Questions and Answers 03.pdf

PDF 434 KB Posted

Attached to
F-35 Alter B412 Flow -Through Aircraft Shelter
Solicitation number
W50S9F22R0003
Issued by

About this file

This document contains questions and answers related to a federal contract solicitation for alterations to an F-35 aircraft shelter. Key details include:

  • The solicitation is for alterations to an existing F-16 maintenance hangar at Dane County Regional Airport in Madison, WI to accommodate F-35 operations. Work includes modifications for 270VDC power to parking spots, ducting and power for aircraft avionics cooling, upgrades to the lightning protection system, rooftop and aircraft maintenance fall protection, and upgrades to the fire detection/suppression and security systems.

  • The solicitation will result in a single firm fixed-price construction contract. An option is included for security equipment. The period of performance is 180 days from notice to proceed. The estimated value is between $5-10 million. The NAICS code is 236220 with a size standard of $39.5 million.

  • A pre-proposal conference and site visit will be held on April 8, 2022. The solicitation closing date is April 1, 2022 and the source selection process will follow FAR Part 15 procedures evaluating technical, past performance and price factors. The government intends to award without discussions.

View the file

Other files

File Type Posted
W50S9F-22-R-0003_00002 Conform.pdf PDF
W50S9F-22-R-0003_00002.pdf PDF
B412 XGFG052008 Install IR Heaters_2005.pdf PDF
Questions and Answers 05.pdf PDF
IMG-2699.jpg JPG image
IMG-2698.jpg JPG image
XGFG112032 Repair B412 Alert Shelters - EPDM Roof Submittal.pdf PDF
Questions and Answers 04.pdf PDF
IMG-2700.jpg JPG image
EXHIBIT A PERFORMANCE RELEVANCY QUESTIONNAIRE AND SPECIALIZED COMPANY EXPERIENCE v1.docx DOCX document
Drawing for Q and A 03 Question 24.jpg JPG image
B412 XGFG022024B and C Wolverine Fire Protection_2014.pdf PDF
B412 XGFG 022024B and C Upgrade B412 Fire Supression System_2014.pdf PDF
EXHIBIT G PROPOSAL PRICE SCHEDULE v1.docx DOCX document
Questions and Answers 02.pdf PDF
W50S9F-22-R-0003_00001.pdf PDF
412 Pre Proposal Minutes 08Apr22.pdf PDF
Questions and Answers 01.pdf PDF
Site Visit Attendance Sheet.pdf PDF
Pre-Proposal Slides - 412.pptx PPTX presentation
ATTACHMENT 04 XGFG182004 F35 Alter B412 LBP and Asbestos Results.pdf PDF
ATTACHMENT 08 PRE PROPOSAL SITE VISIT DROP OFF INSTRUCTIONS.pdf PDF
EXHIBIT F SUBCONTRACTING PLAN FORMAT.docx DOCX document
ATTACHMENT 05 XGFG182004 Single Source Determination Monaco_Redacted.pdf PDF
EXHIBIT G PROPOSAL PRICE SCHEDULE.docx DOCX document
EXHIBIT D PAST PERFORMANCE REFERENCE QUESTIONNAIRE.docx DOCX document
EXHIBIT B SUBCONTRACTOR TEAM KEY PERSONNEL INFORMATION AND CONSENT FORM.doc DOC document
ATTACHMENT 02 XGFG182004 F 35 Alter B412 Drawings.pdf PDF
ATTACHMENT 03 XGFG182004 F35 Alter B412 Geotechnical Results.pdf PDF
ATTACHMENT 06 XGFG182004 Single Source Determination Marshall Best_Redacted.pdf PDF
ATTACHMENT 07 SFS FORM 12.xlsx XLSX spreadsheet
EXHIBIT C LETTER OF COMMITMENT.docx DOCX document
EXHIBIT A PERFORMANCE RELEVANCY QUESTIONNAIRE AND SPECIALIZED COMPANY EXPERIENCE.docx DOCX document
ATTACHMENT 01 XGFG182004 F35 Alter B412 Plans and Specifications.pdf PDF
W50S9F-22-R-0003.pdf PDF
EXHIBIT E SMALL BUSINESS PARTICIPATION PLAN FORMAT.docx DOCX document
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W50S9F22R0003; Alter B412 Q&A #03

19. UPDATED RESPONSE: Note 1/T102 - Please provide approximate length to server room in base ops in B404. Please confirm existing conduit that we are run fiber in runs.

