Fuel Cell_Pre_Bid_Site_Visit.pdf

PDF 999 KB Posted

Attached to
Maine Air National Guard Fuel Cell Hangar Construction
Solicitation number
W50S8326BA001
Issued by

About this file

This is a Pre-Bid Conference presentation for a federal construction contract regarding the Maine Air National Guard Fuel Cell Hangar Construction project.

The solicitation is an Invitation for Bid (IFB) designated W50S83-26-B-A001 (Project #FKNN159044) under the Revolutionary FAR Overhaul (RFO) framework. This is a 100% small business set-aside for commercial and institutional building construction (NAICS Code 236220) with a size standard of $45,000,000. The contract involves a 670 calendar day period of performance and requires a bid guarantee of 20% of the bid price or $3,000,000, whichever is less. Bids are due June 3, 2026 at 10:00 AM local time with bid opening at the same date and time at Maine Air National Guard, Building 505, Bangor International Airport, Maine. The procuring agency is the 101st Air Refueling Wing/Message Squadron under the Department of Defense.

The contract structure includes six contract line items (CLINs): five base bid items covering fuel cell hangar construction, PFAS sampling, PFAS dewatering, soil disturbance and disposal, and demolition material disposal; plus one additive option item for satellite parking. Bidders must price all items or risk non-responsive bids. Award will be based solely on price and price-related factors, with an Independent Government Estimate (IGE) determining whether the additive item is evaluated. Key requirements include submission of signed SF 1442 forms, priced bid schedules, bid bonds (SF 24), completed representations and certifications, acknowledgement of all amendments, and an executed Project Labor Agreement prior to award. Critical site considerations include PFAS-contaminated soils requiring sampling and treatment, Foreign Object Damage (FOD) prevention due to airfield proximity, temporary fencing with multiple phases, and DigSafe utility locating requirements. The contracting officer is 1st Lt Cameron M. Doncet Hall; the contract specialist is MSgt Daniel Boone; and the COR is 1st Lt Tyler Field.

View the file

Other files

File Type Posted
Conformed_W50S8326BA0010009.pdf PDF
Solicitation Amendment W50S8326BA0010009 SF 30.pdf PDF
OF_1419_Signed.pdf PDF
Bid Opening Attendance.pdf PDF
W50S8326BA001_RFIs 2_responses.pdf PDF
Conformed_W50S8326BA0010008.pdf PDF
Solicitation Amendment W50S8326BA0010008 SF 30.pdf PDF
Solicitation Amendment W50S8326BA0010007 SF 30.pdf PDF
ATTACHMENT 12 - ME ANG Fuel Cell Hangar_ARCH AMD 07.pdf PDF
ATTACHMENT 11 - 22 00 00_AM07 20Jul26.pdf PDF
Solicitation Amendment W50S8326BA0010006 SF 30.pdf PDF
Conformed_W50S8326BA0010006.pdf PDF
Conformed_W50S8326BA0010005.pdf PDF
RFI_responses_W50S8326BA001.pdf PDF
Solicitation Amendment W50S8326BA0010005 SF 30.pdf PDF
Fuel Cell_Pre_Bid_Site_Visit_Attendance.pdf PDF
Solicitation Amendment W50S8326BA0010004 SF 30.pdf PDF
Conformed_W50S8326BA0010004.pdf PDF
Solicitation Amendment - W50S8326BA0010003 Professional Appearance.pdf PDF
Solicitation Amendment W50S8326BA0010003 SF 30.pdf PDF
Solicitation Amendment - W50S8326BA0010002 Professional Appearance.pdf PDF
Solicitation Amendment W50S8326BA0010002 SF 30.pdf PDF
Solicitation Amendment W50S8326BA0010001 SF 30.pdf PDF
Solicitation Amendment - W50S8326BA0010001 Professional Appearance.pdf PDF
W50S8326BA001 FKNN159044 MeANG Fuel Cell Hangar Construction.pdf PDF
Sheet List Drawings_Volume I of II.pdf PDF
ATTACHMENT 7 - Appendix I1 Bangor Fuel Cell Hangar-Exterior Materials Package-RTA.pdf PDF
ATTACHMENT 8 - Appendix I2 Bangor Fuel Cell Hangar - SID Package - RTA.pdf PDF
Sheet List Drawings_Volume II of II.pdf PDF
ATTACHMENT 10 - Brand Name Item JA FKNN159044 Construct Tanker Fuel Cell_Redacted.pdf PDF
ATTACHMENT 9 - REGISTER.pdf PDF
ATTACHMENT 1 - SOW - FKNN159044 Construct Tanker Fuel Cell.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Maine Air National Guard Fuel Cell Hangar Construction W50S83-26-B-A001

Project #: FKNN159044 Pre-Bid Conference/Site Visit

12 MAY 2026

POINTS OF CONTACT

• Contracting Officer: 1st Lt Cameron M. Doncet

Hall

• cameron.doncet_hall.2@us.af.mil

• 101.msg.msc.contracting@us.af.mil

• Contract Specialist: MSgt Daniel Boone

• daniel.boone.5@us.af.mil

• Contracting Officer Representative (COR): 1st Lt Tyler Field

• tyler.field@us.af.mil https://www.google.com/url?q=mailto%3Acameron.doncet_hall.2%40us.af.mil https://www.google.com/url?q=mailto%3Acameron.doncet_hall.2%40us.af.mil https://www.google.com/url?q=mailto%3A101.msg.msc.contracting%40us.af.mil https://www.google.com/url?q=mailto%3A101.msg.msc.contracting%40us.af.mil https://www.google.com/url?q=mailto%3Adaniel.boone.5%40us.af.mil https://www.google.com/url?q=mailto%3Adaniel.boone.5%40us.af.mil https://www.google.com/url?q=mailto%3Atyler.field%40us.af.mil https://www.google.com/url?q=mailto%3Atyler.field%40us.af.mil

W50S83-26-B-A001

IFB SUMMARY

• Procurement Method: Sealed Bidding (IFB) under Revolutionary FAR Overhaul (RFO)

• Set Aside: 100% Small Business

• NAICS Code: 236220 - Commercial and Institutional Building Construction

• Size Standard: $45,000,000

• Period Of Performance: 670 Calendar Days

• Bid Guarantee: 20% of the bid price or $3,000,000.00, whichever is less.

