Response: There are no drawing trees available for WTG000156, WTG00040-001 and

WTG00091.