This document contains a summary of questions and answers regarding a federal contract solicitation for logistics support services. The solicitation seeks proposals for the Logistics Civil Augmentation Program (LOGCAP) V, which provides worldwide logistical support to the U.S. Military. Services include setting the theater, supply operations, transportation, engineering, base camp services, and other logistics and sustainment functions. The Army Contracting Command-Rock Island plans to issue the request for proposal on November 6, 2017, with a North American Industry Classification code of 561210 and size standard of $38.5 million. The Army intends to award indefinite delivery, indefinite quantity contracts to 4 to 6 offerors, with an estimated maximum value of $82 billion over 10 years. The base period of performance is 5 years with options to extend for an additional 5 years. Concurrent task orders will also be awarded for initial known requirements.
Attachment 0048
View the file
Other files for this federal contract opportunity
Show all 50
Logistics Civil Augmentation Program (LOGCAP) V has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Item # | Subject | RFP/Attachment Reference | Question/Comment | Public / Private | USG Response |
| 01 | Small Business | Amendment 0005 |
Attachment 0017 - FFP Pricing Template Revised - Rev3.xlsx Small Business Tab The Amendment 0005, Attachment 0017, Small Business Tab (at rows 7 & 8, lines 1 & 2 - respectively), states "… not included in Table 1 above:"
The Small Business Tab "Instruction" text block gives directions for line 1 and line 2; however, at line 5 the instructions refers to ""Table 2".
Please identify referenced Table 1 and referenced Table 2, and confirm the data desired by the Government. Public Attachment 0017 has been revised to remove the references to the two tables. In addition, for clarity, the word "total" has been added to Instruction paragraph 2 of the Small Business tab. The small business data (including the total subcontractor dollars, which includes large business subcontractor dollars) to be provided in the Small Business tab is for the Setting the Theater task orders only. The data in this tab, in combination with similar data required in Attachment 0016, is needed to validate the offeror's small business information provided in Attachment 0019.
02 Amendment 0006 anticipated corrections Attachment 0047 - RFP Q_A's Round 4.xlsx, Item 11
Attachment_0002_- _Kuwait_Tech_Exhibit_-_Rev4.xlsx, Exhibit K The USG responded "USG acknowledges error; correction is part of Amendment 0006 attachment 0002." to RFI "In the Kuwait "Tech Exhibit K," cells D7 to D35 do not indicate the Category of Personnel required (Expat/OCN/LN). Can the offeror choose the category, or will the Government specify?"
Labor categories have not been updated from those in Amendment 0005. When will the Government provide the updated information?
| Public | Labor categories have been added to the Technical Exhibit K in Attachment 0002 - Kuwait Tech Exhibit. Please see revised Attachment 0002 in Amendment 0007. | |
| 03 | Amendment 0006 anticipated corrections | Attachment 0047 - RFP Q_A's Round 4.xlsx, Item 49 |
Attachment 0003 - Arabian Peninsula, Technical Exhiit K The Government's response to Attachment 0047 question 0049 was "The USG acknowledges error; correction is part of Amendment 0006 attachments."
This information was not included in Amendment 0006, does the Government still intend to provide the updated information?
| Public | Initial response in Attachment 0047 - RFP Q&A's Round 4 was incorrect. Technical Exhibit K rows 6, 7, 9, and 10 listing WBS 04.07.03 Role 2 Medical Facility are correct. | |
| 04 | Amendment 0006 anticipated corrections | Attachment 0047 - RFP Q_A's Round 4.xlsx, Item 52 |
Attachment 0003 - Arabian Peninsula, H.2 The Government's response to Attachment 0047 question 0052 was "The USG acknowledges error; correction is part of Amendment 0006 attachments."
This information was not included in Amendment 0006, does the Government still intend to provide the updated information?
| Public | USG could not replicate the error; PWS Paragraphs 04.07.03.01, 04.07.03.01.01, and 04.07.03.01.02 are listed in Technical Exhibit K. | ||
| 05 | Duplicate workload data | Attachment 0005_-_EUCOM_Tech_Exhibit_-_Rev5.xlsx, Data Pkg for A.1 and H.2, WBS 09.09.05 (rows 789:802) | Workload identified in rows 789:802 of Attachment 0005 appear duplicated. |
Please confirm the intent is for offerers to propose for both sets of workload. Public Workload for all Kosovo sites has been adjusted;
- Workload for KOS001 has been adjusted across multiple WBSs.
- Workload for KOS002 and KOS004 has been removed completely.
- Workload in WBS 04.09.05, 04.14, 04.16, and 06.01 was removed for KOS003.