• Bids Due: 03 June 2026, 10:00 AM Local Time (Amendment #1)

CLIN Structure & Pricing

CLIN Description Type 0001 Base Bid - Construction of Fuel Cell Hangar Base 0002 Base Bid - PFAS Sampling Base 0003 Base Bid - PFAS Dewatering Base 0004 Base Bid - Soil Disturbance and Disposal Base 0005 Base Bid - Demolition Material and Disposal Base 0006 Additive Bid Item - Satellite Parking Option

Bidders MUST submit a price for EVERY line item.

Failure to price all items will render the bid non-responsive.

Instructions to Bidders – Critical Requirements

Bid Submission: Bids must be submitted to the address in Item 8 of the SF 1442 before the exact time and date specified. Late bids will not be considered.

Complete Bid Package:

Signed SF 1442 (front and back).

Priced Bid Schedule (Section 00 10 00).

Bid Bond (SF 24) and Power of Attorney.

Completed Representations and Certifications (Section 00 45 00).

Acknowledgement of all solicitation amendments.

Project Labor Agreement (PLA): The apparent successful offeror must submit an executed PLA prior to award.

Bid Opening Bid repository for hand carried bids located at

101st Air Refueling Wing/MSG, Base Contracting Office, Bldg. 505, MEANG, Bangor IAP, ME.

Late receipt of bids due to entry delays may not be deemed excusable and the Contracting Officer may declare the bid “late” in accordance with FAR 14.304.

Bid opening: 03 June 2026, 1000Hrs, Maine Air National Guard, Large Classroom Bldg. 505 Bangor IAP, Bangor, ME

BASIS FOR AWARD

• Primary Factors: Price and Price-Related Factors Only

• Evaluation Process (Reference DFARS 252.236-7007):

1. The Independent Government Estimate (IGE) for the base bid (CLINs 0001-0005) is recorded.

2. Bids are evaluated.

3. If a bidder's base amount (CLINs 0001-0005) is HIGHER than the IGE base amount, the additive item (CLIN 0006) is NOT considered.

4. If a bidder's base amount is UNDER the IGE base amount, the additive item (CLIN

0006) is evaluated to determine the apparent low bidder.

• Award: The Government must award to the responsible bidder whose bid conforms and is most advantageous, considering only evaluated price.

1. Responsibility is determined IAW RFO FAR 9.104

Presenter Notes Presentation Notes

PROJECT OVERVIEW

W50S83-20-B-0002

SITE PLAN

FUEL CELL HANGAR SITE

SATELLITE PARKING SITE

TEMPORARY FENCING

FOREIGN OBJECT DAMAGE

BASE ACCESS

PFAS

- GENERAL CIVIL NOTE #1 C-001

- GENERAL DEM0LITON NOTE #5 C-001

Presenter Notes Presentation Notes

DIGSAFE

- GENERAL CIVIL NOTE #16 C-001

SUBMITTALS

SUBMIT ELECTRONIC FILES VIA

PROJECT MANAGEMENT SOFTWARE

PROVIDED BY THE CONTRACTOR

ALLOW 10 BUSINESS DAY FOR

COORDINATION (14 CALENDAR DAYS)

- SPEC 01 33 00

FAR 52.236-21

Specifications and Drawings for Construction.

This clause provides the guidance that anything mentioned in the specifications and not shown on the drawings or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both.

Furthermore, in the case of difference between drawings and specifications, the specifications shall govern.

IMPORTANT ITEMS

Revolutionary FAR Overhaul (RFO): This solicitation is governed by the RFO framework. Provisions are identifiable by "RFO" or deviation numbers starting with "2026-O". Do not rely on legacy FAR versions.

Site Visit: Stay with the group. No photos are permitted.

Requests for Information (RFIs):

All questions must be submitted in writing via email.

Deadline: 7 working days prior to bid opening.

Verbal answers are not binding. Only written amendments change the solicitation.

System for Award Management (SAM): Prospective awardees must have an active registration in SAM.gov at the time of bid submission and award.

Clarifications?

Reminder ALL questions shall be submitted in writing.

Responses to “questions/clarifications” are not official until written responses are received.

Maine Air National Guard Fuel Cell Hangar Construction�W50S83-26-B-A001�Project #: FKNN159044�Pre-Bid Conference/Site Visit
POINTS OF CONTACT
W50S83-26-B-A001 �IFB SUMMARY
CLIN Structure & Pricing
Instructions to Bidders – Critical Requirements
Bid Opening
BASIS FOR AWARD
PROJECT OVERVIEW�W50S83-20-B-0002
SITE PLAN
FUEL CELL HANGAR SITE
SATELLITE PARKING SITE
TEMPORARY FENCING
FOREIGN OBJECT DAMAGE
BASE ACCESS
PFAS
DIGSAFE
SUBMITTALS
FAR 52.236-21
IMPORTANT ITEMS
Clarifications?

File details come from the government source that posted it. Updated .