This solicitation seeks proposals for execution of the USS TRIPOLI (LHA 7) FY23 Selected Restricted Availability. The Naval Sea Systems Command will award a single contract to complete maintenance, modernization, and repair requirements aboard the ship over approximately 12 months beginning in March 2023. Interested parties must register in the System for Award Management and monitor the solicitation on SAM.gov, where amendments will be posted. While set aside for small businesses was considered due to complexity and magnitude, the requirement will not be so designated. Requests for additional attachments containing execution milestones, pricing workbooks, and compartment closeout details should be directed to specified Navy personnel. Proposals are due in or around December 2022, with award anticipated that same month.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Prioritized List
| USS TRIPOLI (LHA 7) FY23 SRA - J-10 Milestone Reports Due | |||||
| No. | Work Item | Title | Para. | Milestone | |
| 1 | 123-10-001 | Tank and Void; Open, Cleaning and Pumping; accomplish | 3.1.3, 3.5.1.2 | 20% Open/Inspect (High Priority) | |
| 2 | 123-11-001 | Compensated Fuel Tank; repair | 3.1.1 | 20% Open/Inspect (High Priority) | |
| 3 | 123-14-002 | Water Mist Stowage Tank; repair | 3.1.1 | 20% Open/Inspect (High Priority) | |
| 4 | 123-14-003 | Potable Water Tank Base Metal; repair | 3.1.1 | 20% Open/Inspect (High Priority) | |
| 5 | 123-16-001 | Ballast Tank; repair | 3.1.1 | 20% Open/Inspect (High Priority) | |
| 6 | 123-17-001 | Contaminated Oil Tank; repair | 3.1.1 | 20% Open/Inspect (High Priority) | |
| 7 | 123-19-001 | Collection, Holding and Transfer (CHT) Tank; repair | 3.1.1 | 20% Open/Inspect (High Priority) | |
| 8 | 123-20-001 | Accessible Void; repair | 3.1.1 | 20% Open/Inspect (High Priority) | |
| 9 | 167-11-001 | Bolted Equipment Removal Plate (BERP); remove | 3.2.1 | 20% Open/Inspect (High Priority) | |
| 10 | 234-11-002 | Pipe Hanger Liner; install | 3.1.1 | 20% Open/Inspect (Low Priority) | |
| 11 | 237-10-001 | Number 2 Auxiliary Propulsion Motor (APM) Bearing Seal; | |||
| replace | 3.5.4.1 | 20% Open/Inspect (High Priority) | |||
| 12 | 241-11-001 | Number One Main Reduction Gear (MRG) Gasket; replace (Option Item) | 3.5.2.1 & 3.7.1.2 | 20% Open/Inspect (High Priority) | |
| 13 | 241-12-001 | Number 2 Main Reduction Gear (MRG) Gasket; replace (Option Item) | 3.5.2.1 & 3.7.1.2 | 20% Open/Inspect (High Priority) | |
| 14 | 262-41-001 | Number 1A Lube Oil Service Pump (LOSP) Mechanical Seal; replace | 3.5.5.1 | 20% Open/Inspect (High Priority) | |
| 15 | 262-41-002 | Number 1B Lube Oil Service Pump (LOSP) Mechanical Seal; replace | 3.5.5.1 | 20% Open/Inspect (High Priority) | |
| 16 | 262-41-003 | Number One Main Lube Oil Cooler Clean and Inspect; accomplish | 3.2.2.2 | 20% Open/Inspect (High Priority) | |
| 17 | 262-42-001 | Number 2A Lube Oil Service Pump (LOSP) Mechanical Seal; replace | 3.5.5.1 | 20% Open/Inspect (High Priority) | |
| 18 | 262-42-002 | Number 2 Main Lube Oil Cooler Clean and Inspect; accomplish | 3.2.2.2 | 20% Open/Inspect (High Priority) | |
| 19 | 264-31-001 | Main Engine Room 2 Main Reduction Gear (MRG) and Controllable Pitch Propeller (CPP) Lube Oil Purifier Heater; clean | 3.2.2.1 & 3.3.6 | 20% Open/Inspect (High Priority) | |
| 20 | 264-32-001 | Main Engine Room One Main Reduction Gear (MRG) and Controllable Pitch Propeller (CPP) Lube Oil Purifier Heater; clean | 3.2.2.1 & 3.3.6 | 20% Open/Inspect (High Priority) | |
