This document contains a sample First Article Test waiver worksheet and instructions. The worksheet requests information from contractors seeking a waiver of first article testing requirements for a particular part number. It outlines the type of waiver being requested, the justification and supporting documentation required depending on whether the waiver is based on a previous first article test, similar item test, or continuous production. Contractors must provide details of the previous test such as contract and approval dates. The worksheet also requests information on any quality issues or changes to manufacturing that could impact approval. Supporting documentation must be submitted with the signed worksheet.

This federal contract opportunity notice is for the U.S. Army Contracting Command-Warren to award a requirements contract for the fabrication of two models of Army Standard Family International Standard Organization shelters. The shelters come in four configurations depending on whether they are one-side or two-side expandable and have 60-amp or 100-amp electrical service. The five-year contract includes a two-year base and three one-year options and will be awarded on a best value basis through full and open competition.

Attachment 0024

View the file

Other files

File Type Posted
W56HZV-18-R-0057_Conformed_Copy_14_JUN_2018.pdf PDF
W56HZV-18-R-0057_AMD_0004.pdf PDF
QAs_(3)_for_ISO_Shelter.pdf PDF
Attachment_0020_Pricing_Attachment.xlsx XLSX spreadsheet
Attachment_0002_SOW_for_ISO_Two-sided_Shelter_TM_-13&P-20180523.docx DOCX document
W56HZV18R0057-0003.pdf PDF
Attachment_0005_TWO_SIDED_Provisioning_SOW_7_June__2018.doc DOC document
Attachment_0001_SOW_for_ISO_One-Sided_Shelter_TM_-13&P-20180523.docx DOCX document
Attachment_0007_SOW_for_MERWS_TM_-13&P_20180523.docx DOCX document
Attachment_0004_One_Sided_SIDED_Provisioning_SOW_7_June__2018.doc DOC document
Attachment_0020_Pricing_Attachment.xlsx XLSX spreadsheet
Q&As_(2).pdf PDF
W56HZV18R0057-0002.pdf PDF
Q&As_(1).pdf PDF
W56HZV18R0057-0001.pdf PDF
Attachment_0010_Camouflage_Pattern,_ISO_One_Side_Exp.pdf PDF
CDRLs.zip ZIP file
Attachment_0011_Camouflage_Pattern,_ISO_Two_Side_Exp.pdf PDF
Attachment_0007_SOW_for_MERWS_TM_-13&P_20180312_HLD.DOCX DOCX document
W56HZV18R0057.pdf PDF
Attachment_0004_One_Sided_SIDED_Provisioning_SOW_5_March_2018_FINAL_(003....doc DOC document
Attachment_0001_SOW_for_ISO_One-Sided_Shelter_TM_-13&P-20180315_HLD.DOCX DOCX document
Attachment_0003_ISO_Shelter_Exp_One_Side,_Two_Side_PKG_SOW.DOCX DOCX document
Attachment_0020_Pricing_Attachment.xlsx XLSX spreadsheet
Attachment_0012_TDPL_5-4-2828_One_Side_Exp_60_amp.zip ZIP file
Attachment_0023_SBP-Certification-Subcontractor.docx DOCX document
Attachment_0002_SOW_for_ISO_Two-sided_Shelter_TM_-13&P-20180315_HLD.DOCX DOCX document
Attachment_0009_MTA_Supportability_Analysis_MERWS_14_APRIL_2017.docx DOCX document
Attachment_0015_TDPL_5-4-3201_Two_Side_Exp_100_amp.zip ZIP file
Attachment_0021_SBP-Workbook.xlsx XLSX spreadsheet
Attachment_0013_TDPL_5-4-3200_One_Side_Exp_100_amp.zip ZIP file
Attachment_0006_Draft_ECP,_Hinged_Endwall_Closeout_Panel_Option_(5-4-320....pdf PDF
Attachment_0008_MERWS__Provisioning_SOW_5_March_2018_FINAL_(003).doc DOC document
Attachment_0014_TDPL_5-4-3118_Two_Side_Exp_60_amp.zip ZIP file
Attachment_0022_SBP-WorkbookInstructions.docx DOCX document
Attachment_0005_TWO_SIDED_Provisioning_SOW_5_March_2018_FINAL_(003).doc DOC document
Attachment_0016_TDPL_17-2-1250_MERWS.zip ZIP file
Attachment_0019_PPQ.doc DOC document
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Version - September 2015

This information/supporting documentation is part of your request.

It must be submitted on company letterhead and signed by an agent of the company.

Contact the Contracting Officer if you have any questions about the acquisition offer/quote requirements.

FIRST ARTICLE - WAIVER WORKSHEET

Request for Information and Supporting Documentation

This is a Sample of a Contractor's Request for First Article Waiver Worksheet. If waivers will be considered by the Government, this form or memorandum similar to this should be an attachment in Section J of the solicitation.

Contracting Officer's Name

1. CURRENT ACQUISITION INFORMATION:

NOUN

PART #

CONTRACTOR NAME

NSN

TOP DRAWING #

SOLICITATION/CONTRACT #

CONTRACTOR CAGE

REVISION LEVEL

2. TYPE OF REQUEST:

Partial Waiver: Includes waiver of only a specific test(s) of the First Article Test requirement as required by the Technical Data Package (TDP), contract and/or solicitation.

