ATTACHMENT 8 - Appendix I2 Bangor Fuel Cell Hangar - SID Package - RTA.pdf

PDF 17 MB Posted

Attached to
Maine Air National Guard Fuel Cell Hangar Construction
Solicitation number
W50S8326BA001
Issued by

About this file

This document is a Structural Interior Design (SID) Type B-3 Submittal for the ME ANG Fuel Cell Hangar project at Bangor Air National Guard Base in Maine (Project No. FKNN159044), prepared by BlairRemy Architects and Otie Merrick in August 2025.

The submittal establishes comprehensive interior design standards for a new 101st Air Refueling Wing fuel cell hangar facility. The design incorporates a cool, analogous color scheme with materials prioritizing durability, appearance retention, and sustainability. Color blocking is utilized as a visual cue to maintain personnel flow from dirty to clean areas, with green-painted partitions in clean spaces and gray-painted partitions in dirty areas. Key interior finishes include lay-in acoustic ceiling tiles in offices and corridors; moisture and mold-resistant gypsum board in wet areas; exposed painted structure in the hangar bay, tool room, and support areas. Flooring specifications vary by space: 5-coat fuel-resistive epoxy with slip-resistant finish in vestibules, corridors, hangar bay, tool room, and restrooms per UFC 4-211-01; sheet linoleum in the supervisor's office; and static-dissipative vinyl tile in the communications room. Restrooms feature porcelain tile wainscot with full-height tile at lavatories, solid phenolic toilet partitions, acrylic shower basins, and solid surface material surrounds. The multipurpose room includes plastic laminate casework, solid surface countertops, and porcelain tile backsplash. Stainless-steel corner guards protect exposed gypsum board corners. Interior signage complies with UFC 3-120-01, including confined space, PSI notification, and eyewash/shower station signage within the hangar bay. The submittal includes finish material samples, architectural floor plans, interior elevations, room finish schedules, casework sections, and detailed signage specifications with mounting requirements and location plans across multiple areas of the facility.

View the file

Other files

File Type Posted
Conformed_W50S8326BA0010009.pdf PDF
Solicitation Amendment W50S8326BA0010009 SF 30.pdf PDF
OF_1419_Signed.pdf PDF
Bid Opening Attendance.pdf PDF
Conformed_W50S8326BA0010008.pdf PDF
W50S8326BA001_RFIs 2_responses.pdf PDF
Solicitation Amendment W50S8326BA0010008 SF 30.pdf PDF
Solicitation Amendment W50S8326BA0010007 SF 30.pdf PDF
ATTACHMENT 12 - ME ANG Fuel Cell Hangar_ARCH AMD 07.pdf PDF
ATTACHMENT 11 - 22 00 00_AM07 20Jul26.pdf PDF
Solicitation Amendment W50S8326BA0010006 SF 30.pdf PDF
Conformed_W50S8326BA0010006.pdf PDF
Solicitation Amendment W50S8326BA0010005 SF 30.pdf PDF
Conformed_W50S8326BA0010005.pdf PDF
RFI_responses_W50S8326BA001.pdf PDF
Fuel Cell_Pre_Bid_Site_Visit.pdf PDF
Fuel Cell_Pre_Bid_Site_Visit_Attendance.pdf PDF
Solicitation Amendment W50S8326BA0010004 SF 30.pdf PDF
Conformed_W50S8326BA0010004.pdf PDF
Solicitation Amendment W50S8326BA0010003 SF 30.pdf PDF
Solicitation Amendment - W50S8326BA0010003 Professional Appearance.pdf PDF
Solicitation Amendment - W50S8326BA0010002 Professional Appearance.pdf PDF
Solicitation Amendment W50S8326BA0010002 SF 30.pdf PDF
Solicitation Amendment - W50S8326BA0010001 Professional Appearance.pdf PDF
Solicitation Amendment W50S8326BA0010001 SF 30.pdf PDF
ATTACHMENT 9 - REGISTER.pdf PDF
Sheet List Drawings_Volume II of II.pdf PDF
ATTACHMENT 10 - Brand Name Item JA FKNN159044 Construct Tanker Fuel Cell_Redacted.pdf PDF
W50S8326BA001 FKNN159044 MeANG Fuel Cell Hangar Construction.pdf PDF
Sheet List Drawings_Volume I of II.pdf PDF
ATTACHMENT 7 - Appendix I1 Bangor Fuel Cell Hangar-Exterior Materials Package-RTA.pdf PDF
ATTACHMENT 1 - SOW - FKNN159044 Construct Tanker Fuel Cell.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ME ANG Fuel Cell Hangar

Bangor, Maine

Project Number: FKNN159044

SID Package— Type B-3 Submittal

AUGUST 2025

Prepared for:

Maine Air National Guard

Prepared by:

601 NE 63rd Street

Oklahoma City, OK 73105

5970 Greenwood Plaza Boulevard

Greenwood Village, CO 80111

This page intentionally left blank.