Changes are highlighted in yellow. Please see revised Attachment 0005 - EUCOM Tech Exhibit in Amendment 0007.
06 07.03 Number of Dispatches issued Attachment 0005_-_EUCOM_Tech_Exhibit_-_Rev5.xlsx, Data Pkg for A.1 and H.2, WBS 07.03 (rows 1614 & 1630) Number of dispatches per month at KOS001 and BUL001 seem excessive for WBS 07.03 in rows 1614 and 1630 of Attachment 0005.
| Please confirm quantities are correct. | Public | Please see revised Attachment 0005 - EUCOM Tech Exhibit in Amendment 0007 for revisions. | ||
| 07 | Amendment Response Instructions | PCO letter of June 8, 2018 | On page 2 of the USG letter dated 8 June 2018, para 4) Microsoft Excel states: "Microsoft Excel – revisions shall be annotated in a changes summary document (Word or PDF). For each change the Offeror shall identify whether the change was the result of an EN (include the EN control number), the amendment, or other. For any changes identified as “other”, the Offeror shall briefly describe the reason for the change (e.g. correct error, changed approach, etc.). |
| Question: Is it the USG intent to receive a Change Management Document for MS Excel files, only? Or does this requirement apply to all files (including MS Word and PDF documents)? | Public | A changes summary document is for MS Excel files only. File format for the summary documents is Word or PDF. | ||
| 08 | Amendment Response Instructions | PCO letter of June 8, 2018 | Paragraphs 3) and 5) in USG letter dated 8 June 2018, appear to have a conflict related to marking of the changes as it relates to Microsoft Word documents. Paragraph 3) shows "revisions highlighted with yellow highlight function, while paragraph 5) requires to submit a "track changes version (with the changes indicated, deleted/replaced text indicated, and all highlights)". |
Recommendation: Recommend to require offerors to submit change tracking as follows: MS Word files – highlight changes in yellow and mark changed areas with a vertical line in the right page margine. PDF files – shall highlight change in yellow Public Per the email sent 15 June 2018, "The highlights required in paragraph 3 for Microsoft Word and Adobe PDF documents are to be included in the track changes version required in paragraph 5 that includes "the changes indicated, deleted/replaced text indicated, and all highlights"."
| 09 | Regional Capability - Points of Contacts | Attachment 0021 - Regional Capability Matrix - Rev3 | Does the USG desire the contractor add in the POC tab as required by the instructions provided in Attachment 0021? The attachment provided by the USG does not contain a POC tab. | Public | The instructions were not changed as a result of Amendment 0006. The instructions do not require the Offeror to add a seperate POC tab. Within attachment 0021, the instructions state, "A point of contact with phone number and email shall be provided for each contract listed." |
| 10 | Proposal Submittal Instructions | Letter - EN and Amendment Response Instructions |
Amendment 0006 Solicitation Document USG letter dated 8 June 2018 states that EN responses and any revisions are to be submitted via AMRDEC Safe and a DVD containing the entire proposal.
However, paragraph L.3 in Amendment 0006 contains the requirement to provide printed copies of each volume.
Recommendation: Recommend the USG removes the requirement for printed copies of the EN responses and revised proposal
| Public | Printed copies are not required for these proposal revisions. Per amendment 0006, Section L narrative L0002, "This narrative supersedes prior instruction for submittal of proposal information. Offerors shall follow guidance and instruction provided in discussion letters to offerors until such time final proposal revisions (FPR) are requested. This RFP will be amended with all final instructions for submittal of FPR." | ||
| 11 | Transportation Motor Pool in Kuwait | WBS Ref 07.03 Transportation | The Transportation Motor Pool (TMP) in Kuwait has a Workload Driver to "Provide Training to Motor Vehicle Drivers and Equipment Operators", with a Workload Decriptor of Average Classes given per month as 30. |
Is the number 30 representative of 30 students per month or does that number reflect conducting 30 Drivers Education Classes per month? Public Workload in PWS WBS 07.03 Transportation Motor Pool (TMP) is amended.
Please see revised Attachment 0002 - Kuwait Tech Exhibit in Amendment 0007.
12 Bus Shuttle Route Reference: Attachment 0009_-_Soto_Cano_Tech_Exhibit_-_Rev4, Lines 617 and 658 Is the Bus Shuttle route on line 617 under PWS 07.02.03.01 in addition to the Bus Shuttle routes on line 658 under PWS 07.03.01? Public Workload in PWS WBS PWS 07.02.03.01 Bus Shuttle route on line 617 was deleted.
Please see revised Attachment 0009 - Soto Cano Tech Exhibit in Amendment 0007.