These are pre-bid conference slides for a solicitation by the Tennessee National Guard to construct a new Network Control Center. The contract (W50S97-25-B-A002) is a firm-fixed-price, 100% small business set-aside for constructing an approximately 1,500 square foot building (B818) at Berry Field Air National Guard Base in Nashville. The project has an estimated value between $1-5 million, with a 365-calendar day performance period after notice to proceed. Key requirements include using specific branded systems for energy management, direct digital controls, computer room air conditioning, and fire suppression to ensure compatibility with existing installations.
The pre-bid conference is scheduled for 16 July 2025, with a site visit to follow. Bids are due by 1:00 PM CST on 1 August 2025, and must be submitted electronically with a bid bond. Interested contractors must be registered in the System for Award Management (SAM), submit questions by 9 July 2025 via specified email addresses, and comply with subcontracting limitations, including not paying more than 85% of the contract amount to non-similarly situated subcontractors. The solicitation, specifications, and amendments will be posted exclusively on SAM.gov.
View the file
Other files for this federal contract opportunity
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W50S97-25-B-A002 BKTZ222001- Construct Network Control Center CLIN 001 - Construction CLIN 002 - Communications Pre-Bid Conference
16 July 2025
118 MSC
BERRY FIELD ANGB
NASHVILLE, TN
INTRODUCTION
• Capt Greg Allen– Contracting Officer
• MSgt Jonathan Forren – Contract Specialist
• Lt Col Nathan Smith– COR/Technical Representative
SYNOPSIS
• Construct Network Control Center, B818
• The estimated cost range -$1,000,000 and $5,000,000.
• A firm-fixed price contract will be awarded.
• Award is 100% small businesses (NAICS – 236220)
• Small Business Size Standard is $45 Million
• Based on FY Funds availability.
• Award will be made to the responsible bidder whose bid conforms to the invitation for bids and is most advantageous to the government will consider only price and price related factors. The government intends to award without discussions.
• Automated Logic Energy Management System (EMS) for Direct Digital Controls (DDC), Vertiv Liebert units for Computer Room Air Conditioning (CRAC) system and Monaco fire system are sole source/brand name specific for compatibility with existing installation systems, justifications posted with solicitation.
SOLICITATION, PLANS
& SPECIFICATIONS
• On the web: https://www.sam.gov/
• Solicitation
• Specifications
• Drawings
• Statement of Work
• Questions & Answers document
• Pre-Bid presentation
• Amendments
• check regularly & refresh web page
IFB
• In the invitation for bid (IFB), FAR Part 14, process, a public bid opening occurs when the bids are due and the prices are read to the public
• There can be no discussion
• No correction of mistakes in most cases
• Award is always to the low responsible bidder
CONTRACT PERIOD
Construction period is 365 calendar days after receiving the Notice to Proceed
BID PACKAGE IN ACCORDANCE WITH SECTION 00010
NOTES, NOTE 11
• Offer, Standard Form (SF) 1442 front and back signed
• Section 00 10 00 Line Items- all items must be priced
• A valid Bid Bond. Standard Form 24. Section 00 21 00 – Clause 52.228-1.
• Section 00 70 00, Representations and Certifications, completed and return only additional certifications found in this section In addition, the offeror must have entered current and complete data within the past year in Online Representations and Certifications at https://www.sam.gov see 52.204-8 in solicitation
• ALERT: If you are registering a new entity in SAM.gov, you must provide an original, signed notarized letter stating that you are the authorized Entity Administrator before your registration will be activated.
BID PACKAGE IN ACCORDANCE WITH SECTION 00 10 00
NOTES, NOTE 11 - Continued
• When completing the “Offeror” portion of the SF 1442 (Blocks 14 – 20), an official having the authority to contractually bind the company must sign the SF 1442 in accordance with FAR 4.102. One copy of the SF1442 is required to have an original signature. Section 00 10 00 Line Items- all items must be priced
• All amendments to the solicitation must be acknowledged.