Structural Interior Design (SID)

Project No. FKNN159044

TABLE OF CONTENTS

PART 1— SID NARRATIVE

PART 2—INTERIOR FINISH SAMPLES

PART 3—DRAWINGS

Finish Materials List Floor Pattern Plans Striping Plans Room Finish Schedule Interior Elevations Casework Sections Signage

Project No. FKNN159044

PART 1

SID NARRATIVE

Project No. FKNN159044

SID NARRATIVE

DESIGN REFERENCES:

ANGETL 15-01 Air National Guard Design Policy

ANGETL 10-03 Air National Guard Design Objectives and Procedures

UFC 3-120-01 Design: Sign Standards, with Change 4

UFC 3-120-10 Interior Design, with Change 2

UFC 4-211-01 Aircraft Maintenance Hangars

UFC 4-211-02 Aircraft Corrosion Control and Paint Facilities

101 CES/CE Memorandum for Paint Standardization

101 CES/CE Memorandum for Flooring Standardization

101 CES/CE Memorandum for Acoustical Ceiling Tiles

INTRODUCTION:

This project will provide a Fuel Cell Hangar for the 101st Air Refueling Wing (101 ARW) of the Maine Air

National Guard (ME ANG). The new facility will include a Hangar Bay, clean and dirty restrooms and showers, Tool Room, Supervisor’s Office, Multipurpose Room which will function as both a break room and open office, and building support spaces.

COMPREHENSIVE INTERIOR DESIGN (CID)

The goal of the Comprehensive Interior Design (CID) for the new Fuel Cell Hangar is to create a safe, functional, and attractive space in which to carry out the mission of 101 ARW.

FURNITURE, FIXTURES AND EQUIPMENT (FF&E)

The FF&E package has been provided under a separate cover.

EXTERIOR FINISHES

The Exterior Finish package has been provided under a separate cover.

STRUCTURAL INTERIOR DESIGN (SID).

The design of the project includes the selection and coordination of interior and exterior materials and finishes.

These finishes have been selected from a cool, analogous color scheme compatible with the character of the surrounding facilities. Materials and finishes selected prioritize durability, appearance retention and sustainability.

Project No. FKNN159044

Color blocking has been utilized as a visual cue to assist in maintaining the flow of personnel from dirty to clean areas of the facility. Partitions in rooms designated as clean spaces will receive a green painted finish, and those occurring in rooms designated as dirty will receive gray.

Exposed outside gypsum wall board corners will receive stainless-steel corner guards.

Ceilings, Doors, and Windows

Lay-in Acoustic Ceiling Tile (ACT) will be provided in the Supervisor’s Office, Multipurpose Room, and

Corridors. Moisture and mold resistant gypsum board will be used in all wet areas, such as Restrooms, Showers, and Locker Rooms. Gypsum board will also be provided in the Vestibule and Comm Room. The

Hangar Bay, Tool Room, Janitor Closet, and building support areas will be exposed to the structure above and painted.

Doors will have metal leaves, and both doors and windows will have metal frames. All will receive a painted finish. Windows will receive an Soild Surface Material (SSM) sill to provide a durable and maintainable surface. Light filtering roller shades will be provided at all windows for visual privacy and glare control.

Vestibules and Corridors

Both corridors provide direct access to the Hangar Bay; they will receive a 5-coat, fuel-resistive epoxy flooring with slip resistant finish in accordance with UFC 4-211-01. A recessed entry mat will be provided at the Vestibule, and both spaces will receive resilient rubber wall base, and painted partitions.

Supervisor’s Office (Clean)

The private office will receive sheet linoleum flooring in accordance with Installation standards, along with resilient rubber wall base, and painted partitions.

Multipurpose Room

The multipurpose will serve as an open office space, and a break room. Finishes will include sheet linoleum flooring, resilient rubber wall base, painted partitions, plastic laminate casework, SSM countertops, and a porcelain tile backsplash.

Restrooms, Showers, and Locker Rooms

Restrooms, Showers, and Locker Rooms will receive epoxy flooring with slip resistant finish, and porcelain tile wainscot with painted moisture and mold resistant gypsum board above. Full height wall tile will be installed at lavatories to eliminate the need for spacers when installing mirrors and other wall mounted accessories.

SSM surround will be provided at shower stalls as well as acrylic shower basins. Toilet and urinal partitions will be solid phenolic material. Dual-height lockers and benches will be provided in the Locker Rooms.

Wall paint and partitions will follow the color blocking system described above.

Project No. FKNN159044

Hangar Bay and Tool Room

Both rooms will receive 5-coat, fuel-resistive epoxy flooring with slip resistant finish in accordance with UFC 4-211-

01. Partitions in the Hangar Bay will be concrete masonry units (CMU), with prefinished insulated metal panels above. CMU partitions have also been planned for the Tool Room. Masonry will receive a gray painted finish to better mask soiling and signs of wear, and wall base will not be provided as it is not necessary.

The Hangar Bay will be receive safety markings in accordance with UFC 4-211-01.

Janitor

The Janitor Closet will receive sealed concrete flooring, resilient rubber wall base, and painted partitions. A stainless-steel floor sink will be provided to minimize periodic maintenance as is required by terrazzo. Fiber-

Reinforced Plastic (FRP) panels will be used around the floor sink protect the surrounding wall board from impact and/or water damage.

Comm Room

The Comm Room will receive Static-Dissipative (SD) vinyl tile, resilient rubber wall base, painted partitions, and unpainted, fire-retardant plywood to serve as a substrate for wall mounted equipment.

Signage

Signage will be provided in the interior of the building in accordance with UFC 3-120-01. Confined space signage will be provided at the hangar door pockets, PSI notification signage will be provided at all air hose reel locations in the Hangar Bay, and eye wash/shower notification signage will be provided at all instances in the Hangar Bay.

Refer to the Exterior Finishes package for exterior signage.

Project No. FKNN159044

PART 2

INTERIOR FINISH SAMPLES

Project No. FKNN159044

PART 3

DRAWINGS

Table of Contents
Part 1 - SID Narrative
Part 2 - Interior Finish Samples
Part 3 - Drawings