Instructions
| Overall Instructions: |
| * All financial data/totals should tie to the monthly data dumps from your system of record and cumulate to the costs on the ITD (Inception to Date) Actuals tab for the current POP. If your contract has multiple POPs occuring at the same time, |
| possibly certain SLINs extended on a particular option year yet the current POP is for a new option year, then you are required to populate two separate cost reports. Do not mix cost/actuals for different periods of performance. |
| * Do not change the layout/any cells in this template. You may populate the report with either formulas of your choosing or hard coded numbers but all data (monthly and cumulative) must be supported and match the monthly actuals and cum actuals |
| on the ITD actuals tab. Spot checks will be done to ensure totals match the data. You may add comments off to the side of cells or add a comment on a particular cell to provide the COR with additional information if needed. |
| * All cells/totals may not need to be populated depending on the costs incurred and work being performed contract by contract. If a cell or total doesn't apply to actuals incurred, leave the cell blank or enter a $0.00 value. Columns have been provided for all |
| cost types, even where that particular costs type might not seem reasonable, to account for any mischarging and adjustments/corrections that might need to occur. |
| * Before receiving this cost report, the COR should have identified and created individual tabs for each effort/system so you are aware of the cost reporting structure. If this hasn't been done please work with your COR to create the necessary tabs before |
| populating the report. |
| Program Summary Instructions: |
| * This tab is to be populated with totals for the entire current POP, from Inception to date through the most recent month close actuals, and also requests totals for most recent reporting period. Example: The current POP is 1/1/2019 - 12/31/2019 and the most |
| recent month close was April, the reporting period is 4/1/2019 - 4/30/2019 and the Cumulative Totals should be from 1/1/2019 - 4/1/2019. |
| * ITD actuals by Funding Type should be pulled from the SLIN data on each effort/system tab. You can add a formula to calculate this, create a pivot, or manually calculate. Keep in mind not all funding types will apply to all contracts. |
| Contract Mods Instructions: |
| * As each new Mod is received (award, funding increase/decrease, admin, etc) you are required to populate a new Mod box to account for changes in that Mod. |
| Effort/Sytem Tab Instructions: |
| * The total summary box, and data on each tab, is soley for the effort/system identified. The estimated burn out date can be calculated using a formula/theory of your choosing but you must account for actuals to date, the remaining ETC (estimate to complete), |
| known requirements, and known cost that is expected to post (such as lagging subcontractor invoices, labor adjustments, material/ODC costs to post once received). |
| * Each SLIN must have its own data set and as you receive additional funding, create a data set box for all SLINs for each effort/system. You must also identify the Mod in which the funding was provided and the Funding Type. |
| * All other cells should be self explainatory but if you require additional claraifcation please reach out to your COR. |
Program Summary
| Program Summary - Financial Reporting | | | Mod 1 - Award | | Mod 2 - Funding Increase | | Mod 3 - Admin | |
| | | | Base Ceiling | $0.00 | Base Ceiling | $0.00 | Base Ceiling | $0.00 |