• Mark the front of the envelope with the following: “BID No. W50S97-25-B-A002 and the Name and Address of Bidder. See Block 13A of SF 1442 for required number of copies.
BID PACKAGE IN ACCORDANCE WITH SECTION 00010
NOTES, NOTE 11 - Continued
• ALL ITEMS ON THE PREVIOUS SLIDES ARE IN THE SOLICITATION INSTRUCTIONS. IT IS THE
RESPONSIBILITY OF THE BIDDER TO MAKE SURE THAT THEIR BID CONFORMS TO THE
SOLICITATION.
BID DUE DATES
Bids are due 1:00 P.M. (CST)
01 August 2025
Proposal must be signed by officer of your company
Electronic offers will be accepted, must have before bid opening and with bid bond
IMPORTANT REMINDERS
• All questions and requests for information (RFI) must be received NOT LATER THAN the fifth working day prior to bid opening.
• OFFERORS ARE STRONGLY ENCOURAGED TO SUBMIT QUESTIONS EARLY IN THIS PROCESS.
• Contractor must submit information listed in Section 00 21 00 Notes, paragraph 4.2 in order to gain access to installation for dropping off bids. Delivery must allow for vehicle inspection time at gate. Additional information will be requested after request such as DBIDS pre-enrollment. If cleared for site visit then you should already cleared for bid drop off and opening.
• Wage determination TN20240178 , Dated 06/06/2025, Building is applicable
HELPFUL WEBSITES
https://www.sam.gov https://www.aptac-us.org/ https://www.sam.gov/ https://www.aptac-us.org/
HOW QUESTIONS WILL BE HANDLED
• Questions must be submitted in writing only via email to:
gregory.allen.8@us.af.mil and jonathan.forren@us.af.mil
• Use Format in Section 00 21 00, Para 5.1
• DO NOT CALL TECHNICAL PERSONNEL OR A&E- THIS WILL DELAY GETTING AN ANSWER
• Due 5 business days prior to Bid Opening mailto:gregory.allen.8@us.af.mil mailto:jonathan.forren@us.af.mil
ANSWERS TO QUESTIONS
• All questions, on a non-attribution basis, and the answers will be posted to the web site https://www.sam.gov/
• If necessary addendums, issued by an amendment, will also be posted
• Check web site regularly and don’t forget to refresh web page!!
IMPORTANT
OFFERORS ARE STRONGLY CAUTIONED TO CAREFULLY READ THE REQUIREMENTS OF THE
SOLICITATION AND COMPLY ACCORDINGLY
**POSSIBLE THE COMMUNICATION LINE ITEMS WILL BE SPLIT INTO 2 LINE ITEMS. 1 JUST
FOR THE RACKS AND THE OTHER FOR THE REST OF THE ITEMS. IF THIS IS CASE AND
AMENDMENT WILL BE SUBMITTED ON SAM.GOV**
Questions ???
Site Visit Follows This Briefing
| �W50S97-25-B-A002�BKTZ222001- Construct Network Control Center�CLIN 001 - Construction�CLIN 002 - Communications������ |
| INTRODUCTION |
| SYNOPSIS |
| SOLICITATION, PLANS�& SPECIFICATIONS |
| IFB |
| CONTRACT PERIOD |
| BID PACKAGE IN ACCORDANCE WITH SECTION 00010 NOTES, NOTE 11 |
| BID PACKAGE IN ACCORDANCE WITH SECTION 00 10 00 NOTES, NOTE 11 - Continued |
| BID PACKAGE IN ACCORDANCE WITH SECTION 00010 NOTES, NOTE 11 - Continued |
| BID DUE DATES |
| IMPORTANT REMINDERS |
| HELPFUL WEBSITES |
| HOW QUESTIONS WILL BE HANDLED |
| ANSWERS TO QUESTIONS |
| IMPORTANT |
| Questions ??? |
File details come from the government source that posted it. Updated .