ATTACHMENT 0007 RIA HVAC PRICING MATRIX
| OFFEROR NAME: | |||||||||
| OFFEROR CAGE CODE: | |||||||||
| SOLICITATION: | W52P1J-19-R-5002 | ||||||||
| PROPOSAL DATE: | |||||||||
| Base Pd (4mos) & Phase-In (2mos) | Option Period 1 | Option Period 2 | Option Period 3 | Option Period 4 | Option Period 5 | ||||
| 12 months | 12 Months | 12 months | 12 months | 6 months | |||||
| CLIN TYPE | CLINs | Description | Total $ | Total $ | Total $ | Total $ | Total $ | Total $ | Total Evaluated Price $ |
FFP 0001 SECTION #1 GENERAL INFORMATION & Phase-In Transition Period $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
FFP 0002 SECTION #2 CHILLER OPERATIONS (IAW Section 5, Part 1 of Performance Work Statement) $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
FFP 0003 SECTION #3 HVAC SCHEDULED OPERATION (IAW Section 5, Part 2 of Performance Work Statement) $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
FFP 0004 SECTION #4 HVAC SCHEDULED PM REQUIREMENTS (IAW Section 5, Part 3 of Performance Work Statement) $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
FFP 0005 SECTION #5 PREDICTIVE PM (IAW Section 5, Part 4 of Performance Work Statement) $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
T&M (Orders TBD) 0006 SECTION #6 UNSCHEDULED Demand Maintenance Orders (DMOs) (IAW Section 5, Part 5 of Performance Work Statement) $ 117,500.00 $ 235,000.00 $ 235,000.00 $ 235,000.00 $ 235,000.00 $ 117,500.00 $ 1,175,000.00
T&M (Orders TBD) 0007 SECTION #7 UNSCHEDULED Project Work Orders (PWOs) (IAW Section 5, part 5 of Performance Work Statement) $ 100,000.00 $ 200,000.00 $ 200,000.00 $ 200,000.00 $ 200,000.00 $ 100,000.00 $ 1,000,000.00
NSP 0008 Contractor Man Hour Reporting (Not Seperately Priced -NSP) NSP NSP NSP NSP NSP NSP NSP
| 0009 | Option to Extend Service IAW Clause 52-217-8 | $ 217,500.00 | ||||||
| TOTAL EVALUATED PRICE | $ 217,500.00 | $ 435,000.00 | $ 435,000.00 | $ 435,000.00 | $ 435,000.00 | $ 217,500.00 | $ 2,392,500.00 |
Phase-In & Base Period
ATTACHMENT 0007 RIA HVAC PRICING MATRIX
| OFFEROR NAME: | 0 |
| OFFEROR CAGE CODE: | 0 |
| SOLICITATION: | W52P1J-19-R-5002 |
| PROPOSAL DATE: | 0 |
CLIN TYPE CLIN Phase-In Transition Pd ( Pop Mos 31 May 2019 - 31 July 2019) & BASE Pd (PoP 6 Mos 1 August 2019 - 31 January 2020) Total $
| FFP | 0001 | SECTION #1 GENERAL INFORMATION & PHASE-IN TRANSITION PERIOD | $ - 0 |
| 0001AA | SECTION #1 PHASE-IN TRANSITION PERIOD | $ - 0 | |
| 0001AB | SECTION #1 GENERAL INFORMATION (IAW Section 1 of Performance Work Statement) | $ - 0 |
FFP 0002 SECTION #2 CHILLER OPERATIONS (IAW Section 5, Part 1 of Performance Work Statement) $ - 0