| Funding Remaining | | | Previous Ceiling Amount | $0.00 | Previous Ceiling Amount | $0.00 | Previous Ceiling Amount | $0.00 |
| Contract Number/TO | 12345 TO #1 | | Ceiling Increase | $0.00 | Ceiling Increase | $0.00 | Ceiling Increase | $0.00 |
| Program Name | StarLite | | Labor Funding | $0.00 | Labor Funding | $0.00 | Labor Funding | $0.00 |
| Reporting Period | 9/1/2019 - 9/30/2019 | | Travel/ODC Funding | $0.00 | Travel/ODC Funding | $0.00 | Travel/ODC Funding | $0.00 |
| POP | 9/1/2019 - 9/1/2020 | | Material Funding | $0.00 | Material Funding | $0.00 | Material Funding | $0.00 |
| | | | Total Funding | $0.00 | Total Funding | $0.00 | Total Funding | $0.00 |
| Task Order | Labor | ODC | | | | | | |
| Funding | $0.00 | $0.00 | $0.00 | | | | | | |
| Funding Expended | $0.00 | $0.00 | $0.00 | | | | | | |
| Funding Remaining | | | | | | | | | |
| Ceiling | $0.00 | $0.00 | $0.00 | | | | | | |
| Ceiling Expended | $0.00 | $0.00 | $0.00 | | | | | | |
| Ceiling Remaining | | | | | | | | | |
| Reporting Period Amount | | | | | |
| Labor | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | |
| Monthly Prime Cost | | | | | | |
| Total | | | | | | |
| ODC | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | |
| Monthly Prime Cost | | | | | | |
| Total | | | | | | |
| Cumulative Amount (for Current POP) | | | | | |
| Labor | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Cumulative Sub Cost | | | | | | |
| Cumulative Prime Cost | | | | | | |
| Total | | | | | | |
| ODC | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Cumulative Sub Cost | | | | | | |
| Cumulative Prime Cost | | | | | | |
| Total | | | | | | |
CLINs1001-5110 - T & I
| Funding Remaining | |
| Contract Number | 12345 TO #1 |
| Effort Name | Test & Inspection |
| Reporting Period | 9/1/2019 - 9/30/2019 |
| POP | 9/1/2019 - 9/1/2020 |
| Est Burn Out Date | |
| | Reporting Period Amount | 9/1/2019 - 9/30/2019 | | | | |
| ANTENNA ASSEMBLY P/N 225K946G02 | | | | | | | |
| NSN: 5895-01-603-3398 | | | | | | | |
| Funding Expended: | | | | | | | |
| Labor | Quantity | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | | |
| Monthly Prime Cost | | | | | | | |
| Total | | | | | | | |
| RECEIVER SUBASSEMBLY RADAR ELECTRONIC_P/N247k760G01 | | | | | | | |
| NSN: 5481-01-603-3428 | | | | | | | |
| Funding Expended: | | | | | | | |
| Labor | Quantity | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | | |
| Monthly Prime Cost | | | | | | | |
| Total | | | | | | | |
| POWER SUPPLY P/N 146K162G01/G02/G03 | | | | | | | |
| NSN: 6120-01-603-3385 | | | | | | | |
| Funding Expended: | | | | | | | |
| Labor | Quantity | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | | |
| Monthly Prime Cost | | | | | | | |
| Total | | | | | | | |
| CONTROL UNIT NAVIGATION SET P/N 231K935G01 | | | | | | | |
| NSN: 6605-01-578-4629 | | | | | | | |
| Funding Expended: | | | | | | | |
| Labor | Quantity | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | | |
| Monthly Prime Cost | | | | | | | |
| Total | | | | | | | |
| BLOWER ASSEMBLY P/N 215K772G01 | | | | | | | |
| NSN: 4140-01-582-1363 | | | | | | | |
| Funding Expended: | | | | | | | |
| Labor | Quantity | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | | |
| Monthly Prime Cost | | | | | | | |
| Total | | | | | | | |
| RECEIVER/EXCITER PROGRAMMED ASSEMBLY P/N219K256G02 | | | | | | | |
| NSN: 5841-01-646-2364 | | | | | | | |
| Funding Expended: | | | | | | | |
| Labor | Quantity | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | | |
| Monthly Prime Cost | | | | | | | |
| Total | | | | | | | |
| RF DOWNCONVERTER PROGRAMMED ASSEMBLY P/N219K225G03 | | | | | | | |