| 21 | 321-11-001 | Multi Cable Transit (MCT) Block; repair | 3.1.1 | 20% Open/Inspect (High Priority) | |
| 22 | 321-11-003 | Chaffing Ring, Multi-Cableway Hanger/Standoff and Clamp; install | 3.1.1 | 20% Open/Inspect (Low Priority) | |
| 23 | 321-11-005 | Stuffing Tube; repair | 3.2.1 | 20% Open/Inspect (High Priority) | |
| 24 | 321-23-001 | Rectifier; repair | 3.1.2 | 20% Open/Inspect (High Priority) | |
| 25 | 331-11-001 | Terminal Box; install | 3.1.1 | 20% Open/Inspect (Low Priority) | |
| 26 | 441-71-001 | Antenna AS-4667/WSC-9(V)1 Radome, Foundation, and Access Hatch; preserve | 3.1.4.1, 3.1.7.1 | 20% Open/Inspect (High Priority) | |
| 27 | 456-09-001 | SPQ-9B Antenna Bracket; replace | 3.1.1 | 20% Open/Inspect (High Priority) | |
| 28 | 512-11-001 | Ventilation Ducting; replace | 3.1.1 | 20% Open/Inspect (Low Priority) | |
| 29 | 512-11-003 | Cooling Coil; replace | 3.1.1 | 20% Open/Inspect (High Priority) | |
| 30 | 512-11-006 | Ventilation Ducting; repair | 3.1.1 | 20% Open/Inspect (Low Priority) | |
| 31 | 512-11-013 | Fan Coil Unit 1-12-3 Differential Pressure Gauge; replace | 3.1.1 | 20% Open/Inspect (Low Priority) | |
| 32 | 512-11-016 | 01 Level Fan Room; repair | 3.1.1 | 20% Open/Inspect (Low Priority) | |
| 33 | 514-11-002 | Chill Water Valve and Remote Operator; repair | 3.1.1 | 20% Open/Inspect (High Priority) | |
| 34 | 514-20-001 | Air Conditioning Plant Condenser Water Control Valve (CWCV); replace | 3.1.1 | 20% Open/Inspect (High Priority) | |
| 35 | 514-21-001 | Number One Air Conditioning (AC) Plant Condenser; mechanically clean | 3.1.5 | 20% Open/Inspect (High Priority) | |
| 36 | 514-22-001 | Number 2 Air Conditioning (AC) Plant Condenser; mechanically clean | 3.1.5 | 20% Open/Inspect (High Priority) | |
| 37 | 514-23-001 | Number 3 Air Conditioning (AC) Plant Condenser; mechanically clean | 3.1.5 | 20% Open/Inspect (High Priority) | |
| 38 | 514-23-002 | Air Conditioning (AC) Plant Number 3 Seawater Pump; replace | 3.3.1.1 | 20% Open/Inspect (High Priority) | |
| 39 | 514-24-001 | Number 4 Air Conditioning (AC) Plant Condenser; mechanically clean | 3.1.5 | 20% Open/Inspect (High Priority) | |
| 40 | 514-24-003 | Air Conditioning (AC) Plant Number 4 Seawater Pump; replace | 3.3.1.1 | 20% Open/Inspect (High Priority) | |
| 41 | 514-25-001 | Number 5 Air Conditioning (AC) Plant Condenser; mechanically clean | 3.1.5 | 20% Open/Inspect (High Priority) | |
| 42 | 514-25-003 | Number 5 Air Conditioning (AC) Plant Seawater Pump; repair | 3.2.4.1 & 3.3.5.2 | 20% Open/Inspect (High Priority) | |
| 43 | 524-10-001 | Flush Overboard Isolation Valve (6G-ASW-V-30) Rigid Rod Extension; fabricate and install | 3.1.2 | 20% Open/Inspect (Low Priority) | |
| 44 | 529-11-002 | Remote Valve Operator Teleflex Cable; replace | 3.3.1.1 | 20% Open/Inspect (High Priority) | |
| 45 | 529-11-003 | Overboard Discharge Valve Teleflex Cable Assembly; Replace | 3.2.2.1 | 20% Open/Inspect (High Priority) | |
| 46 | 529-11-005 | Secondary Drainage Valve and Remote Valve Operator Reach Rod; repair | 3.1.2 | 20% Open/Inspect (High Priority) | |
| 47 | 529-11-009 | Eductor Overboard Discharge Valve; replace | 3.2.1.1 | 20% Open/Inspect (High Priority) | |
| 48 | 529-11-014 | Secondary Drainage Valve and Remote Operator Teleflex Cable Assembly; repair | 3.2.1 | 20% Open/Inspect (High Priority) | |
| 49 | 529-11-015 | Eductor Suction Valve and Remote Operator Teleflex Assembly; repair | 3.2.1 | 20% Open/Inspect (High Priority) | |