A. Chord Lengths:

B412-MH0035: 45.01ft MH0035-MH0032: 160.10ft MH0032-MH0033: 320.54ft MH0033-B404: 171.56ft Total Length: 697.21ft

* Does not include length in manholes, length from building entrance to termination, or any maintenance loops. Contractor shall field verify the actual length of cable.

20. Please provide the existing roofing information – type, thickness, manufacturer, warranty?

A. See document Supplemental Information Document: XGFG112032 Repair B412, Alert Shelters -

EPDM Roof Submittal

21. Preaction System As-Builts - Are as-built drawings (showing the existing pipe sizing, pipe layout, sprinkler head locations) of the existing preaction fire suppression system available? These are necessary to determine what upgrades are required to the existing piping system to meet the proposed increased design density. They will also assist in determining the extent of work required to reroute piping for the new structural steel.

A. See document Suplemental Information Documents:

"B412 XGFG022024B&C Upgrade B412 Fire Supression System (2014)" "B412 XGFG022024B&C Wolverine Fire Protection (2014)"

22. High Expansion Foam System As-Builts - Are as-built drawings (showing the existing pipe sizing, pipe layout, foam generator locations) of the existing high expansion foam system available? These would assist with determining the extent of demolition work required. They will also assist in determining the amount of foam that must be disposed of.

A. See question 18.

23. High Expansion Foam System Signage - Drawing FX401 Sheet Keynote number one references installing signage at the foam concentrate tank. The other drawings indicate the high expansion foam system is being removed. Please confirm that the signage is not required.

A. Contract Drawing FX401 was deleted from the 02/18/2022 Issued For Bid set. High expansion foam systems and associated signage are not required.

24. The one line diagram on page on E701, on the new one line. On the electrical power plans they do not show any generator or ATS as shown on E701.

A. Existing generator to remain. New ATS to be located beside existing panel D.

25. Is it assumed the existing ground loop & Lighting protection system meets the standards laid out on the plans?

A. Yes, the current system meets standards.

26. Is Monaco the FA supplier? For parts and smarts?

A. Provide a Monaco MAAP-X FACU/ACU/FAC and a Det-Tronics Eagle Quantum Premier RSFACU in accordance with Contract Drawing FA001 General Note 1. Provide Det-Tronics

X3301 optical flame detectors in accordance with Contract Specification 28 31 76 section 2.10.

The contract documents do not require other fire alarm equipment to be by a specific manufacturer.

Provide equipment and devices in accordance with the fire alarm Contract Drawings and Contract Specification 28 31 76. All equipment and devices shall be compatible and operable with existing supervising station fire alarm system and shall not impair reliability of operational functions of existing supervising station fire alarm system per 28 31 76 section 1.7.

27. Are MG&E charges by WANG? Please confirm A. All costs associated with MG&E are contract costs. The Government does not have the ability to pay for MG&E costs outside of the construction contract.

28. General notes on T101 say that Advantor the security vendor, we shall get a price from them for the installation of this part, but on page T102 it says we are only supposed to sleeve the items for the government’s security vendor to do the installation, please advise what page is correct? Also if we are to provide a price for the system a contact to reach directly A. General Notes on T-101 shall read as follows:

1. REFER TO SHEETS T-001 AND T-002 FOR ELECTRICAL LEGEND.

2. INSTALL RACEWAYS, BOXES AND ASSOCIATE COMPONENTS FOR

GOVERNMENT FURNISHED SECURITY SYSTEM.

3. THE SECURITY AND CCTV EQUIPEMENT SHALL BE PROVIDED BY ADVANTOR.

ADVANTOR SHALL DO INTALLATION AND TESTING OF ALL SECUIRTY AND CCTV

SYSTEMS.

4. NOT ALL EXISTING OUTLET AND COMM DEVICES ARE SHOWN. IF DEVICE ARE

SHOWN LOCATIONS ARE BASED OFF AS BUILT DRAWINGS. THE CONTRACTOR

SHALL FIELD LOCATION.

The Government will provide the contractor with Advantor's submittal post-award.

29. A4 270V DC Input 480V/150A 3P Receptacle please provide more information on specific model required. Shown on one line E701 A. Refer to detail A1 on sheet E-501 for receptacle A4, B4, C4 and D4 detail.

30. I would to clarify if it includes any epoxy flooring.

A. Epoxy flooring is not considered in the scope of work.