| NSN: 5895-01-646-2368 | | | | | | | |
| Funding Expended: | | | | | | | |
| Labor | Quantity | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | | |
| Monthly Prime Cost | | | | | | | |
| Total | | | | | | | |
| POWER SUPPLY CASE P/N 309K116G01 | | | | | | | |
| NSN: 6130-01-664-8370 | | | | | | | |
| Funding Expended: | | | | | | | |
| Labor | Quantity | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | | |
| Monthly Prime Cost | | | | | | | |
| Total | | | | | | | |
| RECEIVER SUBASSEMBLY WIRED CHASSIS P/N 146K167G03 | | | | | | | |
| NSN: 5841-01-646-2367 | | | | | | | |
| Funding Expended: | | | | | | | |
| Labor | Quantity | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | | |
| Monthly Prime Cost | | | | | | | |
| Total | | | | | | | |
| SENSOR PROCESSOR ASSEMBLY P/N 247K759G04 | | | | | | | |
| NSN: 5895-01-649-9033 | | | | | | | |
| Funding Expended: | | | | | | | |
| Labor | Quantity | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | | |
| Monthly Prime Cost | | | | | | | |
| Total | | | | | | | |
Funding Remaining:
| Cumulative Amount (for Current POP) |
| All SLINs | |
| Funding Awarded: | |
| Funding Expended: | | | | | | | |
| Labor | Quantity | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Cumulative Sub Cost | | | | | | | |
| Cumulative Prime Cost | | | | | | | |
| Total | | | | | | | |
| ODC | Quantity | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Cumulative Sub Cost | | | | | | | |
| Cumulative Prime Cost | | | | | | | |
| Total | | | | | | | |
| Funding Remaining: | | | | | | | |
| | Monthly Actuals Labor Data - Prime | | | | | | | | | | | |
| Serial # | Employee | Hours | Direct Labor Rate | Unique Numeric Identifier (LCAT) | Proposed/Invoiced Labor Category (LCAT) | Fringe $'s | Overhead $'s | MHC $'s | G&A $'s | Misc. Indirect $'s | Misc. Indirect $'s | Fee/Profit $'s | Total Cost |
| 06 | | | | | | | | | | | | | |
Wienecke, Steven M CIV US USA: Wienecke, Steven M CIV US USA:
| Temporary placeholder for the assets' actual serial number; serial number to be provided/updated upon task order award. | | TE1001 | Test Engineer Entry | | Columns (D* E) + Sum(H:N) | |
| 08 | | TE1001 | Test Engineer Entry | | Columns (D* E) + Sum(H:N) |
| 52 | | TE1004 | Test Engineer Senior | | Columns (D* E) + Sum(H:N) |
| 16 | | TE1004 | Test Engineer Senior | | Columns (D* E) + Sum(H:N) |
| 37 | | BA 2601 | Budget Analyst Entry | | Columns (D* E) + Sum(H:N) |
| 49 | | BA2604 | Budget Analyst Senior | | Columns (D* E) + Sum(H:N) |
| 50 | | PM1404 | Program Manager Senior | | Columns (D* E) + Sum(H:N) |
| 03 | | | | | |
| | Monthly Actuals Labor Data - Sub | | | | |
| Serial # | Employee | Hours | Direct Labor Rate | Unique Numeric Identifier (LCAT) | Proposed/Invoiced Labor Category (LCAT) | Total Cost |
| 06 | | | | | | |
Wienecke, Steven M CIV US USA: Wienecke, Steven M CIV US USA:
| Temporary placeholder for the assets' actual serial number; serial number to be provided/updated upon task order award. | | | | SE3102 | Software Engineer Intermediate | | Column D * E | |
| 08 | | | | SE3103 | Software Engineer Journeyman | | Column D * E |
| 52 | | | | SE3104 | Software Engineer Senior | | Column D * E |
| 16 | | | | SE3104 | Software Engineer Senior | | Column D * E |
| 37 | | | | | | | |
| 49 | | | | | | | |
| 50 | | | | | | | |
| 03 | | | | | | | |
| | | Monthly Actuals Material - Prime | | | | | |
| | Beginning Month Material Balance | Material Purchased during Month | Materials Consumed during Month | Ending Month Balance | | | |
Wienecke, Steven M CIV US USA: Suggested numbers to be replaced with actuals in the future.