FFP 0003 SECTION #3 HVAC SCHEDULED OPERATION (IAW Section 5, Part 2 of Performance Work Statement) $ - 0
FFP 0004 SECTION #4 HVAC SCHEDULED PM REQUIREMENTS (IAW Section 5, Part 3 of Performance Work Statement) $ - 0
FFP 0005 SECTION #5 PREDICTIVE PM (IAW Section 5, Part 4 of Performance Work Statement) $ - 0
| T&M (Orders TBD) | 0006 | SECTION #6 UNSCHEDULED Demand Maintenance Orders (DMOs) (IAW Section 5, Part 5 of Performance Work Statement) | |||||
| LABOR CATEGORY | CONTRACTOR LABOR CATEGORY CONFORMANCE | COMPANY NAME | LOADED LABOR RATES | LABOR HOURS | TOTAL $ | ||
| Heating, Ventilation, and Air-Conditioning Mechanic | 3,900 | $ - 0 | |||||
| Maintenance Trades Helper | 39 | $ - 0 | |||||
| Material (Government Surrogate Ceiling) | $ 117,500.00 | ||||||
| SECTION #6 - DMOs TOTALS: | $ 117,500.00 |
| T&M (Orders TBD) | 0007 | SECTION #7 UNSCHEDULED Project Work Orders (PWOs) (IAW Section 5, Part 5 of Performance Work Statement) | |||||
| LABOR CATEGORY | CONTRACTOR LABOR CATEGORY CONFORMANCE | COMPANY NAME | LOADED LABOR RATES | LABOR HOURS | TOTAL $ | ||
| Heating, Ventilation, and Air-Conditioning Mechanic | 1,250 | $ - 0 | |||||
| Maintenance Trades Helper | 13 | $ - 0 | |||||
| Material (Government Surrogate Ceiling) | $ 100,000.00 | ||||||
| SECTION #7 - PWOs TOTALS: | $ 100,000.00 |
NSP 0008 Contractor Man Hour Reporting (Not Seperately Priced -NSP) NSP
BASE YEAR TOTAL $ 217,500.00
Option Period 1
ATTACHMENT 0007 RIA HVAC PRICING MATRIX
| OFFEROR NAME: | 0 |
| OFFEROR CAGE CODE: | 0 |
| SOLICITATION: | W52P1J-19-R-5002 |
| PROPOSAL DATE: | 0 |
CLIN TYPE CLIN OPTION Period 1 (PoP 12 Mos 01 February 2020 - 31 January 2021) Total $
FFP 0101 SECTION #1 GENERAL INFORMATION (IAW Section 1 of Performance Work Statement) $ - 0
FFP 0102 SECTION #2 CHILLER OPERATIONS (IAW Section 5, Part 1 of Performance Work Statement) $ - 0
FFP 0103 SECTION #3 HVAC SCHEDULED OPERATION (IAW Section 5, Part 2 of Performance Work Statement) $ - 0
FFP 0104 SECTION #4 HVAC SCHEDULED PM REQUIREMENTS (IAW Section 5, Part 3 of Performance Work Statement) $ - 0
FFP 0105 SECTION #5 PREDICTIVE PM (IAW Section 5, Part 4 of Performance Work Statement) $ - 0
| T&M (Orders TBD) | 0106 | SECTION #6 UNSCHEDULED Demand Maintenance Orders (DMOs) (IAW Section 5, Part 5 of Performance Work Statement) | |||||
| LABOR CATEGORY | CONTRACTOR LABOR CATEGORY CONFORMANCE | COMPANY NAME | LOADED LABOR RATES | LABOR HOURS | TOTAL $ | ||
| Heating, Ventilation, and Air-Conditioning Mechanic | 7,800 | $ - 0 | |||||
| Maintenance Trades Helper | 78 | $ - 0 | |||||
| Material (Government Surrogate Ceiling) | $ 235,000.00 | ||||||
| SECTION #6 - DMOs TOTALS: | $ 235,000.00 |