| 50 | 541-11-002 | Auxiliary Fuel Oil Service Tank Valve; replace | 3.1.1 | 20% Open/Inspect (High Priority) | |
| 51 | 551-11-001 | Number 2 and 3 Ship Service Diesel Generator High Pressure Air Piping; repair | 3.1.1 | 20% Open/Inspect (High Priority) | |
| 52 | 553-30-001 | Number One and 2 Nitrogen Generator/Compressor; overhaul and system clean | 3.2.1, 3.5.1, 3.6.1, 3.7.4, 3.12.1 & 3.14.1 | 20% Open/Inspect (High Priority) | |
| 53 | 588-21-001 | Aft Aircraft Maintenance Bridge Crane; repair | 3.5 | 20% Open/Inspect (High Priority) | |
| 54 | 589-21-001 | Starboard Sideport Cargo Crane, Port Sideport Stores Crane, | |||
| and Ventilation Controller; repair | 3.2.8 | 20% Open/Inspect (High Priority) | |||
| 55 | 593-11-001 | Collection, Holding, and Transfer (CHT) Valve and Rigid Rod Valve Remote Control System; repair | 3.1.1 | 20% Open/Inspect (High Priority) | |
| 56 | 593-11-002 | Collection Holding and Transfer (CHT) Teleflex Remote Valve Operator; repair | 3.2.1 | 20% Open/Inspect (High Priority) | |
| 57 | 593-11-004 | Collection Holding Tank (CHT) Valve and Rigid Rod Valve Remote Control System; repair | 3.1.1 | 20% Open/Inspect (High Priority) | |
| 58 | 593-12-001 | Collection, Holding, and Transfer (CHT) Valve and Rigid Rod Valve Remote Control System; repair | 3.1.1 | 20% Open/Inspect (High Priority) | |
| 59 | 593-12-002 | Collection, Holding, and Transfer (CHT) Remote Operator Assembly and Valve; repair | 3.1.1 | 20% Open/Inspect (High Priority) | |
| 60 | 593-12-003 | Collection Holding Tank (CHT) Valve and Rigid Rod Valve Remote Control System; repair | 3.1.1 | 20% Open/Inspect (High Priority) | |
| 61 | 612-11-001 | Glass Reinforced Plastic (GRP) Stanchion Assembly; replace | 3.1.1 | 20% Open/Inspect (Low Priority) | |
| 62 | 621-11-001 | Crew Shower, Coaming and Deck; repair | 3.2.1 | 20% Open/Inspect (Low Priority) | |
| 63 | 622-12-001 | Cargo Elevator Trunk Number One Grating; repair | 3.1.1 | 20% Open/Inspect (Low Priority) | |
| 64 | 624-11-001 | Balanced Joiner Door; remove, store and install | 3.1.2 | 20% Open/Inspect (High Priority) | |
| 65 | 625-11-001 | Primary Flight Control Station Window; replace | 3.1.2 & 3.4.1 | 20% Open/Inspect (Low Priority) | |
| 66 | 625-11-002 | Flight Deck Control Station Window; replace | 3.1.1 | 20% Open/Inspect (Low Priority) | |
| 67 | 634-11-008 | Vehicle Stowage Area Nonskid; repair | 3.1.1 | 20% Open/Inspect (Low Priority) | |
| 68 | 634-11-009 | Non-Critical Nonskid; replace | 3.1.1 & 3.1.2 & 3.3.1 | 20% Open/Inspect (Low Priority) | |
| 69 | 634-21-001 | Flight Deck Nonskid Deck Covering; repair | 3.1.1, 3.2.1, 3.3.1 & 3.4.1 | 20% Open/Inspect (High Priority) | |
| 70 | 634-21-002 | Flight Deck Thermal Spray Nonskid; repair | 3.1.1, 3.2.1, 3.3.1 & 3.4.1 | 20% Open/Inspect (High Priority) | |
| 71 | 637-11-001 | Crew Shower Overhead Cribbing and Sheathing; repair | 3.1.1 | 20% Open/Inspect (Low Priority) | |
| 72 | 637-11-002 | Overhead Sheathing; replace | 3.1.1 | 20% Open/Inspect (Low Priority) | |
| 73 | 637-11-003 | Access Panel for Reheater; install | 3.1.1 | 20% Open/Inspect (Low Priority) | |
| 74 | 772-22-001 | Number 2 Cargo Weapons Elevator Door; repair | 3.1.2 | 20% Open/Inspect (Low Priority) | |
| 75 | 772-25-001 | Cargo Elevator Number 5 Door Dogging Assembly; repair | 3.1.1 & 3.2.4.1 | 20% Open/Inspect (Low Priority) | |
| 76 | 992-11-004 | Transport Control Protocol/Internet Protocol Based T-1 Type | |||
| Computer Network (T-1 Line) Support Service; provide | 3.1.1.2 | 20% Open/Inspect (High Priority) |