This document is a Project Table of Contents for the construction of the Munitions Maintenance, Inspection, and Assembly (M&I) Facility at Truax Field, Wisconsin to support the F-35 mission. The project includes constructing a new 3,500 sq ft earth-covered, two-bay facility with a Secure Work Area, as well as new mechanical, electrical, and fire protection systems. Site work includes a Munitions Assembly Conveyor pad, a new access road, security fencing modifications, and utility work. The project has a 273-calendar day contract duration and is set aside 100% for Small Businesses under NAICS code 236220 with a contract value between $1-5 million. The solicitation requires several brand name products, including security and fire alarm systems. Award will be made to the lowest responsive and responsible bidder.
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ANG/ WI - F- 35: Muni t i ons M&I Faci l i t y Tr uax Fi el d, WI I ssued For Const r uct i on 27 Oct ober 2023
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRI CTI ONS
01 20 00 PRI CE AND PAYMENT PROCEDURES
01 30 00 ADMI NI STRATI VE REQUI REMENTS
01 32 01. 00 10 PROJECT SCHEDULE
01 33 00 SUBMI TTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUI REMENTS
01 42 00 SOURCES FOR REFERENCE PUBLI CATI ONS
01 45 00. 00 10 QUALI TY CONTROL
01 45 35 SPECI AL I NSPECTI ONS
01 50 00 TEMPORARY CONSTRUCTI ON FACI LI TI ES AND CONTROLS
01 57 19 TEMPORARY ENVI RONMENTAL CONTROLS
01 74 19 CONSTRUCTI ON WASTE MANAGEMENT AND DI SPOSAL
01 78 00 CLOSEOUT SUBMI TTALS
01 78 23 OPERATI ON AND MAI NTENANCE DATA
01 91 00. 15 10 TOTAL BUI LDI NG COMMI SSI ONI NG
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 61 13 EXCAVATI ON AND HANDLI NG OF CONTAMI NATED MATERI AL
02 81 00 TRANSPORTATI ON AND DI SPOSAL OF HAZARDOUS MATERI ALS
DI VI SI ON 03 - CONCRETE
03 30 00 CAST- I N- PLACE CONCRETE
03 45 33 PRECAST AND PRESTRESSED STRUCTURAL CONCRETE
DI VI SI ON 04 - MASONRY
04 20 00 UNI T MASONRY
DI VI SI ON 05 - METALS
05 05 20. 00 27 POST- I NSTALLED CONCRETE AND MASONRY ANCHORS
05 12 00 STRUCTURAL STEEL
05 40 00 COLD- FORMED METAL FRAMI NG
05 50 13 MI SCELLANEOUS METAL FABRI CATI ONS
DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES
06 10 00 ROUGH CARPENTRY
DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON
07 14 00 FLUI D- APPLI ED WATERPROOFI NG AND DRAI NAGE BOARD
07 21 13 BOARD AND BLOCK I NSULATI ON
07 21 16 MI NERAL FI BER BLANKET I NSULATI ON
07 84 00 FI RESTOPPI NG
07 92 00 JOI NT SEALANTS
DI VI SI ON 08 - OPENI NGS
08 11 13 STEEL DOORS AND FRAMES
08 34 73 SOUND CONTROL DOOR ASSEMBLI ES
08 39 55 SLI DI NG METAL BLAST RESI STANT DOORS
PROJECT TABLE OF CONTENTS Page 1
ADDENDUM #3; 05-09-2024
Gallagher, Brad K.