| T&M (Orders TBD) | 0107 | SECTION #7 UNSCHEDULED Project Work Orders (PWOs) (IAW Section 5, Part 5 of Performance Work Statement) | |||||
| LABOR CATEGORY | CONTRACTOR LABOR CATEGORY CONFORMANCE | COMPANY NAME | LOADED LABOR RATES | LABOR HOURS | TOTAL $ | ||
| Heating, Ventilation, and Air-Conditioning Mechanic | 2,500 | $ - 0 | |||||
| Maintenance Trades Helper | 25 | $ - 0 | |||||
| Material (Government Surrogate Ceiling) | $ 200,000.00 | ||||||
| SECTION #7 - PWOs TOTALS: | $ 200,000.00 |
NSP 0108 Contractor Man Hour Reporting (Not Seperately Priced -NSP) NSP
OPTION YEAR 1 TOTAL $ 435,000.00
Option Period 2
ATTACHMENT 0007 RIA HVAC PRICING MATRIX
| OFFEROR NAME: | 0 |
| OFFEROR CAGE CODE: | 0 |
| SOLICITATION: | W52P1J-19-R-5002 |
| PROPOSAL DATE: | 0 |
CLIN TYPE CLIN OPTION Period 2 (PoP 12 Mos 01 February 2021 - 31 January 2022) Total $
FFP 0201 SECTION #1 GENERAL INFORMATION (IAW Section 1 of Performance Work Statement) $ - 0
FFP 0202 SECTION #2 CHILLER OPERATIONS (IAW Section 5, Part 1 of Performance Work Statement) $ - 0
FFP 0203 SECTION #3 HVAC SCHEDULED OPERATION (IAW Section 5, Part 2 of Performance Work Statement) $ - 0
FFP 0204 SECTION #4 HVAC SCHEDULED PM REQUIREMENTS (IAW Section 5, Part 3 of Performance Work Statement) $ - 0
FFP 0205 SECTION #5 PREDICTIVE PM (IAW Section 5, Part 4 of Performance Work Statement) $ - 0
| T&M (Orders TBD) | 0206 | SECTION #6 UNSCHEDULED Demand Maintenance Orders (DMOs) (IAW Section 5, Part 5 of Performance Work Statement) | |||||
| LABOR CATEGORY | CONTRACTOR LABOR CATEGORY CONFORMANCE | COMPANY NAME | LOADED LABOR RATES | LABOR HOURS | TOTAL $ | ||
| Heating, Ventilation, and Air-Conditioning Mechanic | 7,800 | $ - 0 | |||||
| Maintenance Trades Helper | 78 | $ - 0 | |||||
| Material (Government Surrogate Ceiling) | $ 235,000.00 | ||||||
| SECTION #6 - DMOs TOTALS: | $ 235,000.00 |
| T&M (Orders TBD) | 0207 | SECTION #7 UNSCHEDULED Project Work Orders (PWOs) (IAW Section 5, Part 5 of Performance Work Statement) | |||||
| LABOR CATEGORY | CONTRACTOR LABOR CATEGORY CONFORMANCE | COMPANY NAME | LOADED LABOR RATES | LABOR HOURS | TOTAL $ | ||
| Heating, Ventilation, and Air-Conditioning Mechanic | 2,500 | $ - 0 | |||||
| Maintenance Trades Helper | 25 | $ - 0 | |||||
| Material (Government Surrogate Ceiling) | $ 200,000.00 | ||||||
| SECTION #7 - PWOs TOTALS: | $ 200,000.00 |
NSP 0208 Contractor Man Hour Reporting (Not Seperately Priced -NSP) NSP
OPTION YEAR 2 TOTAL $ 435,000.00
Option Period 3
ATTACHMENT 0007 RIA HVAC PRICING MATRIX
| OFFEROR NAME: | 0 |
| OFFEROR CAGE CODE: | 0 |
| SOLICITATION: | W52P1J-19-R-5002 |
| PROPOSAL DATE: | 0 |
CLIN TYPE CLIN OPTION Period 3 (PoP 12 Mos 01 Februar 2022 - 31 January 2023) Total $