Wienecke, Steven M CIV US USA: Wienecke, Steven M CIV US USA:
| Temporary placeholder for the assets' actual serial number; serial number to be provided/updated upon task order award. | $8,000,000.00 | | $1,000,000.00 | $500,000.00 | $8,500,000.00 | |
| | | | Monthly Actuals Material - Sub | | |
| | Beginning Month Material Balance | | Material Purchased during Month | Materials Consumed during Month | Ending Month Balance |
| | $2,000,000.00 | | $1,000,000.00 | $500,000.00 | $2,500,000.00 |
CLINs1021-5121 - Tech SVCS SUPP
| Funding Remaining | $0.00 | | | | | DMSMS Monitoring & Mitigation-CLIN1021 |
| Contract Number | 12345 TO #1 | | | | | Provisioning/Design Change Notice-CLIN1021 |
| Effort Name | Tech Services | | | | | Test Equipment Services-CLIN1021 |
| Reporting Period | 9/1/2019 - 9/30/2019 | | | | | Mission Assurance-CLIN1021 |
| POP | 9/1/2019 - 9/1/2020 | | | | | Contract Administration/OPSEC Plan-CLIN1021 |
| Est Burn Out Date | | | | | | |
| | | | | | | DMSMS Monitoring & Mitigation-CLIN2021 |
| Reporting Period Amount | 9/1/2019 - 9/30/2019 | | | | | Provisioning/Design Change Notice-CLIN2021 |
| DMSMS Monitoring & Mitigation | | | | | | | Test Equipment Services-CLIN2021 |
| Funding Awarded: | | | | | | $0.00 | Mission Assurance-CLIN2021 |
| | | | | | | Contract Administration/OPSEC Plan-CLIN2021 |
| Funding Expended: | | | | | | $0.00 | |
| Labor | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total | DMSMS Monitoring & Mitigation-CLIN3021 |
| Monthly Sub Cost | | | | | | | Provisioning/Design Change Notice-CLIN3021 |
| Monthly Prime Cost | | | | | | | Test Equipment Services-CLIN3021 |
| Total | | | | | | | Mission Assurance-CLIN3021 |
| | | | | | | Contract Administration/OPSEC Plan-CLIN3021 |
| ODC | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total | |
| Monthly Sub Cost | | | | | | | DMSMS Monitoring & Mitigation-CLIN4021 |
| Monthly Prime Cost | | | | | | | Provisioning/Design Change Notice-CLIN4021 |
| Total | | | | | | | Test Equipment Services-CLIN4021 |
| | | | | | | Mission Assurance-CLIN4021 |
| Funding Remaining: | | | | | | | Contract Administration/OPSEC Plan-CLIN4021 |
| Provisioning/Design Change Notice | | | | | | | DMSMS Monitoring & Mitigation-CLIN5021 |
| Funding Awarded: | | | | | | | Provisioning/Design Change Notice-CLIN5021 |
| | | | | | | Test Equipment Services-CLIN5021 |
| Funding Expended: | | | | | | | Mission Assurance-CLIN5021 |
| Labor | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total | Contract Administration/OPSEC Plan-CLIN5021 |
| Monthly Sub Cost | | | | | | | |
| Monthly Prime Cost | | | | | | | DMSMS Monitoring & Mitigation-CLIN5121 |
| Total | | | | | | | Provisioning/Design Change Notice-CLIN5121 |
| | | | | | | Test Equipment Services-CLIN5121 |
| ODC | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total | Mission Assurance-CLIN5121 |
| Monthly Sub Cost | | | | | | | Contract Administration/OPSEC Plan-CLIN5121 |
| Monthly Prime Cost | | | | | | | |
| Total | | | | | | | |
| Test Equipment Services |
| Funding Awarded: |
| Funding Expended: | | | | | | |
| Labor | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | |
| Monthly Prime Cost | | | | | | |
| Total | | | | | | |
| ODC | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | |
| Monthly Prime Cost | | | | | | |
| Total | | | | | | |
| Funding Remaining: | | | | | | |
| Mission Assurance |
| Funding Awarded: |
| Funding Expended: | | | | | | |
| Labor | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | |
| Monthly Prime Cost | | | | | | |
| Total | | | | | | |
| ODC | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | |
| Monthly Prime Cost | | | | | | |
| Total | | | | | | |
| Contract Administration/OPSEC plan |
| Funding Awarded: |
| Funding Expended: | | | | | | |