Cloud
08 71 00 DOOR HARDWARE
08 91 00 METAL WALL LOUVERS
DI VI SI ON 09 - FI NI SHES
09 22 00 SUPPORTS FOR GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 51 00 ACOUSTI CAL CEI LI NGS
09 62 38 STATI C- CONTROL FLOORI NG
09 67 23. 16 FUEL RESI STI VE RESI NOUS FLOORI NG, 5- COAT SYSTEM
09 90 00 PAI NTS AND COATI NGS
DI VI SI ON 10 - SPECI ALTI ES
10 14 00. 20 I NTERI OR SI GNAGE
10 26 00 WALL AND DOOR PROTECTI ON
10 44 16 FI RE EXTI NGUI SHERS
DI VI SI ON 21 - FI RE SUPPRESSI ON
21 13 13 WET PI PE SPRI NKLER SYSTEMS, FI RE PROTECTI ON
DI VI SI ON 22 - PLUMBI NG
22 00 00 PLUMBI NG, GENERAL PURPOSE
DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)
23 05 48. 00 40 VI BRATI ON AND SEI SMI C CONTROLS FOR HVAC PI PI NG AND
EQUI PMENT
23 05 93 TESTI NG, ADJUSTI NG, AND BALANCI NG FOR HVAC
23 07 00 THERMAL I NSULATI ON FOR MECHANI CAL SYSTEMS
23 09 00 I NSTRUMENTATI ON AND CONTROL FOR HVAC
23 09 13 I NSTRUMENTATI ON AND CONTROL DEVI CES FOR HVAC
23 09 23. 02 BACNET DI RECT DI GI TAL CONTROL FOR HVAC AND OTHER BUI LDI NG
CONTROL SYSTEMS
23 23 00 REFRI GERANT PI PI NG
23 30 00 HVAC AI R DI STRI BUTI ON
23 31 13. 00 40 METAL DUCTS
23 81 00 DECENTRALI ZED UNI TARY HVAC EQUI PMENT
23 82 46. 00 40 ELECTRI C UNI T HEATERS
DI VI SI ON 26 - ELECTRI CAL
26 05 19. 10 10 I NSULATED WI RE AND CABLE
26 05 26. 00 40 GROUNDI NG AND BONDI NG FOR ELECTRI CAL SYSTEMS
26 08 00 APPARATUS I NSPECTI ON AND TESTI NG
26 20 00 I NTERI OR DI STRI BUTI ON SYSTEM
26 28 00. 00 10 MOTOR CONTROL CENTERS, SWI TCHBOARDS AND PANELBOARDS
26 28 01. 00 10 COORDI NATED POWER SYSTEM PROTECTI ON
26 41 00 LI GHTNI NG PROTECTI ON SYSTEM
26 51 00 I NTERI OR LI GHTI NG
DI VI SI ON 28 - ELECTRONI C SAFETY AND SECURI TY
28 31 76 I NTERI OR FI RE ALARM AND MASS NOTI FI CATI ON SYSTEM,
ADDRESSABLE
DI VI SI ON 31 - EARTHWORK
PROJECT TABLE OF CONTENTS Page 2
31 00 00 EARTHWORK
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 01 19. 61 SEALI NG OF JOI NTS I N RI GI D PAVEMENT
32 11 20 BASE COURSE FOR RI GI D PAVI NG AND SI DEWALK AND SUBBASES FOR
FLEXI BLE PAVI NG
32 12 13 BI TUMI NOUS TACK AND PRI ME COATS
32 12 16. 16 ROAD- MI X ASPHALT PAVI NG
32 13 13. 06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SI TE
FACI LI TI ES
32 16 19 CONCRETE CURBS, GUTTERS AND SI DEWALKS
32 31 13 CHAI N LI NK FENCES AND GATES
32 92 19 SEEDI NG
DI VI SI ON 33 - UTI LI TI ES
33 40 00 STORM DRAI NAGE UTI LI TI ES
DI VI SI ON 41 - MATERI AL PROCESSI NG AND HANDLI NG EQUI PMENT
41 22 13. 14 BRI DGE CRANES, OVERHEAD ELECTRI C, TOP RUNNI NG
- - End of Pr oj ect Tabl e of Cont ent s - -
PROJECT TABLE OF CONTENTS Page 3
THI S PAGE I NTENTI ONALLY LEFT BLANK
PROJECT TABLE OF CONTENTS Page 4
PROJECT TABLE OF CONTENTS
File details come from the government source that posted it. Updated .