FFP 0301 SECTION #1 GENERAL INFORMATION (IAW Section 1 of Performance Work Statement) $ - 0
FFP 0302 SECTION #2 CHILLER OPERATIONS (IAW Section 5, Part 1 of Performance Work Statement) $ - 0
FFP 0303 SECTION #3 HVAC SCHEDULED OPERATION (IAW Section 5, Part 2 of Performance Work Statement) $ - 0
FFP 0304 SECTION #4 HVAC SCHEDULED PM REQUIREMENTS (IAW Section 5, Part 3 of Performance Work Statement) $ - 0
FFP 0305 SECTION #5 PREDICTIVE PM (IAW Section 5, Part 4 of Performance Work Statement) $ - 0
| T&M (Orders TBD) | 0306 | SECTION #6 UNSCHEDULED Demand Maintenance Orders (DMOs) (IAW Section 5, Part 5 of Performance Work Statement) | |||||
| LABOR CATEGORY | CONTRACTOR LABOR CATEGORY CONFORMANCE | COMPANY NAME | LOADED LABOR RATES | LABOR HOURS | TOTAL $ | ||
| Heating, Ventilation, and Air-Conditioning Mechanic | 7,800 | $ - 0 | |||||
| Maintenance Trades Helper | 78 | $ - 0 | |||||
| Material (Government Surrogate Ceiling) | $ 235,000.00 | ||||||
| SECTION #6 - DMOs TOTALS: | $ 235,000.00 |
| T&M (Orders TBD) | 0307 | SECTION #7 UNSCHEDULED Project Work Orders (PWOs) (IAW Section 5, Part 5 of Performance Work Statement) | |||||
| LABOR CATEGORY | CONTRACTOR LABOR CATEGORY CONFORMANCE | COMPANY NAME | LOADED LABOR RATES | LABOR HOURS | TOTAL $ | ||
| Heating, Ventilation, and Air-Conditioning Mechanic | 2,500 | $ - 0 | |||||
| Maintenance Trades Helper | 25 | $ - 0 | |||||
| Material (Government Surrogate Ceiling) | $ 200,000.00 | ||||||
| SECTION #7 - PWOs TOTALS: | $ 200,000.00 |
NSP 0308 Contractor Man Hour Reporting (Not Seperately Priced -NSP) NSP
OPTION YEAR 3 TOTAL $ 435,000.00
Option Period 4
ATTACHMENT 0007 RIA HVAC PRICING MATRIX
| OFFEROR NAME: | 0 |
| OFFEROR CAGE CODE: | 0 |
| SOLICITATION: | W52P1J-19-R-5002 |
| PROPOSAL DATE: | 0 |
CLIN TYPE CLIN OPTION Period 4 (PoP 12 Mos 01 February 2023 - 31 January 2024) Total $
FFP 0401 SECTION #1 GENERAL INFORMATION (IAW Section 1 of Performance Work Statement) $ - 0
FFP 0402 SECTION #2 CHILLER OPERATIONS (IAW Section 5, Part 1 of Performance Work Statement) $ - 0
FFP 0403 SECTION #3 HVAC SCHEDULED OPERATION (IAW Section 5, Part 2 of Performance Work Statement) $ - 0
FFP 0404 SECTION #4 HVAC SCHEDULED PM REQUIREMENTS (IAW Section 5, Part 3 of Performance Work Statement) $ - 0
FFP 0405 SECTION #5 PREDICTIVE PM (IAW Section 5, Part 4 of Performance Work Statement) $ - 0
| T&M (Orders TBD) | 0406 | SECTION #6 UNSCHEDULED Demand Maintenance Orders (DMOs) (IAW Section 5, Part 5 of Performance Work Statement) | |||||
| LABOR CATEGORY | CONTRACTOR LABOR CATEGORY CONFORMANCE | COMPANY NAME | LOADED LABOR RATES | LABOR HOURS | TOTAL $ | ||