| Labor | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | |
| Monthly Prime Cost | | | | | | |
| Total | | | | | | |
| ODC | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | |
| Monthly Prime Cost | | | | | | |
| Total | | | | | | |
| Funding Remaining: | | | | | | |
| Cumulative Amount (for Current POP) |
| All SLINs | |
| Funding Awarded: | |
| Funding Expended: | | | | | | |
| Labor | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Cumulative Sub Cost | | | | | | |
| Cumulative Prime Cost | | | | | | |
| Total | | | | | | |
| ODC | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Cumulative Sub Cost | | | | | | |
| Cumulative Prime Cost | | | | | | |
| Total | | | | | | |
| Funding Remaining: | Mirror for each Tech services Line | | | | | |
| | Monthly Actuals Labor Data - Prime | | | | | | | | | | | |
| Tech Services | Employee Name | Hours | Direct Labor Rate | Unique Numeric Identifier (LCAT) | Proposed/Invoiced Labor Category (LCAT) | Fringe $'s | Overhead $'s | MHC $'s | G&A $'s | Misc. Indirect $'s | Misc. Indirect $'s | Fee/Profit $'s | Total Cost |
| DMSMS Monitoring & Mitigation-CLIN1021 | | | | TE1001 | Test Engineer Entry | | | | | | | | Columns (C * D) + Sum(G:M) |
| DMSMS Monitoring & Mitigation-CLIN2021 | | | | TE1001 | Test Engineer Entry | | | | | | | | Columns (C * D) + Sum(G:M) |
| DMSMS Monitoring & Mitigation-CLIN3021 | | | | TE1004 | Test Engineer Senior | | | | | | | | Columns (C * D) + Sum(G:M) |
| DMSMS Monitoring & Mitigation-CLIN4021 | | | | TE1004 | Test Engineer Senior | | | | | | | | Columns (C * D) + Sum(G:M) |
| DMSMS Monitoring & Mitigation-CLIN5021 | | | | BA 2601 | Budget Analyst Entry | | | | | | | | Columns (C * D) + Sum(G:M) |
| Contract Administration/OPSEC Plan-CLIN5121 | | | | BA2604 | Budget Analyst Senior | | | | | | | | Columns (C * D) + Sum(G:M) |
| | | | PM1404 | Program Manager Senior | | | | | | | | Columns (C * D) + Sum(G:M) |
| | Monthly Actuals Labor Data - Sub | | | | |
| Tech Services | Employee Name | Hours | Direct Labor Rate | Unique Numeric Identifier (LCAT) | Proposed/Invoiced Labor Category (LCAT) | Total Cost |
| Contract Administration/OPSEC Plan-CLIN1021 | | | | SE3102 | Software Engineer Intermediate | Column C * D |
| Test Equipment Services-CLIN2021 | | | | SE3103 | Software Engineer Journeyman | Column C * D |
| Provisioning/Design Change Notice-CLIN3021 | | | | SE3104 | Software Engineer Senior | Column C * D |
| Contract Administration/OPSEC Plan-CLIN4021 | | | | SE3104 | Software Engineer Senior | Column C * D |
| Mission Assurance-CLIN4021 | | | | | | |
| Contract Administration/OPSEC Plan-CLIN5121 | | | | | | |
| Monthly Actuals Material - Prime | | |
| Beginning Month Material Balance | Material Purchased during Month | Materials Consumed during Month | Ending Month Balance |
Wienecke, Steven M CIV US USA: Fixed highlighting. Figures are placed are not actuals.
$8,000,000.00 $1,000,000.00 $500,000.00 $8,500,000.00
| Monthly Actuals Material - Sub | | |
| Beginning Month Material Balance | Material Purchased during Month | Materials Consumed during Month | Ending Month Balance |
| $2,000,000.00 | $1,000,000.00 | $500,000.00 | $2,500,000.00 |
CLINs1022-5123 LIM & DMSMS
| Funding Remaining | |
| Contract Number | 12345 TO #1 |
Wienecke, Steven M CIV US USA: edited
To add Lay-In Material & DMSMS material as separate entities.
| Effort Name | Lay-In Material |
| Reporting Period | 9/1/2019 - 9/30/2019 |
| POP | 9/1/2019 - 9/1/2020 |
| Est Burn Out Date | |
| Reporting Period Amount | 9/1/2019 - 9/30/2019 | |
| Lay-In Material | | | |
| Funding Awarded: | | | $0.00 |
| Funding Expended: | | | | | | |
| Labor | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | |
| Monthly Prime Cost | | | | | | |
| Total | | | | | | |
| ODC | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | |
| Monthly Prime Cost | | | | | | |
| Total | | | | | | |
| Funding Remaining: | | | | | | |
| DMSMS Material | |
| Funding Awarded: | $0.00 |
| Funding Expended: | | | | | | |
| Labor | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | |
| Monthly Prime Cost | | | | | | |
| Total | | | | | | |
| ODC | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | |
| Monthly Prime Cost | | | | | | |
| Total | | | | | | |
| Funding Remaining: | | | | | | |
| Cumulative Amount (for Current POP) |
| All SLINs | |
| Funding Awarded: | |
| Funding Expended: | | | | | | |
| Labor | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Cumulative Sub Cost | | | | | | |
| Cumulative Prime Cost | | | | | | |
| Total | | | | | | |
| ODC | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Cumulative Sub Cost | | | | | | |
| Cumulative Prime Cost | | | | | | |
| Total | | | | | | |
| Funding Remaining: | | | | | | |
| | | Monthly Actuals Labor Data - Prime | | | | | | | | | | | |
| Serial # | CLIN # | Employee | Hours | Direct Labor Rate | Unique Numeric Identifier (LCAT) | Proposed/Invoiced Labor Category (LCAT) | Fringe $'s | Overhead $'s | MHC $'s | G&A $'s | Misc. Indirect $'s | Misc. Indirect $'s | Fee/Profit $'s | Total Cost |
| 06 | | | | | | | | | | | | | | |
Wienecke, Steven M CIV US USA: Wienecke, Steven M CIV US USA:
| Temporary placeholder for the assets' actual serial number; serial number to be provided/updated upon task order award. | LIM-CLIN1022 | | | | TE1001 | Test Engineer Entry | | Columns (D * E) + Sum(H:N) | | 01 | LIM-CLIN1022 | |
| 08 | LIM-CLIN2022 | | | | TE1001 | Test Engineer Entry | | Columns (D * E) + Sum(H:N) | | 02 | LIM-CLIN2022 |
| 52 | LIM-CLIN3022 | | | | TE1004 | Test Engineer Senior | | Columns (D * E) + Sum(H:N) | | 03 | LIM-CLIN3022 |
| 16 | LIM-CLIN4022 | | | | TE1004 | Test Engineer Senior | | Columns (D * E) + Sum(H:N) | | 04 | LIM-CLIN4022 |
| 37 | LIM-CLIN5022 | | | | BA 2601 | Budget Analyst Entry | | Columns (D * E) + Sum(H:N) | | 05 | LIM-CLIN5022 |
| 49 | DMSMS-CLIN1023 | | | | BA2604 | Budget Analyst Senior | | Columns (D * E) + Sum(H:N) | | 06 | LIM-CLIN5122 |
| 50 | DMSMS-CLIN2023 | | | | PM1404 | Program Manager Senior | | Columns (D * E) + Sum(H:N) | | 07 | |
| 03 | DMSMS-CLIN4023 | | | | | | | | | 08 | DMSMS-CLIN1023 |
| 50 | DMSMS-CLIN5123 | | | | | | | | | 09 | DMSMS-CLIN2023 |
| | | | | | | | | | | 10 | DMSMS-CLIN3023 |
| | | | | | | | | | | 11 | DMSMS-CLIN4023 |
| | | | Monthly Actuals Labor Data - Subcontractor(s) | | | | | | | 12 | DMSMS-CLIN5023 |
| Serial # | CLIN # | Employee | Hours | Direct Labor Rate | Unique Numeric Identifier (LCAT) | Proposed/Invoiced Labor Category (LCAT) | | Total Cost | | 13 | DMSMS-CLIN5123 |
| 06 | | | | | | | | | | | |
Wienecke, Steven M CIV US USA: Wienecke, Steven M CIV US USA:
| Temporary placeholder for the assets' actual serial number; serial number to be provided/updated upon task order award. | LIM-CLIN1022 | | | | SE3102 | Software Engineer Intermediate | | Column D * E | | 14 | |
| 08 | LIM-CLIN2022 | | | | SE3103 | Software Engineer Journeyman | | Column D * E | | 15 |
| 52 | LIM-CLIN3022 | | | | SE3104 | Software Engineer Senior | | Column D * E | | 16 |
| 16 | LIM-CLIN4022 | | | | SE3104 | Software Engineer Senior | | Column D * E | | 17 |
| 37 | LIM-CLIN5022 | | | | | | | | | 18 |
| 49 | DMSMS-CLIN1023 | | | | | | | | | 19 |
| 50 | DMSMS-CLIN2023 | | | | | | | | | 20 |
| 47 | DMSMS-CLIN4023 | | | | | | | | | 21 |
| 27 | DMSMS-CLIN5123 | | | | | | | | | 22 |
| | | | Monthly Actuals Material - Prime | | | | | | | 23 |
| | | Beginning Month Material Balance | Material Purchased during Month | Materials Consumed during Month | Ending Month Balance | | | | | |
Wienecke, Steven M CIV US USA: Suggested numbers to be replaced with actuals in the future.