Full Waiver: Includes waiver of all First Article Testing as required by the TDP, contract and/or solicitation.

TDP Reference(s) of test(s) to be waived: (Please be specific and reference specification paragraph and/or drawing note as appropriate).

3. JUSTIFICATION TO SUPPORT WAIVER REQUEST: (Check and complete all that apply)

Successful completion of a First Article Test on a recent contract for the same item(s).

Complete the following & attach supporting documentation*.

If NO, please describe the differences in detail below and include any considerations these changes will require for the First Article Test waiver request

DATE OF FIRST ARTICLE TEST APPROVALCONTRACT # ISSUING GOVERNMENT AGENCY

Was the above contract manufactured at the same facilities using the same equipment, processes, procedures, and subcontractors in which the current item will be produced?

A)

Successful completion of a First Article Test on a similar item on a recent contract and the item has been tested per the same requirements as those referenced in the solicitation and/or contract.

Complete the following for the similar item & attach supporting documentation*:

Briefly describe the major differences between the similar item and the item being procured.

NSN

CONTRACT #

DATE OF FIRST ARTICLE TEST APPROVAL

Was the similar item manufactured at the same facilities using similar equipment, processes, and procedures in which the current item will be produced?

B)

NOMENCLATURE

PART NUMBER

If NO, please describe the differences in detail below and include any considerations these changes will require for the First Article Test waiver request

Material has been in continuous production. Complete and attach supporting documentation*:

Remarks (if needed)

LENGTH OF PRODUCTION RUN

C)

APPROVAL DATE OF LAST SUCCESSFUL FIRST ARTICLE TEST

Provide a full explanation justifying why duplicate testing is unnecessary:

Recent and successful performance of a first article test on the next higher assembly. A waiver may be requested in order to eliminate duplication of testing on the lower assembly.

Complete the following for the next higher assembly and attach supporting documentation*:

D)

NSN

CONTRACT #

DATE OF FIRST ARTICLE TEST APPROVAL

NOMENCLATURE

PART NUMBER

Was the next higher assembly manufactured at the same facilities using similar equipment, processes, and procedures in which the current item will be produced?

If NO, please explain:

Other: A waiver or partial waiver of the FAT is being requested based on the following:

Please be specific and attach supporting documentation* as appropriate:E)

4. OTHER PERTINENT INFORMATION

There are or have been quality issues (history) for this or similar items to include Product Quality Deficiency Reports (PQDRs), Corrective Action Request, and/or show-cause letters. Please briefly discuss below:A)

There have been changes to the manufacturing data (e.g. drawing revisions that change materials, dimensions, processes, inspection or testing requirements) or subcontractors used to manufacture the items successfully in the past.

Please describe below.

B)

There have been Requests for Waiver/Deviation submitted or Material Review Board (MRB) actions related to manufacture of this item. Please describe below. C)

5. ATTACH SUPPORTING DOCUMENTATION

6. SUBMISSION

The submitter, by signing the below certifies that the above statements are true and correct.

Please provide printed name, signature, company address, and phone number where you can be reached. Again, the signer must be an agent of the company.

PRINTED NAME

COMPANY NAME

PHONE NUMBER

TITLE

COMPANY ADDRESS

Signature

*See the solicitation/contract for information on submitting supporting documentation as well as additional requirements regarding First Article Test Waiver requests.

This information/supporting documentation is part of your request.

It must be submitted on company letterhead and signed by an agent of the company.

Contact the Contracting Officer if you have any questions about the acquisition offer/quote requirements.

FIRST ARTICLE - WAIVER WORKSHEET

Request for Information and Supporting Documentation This is a Sample of a Contractor's Request for First Article Waiver Worksheet. If waivers will be considered by the Government, this form or memorandum similar to this should be an attachment in Section J of the solicitation.

1. CURRENT ACQUISITION INFORMATION:

2. TYPE OF REQUEST:

3. JUSTIFICATION TO SUPPORT WAIVER REQUEST: (Check and complete all that apply) Was the above contract manufactured at the same facilities using the same equipment, processes, procedures, and subcontractors in which the current item will be produced?

Page of A) Was the similar item manufactured at the same facilities using similar equipment, processes, and procedures in which the current item will be produced?

B) C) D) Was the next higher assembly manufactured at the same facilities using similar equipment, processes, and procedures in which the current item will be produced?

Page of Page of E)

4. OTHER PERTINENT INFORMATION

A) B) C)

5. ATTACH SUPPORTING DOCUMENTATION

6. SUBMISSION

The submitter, by signing the below certifies that the above statements are true and correct. Please provide printed name, signature, company address, and phone number where you can be reached. Again, the signer must be an agent of the company.

*See the solicitation/contract for information on submitting supporting documentation as well as additional requirements regarding First Article Test Waiver requests.

8.2.1.4029.1.523496.503679

TextField7:
:
DateTimeField1:
TextField8:
DropDownList1:
CurrentPage: 1.00000000
CurrentPage: 2.00000000
CurrentPage: 3.00000000
PageCount: 3.00000000
PageCount: 3.00000000
PageCount: 3.00000000
ResetButton1:
TextField9:
DateTimeField2:
TextField10:
NumericField1: 0
SignatureField1:
Button1:
Button2:
ListBox1:
Button3:

File details come from the government source that posted it. Updated .