| Heating, Ventilation, and Air-Conditioning Mechanic | 7,800 | $ - 0 | |||||
| Maintenance Trades Helper | 78 | $ - 0 | |||||
| Material (Government Surrogate Ceiling) | $ 235,000.00 | ||||||
| SECTION #6 - DMOs TOTALS: | $ 235,000.00 |
| T&M (Orders TBD) | 0407 | SECTION #7 UNSCHEDULED Project Work Orders (PWOs) (IAW Section 5, Part 5 of Performance Work Statement) | |||||
| LABOR CATEGORY | CONTRACTOR LABOR CATEGORY CONFORMANCE | COMPANY NAME | LOADED LABOR RATES | LABOR HOURS | TOTAL $ | ||
| Heating, Ventilation, and Air-Conditioning Mechanic | 2,500 | $ - 0 | |||||
| Maintenance Trades Helper | 25 | $ - 0 | |||||
| Material (Government Surrogate Ceiling) | $ 200,000.00 | ||||||
| SECTION #7 - PWOs TOTALS: | $ 200,000.00 |
NSP 0408 Contractor Man Hour Reporting (Not Seperately Priced -NSP) NSP
OPTION YEAR 4 TOTAL $ 435,000.00
Option Period 5
ATTACHMENT 0007 RIA HVAC PRICING MATRIX
| OFFEROR NAME: | 0 |
| OFFEROR CAGE CODE: | 0 |
| SOLICITATION: | W52P1J-19-R-5002 |
| PROPOSAL DATE: | 0 |
CLIN TYPE CLIN OPTION Period 5 (PoP 6 Mos 01 February 2024 - 31 July 2024) Total $
FFP 0501 SECTION #1 GENERAL INFORMATION (IAW Section 1 of Performance Work Statement) $ - 0
FFP 0502 SECTION #2 CHILLER OPERATIONS (IAW Section 5, Part 1 of Performance Work Statement) $ - 0
FFP 0503 SECTION #3 HVAC SCHEDULED OPERATION (IAW Section 5, Part 2 of Performance Work Statement) $ - 0
FFP 0504 SECTION #4 HVAC SCHEDULED PM REQUIREMENTS (IAW Section 5, Part 3 of Performance Work Statement) $ - 0
FFP 0505 SECTION #5 PREDICTIVE PM (IAW Section 5, Part 4 of Performance Work Statement) $ - 0
| T&M (Orders TBD) | 0506 | SECTION #6 UNSCHEDULED Demand Maintenance Orders (DMOs) (IAW Section 5, Part 5 of Performance Work Statement) | |||||
| LABOR CATEGORY | CONTRACTOR LABOR CATEGORY CONFORMANCE | COMPANY NAME | LOADED LABOR RATES | LABOR HOURS | TOTAL $ | ||
| Heating, Ventilation, and Air-Conditioning Mechanic | 3,900 | $ - 0 | |||||
| Maintenance Trades Helper | 39 | $ - 0 | |||||
| Material (Government Surrogate Ceiling) | $ 117,500.00 | ||||||
| SECTION #6 - DMOs TOTALS: | $ 117,500.00 |
| T&M (Orders TBD) | 0507 | SECTION #7 UNSCHEDULED Project Work Orders (PWOs) (IAW Section 5, Part 5 of Performance Work Statement) | |||||
| LABOR CATEGORY | CONTRACTOR LABOR CATEGORY CONFORMANCE | COMPANY NAME | LOADED LABOR RATES | LABOR HOURS | TOTAL $ | ||
| Heating, Ventilation, and Air-Conditioning Mechanic | 1,250 | $ - 0 | |||||
| Maintenance Trades Helper | 13 | $ - 0 | |||||
| Material (Government Surrogate Ceiling) | $ 100,000.00 | ||||||
| SECTION #7 - PWOs TOTALS: | $ 100,000.00 |
NSP 0508 Contractor Man Hour Reporting (Not Seperately Priced -NSP) NSP
OPTION YEAR 5 TOTAL $ 217,500.00