Wienecke, Steven M CIV US USA: Wienecke, Steven M CIV US USA:
| Temporary placeholder for the assets' actual serial number; serial number to be provided/updated upon task order award. | | | | | 24 | |
| $8,000,000.00 | $1,000,000.00 | $500,000.00 | $8,500,000.00 | | 25 |
| | | | | | 26 |
| | | | | | 27 |
| | | | | | 28 |
| | | | | | 29 |
| | Monthly Actuals Material - Sub | | | | 30 |
| Beginning Month Material Balance | Material Purchased during Month | Materials Consumed during Month | Ending Month Balance | | 31 |
| $2,000,000.00 | $1,000,000.00 | $500,000.00 | $2,500,000.00 | | 32 |
| | | | | | 33 |
| | | | | | 34 |
| | | | | | 35 |
| | | | | | 36 |
| | | | | | 37 |
| | | | | | 38 |
| | | | | | 39 |
| | | | | | 40 |
| | | | | | 41 |
| | | | | | 42 |
| | | | | | 43 |
| | | | | | 44 |
| | | | | | 45 |
| | | | | | 46 |
| | | | | | 47 |
| | | | | | 48 |
| | | | | | 49 |
| | | | | | 50 |
| | | | | | 51 |
| | | | | | 52 |
CLINs1011-5120 - Repairs
| Funding Remaining | |
| Contract Number | 12345 TO #1 |
| Effort Name | Repairs |
| Reporting Period | 9/1/2019 - 9/30/2019 |
| POP | 9/1/2019 - 9/1/2020 |
| Est Burn Out Date | |
| | Reporting Period Amount | 9/1/2019 - 9/30/2019 | | | | |
| ANTENNA ASSEMBLY P/N 225K946G02 | | | | | | | |
| NSN: 5895-01-603-3398 | | | | | | | |
| Funding Expended: | | | | | | | |
| Labor | Serial Number | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | | |
| Monthly Prime Cost | | | | | | | |
| Total | | | | | | | |
| RECEIVER SUBASSEMBLY RADAR ELECTRONIC_P/N247k760G01 | | | | | | | |
| NSN: 5481-01-603-3428 | | | | | | | |
| Funding Expended: | | | | | | | |
| Labor | | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | | |
| Monthly Prime Cost | | | | | | | |
| Total | | | | | | | |
| POWER SUPPLY P/N 146K162G01/G02/G03 | | | | | | | |
| NSN: 6120-01-603-3385 | | | | | | | |
| Funding Expended: | | | | | | | |
| Labor | | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | | |
| Monthly Prime Cost | | | | | | | |
| Total | | | | | | | |
| CONTROL UNIT NAVIGATION SET P/N 231K935G01 | | | | | | | |
| NSN: 6605-01-578-4629 | | | | | | | |
| Funding Expended: | | | | | | | |
| Labor | | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | | |
| Monthly Prime Cost | | | | | | | |
| Total | | | | | | | |
| BLOWER ASSEMBLY P/N 215K772G01 | | | | | | | |
| NSN: 4140-01-582-1363 | | | | | | | |
| Funding Expended: | | | | | | | |
| Labor | | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | | |
| Monthly Prime Cost | | | | | | | |
| Total | | | | | | | |
| RECEIVER/EXCITER PROGRAMMED ASSEMBLY P/N219K256G02 | | | | | | | |
| NSN: 5841-01-646-2364 | | | | | | | |
| Funding Expended: | | | | | | | |
| Labor | | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | | |
| Monthly Prime Cost | | | | | | | |
| Total | | | | | | | |
| RF DOWNCONVERTER PROGRAMMED ASSEMBLY P/N219K225G03 | | | | | | | |
| NSN: 5895-01-646-2368 | | | | | | | |
| Funding Expended: | | | | | | | |
| Labor | | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | | |
| Monthly Prime Cost | | | | | | | |
| Total | | | | | | | |
| POWER SUPPLY CASE P/N 309K116G01 | | | | | | | |
| NSN: 6130-01-664-8370 | | | | | | | |
| Funding Expended: | | | | | | | |
| Labor | | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | | |
| Monthly Prime Cost | | | | | | | |
| Total | | | | | | | |
| RECEIVER SUBASSEMBLY WIRED CHASSIS P/N 146K167G03 | | | | | | | |
| NSN: 5841-01-646-2367 | | | | | | | |
| Funding Expended: | | | | | | | |
| Labor | | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | | |
| Monthly Prime Cost | | | | | | | |
| Total | | | | | | | |
| SENSOR PROCESSOR ASSEMBLY P/N 247K759G04 | | | | | | | |
| NSN: 5895-01-649-9033 | | | | | | | |
| Funding Expended: | | | | | | | |
| Labor | | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Monthly Sub Cost | | | | | | | |
| Monthly Prime Cost | | | | | | | |
| Total | | | | | | | |
| Funding Remaining: | | | | | | | |
| Cumulative Amount (for Current POP) |
| All SLINs | |
| Funding Awarded: | |
| Funding Expended: | | | | | | |
| Labor | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Cumulative Sub Cost | | | | | | |
| Cumulative Prime Cost | | | | | | |
| Total | | | | | | |
| ODC | Hours | Direct Labor | Direct Travel | Materials | Sub Labor | Total |
| Cumulative Sub Cost | | | | | | |
| Cumulative Prime Cost | | | | | | |
| Total | | | | | | |
| Funding Remaining: | | | | | | |
| | Monthly Actuals Labor Data - Prime | | | | | | | | | |
| Serial # | Employee | Hours | Direct Labor Rate | Unique Numeric Identifier (LCAT) | Proposed/Invoiced Labor Category (LCAT) | Fringe $'s | Overhead $'s | MHC $'s | G&A $'s | Misc. Indirect $'s | Misc. Indirect $'s |
Wienecke, Steven M CIV US USA: Wienecke, Steven M CIV US USA:
| OPSEC Security; Direct Charge. Perhaps list as DL entry and a sense of the % of security cost relative to the entire center and other contracts (?). | Fee/Profit $'s | Total Cost |
| 06 | |
Wienecke, Steven M CIV US USA: Wienecke, Steven M CIV US USA:
| Temporary placeholder for the assets' actual serial number; serial number to be provided/updated upon task order award. | | TE1001 | Test Engineer Entry | | Columns (D* E) + Sum(H:N) | |
| 08 | | TE1001 | Test Engineer Entry | | Columns (D* E) + Sum(H:N) |
| 52 | | TE1004 | Test Engineer Senior | | Columns (D* E) + Sum(H:N) |
| 16 | | TE1004 | Test Engineer Senior | | Columns (D* E) + Sum(H:N) |
| 37 | | BA 2601 | Budget Analyst Entry | | Columns (D* E) + Sum(H:N) |
| 49 | | BA2604 | Budget Analyst Senior | | Columns (D* E) + Sum(H:N) |
| 50 | | PM1404 | Program Manager Senior | | Columns (D* E) + Sum(H:N) |
| 03 | | | | | |
| | Monthly Actuals Labor Data - Sub | | | | |
| Serial # | Employee | Hours | Direct Labor Rate | Unique Numeric Identifier (LCAT) | Proposed/Invoiced Labor Category (LCAT) | Total Cost |
| 51 | | | | | | |
Wienecke, Steven M CIV US USA: Wienecke, Steven M CIV US USA:
| Temporary placeholder for the assets' actual serial number; serial number to be provided/updated upon task order award. | | | | SE3102 | Software Engineer Intermediate | | Column D * E | |
| 08 | | | | SE3103 | Software Engineer Journeyman | | Column D * E |
| 52 | | | | SE3104 | Software Engineer Senior | | Column D * E |
| 16 | | | | SE3104 | Software Engineer Senior | | Column D * E |
| 37 | | | | | | | |
| 49 | | | | | | | |
| 50 | | | | | | | |
| 03 | | | | | | | |
| | | Monthly Actuals Material - Prime | | | | | |
| | Beginning Month Material Balance | Material Purchased during Month | Materials Consumed during Month | Ending Month Balance | | | |
Wienecke, Steven M CIV US USA: Suggested numbers to be replaced with actuals in the future.
Wienecke, Steven M CIV US USA: Wienecke, Steven M CIV US USA:
| Temporary placeholder for the assets' actual serial number; serial number to be provided/updated upon task order award. | $8,000,000.00 | | $1,000,000.00 | $500,000.00 | $500,000.00 | |
| | | | Monthly Actuals Material - Sub | | |
| | Beginning Month Material Balance | | Material Purchased during Month | Materials Consumed during Month | Ending Month Balance |
| | $2,000,000.00 | | $1,000,000.00 | $500,000.00 | $500,000.00 |